Construction Report

City of Chandler — Regular Meeting (2025-02-12)

View PDF Meeting page

Extracted text (via pymupdf) 2012 characters
Capital Projects – Design Phase: 
 
West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations 
garage, parking lot and aircraft observation area.  At 90% design. Coordination with County Flood 
Control for permit. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Cost negotiation with vendors. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding 
for $110,000.  Plans at 100%.  FAA environmental clearance received. 
 
Runway 4R-22L Rehabilitation (South Runway): FAA grant for $350,000 for design approved.  
Kick-off meeting 4/6.  100% plans submitted.  Received notice of eligibility of FAA construction 
funding. Proceeding to bid phase with advertising in March/April. 
 
Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000 approved.  FAA environmental 
clearance received.  30% design meeting with ADOT 5/24.  100% sealed plans submittal on 9/27. 
Proceeding to bid phase with advertising this month. 
 
Hangar Area Pavement Rehabilitation:  City funded $7.4 million to redo pavement in and among 
the city-owned hangars. Design Kick-off meeting 10/31. 30% plans received 11/27. Goal for 100% 
plans by early March.  Planning for bid opening in late April 2025 and construction start by 7/1/25. 
 
Capital Projects - Construction Phase: 
 
Automated Weather Observation System (AWOS) Replacement:  FAA funding for $200,000.  FAA 
environmental clearance received.  Council approval on 6/13.  Precon meeting on 7/15 for long-lead 
equipment procurement.  AWOS has been commissioned and is operating. 
 
Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north 
of Queen Creek.  Mobilization starting on 7/8 with remediation originally scheduled to be completed 
by mid-November 2024.  New schedule has completion in summer 2025 with a 5.8 acre restricted 
use area remaining.  
 
 
 
Meeting Date:  
February 12, 2025 
Chandler Municipal Airport 
Construction Report