Impact Fee Audit Report

City of Chandler — Study Session (2025-03-24)

View PDF Meeting page

Extracted text (via pymupdf) 24778 characters
City of Chandler, Arizona 
Report on Applying Agreed-Upon Procedures 
Biennial Certification of Land Use Assumptions, 
Infrastructure Improvement Plan 
and Impact Fees 
For the Period July 1, 2022 through June 30, 2024

City of Chandler, Arizona 
Table of Contents 
 
 
 
Contents 
Page 
 
 
Independent Accountant’s Report on Applying Agreed‐Upon Procedures 
1 
  
Results of Procedures 
3 
 
Appendix A – Progress of Infrastructure Improvement Plan Projects  
8

Independent Accountant’s Report on 
Applying Agreed‐Upon Procedures 
 
 
Honorable Mayor and Members of the City Council 
City of Chandler, Arizona 
 
 
We have performed this agreed‐upon procedures engagement to assist management of the City of 
Chandler,  Arizona  (City),  with  the  requirement  set  forth  in  Arizona  Revised  Statutes  (A.R.S.)  
9‐463.05.G.2 “to provide for a biennial certified audit of the municipality’s land use assumptions, 
infrastructure  improvements  plan  and  development  fees.”  As  such,  we  have  performed  the 
procedures  identified  below,  solely  to  assist  users  in  evaluating  the  City’s  compliance  with  the 
progress  reporting  requirements  of  the  infrastructure  improvement  plan  for  the  period  from  
July 1, 2022 through June 30, 2024, as specified in A.R.S. 9‐463.05.G.2. City of Chandler, Arizona’s 
management is responsible for its compliance with those requirements.  
 
City  of  Chandler,  Arizona’s  management  has  agreed  to  and  acknowledged  that  the  procedures 
performed are appropriate to meet the intended purpose of assisting users in determining whether 
the City complied with the specified requirements. This report may not be suitable for any other 
purpose. The procedures performed may not address all the items of interest to a user of this report 
and  may  not  meet  the  needs  of  all  users  of  this  report  and,  as  such,  users  are  responsible  for 
determining whether the procedures performed are appropriate for their purposes. 
 
We have applied the following procedures:  
 
The progress of the infrastructure improvements plan. 
a. 
Compared growth projections for 2023 and 2024 related to dwelling units, population, 
and  the  various  commercial  square  footage  units  as  reported  in  the  Infrastructure 
Improvement Plan (IIP) to actual results for the proportionate 10‐year projections.  A list  
of all variances  are reported in the Results of Procedures. 
b. 
Obtained  City‐prepared  report  (see  Appendix  A)  documenting  the  progress  of  each 
project  identified  in  the  Infrastructure  Improvement  Plan  (IIP)  and  performed  the 
following procedures: 
i. 
Agreed expenditures as of June 30, 2024 to the underlying accounting records. 
ii. 
Agreed amounts reported as estimated cost to complete to underlying accounting 
records. 
The collection and expenditures of impact fees for each project in the plan. 
c. 
Selected a sample of 80 building permits issued and determined fees were charged in 
accordance with authorized fee schedules and that each permit holder was charged the 
same rate as another equivalent permit holder.  
d. 
Selected  a  sample  of  50  expenditures  and  determined  that  the  expenditures  were 
associated with an approved project in the City’s IIP.  
 
Page 1

Evaluating any inequities in implementing the plan or imposing the impact fee. 
e.
Evaluated any inequities in implementing the plan or imposing the impact fee through
recalculating impact fees at the transaction level for the sample mentioned in procedure
c above.
f.
Determined that there were no instances in which the City waived impact fees, except as
allowed for under A.R.S. 9‐499.10.B and A.R.S. 9‐500.18.
The accompanying Results of Procedures describes the items we noted. 
We  were  engaged  by  City  of  Chandler,  Arizona’s  management  to  perform  this  agreed‐upon 
procedures engagement and conducted our engagement in accordance with attestation standards 
established by the American Institute of Certified Public Accountants.  We were not engaged to and 
did  not  conduct  an  examination  or  review  engagement,  the  objective  of  which  would  be  the 
expression of an opinion or conclusion, respectively, on compliance with the specified requirements. 
Accordingly,  we  do  not  express  such  an  opinion  or  conclusion.  Had  we  performed  additional 
procedures, other matters might have come to our attention that would have been reported to you. 
We  are  required  to  be  independent  of  City  of  Chandler,  Arizona  and  to  meet  our  other  ethical 
responsibilities,  in  accordance  with  relevant  ethical  requirements  related  to  our  agreed‐upon 
procedures engagement.  
This report is intended solely for the information and use of the management of City of Chandler, 
Arizona, and is not intended to be and should not be used by anyone other than these specified 
parties. 
Heinfeld, Meech & Co., P.C. 
Scottsdale, Arizona 
February 25, 2025 
Page 2

City of Chandler, Arizona 
Results of Procedures 
 
 
 
Procedure A  
Compared  growth  projections  for  2023  and  2024  related  to  dwelling  units,  population,  and  the 
various  commercial  square  footage  units  as  reported  in  the  City’s  Land  Use  Assumptions  and 
Infrastructure  Improvements  Plan  (IIP)  to  actual  current  amounts  for  the  proportionate  10‐year 
projections. A list of all variances will be reported. 
 
Exception: 
Variances  were  noted  for  growth  projections  for  dwelling  units,  population,  and  the  various 
commercial  square  footage  as  reported  in  the  Land  Use  Assumptions  and  Infrastructure 
Improvements Plan when compared to actual results.  
 
Management Response: 
Assumptions of equal growth of land development and the resulting fees averaged over a set 
period of time do not reflect the reality of how development occurs. Variances exist due to market 
conditions, demand for various types of land use and structures, the condition of the economy, 
and the availability of capital. The City of Chandler continues to take into account annual planning 
projections, entitled projects, and variations in construction permits to augment the equal growth 
assumptions when forecasting. 
 
 
Total Square Footage  
 
Note: The cumulative projected amounts for square footage assume equal growth for each year 
of the 10‐year period with the incremental cumulative total presented for each year. 
 
Cumulative Total as of 2023 
 
  Projected 
 
Actual 
 
Variance 
  Variance % 
Industrial 
Citywide 
39,591,692
45,598,934
6,007,242 
15% 
Arterial Streets 
19,448,074
24,854,028
5,405,954
28% 
Institutional 
 
 
  
Citywide 
12,830,405
12,427,817
(402,588)
‐3% 
Arterial Streets 
6,870,343
7,423,899
553,556
8% 
Office 
 
  
Citywide 
10,811,074
7,958,008
(2,853,066)
‐26% 
Arterial Streets 
4,632,474
3,934,941
(697,533)
‐15% 
Retail 
 
 
  
Citywide 
19,244,358
19,390,990
146,633
1% 
Arterial Streets 
8,104,330   
8,335,605   
231,275
3% 
 
Page 3

City of Chandler, Arizona 
Results of Procedures 
 
 
 
Procedure A (Continued) 
 
Total Square Footage  
 
Cumulative Total as of 2024 
 
  Projected 
 
Actual 
 
Variance 
  Variance % 
Industrial 
Citywide 
40,489,531
46,146,069
5,656,538
14% 
Arterial Streets 
20,165,130
25,358,764
5,193,634
26% 
Institutional 
 
 
  
Citywide 
12,904,892
12,453,049
(451,843)
‐4% 
Arterial Streets 
6,946,634
7,449,131
502,497
7% 
Office 
 
  
Citywide 
11,337,615
8,260,002
(3,077,613)
‐27% 
Arterial Streets 
4,866,077
4,236,935
(629,142)
‐13% 
Retail 
 
 
  
Citywide 
19,407,272
19,554,465
147,193
1% 
Arterial Streets 
8,231,243   
8,495,899  
264,656
3% 
 
Total Housing Units and Population by Service Area 
 
Note: The cumulative projected amounts for housing units and population assume equal growth 
for each year of the 10‐year period with the incremental cumulative total presented for each year. 
 
Cumulative Total as of 2023 
 
 
Projected 
 
Actual 
 
Variance 
  Variance % 
Single Family 
 
 
 
 
 
 
 
 
Parks Northwest 
 
 11,733   
 11,850   
 118  
1% 
Parks Northeast 
 
 34,995   
 36,091   
 1,096  
3% 
Park Southeast 
 
 33,171   
 34,771   
 1,601  
5% 
Citywide 
 
 79,898   
 82,712   
 2,814  
4% 
Arterial Streets 
 
 43,932   
 52,930   
 8,999  
20% 
Multi‐Family 
 
   
   
   
  
Parks Northwest 
 
 4,990   
 5,269   
 279  
6% 
Parks Northeast 
 
 18,023   
 15,934   
 (2,089)  
‐12% 
Park Southeast 
 
 7,164   
 9,097   
 1,933  
27% 
Citywide 
 
 30,177   
 30,300   
 123  
0% 
Arterial Streets 
 
 11,430   
 15,934   
 4,505  
39% 
Resident Population 
 
   
   
   
  
Parks Northwest 
 
 42,332   
 43,653   
 1,321  
3% 
Parks Northeast 
 
 132,230   
 137,664   
 5,434  
4% 
Park Southeast 
 
 104,771   
 111,863   
 7,092  
7% 
Citywide 
 
 279,332   
 293,180   
 13,848  
5% 
Arterial Streets 
 
 144,724    
 175,603    
 30,879   
21% 
 
Page 4

City of Chandler, Arizona 
Results of Procedures 
 
 
 
Procedure A (Continued) 
 
Cumulative Total as of 2024 
 
 
Projected 
 
Actual 
 
Variance 
  Variance % 
Single Family 
 
   
   
   
 
Parks Northwest 
 
 11,738   
 11,853   
 115  
1% 
Parks Northeast 
 
 35,047   
 36,176   
 1,129  
3% 
Park Southeast 
 
 33,324   
 34,912   
 1,588  
5% 
Citywide 
 
 80,110   
 82,941   
 2,831  
4% 
Arterial Streets 
 
 44,078   
 53,153   
 9,075  
21% 
Multi‐Family 
 
   
   
   
  
Parks Northwest 
 
 4,998   
 5,334   
 336  
7% 
Parks Northeast 
 
 18,465   
 19,019   
 554  
3% 
Park Southeast 
 
 7,164   
 9,227   
 2,063  
29% 
Citywide 
 
 30,627   
 33,580   
 2,953  
10% 
Arterial Streets 
 
 11,487   
 17,238   
 5,751  
50% 
Resident Population 
 
   
   
   
  
Parks Northwest 
 
 42,363   
 43,827   
 43,827  
3% 
Parks Northeast 
 
 133,216   
 140,747   
 140,747  
6% 
Park Southeast 
 
 104,771   
 112,554   
 112,554  
7% 
Citywide 
 
 280,350   
 297,128   
 297,128  
6% 
Arterial Streets 
 
 145,244   
 179,497   
 179,497   
24% 
 
Procedure B 
Obtained City‐prepared report (see Appendix A) documenting the progress of each project identified 
in the Infrastructure Improvement Plan (IIP) and performed the following procedures: 
 
a. Agreed expenditures as of June 30, 2024 to the underlying accounting records. 
 
b. Agreed  amounts  reported  as  estimated  cost  to  complete  to  underlying  accounting 
records. 
 
No exceptions noted. 
 
Procedure C 
Selected a sample of 80 building permits issued and determine fees were charged in accordance with 
authorized fee schedules and that each permit holder is charged the same rate as another equivalent 
permit holder.  
 
No exceptions noted. 
 
Procedure D 
Selected a sample of 50 expenditures and determine that the expenditure was associated with an 
approved project in the City’s IIP. 
 
No exceptions noted.
Page 5

City of Chandler, Arizona 
Results of Procedures 
 
 
 
Procedure E 
Evaluated any inequities in implementing the plan or imposing the impact fee through recalculating 
impact fees at the transaction level for the sample mentioned in procedure c above. 
 
No exceptions noted. 
 
Procedure F 
Determined that there were no instances in which the City waived impact fees, except as allowed for 
under A.R.S. 9‐499.10.B and A.R.S. 9‐500.18 
 
No exceptions noted. 
Page 6

Appendix A 
Page 7

Note: Any negative amount presented are expense recoveries from prior years. 
Fund
Description
415 Arterial Street Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6ST311‐Price Rd and Queen Creek Intersection
‐ 
‐ 
(190,862)
             
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
(190,862)
               
6ST478‐McQueen Rd (Queen Creek Rd to Riggs Rd)
401,157
 
720,556
                
542
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
1,122,255
             
6ST482‐Gilbert Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
(127,921)
             
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
(127,921)
               
6ST548‐Queen Creek Rd (McQueen Rd to Gilbert Rd)
‐ 
262,288
                
246,143
              
601,762
              
2,100,347
             
153,606
              
‐ 
‐ 
‐ 
3,364,147
             
6ST596‐Gilbert Rd (Queen Creek Rd to Riggs Rd)
484,152
 
20,705
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
504,857
                
6ST607‐Ocotillo Rd (Arizona Ave to McQueen Rd)
659,940
 
490
 
‐ 
(1,011)
 
‐ 
‐ 
‐ 
‐ 
‐ 
659,419
                
6ST608‐Chandler Heights (Arizona Ave to McQueen Rd)
32,904
 
114,167
                
604,636
              
‐ 
1,182,277
             
2,983
 
‐ 
‐ 
‐ 
1,936,967
             
6ST641‐Ocotillo Rd (Cooper Rd to 148th St)
147,647
 
513,530
                
1,670,914
           
‐ 
334,675
                
48,918
                
35,048
                
3,244,472
           
1,286,816
           
42,929
 
7,324,949
             
6ST675‐Cooper Rd (Queen Creek Rd to Riggs Rd)
13,741
 
27,498
 
160,137
              
‐ 
45,614
 
2,294,623
           
2,644,544
           
556,933
              
39,632
 
5,782,722
             
6ST692‐Chandler Heights Rd (McQueen Rd to Val Vista Dr)
‐ 
‐ 
181,765
              
469,687
              
119,741
                
122,793
              
858,848
              
5,575,618
           
5,263,101
           
10,813,252
          
23,404,806
           
6ST693‐Lindsay Rd (Ocotillo Rd to Hunt Hwy)
‐ 
‐ 
‐ 
‐ 
17,915
 
110,764
              
84,842
                
125,002
              
128,139
              
28,331,604
          
28,798,266
           
6ST738‐Gilbert Rd (Ocotillo Rd to Chandler Heights Rd)
‐ 
‐ 
‐ 
‐ 
213,989
                
(213,989)
             
‐ 
‐ 
‐ 
‐ 
6ST745‐Alma School Rd (Chandler Blvd to Pecos Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6ST746‐Alma School Rd (Pecos Rd to Germann Rd)
‐ 
‐ 
‐ 
‐ 
176,985
                
2,405,803
           
1,214,127
           
75,306
                
22,602
                
25,613
 
3,920,436
             
6ST747‐Alma School Rd (Germann Rd to Queen Creek Rd)
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
174,310
              
1,069,369
            
1,243,679
             
*As programmed in 2022‐2033 CIP
421 Community Park Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6PR396‐Mesquite Groves Park
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
Note:  This fund was expended and closed as of 6/30/17.
422 Neighborhood Parks Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6PR039‐Neighborhood Park Land Acquisition
3,087
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
3,087
 
6PR044‐Tumbleweed Regional Park
41,759
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
41,759
 
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
22,445
                
72,723
 
‐ 
‐ 
‐ 
‐ 
‐ 
95,168
 
6PR400‐Roadrunner Park
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR631‐Centennial Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
Note:  This fund was expended and closed as of 6/30/20.
424 Park Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6PR389‐Homestead North Park Site
‐ 
‐ 
‐ 
27,588
                
25,564
 
55,091
                
684,404
              
2,071,891
           
‐ 
‐ 
2,864,538
             
6PR390‐Homestead South Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR396‐Mesquite Groves Park Site Phase I
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR400‐Roadrunner Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR420‐Veteran's Oasis Park Site
‐ 
‐ 
(59,740)
               
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
(59,740)
 
6PR629‐Lantana Ranch Park
347,469
              
242,454
              
‐ 
‐ 
‐ 
589,923
                
6PR631‐Centennial Park Site
12,843
 
4,672
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
17,515
 
6PR638‐Valencia Park Site
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
6PR639‐Citrus Vista Park Site
1,412,990
               
4,995
 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
‐ 
1,417,985
             
6PR640‐Layton Lakes Park Site
‐ 
141,285
                
1,191,476
           
139,376
              
‐ 
‐ 
‐ 
‐ 
‐ 
1,472,137
             
*As programmed in 2022‐2033 CIP
Note: This fund was expended and closed as of 6/30/23.
Fiscal Year
Page 8

425 Parks NW Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
None
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
**No growth‐related capital to construct; collecting fees to repay pledged debt
426 Parks NE Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
None
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
**No growth‐related capital to construct; collecting fees to repay pledged debt
427 Parks SE Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6PR396‐Mesquite Groves Park Site Phase I
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
17,073
                
32,729,926
          
32,746,999
           
6PR629‐Lantana Ranch Park Site
‐
                           
‐
                        
‐
                      
‐
                      
88,854
                 
990,630
              
2,013,331
           
‐
                      
‐
                      
7,729,908
            
10,822,722
           
*As programmed in 2022‐2033 CIP
465 Police Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6PD243‐Chandler Heights Subtation
‐
                           
‐
                        
(59,740)
               
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
(59,740)
                 
**No growth‐related capital to construct; collecting fees to repay pledged debt
475 Fire Impact Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6FI611‐Southeast Fire Station
797
                          
361,261
                
3,579,131
           
295,842
              
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
4,237,031
             
6FI638‐Fire Station No. 1 Relocation
147,100
                  
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
147,100
                
**No growth‐related capital to construct; collecting fees to repay pledged debt
603 Water System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6WA029‐Water Master Plan Update
68,498
                    
133,055
                
56,495
                
1,553
                  
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
259,600
                
6WA034‐Well Construction/Rehabilitation
2,260,447
               
1,807,500
             
894,025
              
718,077
              
1,637,212
             
16,503
                
18,132
                
80
                        
29,007
                
3,052,547
            
10,433,529
           
6WA076‐Transmission Mains
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
6WA334‐Joint Water Treatment Plant
‐
                           
6,418,629
             
19,857,848
         
1,639,976
           
1,020,748
             
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
28,937,201
           
6WA672‐Water Purchases
‐
                           
9,999,788
             
4,999,940
           
4,999,940
           
14,731,755
          
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
34,731,423
           
**No growth‐related capital to construct; collecting fees to repay pledged debt
604 Water Resource System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6WW661‐Ocotillo Water Reclamation Facility Expansion
748,052
                  
2,763,414
             
488,533
              
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
4,000,000
             
6WA672‐Water Purchases
‐
                           
‐
                        
‐
                      
‐
                      
128,827
                
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
128,827
                
Note:  This fund was expended and closed as of 6/30/20.
610 Reclaimed Water System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6WW189‐Effluent Reuse‐Storage
97,991
                    
876,519
                
15,513
                
151,138
              
294,279
                
210,698
              
2,171,057
           
690,757
              
142,912
              
178
                       
4,651,043
             
Page 9

6WW192‐Effluent Reuse‐Transmission Mains
1,422,386
               
158,361
                
868,974
              
3,198,432
           
212,433
                
1,738
                  
‐
                      
‐
                      
14,560
                
227,270
                
6,104,155
             
*As programmed in 2022‐2033 CIP
614 Wastewater System Development Fees
2015‐16
2016‐17
2017‐18
2018‐19
2019‐20
2020‐21
2021‐22
2022‐23
2023‐24
2024‐25 though 
2033‐34*
Total
6WW021‐Wastewater Master Plan Update
157,935
                  
266,114
                
112,989
              
3,107
                  
‐
                        
‐
                      
‐
                      
‐
                      
‐
                        
540,145
                
6WW022‐Water Reclamation Facility Expansion
20,126
                    
540
                       
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
20,666
                  
6WW196‐Collection System Facility Improvements
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
6WW651‐Wastewater Land Acquistion
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
6WW642‐South Chandler Sewer Line Expansion
‐
                           
‐
                        
‐
                      
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
‐
                         
6WW661‐Ocotillo Water Reclamation Facility Expansion
19,505,029
             
79,677,431
          
14,085,867
         
‐
                      
‐
                        
‐
                      
‐
                      
‐
                      
‐
                      
‐
                        
113,268,328
         
**No growth‐related capital to construct; collecting fees to repay pledged debt
Page 10