www.srpnet.com
Construction Change Order Estimate.docx 
Or File: 2200676
Coord: 27.25 E 7.50 S
November 4, 2024
City of Chandler
Attn: Mr. Hafiz Noor
P. O. Box 4008
Chandler, AZ 85244-4008
RE:
RYAN RD, UNION PACIFIC RR TO MCQUEEN RD
RYAN ROAD & MCQUEEN ROAD
(Change Order No. 1)
Dear Mr. Noor: 
We have prepared our estimate to complete the referenced change order work for your acceptance.  The 
change involves an additional 1340 LF RGRCP, 1 STR, 2 MH and take lead to obtain the Railroad Utility 
Crossing Permit with UPRR.
The total estimated cost for SRP forces to complete this change order work is $51,790.  Before the work 
can be done, your authorization and agreement to pay is required by signing below and returning this 
letter. 
To avoid construction delay, your authorization must be received by December 4, 2024.  Please send your 
authorization to my attention at the above address and/or fax to (602) 236-5965.
We look forward to the successful completion of your project.  If you have any questions, contact our 
project leader, Victor Lucero, at (602) 236-5586 or at email Victor.Lucero@srpnet.com. 
Sincerely,
Christian Andrews
Manager, Water Engineering
CA:vl
Sincerely,

P.O. Box 52025 
Mail Station: SSW303 
Phoenix, Arizona 85072-2025 
(602) 236-5900 
www.srpnet.com 
Construction Change Order Estimate.docx 
 
Mr. Hafiz Noor 
November 4, 2024 
Page 2 
 
File: 2200676 
 
 
CHANGE ORDER APPROVAL 
 
I approve of SRP proceeding with the work associated with the above-described change.  SRP is hereby 
authorized to bill City of Chandler upon completion of construction. 
 
 
_______________________________           
______________________________ 
____________ 
                   (Signature) 
                          (Title) 
 
 
        (Date) 
 
 
_______________________________ 
                  (Print Name) 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
CIP City Engineer
3/25/2025
Daniel Haskins

ADDITIONAL TERMS AND CONDITIONS: 
•
This Agreement is subject to A.R.S. 38-511
For Customer (City of Chandler): 
MAYOR Signature: 
Authorized Signature: 
Date: 
Printed Name: Daniel Haskins, P.E. 
Title: CIP City Engineer 
Approved as to Form: 
Attest: 
City Attorney 
City Clerk 
Seal 
City Project No.: PR2106.504 CHANGE ORDER No. 1 
City Project Name: TUMBLEWEED PARK SOFTBALL & BASEBALL FIELD COMPLEX 
SRP Project Name: RYAN ROAD AND UNION PACIFIC RAILROAD IMPROVEMENTS 
SRP Job Work Order No.:  2200676 
Job Location: RYAN ROAD & McQUEEN ROAD 
Change Order Amount: $51,790 
3/25/2025