P.O. Box 52025
Mail Station: SSW303
Phoenix, Arizona 85072-2025
(602) 236-5900
www.srpnet.com
Construction Change Order Estimate.docx
Or File: 2200676
Coord: 27.25 E 7.50 S
November 4, 2024
City of Chandler
Attn: Mr. Hafiz Noor
P. O. Box 4008
Chandler, AZ 85244-4008
RE:
RYAN RD, UNION PACIFIC RR TO MCQUEEN RD
RYAN ROAD & MCQUEEN ROAD
(Change Order No. 1)
Dear Mr. Noor:
We have prepared our estimate to complete the referenced change order work for your acceptance. The
change involves an additional 1340 LF RGRCP, 1 STR, 2 MH and take lead to obtain the Railroad Utility
Crossing Permit with UPRR.
The total estimated cost for SRP forces to complete this change order work is $51,790. Before the work
can be done, your authorization and agreement to pay is required by signing below and returning this
letter.
To avoid construction delay, your authorization must be received by December 4, 2024. Please send your
authorization to my attention at the above address and/or fax to (602) 236-5965.
We look forward to the successful completion of your project. If you have any questions, contact our
project leader, Victor Lucero, at (602) 236-5586 or at email Victor.Lucero@srpnet.com.
Sincerely,
Christian Andrews
Manager, Water Engineering
CA:vl
Sincerely,
P.O. Box 52025
Mail Station: SSW303
Phoenix, Arizona 85072-2025
(602) 236-5900
www.srpnet.com
Construction Change Order Estimate.docx
Mr. Hafiz Noor
November 4, 2024
Page 2
File: 2200676
CHANGE ORDER APPROVAL
I approve of SRP proceeding with the work associated with the above-described change. SRP is hereby
authorized to bill City of Chandler upon completion of construction.
_______________________________
______________________________
____________
(Signature)
(Title)
(Date)
_______________________________
(Print Name)
CIP City Engineer
3/25/2025
Daniel Haskins
ADDITIONAL TERMS AND CONDITIONS:
•
This Agreement is subject to A.R.S. 38-511
For Customer (City of Chandler):
MAYOR Signature:
Authorized Signature:
Date:
Printed Name: Daniel Haskins, P.E.
Title: CIP City Engineer
Approved as to Form:
Attest:
City Attorney
City Clerk
Seal
City Project No.: PR2106.504 CHANGE ORDER No. 1
City Project Name: TUMBLEWEED PARK SOFTBALL & BASEBALL FIELD COMPLEX
SRP Project Name: RYAN ROAD AND UNION PACIFIC RAILROAD IMPROVEMENTS
SRP Job Work Order No.: 2200676
Job Location: RYAN ROAD & McQUEEN ROAD
Change Order Amount: $51,790
3/25/2025