May 2025 Project Status Update

City of Chandler — Regular Meeting (2025-05-21)

View PDF Meeting page

Extracted text (via pymupdf) 4060 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
($MILLIONS)
ST1614 Chandler Heights Road Improv. [McQueen Road to Gilbert Road for two 
through lanes each direction]
Kimley-Horn
Granite Construction Co
Project in closeout.
Federal funds
$20.90
ST1804 Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two 
through lanes each direction]
Kimley-Horn
Sunland Asphalt
Construction is underway.  
Federal funds
$9.80
ST2001 Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two
through lanes in each direction]
Kimley-Horn
tbd
Design in progress.  Preparing to submit for Obligation.  Project 
scheduled to go out to bid in June 2025.  
Federal funds
$27.20
ST2007 Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
Redpoint
Construction has reached Substantial Completion.  
$5.20
ST2103 Intersection Improv. at Ray Road and Dobson Road
Kimley Horn
tbd
Design is currently at 95%. Project needs ROW, and anticiaptes 
going out to bid Fall 2026.  
Grant funds & local funds
$11.85
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south 
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively scheduled Winter 
2025.  
$2.00 
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight 
Way & Emmett Dr intersection)
Aztec
tbd
Design is currently at 90%.  Project needs ROW, and anticiaptes 
going out to bid Summer 2026.   
$9.30 
ST2309 Alma School Road Germann Rd to Queen Creek Rd (widening Alma School 
Road from Germann Road tro Queen Creek Road)
Olsson Associates
tbd
Design is currently ot 90%.  Construction tentatively scheduled 
for bid in Fall 2025.  
$11.30 
ST2310 Alley Rehab PM10 Dust Emissions Reduction Phase 3 (FMA Areas 6, 24, 26, 
27)
Premier / Olsson
tbd
Design is at 100%.  Federal Funds availlable in October 2025.  
Federally Funded
$3.50 
ST2403 McQueen Road Improvements - Warner Road to Pecos Road Study (Study 
to widen McQueen Road in three phases from Warner Road to Pecos Road)
Kimley-Horn and 
Associates
tbd
Design Study only
Study is Locally Funded, Project will be Federally Funded and 
Design starts in FY 27-28
$84.00 
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT 
COST 
ESTIMATE
ST2106 Frye Road Protected Bike Lanes [Paseo Trail to San Marcos
Elementary School]
TY Lin
Granite Construction Co
Study completed by Y2K.  Design complete. Construction starts 
April 7, 2025.
$13.5 Million grant awarded for construction and $650,000 for 
design.
$14.00
TP2202  Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
95% Design.  Right-of-Way in Process.  Construction in early 
2026.
Federal grants have been awarded to fund study, design and 
construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study completed by Y2K.  95% Design.  Right-of-Way in Process.  
Construction in late 2025 early 2026.
Study was federally funded.  Construction and design are 
locally funded.
$1.00
Paseo Trail Riggs Road Crossing
Kimley Horn
tbd
Study to develop preliminary design for a Paseo Trail crossing of 
Riggs Road and construction of the path between Riggs Road 
and Hunt Highway.
Awarded $60,000 federal grant for study.
$0.06
Roadway Safety Action Plan
tbd
tbd
Comprehensive study to analyze safety for all road users and 
develop recommentations.
Awarded $560,000 Safe Streets for All grant to complete study 
(with 20% local match).
$0.70
Chandler Flex
NA
Via
Completed Airpark Area Flexible Transit Study. Began minor 
implementation of study recommendations through a two 
square-mile expansion between Arizona Ave. and McQueen Rd. 
and Queen Creek Rd. and Chandler Height Rd.  and opened the 
school-only zone (north of Chandler Blvd.) to all trip types.
Awarded $2 Million grant for project startup and two years of 
operations.  Awarded $1 Million congressionally-directed 
spending grant to continue operations.
$1.3 Annually
Transportation Project Status - May 2025