Construction Report

City of Chandler — Regular Meeting (2025-05-14)

View PDF Meeting page

Extracted text (via pymupdf) 1812 characters
Capital Projects – Design Phase: 
 
West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations 
garage, parking lot and aircraft observation area.  At 90% design. Coordination with County Flood 
Control for permit.  Working with City’s development services.  
 
Airport Fuel Tank Relocation: City funded at $610,000.  Cost negotiation with vendors.  Budget 
transfer under evaluation. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding 
for $110,000.  Revising drawings for circuit change for 24/7 REILs. FAA confirmed environmental 
clearance. 
 
Capital Projects - Construction Phase: 
 
Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000 approved.  FAA environmental 
clearance received.  30% design meeting with ADOT 5/24.  100% sealed plans submittal on 9/27. 
Bids open and tracking for Council action in June.  
 
Runway 4R-22L Rehabilitation (South Runway): FAA grant for $350,000 for design approved.  
Kick-off meeting 4/6.  100% plans submitted.  Received notice of eligibility of FAA construction 
funding. Bid opening on 5/8. 
 
Hangar Area Pavement Rehabilitation:  City funded $7.4 million to redo pavement in and among 
the city-owned hangars. Design Kick-off meeting 10/31. 30% plans received 11/27. Goal for 100% 
plans by early March.  Planned to be out for bid in June.  
 
Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north 
of Queen Creek.  Mobilization starting on 7/8 with remediation originally scheduled to be completed 
by mid-November 2024.  New schedule has completion in summer 2025 with a 5.8 acre restricted 
use area remaining.  On track for completion in June. 
 