DocuSign Envelope ID: CAB5D29E-0975-467F-BOF5-CEOA003F39FO = {SE URVER - BUS APPRUVAL
Maricopa County Deparment of Transportation
Date: 8/1/2023 Change Order Number Amount: $14,500.00 Agenda Item No. C-64-23-077-X-00
Contract No:]2022-058 Work Order No: TT0339
Consultant Name:] Archer Western Construction, LLC
Project Name: | Gilbert Road Bridge at the Salt River
Intial Amount: $48,586,929.00] Contract Notice to Proceed Date: 11/28/2022 Total Prior Change Orders: $995,668.65
The Contractor, by mutual agreement of the parties, shall make the herein described changes to the plans and specifications or do the following described work not included in the plans
and specifications on the above-identified contract. All other contract terms and conditions remain unchanged.
Change order to compensate the contractor for additional material and installation costs associated with increasing storm drain pipe size from 60- in to 66-in., as
detailed in Attachment A.
With this Change Order, the total amount of this contract has increased 2.08%
By reason of this change 0 days extension of time will be allowed for construction work. The construction work completion date is: 2/10/2025
By reason of this change 0 days extension of time will be allowed for administrative purposes, after the time allowed for construction work.
With inclusion of this change, this contract has a revised cumulative performance period of 925 days.
The contract completion date is: 6/10/2025
The following financial information is submitted:
Initial Contract Amount $48,586,929.00
Amended Contract Amount w/ previous change orders $49,582,597.65
Current Change Order Request $14,500.00
Amended Contract Amount w/ current change order $49,597,097.65
We, the undersigned Contractor, having given careful consideration to the change(s) proposed, hereby agree that upon execution of this change order that we will provide all
equipment, furnish all material (except as noted in the Bid Line Item Sheet), perform all work specified in Bid Line Item Sheets; and we will accept as full payment therefore the prices
shown in Bid Line Item Sheet.
IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:
DocuSigned by:
Principal (Signature) Mattlew F ilipowstei
Printed Name MatthadeFnisaanneie--
Title Senior Project Manager
Date 8/73/2023
MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION
DocuSigned by: DocuSigned by:
C27iZ4 8/3/2023 Lise Ruane 8/7/2023
Consultabn @BeniphesBle) - John Hall Date Cohstrdanion aa gir.— Lisa Ruane Date
DocuSigned by: ‘DocuSigned by: / /
on 8/8/2023 he 8/8/2023
(Se /8/ Alina Lewichi.
Bralch-Viaoagwscstracie Riggs Date Division SIMareyeAOARina Lewicki Date
I certit that {iN bapge is within the limits authorized by the Maricopa County | certi that fuads arg available to accomplish this Change Order
Profuremen aie . i ve
8/15/2023 ifs 8/8/2023
Desurly brn chuck williams
Cohtract@orviedsssBeverly Krumm Date CIP GasbeFtawatenrayer - Charles Williams Date
DocuSigned by:
: 8/14/2023
[ ewe wiley
Deptity-Ranaaporaitiots.Director - Steven Wilcox Date IGA PM (if applicable) - Date
COUNTY APPROVAL
R MMEMRIFD:BY: ACCEPTED AND APPROVED:
. 8/15/2023
Jesse ution
Transpurenien DRtor/Engineer - Jesse Gutierrez Date Chairman, Board of Supervisors - Date
LEGAL REVIEW ATTEST:
Approved as to form and within th wers and authority granted under the laws
of }asn§ fudanyia to the Mavicopa County Department of Transportation.
8/16/2023
Meolaus Ducker (S
Deputjodourngeatiemney - Date Clerk of the Board - Date
DocuSign Envelope ID: CAB5D29E-0975-467 F-BOF5-CEOA003F39F0
Maricopa County Department of Transportation
Sheet 1 of 1
Contract No. 2022-058
Bid Line Items Sheet
CONSTRUCTION CHANGE ORDER NO. 4
sestt . Estimated As-Built Difference Unit Difference
Bid Item No. Description Unit Quantity Quantity Gh) Price (an)
618.20360-04 60 in RGRCP Class Il LF t) (250.00) (250.00) $707.00 ($176,750.00)
618,20366-04 66 in RGRCP Class Ill LF 0 250 250.00 $765.00 $191,250.00
14,500.00
14,500.00
Total this Sheet
Total all Sheets
Revised: 7/17/2023
DocuSign Envelope ID: CAB5D29E-0975-467F-BOF5-CEOA003F39F0
Gilbert Road Bridge at Salt River
INDEX OF SUPPORTING DOCUMENTATION
CONSTRUCTION CHANGE ORDER NO. 04
66-in Storm Drain
Document Description
Page(s)
Attachment "A" Scope of Work 1 of 1
DocuSign Envelope ID: CAB5D29E-0975-467F-BOF5-CEOA003F39F0
Maricopa County Department of Transportation
ATTACHMENT “A” (Change Order Scope)
Project #: TT0339 Project Name: Gilbert Road Bridge at Salt River
Contract #: 2022-058 Change Order #: 04
| Reason: | To Establish Change Order 04, 66-in Storm Drain |
Description:
The TT0339 project plans identify 247 LF of existing 60-in storm drain in
conflict with the CSA construction at Abutment 1 to be removed and later
replaced with 250 LF of new 60-in storm drain. During removal, it was
determined that the existing pipe diameter is actually 66-in. This
determination was confirmed by reviewing the Record Drawings for
MCDOT Project No. 68957, which specified that the pipe in question was
1650mm in diameter, or approximately 66-in.
The design team confirmed that 66-in pipe is required for proper operation
of the storm drain system.
This Change Order will compensate the contractor for the additional
material and installation costs associated with increasing the pipe size from
60-in to 66-in.
Bid Items:
Item No. Description Unit Qty Unit Price Amount
618.20360-04 | 60 in RGRCP Class III LF (250) $707.00 ($176,750.00)
618.20366-04 | 66 in RGRCP Class III LF 250 $765.00 $191,250.00
Total $14,500.00
| Cost: | $14,
500.00 | Time: | 0 Calendar Days |
[ Specification:
| None |
| Subcategories: Not Preventable
C1 Utility Conflict Right-of-Way Conflict O Quantity Adjustment
C1 Work out of Scope (MCDOT) 1 Work out of Scope (Other Jurisdiction)
Plan Revisions LC] Changed Physical Condition O Environmental
CO Value Engineering (Other:
Contacts:
Lisa Ruane, P.E.
Construction Engineer MCDOT Concurred 04/03/23
Alana Lewicki, P.E. | Const. & Mat'ls Division Mgr. | MCDOT Concurred 04/03/23
Draft Revised 8-14
SUPPORT DOCUMENTATION
To accompany CHANGE ORDER __ 4
Page 1 of _1