CONSTRUCTION DEADLINES
ACTION
DEADLINE
October 1, 2025
Developer's submittal of
administratively complete
application( s) for any land use
entitlement required for
Minimum Improvements.
Developer obtains final
development approval
including Planned Area
March 31, 2026
Development (PAD) and
Preliminary Development Plan
(PDP)
Developer's submittal of 90%
completed civil plans for the
grading permit.
March 1, 2026
Developer obtains approval of
site and building plans ("Civil
July 1, 2026
Plans")
Developer's Commencement of
Construction ("Construction
October 1, 2026
Commencement")
Developer's Completion of
Construction ("Construction
October 1, 2027
Completion Date")
3.
Term. Section 7.2 is replaced in its entirety with the following language:
4.
language:
The term of this Agreement ("Term") commenced on the Effective Date and will
run until May 31, 2031.
Events of Default. Section 5 .1 is replaced in its entirety with the following
It shall be a default hereunder ("Default") if either Party fails to perform any of
its obligations hereunder or under the Purchase Agreement, and such failure
2