Agreement

City of Chandler — Study Session (2025-06-09)

View PDF Meeting page

Extracted text (via pymupdf) 483847 characters
City of Chandler, Arizona
Public Works & Utilities Department 
Capital Projects Division
CONSTRUCTION BID 
TAXIWAY B IMPROVEMENTS PHASE 1
CITY PROJECT NO.: AI2302.401; ADOT NO.: E3S4C 
MAYOR
Kevin Hartke 
VICE MAYOR
Christine Ellis 
COUNCIL
OD Harris     Matt Orlando     
Angel Encinas    Jane Poston    Jennifer Hawkins 
__________________________________________________ 
Daniel Haskins, P.E. 
CIP City Engineer

CITY OF CHANDLER, ARIZONA 
CONSTRUCTION BID 
TABLE OF CONTENTS 
INVITATION TO BID 
BID SUBMITTAL LIST 
CONSTRUCTION AGREEMENT 
PROJECT SPECIFIC SPECIAL PROVISIONS 
GENERAL CONDITIONS 
TECHNICAL SPECIFICATIONS 
GIS/GPS DATA DELIVERY REQUIREMENTS 
(NOT applicable) 
FEDERAL PROVISIONS 
(NOT applicable)

LEGAL AD DEPARTMENT        
 
 
 
 
INVITATION TO BID 
 
TAXIWAY B IMPROVEMENTS PHASE 1 
CITY PROJECT NO.: AI2302.401; ADOT No.: E3S4C 
 
NOTICE IS HEREBY GIVEN that sealed bids will be received and date/time stamped by the City of Chandler 
Capital Projects Office, 215 East Buffalo Street, Chandler, Arizona 85225 until the bid submission date 
specified below.   
 
All firms must be registered on the Arizona Procurement Portal (https://app.az.gov/) vendor registration 
system prior to submitting a Bid.   Non-registered firms will not receive addenda notifications.  Download 
the 
Bid 
Documents 
and 
any 
Addenda 
at 
www.chandleraz.gov/business/vendor-services/capital-
projects/construction-bids.  It is the contractor's sole responsibility to obtain all addenda from the City 
website prior to submitting their bid proposal, and to acknowledge receipt and acceptance of the addenda 
in their bid proposal submittal.  No separate notification of addenda will be issued. The City recommends 
Contractors regularly check the website for updated information. 
 
 
PRE-BID CONFERENCE: 
 
THERE WILL BE NO PRE-BID CONFERENCE 
 
 
SOLICITATION QUESTIONS DUE DATE: 
April 11, 2025 
5:00 p.m. 
Arizona time 
All solicitation questions must be emailed to Bid.Questions@chandleraz.gov with 
the subject line of: 
“CITY PROJECT No.: AI2302.401; ADOT No.: E3S4C Taxiway B Improvements 
Phase 1 BID QUESTION”.   
Questions received after the due date and time will NOT be considered. 
 
 
BID SUBMISSION: 
April 23, 2025 
3:00 p.m. 
Arizona time 
Sealed bids must be delivered to: City of Chandler Capital Projects Office located at 
215 East Buffalo Street, Chandler, Arizona, 85225.   
Bids must be received on or before date and time specified. 
At that time, bids will be publicly opened and read aloud in the: 
Saguaro Conference Room 
Bids received after the due date and time will be returned unopened without 
consideration.   
 
All bids must be submitted in a sealed envelope plainly marked as follows: 
 
 
BID OF _____________________________, CONTRACTOR 
 
 
FOR: 
“Taxiway B Improvements Phase 1”  
 
 
“CITY PROJECT No.: AI2302.401; ADOT No.: E3S4C” 
.

Work under this Agreement includes:  
The Taxiway B Improvements Phase I: Taxiway L to Taxiway N project includes a partial extension of the 
existing Taxiway B by approximately 1,300 feet. The project includes new taxiway and shoulder pavement, 
pavement markings, grading, lighting, and electrical improvements. The taxiway will be 40 feet wide, and the 
paved shoulders will be 10 feet wide, both to match existing. Work must be completed within 90 consecutive 
calendar days from the Notice to Proceed.   
Bids must be submitted on the Proposal Form provided and be accompanied by the Bid Bond for not less 
than ten percent (10%) of the total bid, payable to the City of Chandler, Arizona, or a certified or cashier's 
check. PERSONAL OR INDIVIDUAL SURETY BONDS ARE NOT ACCEPTABLE. 
 
The successful bidder will be required to execute the standard form of agreement for construction prior to 
Council award 
 
The successful bidder must furnish a Payment Bond and Performance Bond in the amount equal to one 
hundred percent (100%) of the Agreement Price. 
 
The right is hereby reserved to accept or reject any or all bids or parts thereto, to waive any informalities in 
any proposal and reject the bids of any persons who have been delinquent or unfaithful to any agreement 
with the City of Chandler.   
 
All Bids will remain open for 90 days after the Bid opening day, but the City may, in its sole discretion, release 
any Bid and return the bid security prior to that date.  No Bidder may withdraw his Bid during this period 
without written permission from the City. 
 
Find PRELIMINARY BID RESULTS at: https://www.chandleraz.gov/business/vendor-services/capital-projects 
Protest Policy - A protest of a proposed award must be filed WITH THE PURCHASING OFFICE within 5 calendar 
days of the first posting of the award recommendation. Award recommendations are posted on the Capital 
Projects web site or the City Clerk web site. If the due date occurs on a weekend or holiday the protest must 
be filed the next business day.  
A Protest must include: 
• 
The name, address and telephone number of the protester; 
• 
The signature of the protester or its representative; 
• 
Identification of the project and the solicitation or agreement number; 
• 
A detailed statement of the legal and factual grounds of the protest including copies of relevant 
documents; and 
• 
The form of relief requested. 
 
City will review the protest and issue a written response. 
 
 
 
PUBLISHED DATE: 
3/26/2025 
4/2/2025 
Arizona Republic 
AFFIDAVIT OF PUBLICATION

Rev. 11/28/2022 
1 
 
 
 
DO NOT DOUBLE-SIDE ANY PART OF THE BID SUBMITTAL  
PROJECT NAME:   Taxiway B Improvements Phase 1 
 
CITY PROJECT NO.: 
AI2302.401; ADOT No.: E3S4C 
 
 
PLEASE INCLUDE THE FOLLOWING ITEMS IN YOUR SUBMITTAL ACCORDING TO THE DATE 
AND TIME LISTED IN THE INVITATION TO BID ADVERTISEMENT: 
A. Bid Bond (Original – with Seal) 
B. Signed Proposal Acknowledgement, and licenses 
C. Bid Schedule 
D. Subcontractor’s List Form 
E. Non-Collusion Bidding Certification 
F. Certificate of Insurability and Bonding 
G. Arizona Department of Revenue Privilege Tax License 
BID SUBMITTAL LIST 
This list may not include all required bid submission items.  It is the Contractor’s 
responsibility to read the entire bid and determine all items required by the submission 
date and time.

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
Page i 
City Project No.: AI2302.401; ADOT No.: E3S4C 
Rev.10/23/23 
 
  
 
 
 
CITY OF CHANDLER, ARIZONA 
PUBLIC WORKS & UTILITIES DEPARTMENT 
CAPITAL PROJECTS DIVISION 
 
CONSTRUCTION AGREEMENT 
 
TAXIWAY B IMPROVEMENTS PHASE 1 
 
CITY PROJECT NO.: AI2302.401; ADOT No.: E3S4C 
 
 
MAYOR 
Kevin Hartke 
 
VICE MAYOR 
Christine Ellis  
 
COUNCIL 
OD Harris     Matt Orlando      
Angel Encinas     Jane Poston     Jennifer Hawkins 
 
 
 
__________________________________________________ 
Daniel Haskins, P.E. 
CIP City Engineer 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 1 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
CITY OF CHANDLER, ARIZONA 
 
TAXIWAY B IMPROVEMENTS PHASE 1 
 
CITY PROJECT NO.: AI2302.401; ADOT No.: E3S4C 
 
 
 
TABLE OF CONTENTS 
 
 
 PARTICIPANTS AND PROJECT .......................................................................... C-2 
 AGREEMENT DOCUMENTS .............................................................................. C-4 
 CONSTRUCTION SERVICES ............................................................................... C-4 
 CITY RESPONSIBILITIES .................................................................................... C-4 
 AGREEMENT TIME ............................................................................................ C-6 
 AGREEMENT PRICE ........................................................................................... C-7 
 PAYMENT .......................................................................................................... C-7 
 CHANGES TO THE AGREEMENT ....................................................................... C-7 
 SUSPENSION AND TERMINATION .................................................................. C-7 
 INSURANCE AND BONDS ............................................................................... C-7 
 INDEMNIFICATION ......................................................................................... C-8 
 DISPUTE RESOLUTION ................................................................................... C-8 
 FORCED LABOR OF ETHNIC UYGHURS PROHIBITED .................................. C-8 
 
EXHIBIT A – PROJECT SPECIFIC SPECIAL PROVISIONS ..................................................... SP-1 
EXHIBIT B – GENERAL CONDITIONS ................................................................................ GC-1 
EXHIBIT C – TECHNICAL SPECIFICATIONS ........................................................................ TS-1 
EXHIBIT D – GIS / GPS DATA DELIVERY REQUIREMENTS (IF APPLICABLE) ................... GIS-1 
EXHIBIT E – FEDERAL PROVISIONS (IF APPLICABLE) ....................................................... FP-1 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 2 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
CONSTRUCTION SERVICES AGREEMENT 
CITY PROJECT NO.: AI2302.401; ADOT No.: E3S4C 
 
This Agreement (“Agreement”) is made and entered into on the _______ day of ____________, 2025, 
by and between City of Chandler, an Arizona municipal corporation, hereinafter called “City” and 
Combs Construction Company, Inc. the “Contractor” designated below (City and Contractor may 
individually be referred to as “Party” and collectively referred to as “Parties”). 
 
City and Contractor agree as follows: 
 
 
 PARTICIPANTS AND PROJECT 
 
CITY:  
CIP City Engineer: Daniel Haskins, P.E. 
 
Public Works & Utilities Department 
 
P.O. Box 4008, Mail Stop 407   Chandler, AZ  85244-4008 
 
Phone:  480-782-3335     Email:    Daniel.haskins@chandleraz.gov 
 
CITY:  
Construction Project Manager: Raymond.Potts 
 
Public Works & Utilities Department 
 
P.O. Box 4008, Mail Stop 407   Chandler, AZ  85244-4008 
 
Phone:  480-782-3326     Email:    Raymond.Potts@chandleraz.gov 
 
 
Contractor: Legal Company Name:   
Combs Construction Company, Inc. 
 
Mailing Address:   
PO Box 10789 Glendale, AZ 85318 
 
Physical Address:   
1903 West Parkside Lane Suite 100 
Phoenix, AZ 85027 
 
Arizona Roc No.:   
100380 
 
Federal Tax Id No.:   
 
85-0744516 
 
State Where Organized:   
 
Arizona 
 
Business Organization:    
Corporation 
 
Statutory Agent Name:    
Ryan Combs 
 
Statutory Agent Mailing Address: 
PO Box 10789 Glendale, AZ 85318 
 
Statutory Agent Physical Address:   
1903 West Parkside Lane Suite 100 
Phoenix, AZ 85027 
 
Contractor’s Authorized Project Representative:   
 
Name: 
Ryan Combs 
 
Title: 
President 
 
Phone: 
602-920-9314 
 
Email: 
ryan@combsaz.com 
 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 3 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
PROJECT DESCRIPTION: 
 
The Taxiway B Improvements Phase I: Taxiway L to Taxiway N project includes a partial 
extension of the existing Taxiway B by approximately 1,300 feet. The project includes new 
taxiway and shoulder pavement, pavement markings, grading, lighting, and electrical 
improvements. The taxiway will be 40 feet wide, and the paved shoulders will be 10 feet 
wide, both to match existing. 
 
 
PROJECT LOCATION: 
 
Chandler Municipal Airport 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 4 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
 AGREEMENT DOCUMENTS 
 
2.1 
AGREEMENT DOCUMENTS 
 
The Agreement between City and Contractor will consist of the following Agreement 
Documents: 
 
1. This Construction Services Agreement and all of its Exhibits, including Project 
Plans and Technical Specifications. 
2. General Conditions and General Conditions Appendices, incorporated by 
reference. 
3. Project Specific Special Provisions as set forth in Exhibit A, incorporated by 
reference. 
4. Project Bid Proposal. 
 
2.2 
In the event of any inconsistency, conflict, or ambiguity between or among the 
Agreement Documents, the Agreement Documents will take precedence as described 
in Section 14.1.4 of the General Conditions. 
 
2.3 
DEFINITIONS 
 
The definitions in Section 2 of the General Conditions apply to all the Agreement 
Documents, including this Agreement. 
 
 CONSTRUCTION SERVICES 
 
3.1 
GENERAL 
 
3.1.1 
Scope of Work.  All terms and conditions are set forth in the Agreement. Any terms 
and conditions and exceptions noted in the Contractor’s proposal or other 
documents do not apply unless agreed to in this Agreement or an approved 
addendum. 
 
3.1.2 
Contractor agrees this is a Unit Price Agreement. Contractor agrees at its own cost and 
expense, to do all Work necessary required to fully, timely and properly complete 
the construction of the Project in strict accordance with the Agreement Documents 
in a good and workmanlike manner, free and clear of all claims, liens, and charges 
whatsoever, in the manner and under the conditions specified, within the Agreement 
time. 
 
3.1.3 
Contractor must provide all of the labor and materials, and perform the Work in 
accordance with Section 4 of the General Conditions. Some, but not all, of the major 
components of the Construction Services and the corresponding subsections of 
Section 4 of the General Conditions are set forth below. 
 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 5 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
3.1.4 
At all times relevant to this Agreement and performance of the Work, the Contactor 
must fully comply with all Laws, Regulations, or Legal Requirements applicable to City, 
the Project and the Agreement, 
including, without limitation, those set forth on 
attached Exhibit A. 
 
3.1.5 
Contractor must perform the Work under this Agreement using only those firms, 
team members and individuals designated by Contractor consistent with 
Contractor’s accepted Bid, or otherwise, approved by City pursuant to the General 
Conditions. No other entities or individuals may be used without the prior written 
approval of the Project Manager. 
 
3.1.6 
Contractor must comply with all terms and conditions of the General Conditions. 
 
3.1.7 
In the event of a conflict between this Agreement and the General Conditions or an 
exhibit hereto or appendix thereto, the terms of this Agreement will control. 
 
3.1.8 
Ownership of Work Product.  Notwithstanding anything to the contrary in this 
Agreement, all Work Product prepared or otherwise created in connection with the 
performance of this Agreement, including the Work, are to be and remain the 
property of City. For purposes of this provision, “Work Product” will include all designs, 
drawings, plans, specifications, ideas, renderings and other information or matter, in 
whatever form created (e.g., electronic or printed) and in all media now known or 
hereinafter created. All Work Product will be considered Work Made for Hire as 
defined in the United States Copyright Act 17 U.S.C. § 101 (Copyright Act). If for any 
reason, any such Work is found not to be a Work Made for Hire, Contractor hereby 
transfers and assigns ownership of the copyright in such Work to City. The rights in 
this Section are exclusive to City in perpetuity. 
 
3.2 
CONTRACTOR’S PRE-AGREEMENT AND PRE-WORK DELIVERABLES 
 
3.2.1 
The Contractor must provide the Deliverables in accordance with Section 4.2 of 
the General Conditions. 
 
3.3 
PRE-CONSTRUCTION CONFERENCE 
 
Contractor must attend the Pre-Construction Conference in accordance with Section 
4.3 of the General Conditions. 
 
3.4 
PERFORMANCE OF THE WORK (INCLUDING FIELD MEASUREMENTS, 
SUBCONTRACTORS, AND SUPPLIERS) 
 
Contractor must perform the Work in accordance with Section 4.4 of the General 
Conditions. 
 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 6 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
3.5 
CONTROL OF THE PROJECT SITE 
 
Contractor must control and maintain the Project Site in accordance with Section 4.5 
of the General Conditions. 
 
3.6 
PROJECT SAFETY 
 
Contractor must implement and enforce Project safety in accordance with Section 4.6 
of the General Conditions. 
 
3.7 
MATERIALS QUALITY, SUBSTITUTIONS AND SHOP DRAWINGS 
 
Contractor must provide materials testing and submit substitute materials and Shop 
Drawings in accordance with Section 4.7 of the General Conditions. 
 
3.8 
PROJECT RECORD DOCUMENTS 
 
Contractor must maintain and make available the Project Record Documents in 
accordance with Section 4.8 of the General Conditions. 
 
3.9 
WARRANTY AND CORRECTION OF DEFECTIVE WORK 
 
Contractor must provide warranties and correct defective Work in accordance with 
Section 4.9 of the General Conditions. 
 
 CITY RESPONSIBILITIES 
 
4.1 
City will have the responsibilities, and provide the information specified in, and 
subject to the conditions set forth in, Section 5 of the General Conditions. 
 
 
 AGREEMENT TIME 
 
5.1 
GENERAL 
 
5.1.1 
The total Agreement Duration is 90 Calendar Days (including Substantial Completion 
by 60 Calendars Days and Final Acceptance by 90 Calendar Days). 
 
5.1.2 
The Agreement Time will start with the Notice to Proceed (NTP) and end with 
Final Acceptance, as set forth in Article 5.4 below. 
 
5.1.3 
The Agreement Time will be as set forth in the Project Schedule. Contractor agrees 
that it will commence performance of the Work and complete the Project through 
Final Acceptance within the Agreement Time. 
 
5.1.4 
Time is of the essence of this Agreement for the Project, and for each phase and 
designated Milestone thereof. 
 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 7 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
5.1.5 
Failure on the part of Contractor to adhere to the approved Project Schedule will 
be deemed a 
material breach and sufficient grounds for termination of this 
Agreement by City. 
 
5.2 
PROJECT SCHEDULE 
 
5.2.1 
The Project Schedule will be updated and maintained throughout Contractor’s 
performance under this Agreement in accordance with Section 6.2 of the General 
Conditions. 
 
5.2.2 
Work must be completed to meet the following milestones after the Notice to 
Proceed: 
 
 
Milestone 
 
Time 
Liquidated damages for delay 
1. 
      
within      days 
$      
per calendar day 
 
5.3 
SUBSTANTIAL COMPLETION 
 
Substantial Completion must be achieved no later than the Substantial Completion 
Date set forth in the Project Schedule.  Substantial Completion will be determined in 
accordance with Section 6.3 of the General Conditions. 
 
5.4 
FINAL ACCEPTANCE 
 
5.4.1 
Final Acceptance will be obtained within the time period set forth in the Project 
Schedule. 
 
5.4.2 
Final Acceptance will be issued pursuant to Section 6.5 of the General Conditions. 
 
5.5 
LIQUIDATED DAMAGES 
 
5.5.1 
Substantial Completion Liquidated Damages. Contractor acknowledges and agrees 
that if Contractor fails to obtain Substantial Completion of the Work within the 
Agreement Time, City will sustain extensive damages and serious loss as a result of 
such failure. The exact amount of such damages will be extremely difficult to 
ascertain. Therefore, City and Contractor agree that if Contractor fails to achieve 
Substantial Completion of the Work within the Agreement Time, City will be entitled 
to retain or recover from Contractor, as liquidated damages and not as a penalty, 
the sum per calendar day as indicated in MAG § 108.9. 
 
5.5.2 
Final Acceptance Liquidated Damages. For the same reasons set forth in Article 5.5.1 
above, City and Contractor further agree that if Contractor fails to achieve Final 
Acceptance of the Work within the Agreement Time, City will be entitled to retain or 
recover from Contractor, as liquidated damages and not as a penalty, the sum per 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 8 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
calendar day as indicated in MAG § 108.9 commencing from the actual date of 
Substantial Completion or Final Acceptance as required under the Agreement. 
 
5.5.3 
MAG Liquidated Damages. Liquidated damages provisions in MAG § 108.9 will apply. 
 
5.5.4 
City may deduct liquidated damages described in this Article 5.5 from any unpaid 
amounts then or thereafter due Contractor under this Agreement. Any liquidated 
damages not so deducted from any unpaid amounts due Contractor will be payable 
to City at the demand of City, together with interest from the date of the demand at 
the highest lawful rate of interest payable by Contractor. 
 
5.6 
MUTUAL WAIVER OF CONSEQUENTIAL DAMAGES ONLY 
 
5.6.1 
Contractor and City waive claims against each other for consequential damages 
arising out of or relating to this Agreement. This mutual waiver includes. 
 
1. Damages incurred by City for rental expenses, for losses of use, income, profit, 
financing, business and reputation, and for loss of management or employee 
productivity or of the services of such persons; and 
 
2. Damages incurred by Contractor for principal office expenses including the 
compensation of personnel stationed there, for losses of financing, business and 
reputation, and for loss of profit except anticipated profit arising directly from the 
Work. 
 
5.6.2 
This mutual waiver is applicable, without limitation, to all consequential damages 
due to either party’s termination of this Agreement. Nothing contained in this 
Article 5 .6 will be deemed to preclude an award of liquidated damages, when 
applicable, in accordance with Article 5.5 above. 
 
5.6.3 
Nothing herein will be deemed to constitute a waiver of any other remedy available 
to City in the event of Contractor’s default under this Agreement prior to full 
performance of the Work including, as 
applicable, specific performance or 
completion of the Work on behalf of Contractor, the cost and expense of which will 
be offset against any monies then or thereafter due to Contractor (if any) and 
otherwise immediately reimbursed to City by Contractor. 
 
 AGREEMENT PRICE 
 
6.1 
AGREEMENT PRICE 
 
6.1.1 
In exchange for Contractor’s full, timely, and acceptable performances and 
construction of the Work under this Agreement, and subject to all of the terms of 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 9 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
this Agreement, City will pay Contractor the 
“Agreement Price,” which is 
$1,236,949.70. 
 
6.1.2 
The Agreement Price is all-inclusive and specifically includes all fees, cost, insurance 
and bond premiums, and taxes of any type necessary to fully, properly and timely 
perform and construct Work. 
 
6.2 
CHANGES TO AGREEMENT PRICE 
Shall be determined under Section 9 of the General Conditions. 
 
 PAYMENT 
Payments will be made to Contractor in accordance with Section 8 of the General Conditions. 
 
 CHANGES TO THE AGREEMENT 
Changes to the Agreement may be made in strict accordance with Section 9 of the 
General Conditions. 
 
 SUSPENSION AND TERMINATION 
This Agreement may be suspended or terminated in accordance with Section 10 of the 
General Conditions. 
 
 INSURANCE AND BONDS 
 
10.1 
Contractor must provide insurance in accordance with Sections 11.1 through 11.3 
of the General Conditions. Contractor must provide proof of such insurance and all 
required endorsements in forms acceptable to City prior to commencing any Work 
under this Agreement. 
 
10.2 
Contractor must provide performance and payment bonds to City in Accordance with 
Section 11.4 of the General Conditions and A.R.S. § 34-222. 
 
10.3 
Failure to provide proof of insurance and the required endorsements, or the 
required bonds, in forms acceptable to City, will be a material breach and grounds 
for termination for cause of this Agreement. 
 
 INDEMNIFICATION 
Contractor must have and assume the indemnity obligations set forth in Section 12 of the 
General Conditions. 
 
 
 
 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 10 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
 DISPUTE RESOLUTION 
Any claims or disputes relating to this Agreement will be resolved according to the dispute 
resolution process set forth in Section 13 of, and Appendix 6 to, the General Conditions. 
 
 FORCED LABOR OF ETHNIC UYGHURS PROHIBITED  By entering into this 
Agreement, Contractor certifies and agrees Contractor does not currently use and will not 
use for the term of this Agreement: (i) the forced labor of ethnic Uyghurs in the People's 
Republic of China; or (ii) any goods or services produced by the forced labor of ethnic 
Uyghurs in the People's Republic of China; or (iii) any contractors, subcontractors or suppliers 
that use the forced labor or any goods or services produced by the forced labor of ethnic 
Uyghurs in the People's Republic of China. 
 
 
 
SIGNATURE PAGE TO FOLLOW 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44

Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 Page 11
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev 10/23/23 
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement through their duly 
authorized representatives and bind their respective entitles as of the effective date. 
“CITY”  
CITY OF CHANDLER 
Mayor 
RECOMMENDED BY: 
Daniel Haskins, P.E. 
CIP City Engineer   
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
     City Clerk  
  Seal 
“CONTRACTOR” 
COMBS CONSTRUCTION COMPANY, INC. 
Signature  
  Date 
Print Name 
Title 
Signer Email Address 
Docusign Envelope ID: 16EAF312-F98A-4CC5-B7C2-BB4D0C9EFD44
Ryan  Combs
ryan@combsaz.com
President
May 2, 2025
May 5, 2025

EXHIBIT A
 
Project Name: TAXIWAY B IMPROVEMENTS PHASE 1  
 
A-1 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev. 10/23/23 
PROJECT SPECIFIC 
SPECIAL PROVISIONS 
 
 
4.2.7 Aerial Construction Photography 
General Conditions Section 4 Subsections 4.2.7.1 & 4.2.7.2 are not applicable to this project. 
 
4.2.8 Government Approvals and Permits 
General Conditions Section 4 Subsection 4.2.8.1, City permit fees will be paid internally by the 
City and all other fees will be the responsibility of the Contractor. 
 
Subletting of Agreement 
Contractor must perform, with his own organization, work amounting to not less than 50 percent 
of the total Agreement cost. 
 
-performance not less than 50 
percent of the total Agreement cost, will cause the bid to be deemed non-responsive.  
 
Bidders should contact the Arizona Registrar of Contractors for information on license 
requirements.

EXHIBIT B
 
Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 
B-1 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev. 10/23/23 
GENERAL CONDITIONS

GENERAL CONDITIONS
Approved date: July 20, 2022

Revised: 7/20/2022
GC-2 of 75
TABLE OF CONTENTS
SECTION 1 - SCOPE OF THESE GENERAL CONDITIONS............................................................................... 3
SECTION 2 - GENERAL DEFINITIONS ............................................................................................................ 3
SECTION 3 - STANDARD SPECIFICATIONS AND DETAILS........................................................................... 7
SECTION 4 - CONTRACT
RESPONSIBILITIES FOR CONSTRUCTION SERVICES .................................. 8
SECTION 5 - CITY RESPONSIBILITIES ..........................................................................................................27
SECTION 6 - AGREEMENT TIME ...................................................................................................................29
SECTION 7 - AGREEMENT PRICE..................................................................................................................35
SECTION 8 - PAYMENT .................................................................................................................................35
SECTION 9 - CHANGES TO THE AGREEMENT .............................................................................................40
SECTION 10 - SUSPENSION AND TERMINATION ......................................................................................43
SECTION 11 - INSURANCE AND BONDS.....................................................................................................44
SECTION 12 - INDEMNIFICATION ............................................................................................................... 49
SECTION 13 - DISPUTE RESOLUTION..........................................................................................................49
SECTION 14 - MISCELLANEOUS PROVISIONS............................................................................................50
SECTION 15 - PROVISIONS APPLICABLE SOLELY TO GMP AND COST-BASED AGREEMENTS, CHANGE
ORDERS, AND JOB ORDERS .........................................................................................................................57
SECTION 16 - PROVISIONS APPLICABLE SOLELY TO JOB ORDER AGREEMENTS (JOC) ........................ 61
SECTION 17 - PROVISIONS APPLICABLE SOLELY TO PRE-CONSTRUCTION SERVICES FOR 
CONSTRUCTION MANAGER AT RISK..........................................................................................................66
SECTION 18 - APPENDICES ......................................................................................................APP-1 of 30
Appendix 1
Policy Statement for Calculating Delays and Damages
Appendix 2
Cost Reduction Incentive Proposals for Design Bid Build Agreements
Appendix 3
Affidavit Regarding Settlement of Claims
Appendix 4
Forms of Performance Bond
Appendix 5
Forms of Payment Bond
Appendix 6
Dispute Resolution
Appendix 7 Certificate of Completion
Appendix 8 Construction Sign Detail
Appendix 9 Cost of the Work (Applicable solely to Construction Manager at Risk and 
Job Order Contracting)
Appendix 10 Landscape Establishment Period

General Conditions
Revised: 7/20/22
GC-3 of 75
SECTION 1 - SCOPE OF THESE GENERAL CONDITIONS
These
General
Conditions
encompass
provisions
that
apply,
and
are
incorporated
into all 
construction Agreements entered into by the City of Chandler, unless otherwise specifically excluded in
the executed Agreement.
SECTION 2 - GENERAL DEFINITIONS
Allowance :  A specific amount for a specific item of Work, if any, that City agrees has not been sufficiently
designed, detailed, or selected (including design changes from 90% to 100% as authorized by and at
the discretion of theCity)atthetimetheAgreementPrice isagreed tofor Contractortoprovide adefinitive
price.
Alternate Systems Evaluations or Alternative Analysis:  Alternatives for design, means and methods or
other scope considerations that are evaluated using value analysis principles and have the potential to
reduce construction costs while still delivering a quality and
functional Project that meets City
requirements.
Change Order:  A written instrument issued after execution of the Agreement Documents signed by
City and Contractor, stating their agreement upon all of the following: the addition, deletion or revision
in the scope of services or deliverables; the amount of the adjustment to the Agreement Price, the
extent of the adjustment to the Agreement Time, or modifications of other agreement terms. The
Agreement Price and the Agreement Time may be changed only by Change Order.
Consultant:  Person or firm that provides professional services.
City (Owner or OWNER):  City of Chandler, a municipal corporation, with whom Contractor has entered
into the Agreement and for whom the Work or Services are to be provided pursuant to the Agreement(s).
Contingent Bid Items:  This is a minor bid item which is likely, but not certain, to occur during the course
of work. If the Engineer determines that this work is required, the Contractor will accomplish the work
and payment will be made based on the contingent unit bid price included in the proposal. Since the
quantity listed in the proposal is primarily for bid comparison, the amount of work required by the
Engineer may vary materially from this.
Agreement:  The written agreement executed between City and Contractor, including all of the Agreement
Documents.
Agreement Documents:  The documents which together form the Agreement between City and
Contractor, as identified in Article 2 of
the Agreement, or are otherwise incorporated into the
Agreement, including the Agreement, the exhibits thereto, these General Conditions, any Notice to
Proceed, and any Job Order (if applicable), the Plans and Specifications, Project Schedule, written
and properly executed Change Orders, MAG Specifications and
amendments thereto, and any
other documents so designated in the Agreement.
Agreement Price:  The agreed-upon price to be paid to Contractor for full, timely, and acceptable 
completion of the Work or Services under the terms of the Agreement.
Agreement Time(s):  The number of calendar days or the dates related to the applicable phase,
Substantial Completion, or Final Acceptance as stated in Agreement Documents. Agreement Time starts

General Conditions
Revised: 7/20/22
GC-4 of 75
with the Notice to Proceed (NTP) and ends with Final Acceptance. The Agreement Time is set forth in
the Agreement and is based upon the Project Schedule agreed to by City in writing.
Contractor:  The person or business association with whom City has entered into an agreement for
construction related Work or Services in relation to the Project at issue.
Contractor Payment Request:  The form that is accepted by City and used by Contractor in requesting
progress payments or final payment
and which must include such supporting documentation as is
required by the Agreement Documents or City.
Construction Budget:  The
budget for construction of the Project.
Construction Documents:  The Plans, Specifications, and Drawings prepared and issued by the Design
Professional and approved by City for construction, meaning the documents are sealed by the
Design Professional (as required), acceptable for permitting and incorporated into the Agreement by
this reference. All amendments and modifications to the Construction Documents must be approved in
writing by City prior to incorporation into the Agreement.
Cost of the Work:  The term Cost of the Work will mean costs necessarily incurred by Contractor in the 
proper performance of the Work. Such costs will be at rates not higher than the standard paid at the
place of the Project except with prior consent of City.
Critical Path Method (CPM):  A scheduling technique which identifies the logical sequence of the activities
occurring in a Construction Project, the anticipated time required to complete each activity in the
Project, and the activities that must be completed on schedule to finish the Project within the anticipated
time. Typically, activities are arranged in a network that shows both activities and their dependencies.
CPM is also used as a management
technique which enables contracting parties to predict when
activities may occur so that resources can be effectively used and limitations can be identified.
Critical Path:  Critical Path is the sequence of project network activities which add up to the longest overall
duration. Once established in the Project Schedule, the Critical Path for the Project must not be
changed without prior written approval of City.
Day:  Calendar day(s) unless otherwise specifically stated in the Agreement Documents.
Design Professional:  The qualified, licensed person, firm or corporation who furnishes design and
construction administration services required under the Agreement Documents. These services may
include, but are not limited to: development of Construction Drawings and Documents, review of
Contractor Submittal(s), review of and
response
to
Requests for Information, approval and
certification of progress payment
applications,
construction administration, and construction
agreement close out.
Differing Site Conditions:  Concealed or latent physical conditions or subsurface conditions at the Site
that, (i) materially differ from
the conditions indicated in the Agreement Documents, or (ii) are of an
unusual nature, differing materiallyfrom the conditions ordinarily encountered and generally recognized
as inherent in the Work at the general area of the Site. Caliche, rock, hard-digging or sandy/silty soil
encountered on a project is not considered a
Site
Drawings (Plans):  Documents, which visually represent the scope, extent and character of the Work to
be furnished and performed by Contractor during the construction phase and which have been prepared

General Conditions
Revised: 7/20/22
GC-5 of 75
or approved by the Design Professional and City.  These documents include Drawings that have reached
a sufficient state of completion and released by Design Professional solely for the purposes of review
and use in performing constructability or bid-ability reviews by Contractor and in preparing cost
estimates (e.g. Master Planning and Programming, Schematic Design, Design Development, and
Construction Drawings), but
for construction
Shop Drawings are not Drawings as so defined.
Final Acceptance:  The
acceptance of the facility or project from the Contractor after all Work is
completed, tested, and inspected in accordance with the Agreement requirements. Final Acceptance
results in a Letter of Acceptance (LOA).
Fixed Price:  A fixed price or amount for an Agreement Price, Scope of Work, materials, or other item
under an Agreement, Change Order, or other agreement, which City agrees, in writing, to pay instead
of the actual cost.
Float:  The number of Days by which an activity can be delayed without lengthening the Critical Path and
extending the Agreement Time. Unless otherwise expressly agreed in writing, all Float belongs to City.
Laws, Regulations, or Legal Requirements:  Any and all applicable laws, rules, regulations, ordinances,
codes and orders applicable to the Project of any and all governmental bodies, agencies, authorities
and courts having jurisdiction and any applicable provisions of the Development Agreement for the
Project (if any), including, without limitation, those provisions relating to the design and construction
of the Project.
Line Item:  The individual elements of Work identified on a bid or other schedule and associated with a
price or a unit
price and quantity particular to that individual element of the Work.
Also refers to
individual items of work within the Schedule of Values.
Liquidated Damages:  Designated damages for the City to collect as compensation upon a specific breach
(example: late delivery).
Long-Lead Item:  Long-lead item refers to the equipment, product, or system that is identified at the
earliest stage of a project to have a delivery time long enough to affect directly the Critical Path/the overall
lead time of the project.
MAG:  The Maricopa Association of Governments.
MAG Specifications:  The most current version of the Uniform Standard Specifications for Public Works
Construction published by MAG.
MAG Standard Details:  The most current version of the Uniform Standard Details as published by MAG.
Minor change:  A change in the Work having no impact on cost or time or the City-approved design intent,
as determined by City.
Notice to Proceed (NTP):  A written notice given by City to Contractor fixing the date on which
Contractor will start to perform
obligations under the Agreement.
Project:  The Project specified in the Agreement (including a Job Order).
Project Manager:  The Project Manager designated in Article 1 of the Agreement, or any successor thereto

General Conditions
Revised: 7/20/22
GC-6 of 75
designated by City. The Project Manager has the authority to act on behalf of City, as delineated and
limited by the Agreement Documents and applicable law. And City will communicate with Contractor
through the Project Manager.
However, the Project Manager has no authority to bind City or City
Council in contravention of any City code, State or Federal statute or regulation, or these General
Conditions.
Project Schedule:  The schedule for the completion of the Project agreed to and required by City.
Project Specific Conditions:  Additional conditions which apply to the specific Project and Scope of Work
which are set forth in Exhibit D of the Agreement.
Project Team:  The Project Team consisting of the Design Professional, Contractor, Project Manager, and
such others as City may designate.
Punch List:  The list initially prepared by Contractor pursuant to the Agreement Documents, reviewed 
and supplemented by the Project Manager (and at the sole option of the Project Manager, the Design
Professional) and
approved by City containing items of incomplete work not impacting Substantial
Completion, if allowed for under the Agreement, and to be completed or corrected by Contractor after
Substantial Completion and before Final Acceptance in accordance with the Agreement Documents.
Quality Assurance (QA) Testing:  Testing performed to verify the accuracy and applicability of the QC
testing results and to ascertain that the
materials installed meet the specified levels of quality in
accordance with the Agreement Documents.
Quality Control (QC) Testing:  Testing performed to assure that the materials installed comply with the
requirements in the Agreement Documents.
Requests for Information (RFIs):  Formal written request from Contractor to City or Design Professional
for the Project
seeking
clarification or additional information needed for Contractor to properly
complete the Work or Services under the Agreement. City may require
to be submitted on a specific
form or in a specified format.
Schedule of Values (SOV):  The specified document prepared by Contractor, and approved and accepted
by City, which divides the Agreement Price into pay items, such that the sum of all pay items equals
the Agreement Price for the construction phase Work, or for any portion of the Work having a separate
specified Agreement Price.
Scope of Work:  The scope of work agreed to or required by City and incorporated into the Agreement as
Exhibit A.
Shop Drawings:  All drawings, diagrams, schedules and other data specifically prepared for the Work
by Contractor or a
Subcontractor, Sub-subcontractor, manufacturer, supplier or distributor to
illustrate some portion of the Work.
Site:  The land or premises on which the Project is located.
Specifications:  The part(s) of the Agreement Documents for the construction phase consisting of written
technical descriptions of materials, equipment, construction systems, standards and workmanship as
applied to the Work and certain administrative details applicable thereto. Where specified, the Project
must be constructed using the current Uniform Standard Specifications and Details for Public Works

General Conditions
Revised: 7/20/22
GC-7 of 75
Construction as furnished by the Maricopa Association of Governments, as amended by City.
Subconsultant:  A person, firm or corporation having an Agreement with Consultant/Contractor to
furnish services required as its independent professional associate or consultant with respect to the
Project.
Subcontractor:  An individual or firm having a direct Agreement with Contractor or any other individual or
firm having an Agreement with the aforesaid contractors at any tier, who undertakes to perform a part
of pre-construction services or construction phase Work at the Site for which Contractor is responsible.
Subcontractors must be selected
through the Subcontractor selection process described in the
Agreement Documents, if any.
Substantial Completion:  The date when the City determines that the Work (or separable units of Phases
as provided in the Agreement Documents) is essentially and satisfactorily complete in accordance with
the Agreement Documents such that
the Project is ready for use by the City for its intended purpose,
opening to the general public,full occupancy or use by City (including, without limitation, all separate
units, or rooms, facilities, access, income-generating areas, and all areas serving the general public, as
applicable, must be ready for full operation without material inconvenience or discomfort), including, to
the extent applicable to the Work, the following: all materials, equipment, systems, controls, features,
facilities, accessories, and similar elements are
installed in the proper manner and in operating
condition, inspected, and approved; surfaces have been painted; masonry and concrete cleaned with
any sealer or other finish applied; utilities and systems
connected and functioning; site work
complete; permanent heating, ventilation, air conditioning, vertical transportation, and other systems
properly operating with proper controls; lighting and electrical systems
installed, operable and
controlled; paving completed, signage installed, and other work as applicable, has been performed to
a similar state of essential and satisfactory completion.
Supplier:  A manufacturer, fabricator, distributor, or vendor having a direct Agreement with Contractor
or with any Subcontractor to furnish materials or equipment to be incorporated in the construction
phase Work by Contractor or any Subcontractor.
Total Float:  Number of Days by which pre-construction services or construction phase Work or any part
of the same may be delayed without necessarily extending a pertinent Agreement Time or schedule
milestone in the Project Schedule.
Work:  The entire completion of construction or the various separately identifiable parts thereof,
required to be furnished during the construction phase. Work includes and is the result of performing
or furnishing labor
and furnishing and incorporating materials, resources and equipment into the
construction, and performing
or furnishing services and documents as required by the Agreement
Documents for the construction phase.
Writing:  Typing, printing, photography and other modes of representing or reproducing words in a
visible form, including email, and expressions.
SECTION 3 - STANDARD SPECIFICATIONS AND DETAILS
3.1
City operates under the latest revision of the MAG Specifications and MAG Standard 
Details as amended by City.
current amendment to the MAG Specifications, part of 
Unified Development Manual, may be found and downloaded from
website
at http://www.chandleraz.gov.

General Conditions
Revised: 7/20/22
GC-8 of 75
3.2
Copies of the MAG Specifications and MAG Standard Details are available at the
Maricopa Association of Governments office, 302 N. 1st Avenue, Suite 300, Phoenix,
Arizona. 
 
They
may
also
be
downloaded
from 
their
website
at:
http://www.azmag.gov/Newsroom/Publications
3.3
The MAG Specifications and Standard Details and
amendments thereto are
incorporated into the Agreement by this reference.
SECTION 4 - CONTRACT
RESPONSIBILITIES FOR CONSTRUCTION SERVICES
4.1
GENERAL
4.1.1
Contractor must construct the Work in accordance with the Agreement Documents and as 
outlined in Exhibit A of the Agreement to the satisfaction of City, exercising the degree of 
professional care, skill, diligence, quality and judgment that a professional construction 
manager engaged, experienced and specializing in the construction management of 
construction and facilities of similar scope, function, size, quality, complexity and detail in 
urban areas throughout the United States comparable to Chandler, Arizona would exercise 
at such time, under similar conditions. Contractor must, at all times, perform the Work in 
conformance with sound and generally accepted engineering principles and construction 
management and construction contracting practices.
4.1.2
If Contractor observes errors, discrepancies or omissions in the Agreement Documents,
Contractor must promptly notify the Design Professional and City and request clarification.
If Contractor, with the exercise of reasonable care, should have recognized such error,
inconsistency, omission, or
difference and fails to report it to City, and if Contractor
proceeds with the Work affected by such
observed errors, discrepancies or omissions,
without receiving such clarifications, Contractor does so at its own risk and will be liable to
City for damages resulting from proceeding without clarification.
4.1.3
Project Team and agents of each of them, testing agencies and governmental agencies with 
jurisdictional interests will be provided access to the Work at reasonable times for their 
observation, inspection, and testing.  Contractor must provide proper and safe conditions 
for such access.
4.1.4
Contractor must comply with, and require all Subcontractors to comply with, the Arizona
license laws, including all requirements with respect to being duly registered
and licensed.
4.1.5
Contractor must ensure that all employees performing any Work for which Contractor is
responsible
have a legal right to live and work in the United States.
In addition, all
compensation of any such employee must meet all applicablerequirementsoftheFairLabor
Standards Act (FLSA) and Federal Minimum Wage laws.
4.1.6
Contractor must comply with the Immigration Reform and Control Act of 1986 (IRCA).  
Contractor understands and acknowledges the applicability of the IRCA activities.  
Contractor agrees to comply with the IRCA while performing their work and to permit City 
inspection of Contractor personnel records to verify such compliance.
4.1.7
Pursuant to MAG Specifications §§ 107.4, Contractor must report immediately any discovery 
of archeological ruins or artifacts.  Excavation must stop immediately so that City can decide 
on the pertinent steps to follow such discovery.

General Conditions
Revised: 7/20/22
GC-9 of 75
4.1.8
All property owners that may be affected by the proposed construction activities must be 
notified of the scope, duration of the construction activities and possible interference with 
their day-to-day activities by Contractor prior to start of construction.  In addition, individual 
residential or commercial interferences, such as driveway restrictions, water outages, and 
all other Work adjacent to residence/business, require 48-hour notification in advance of 
specific adjoining Work.  Notification may be through door hangers or other procedures 
approved by the City.
4.1.9
Access must be maintained to adjacent properties at all times during construction. Where 
property has more than one point of access, no more than one access will be restricted or 
closed at any one time. Access to adjacent private driveways will be maintained during all 
non-working hours.
4.1.10
Contractor must furnish and erect construction signs in accordance with Project 
Specifications. The signs must be professionally prepared and subject to approval by City, 
must be maintained by Contractor for the duration of the project, and must be removed by 
Contractor during the final project clean up. 
4.1.11
The number of signs required, the size, shape, installation requirements and information to 
be included for construction signs is established on the detail sheet, provided, however, 
signs must be a minimum of 4 foot by 8 foot and must be installed so that the bottom of 
the sign is at least 4 foot above grade.  No direct payment will be made for furnishing and 
erecting construction signs. The cost thereof must be included in other items for which 
direct payment is made. Sign locations will be determined by City.
4.1.12
All required construction signs must be installed by Contractor within 7 Days of Notice to 
Proceed.  
4.1.13
The Work to be accomplished under these Agreement Documents has been designed for 
City by a Design Professional retained by City for this purpose.  It is understood that normal 
construction Administration for the purpose of interpretation of the Agreement Documents 
is provided by City. Should any services of the Design Professional be required to assist in 
the corrections of errors or omissions by Contractor, or services of the Design Professional 
be required because of changes in structure or equipment where Contractor has requested 
approval of substitute methods or material, or any other items detailed herein below, those 
services will be provided by the Design Professional at the standard hourly rates previously 
negotiated with City and must be paid for by the Contractor.
4.1.14
Contractor must reimburse City for costs incurred by the Design Professional for additional 
services to the Project through no fault of City or the Design Professional including, but not 
limited to, the following conditions:
a.
Additional Site visits, investigations, inspections, design work or reports by 
the Design Professional which are required due to damages to existing 
facilities or completed Work caused by the Contractor in his performance, 
C
negligence, or C
Work which is rejected as defective 
or as failing to conform to the Agreement Documents;
b.
Design Professional construction phase services rendered on the project 
during the time the project remains incomplete after the Agreement date of 
final completion will be charged to Contractor at a rate previously negotiated 
City; and

General Conditions
Revised: 7/20/22
GC-10 of 75
c.
All retesting required due to the failure of C
Work to meet the 
requirements of the Agreement Documents will be at 
expense.  
All standby and travel time by the C
testing lab, the Design Professional 
or City due to C
inability to be prepared for testing at the agreed 
upon time will be at the C
expense.
4.1.15
City may withhold from any payment otherwise due to Contractor any amounts necessary 
to pay the Design Professional for such additional services as provided herein above.  
4.1.16
Contractor will not be required to bear additional costs incurred by City due to errors by the 
Design Professional.
4.2
-AGREEMENT AND PRE-WORK DELIVERABLES
4.2.1
Prior to award of the Agreement, Contractor must execute Agreement and deliver to City.  
Failure to do so may delay Agreement award.  Contractor must als o provide to City its
License classification and number and its Federal Tax I.D. number.
4.2.2
Before beginning any Work under the Agreement, Agreement must be fully executed by
City.
4.2.3
After Agreement award, City will issue to Contractor an award letter.  At that time Contractor
must deliver to City such bonds and certificates of insurance with endorsements in such
amounts (and other evidence of insurance requested by City) required under Section 11 of 
these General Conditions, and as the Agreement requires.
4.2.4
As evidence of
Compensation Insurance, Contractor must, upon request, 
provide a letter of certification from the Industrial Commission of Arizona that Contractor
is insured by the State Compensation Fund or is an authorized self-insurer or a certificate
of insurance issued by an insurance company authorized by the Insurance Department
of Arizona to write
Compensation and Occupational Disease Insurance in the
State of Arizona.
4.2.5
Within 10 Days of the date of the executed Agreement letter issued by City, Contractor must
submit to City for review and acceptance the following items:
4.2.5.1
Comprehensive construction Project Schedule including a Critical Path
Method (CPM)
diagram schedule as described in Section 6.2.  Project Schedule must be in Microsoft Project 
standard file format.  
all required corrections, adjustments, and additions to complete the Project Schedule and 
resubmit to City for review.  
4.2.5.2
Preliminary schedule of submittals and Shop Drawings.  Within 10 Days of
comments, Contractor must submit the corrected and completed schedule of Shop 
Drawings submissions for approval
sample 
submittals will be acceptable to City if it provides a workable arrangement for reviewing and 
processing the required submittals.  
4.2.5.3
Schedule of Values in a form specified by City reflecting the subcontracts and other
categories that will be used to submit Pay Applications for the Work. The total amount of
the Schedule of Values must not be greater than the Agreement Price. The Schedule of
Values will be reviewed at the Pre-Construction Conference and revised by Contractor within 
10 Days after Pre-Construction Conference in response to comments and questions from

General Conditions
Revised: 7/20/22
GC-11 of 75
City.
Once accepted by City in writing, the Schedule of Values for the Project must not be
changed without the prior written approval of City.
4.2.6
Video Recording Requirement. Prior to performing any Work, Contractor must document
the existing conditions of the Site, all other areas where Work will occur and all adjacent
areas that may be impacted by the Work via digital video format. Contractor must video
record and index all areas, features, buildings and other public and private improvements 
that could potentially be impacted by the Work.  Video recording must be coordinated with
City.  When video recording private property, Contractor must also coordinate the video
recording with the private property owner, if possible. Contractor must provide City with a 
copy of said digital video format prior to performing any Work.
4.2.7
Aerial Drone Construction Photography.
4.2.7.1
If Agreement duration is greater than 90 calendar days, Contractor must engage a 
professional unmanned aerial vehicle (UAV) aerial pilot to photograph the Site prior to 
construction mobilization, at three-month intervals during construction, and following final 
inspection.  Drone camera specifications must meet the following minimum requirements: 
a.
1-inch CMOS
b.
Pixels: 20M
c.
FOV 84 8.8 mm/24 mm (35 mm format equivalent) f/2.8-f/11 auto focus at 1 m-  
d.
For photographing: 16.9 Aspect Ratio: 5472x3078
e.
For video shooting: MP4/MOV/H.264
f.
FHD: 1920x1080 120p @100Mbps
g.
File format: High Definition (HD) JPEG for digital photos and HD MPEG 4 for 
digital video.
h.
All metadata to be recorded including GPS data and preserved with photographs 
provided.  
Interval
JPEG
3 month intervals
At an altitude (AGL) between 
70-90 ft.
3 month intervals
Images to be taken every 50-
100 ft. to be determined based 
on project scope.
4.2.7.2
Drone photos to be taken in sequential geographical order and then organized and provided in 
the same manner unless otherwise specified.
4.2.7.3
Photos to be provided digitally via an online file share service and/or by a USB drive to contractor.
4.2.7.4
Drone pilots to obey ALL local (city, county, state) UAV regulations as well as FAA UAV 
guidelines including, but not limited to, conducting all flights during daylight hours, not exceeding 
maximum altitude ceilings (depending on area), not flying over people, yielding to other aircraft.
4.2.7.5
Drone pilots must fly drone within visual line of sight (VSOL) and have visual spotter when 
needed. Drone pilots only to operate in favorable weather conditions when minimum visibility is 
3 miles or greater.
4.2.7.6
Drone pilots to conduct a preflight checklist and visually inspect the entire flight path prior to flying 
to ensure a safe flight.

General Conditions
Revised: 7/20/22
GC-12 of 75
4.2.7.7
Airspace Authorizations. Operations in Class G airspace are allowed without air traffic control 
(ATC) permission. Operations in Class B, C, D and E airspace need ATC authorization. Drone 
pilots to schedule each flight in advance and based on airspace if required will notify nearby 
airports/control towers, etc.
4.2.8
Government Approvals and Permits.
4.2.8.1
Contractor must obtain all necessary permits for the Work and pay all applicable fees,
unless otherwise noted on the Plans and in the Specifications. City permit fees will be paid 
internally by City. For bidding purposes, an allowance for all permit fees is included in the
bid schedule under the item
for permit
The Contractor will be paid for
the actual cost of the permit fees upon submitting a receipt showing the fee Contractor
has paid. Excluded from the above allowance are items such as all costs incurred by the
Contractor in securing the permit except for the actual permit fee established by the
agency, cost for all shutdowns or outages, cost for pole bracing, cost of permits for
construction water, cost of construction water, cost for any additional insurance
requirements, cost for any licenses, and other similar type costs. Contractor is specifically
notified of the need to obtain the necessary environmental permits or file the necessary
environmental and regulatory permit notices.
4.2.8.2
Copies of all permits and the associated notices must be provided to City prior to starting
the permitted activity.
4.3
PRE-CONSTRUCTIONCONFERENCE
4.3.1
Prior to the commencement of any Work, City will schedule a Pre-Construction Conference.
4.3.2
The purpose of this Conference is to establish a working relationship between Contractor,
the utility firms, and various City agencies. The agenda will include critical elements of the 
Work schedule, submittal schedule, cost breakdown of major lump sum items, Payment 
Requests and processing, coordination with the involved utility firms, and emergency 
telephone numbers for all representatives involved in the course of construction.
4.3.3
Minimum attendance by Contractor at any mandatory meeting with City must be (1)
Representative, who is authorized to execute and sign documents on behalf
of the firm, (2)
on-site Superintendent, and (3)
Safety Office,
or other employee responsible for safety.
4.4
PERFORMANCE OF THE WORK (INCLUDING FIELD MEASUREMENTS, 
SUBCONTRACTORS, AND SUPPLIERS)
4.4.1
Unless otherwise provided in the Agreement Documents to be the responsibility of City or a
separate
Contractor, Contractor must provide through itself or Subcontractors the
necessary supervision, labor, inspection, testing, start-up, material, equipment, machinery,
temporary utilities and other temporary facilities to permit Contractor to complete the
Work consistent with the Agreement Documents.
4.4.2
Contractor must perform all construction activities efficiently and with the requisite 
expertise, skill and competence to satisfy the requirements of the Agreement Documents. 
Contractor must at all times exercise complete and exclusive control over the means, 
methods, safety, sequences and techniques of construction.
4.4.3
must be present at the Site at all times that material Work

General Conditions
Revised: 7/20/22
GC-13 of 75
under this Agreement
must be 
present at the Site at all times any other Work under this Agreement is taking place.  
Superintendent must not be replaced without written notice to City.  Whenever the 
Superintendent is not present at a particular part of the Work where the City or Design 
Professional may desire to inform the Contractor relative to interpretation of the Drawings 
and Specifications or to disapproval or rejection of materials or Work performed, the City 
or Design Professional may provide such information in writing to the foreman or other 
worker in charge of the particular part of the Work in reference to which the information is 
given.  Information so given will be as binding as if given to the Superintendent.
4.4.4
All elements of the Work must be under the direct supervision of a foreman or his
designated representative on the Site who must have the authority to take actions required
to properly carry out that particular element of the Work.
4.4.5
Working Hours.  Except in connection with the safety or protection of persons or the Work 
or property at the Site or adjacent thereto, and except as otherwise indicated, all Work at 
the Site must be performed during regular working hours, and Contractor will not permit 
overtime work or the performance of Work on Saturday, Sunday or any legal holiday without 
written consent given after prior written notice to City.  If it will become absolutely 
necessary to perform Work at night or on Saturdays, Sundays or legal holidays, the City 
must be informed at least 24 hours in advance of the beginning of performance of such 
Work.  Only such Work will be done at night as can be done satisfactorily as determined by 
the City.  Good lighting and all other necessary facilities for carrying out and inspecting the 
Work must be provided and maintained at all points where such Work is being done.  
Further, unless such non-normal work hours are performed at 
request or required by 
the Agreement Documents, Contractor must pay to City all additional costs incurred by City
by reason of such non-normal working hours.  Expenses incurred by City for overtime 
compensation must be reimbursed by Contractor as follows: (i) City staff at the rate set forth 
in current City Fee Schedule as published on City website, (ii) Design Professional and staff 
at the standard hourly rates previously negotiated with City, and (iii) all others at actual cost 
plus ten percent administrative overhead.  Such costs may be deducted by City from any 
payments due to Contractor.  Provided, however, if overtime work or work during other 
than normal hours is at the request of City and not due to Contractor delay, City will pay the 
cost of City overtime expenses.
4.4.6
Where the Agreement Documents require that a particular product be installed or applied
by an applicator approved by the manufacturer, it is
responsibility to ensure
the Subcontractor employed for such work is approved by the manufacturer.  All materials 
and equipment must be stored, applied, installed, connected, erected, used, cleaned and 
conditioned in accordance with the instructions of the applicable manufacturer, fabricator, 
supplier or distributor, except as otherwise provided in the Agreement Documents; but no 
provisions of any such instructions will be effective to impose on City of Design Professional
responsibility for the means, methods, techniques, sequences or procedures of 
construction or for safety precautions incident thereto.
4.4.7
Before starting the Work, Contractor must carefully study and compare the various
Plans, Drawings, other Agreement Documents, and Specifications relative to that portion
of the Work, as well as the information furnished by City, must take field measurements of
any existing conditions related to that portion of the Work and must observe any conditions
at the Site affecting it. The exactness of grades, elevations, dimensions, or locations given
on any Drawings, or the Work installed by other contractors, is not guaranteed by City.

General Conditions
Revised: 7/20/22
GC-14 of 75
4.4.8
Before ordering materials or doing Work, Contractor and each Subcontractor must verify
measurements
at
the
Site
and
will
be
responsible
for
the
correctness
of
such
measurements. No extra charge or compensation will be allowed because of differences
between actual dimensions and the dimensions indicated on the Agreement Documents,
including the Drawings.
4.4.9
Ground Level Construction Photography.
4.4.9.1
The Contractor must furnish progress photographs of the project.  The photographer 
selected by the Contractor must be approved by the City and must be either a commercial 
photographer or an individual experienced and equipped for such photography.  
4.4.9.2
The Contractor must deliver to City all photographs taken during that period with each 
application for payment.  If the current photographs do not accompany the application, the 
application will not be reviewed and will be returned to the Contractor as incomplete.
4.4.9.3
Photographs must be identified by use of typewritten labels affixed to the back of the 
photograph.  The label must provide a description of the view, the direction from which the 
Contractor and the date of the photography.  The stationing must also be included for all 
pipeline installations.  
4.4.9.4
Photographs must be taken during the construction period and must be of aesthetic 
composition and depict the progress of the Work from the beginning of construction 
through and including the finished product.  City may vary the specified frequency so that 
significant progress or changes can be recorded on the photographs. 
4.4.10
Underground Facilities.
4.4.10.1
The existence and number of facilities as shown on the Plans are estimated from 
information furnished by the particular utility.  Contractor is responsible for field verification 
and location of all utilities prior to the start of construction.  No field work will be allowed to 
start until Contractor has contacted Arizona 811 and all affected utilities have been located. 
In addition, Contractor must expose and physically locate all potentially conflicting utilities 
prior to construction.  The actual locations of the utilities must be compared to locations 
shown on the Plans and any required changes in alignment and grade must be made at the 
time of construction in consultation with Project Manager.  It is generally recognized and 
Contractor should anticipate that information from Arizona 811 or information from utility 
companies during project design, frequently fails to disclose all underground facilities.  The 
fact that more utility lines or other underground facilities are located in the Project Site than
undisclosed underground facilities do not differ materially from the conditions which 
Contractor should expect. The provisions of Sections 105.4, 105.6, 107.11 and 109.8.1 of the 
MAG Uniform Standard Specifications for Public Works Construction apply and are 
incorporated herein by this reference.  
4.4.10.2
Contractor is responsible for all coordination with utility companies.  The provisions of 
Sections 105.4, 105.6, 107.11 and 109.8.1 of the MAG Uniform Standard Specifications for 
Public Works Construction strictly apply and no additional compensation will be paid to 
Contractor for delays due to utility work on the project.
4.4.11
Relocation of Existing Water Meters.  When a service line has been extended and a line

General Conditions
Revised: 7/20/22
GC-15 of 75
setter installed in a meter box, City forces will re-install meter.  No compression fittings will
be utilized.
4.4.12
Water Turn-On or Turn-Off.
4.4.12.1
Contractor must coordinate all water line turn-ons and turn-offs through the City.  
Application must be made to the Municipal Utility Division and Contractor must pay the 
established charges.  The City will close existing valves, but will not guarantee a bone-dry 
Shutdown.
4.4.12.2
Contractor must notify all customers affected by the turn-off not less than 48 hours in 
advance.  Notification must be in writing, must give the reason for the turn-off and must
give the estimated time and duration that water service will be interrupted. Contractor is 
also notified that water turn-off will not be permitted on the Day before and after 
Thanksgiving Day and Christmas Day.
4.4.12.3
No direct payment will be made to Contractor for turn-ons or turn-offs. Costs associated 
therewith will be included in other items for which direct payment is made.
4.4.13
Tests and Inspections.
4.4.13.1
Contractor must give City timely (at a minimum, twenty-four hours) notice of readiness of 
the Work for all required inspections, tests or approvals.  Contractor must give timely notice 
to City in advance of backfilling or otherwise covering any part of the Work so that city 
representative may, if desired, observe such part of the Work before it is concealed.  
Whenever Contractor varies the normal period during which Work or any portion of it is 
carried on each Day, Contractor must give timely notice to City so that city representative
may, if desired, be present to observe the Work in progress.  If Contractor fails to give such 
timely notice, any Work done in the absence of city representative will be subject to 
rejection.  If Contractor gives such notice to City, but then is not ready for such inspections, 
tests, approvals or observations at the time so noticed, Contractor must reimburse City for 
all costs incurred by the attendance of city representatives.  
4.4.13.2
If any law, ordinance, rule, regulation, code, or orders of any public body having jurisdiction 
requires any Work (or part thereof) to be inspected, tested or approved, Contractor (unless 
another party is specified in the Agreement Documents) must assume full responsibility 
therefor, pay all costs in connection therewith and furnish City the required certificates of 
inspection, testing, or approval. Contractor must also be responsible for and must pay all 
costs in connection with any inspection or testing required by the Specifications in 
connection with City's acceptance of a manufacturer, fabricator, supplier or distributor of 
materials or equipment proposed to be incorporated in the Work, or of materials or 
equipment submitted for approval prior to Contractor's purchase thereof for incorporation 
in the Work. The cost of all other inspections, tests and approvals required by the 
Agreement Documents will be paid by City (unless otherwise specified).
4.4.13.3
All inspections, tests or approvals other than those required by law, ordinance, rule, 
regulation, code or order of any public body having jurisdiction must be performed by 
organizations acceptable to City and by the Design Professional if so specified.
4.4.13.4
Neither observations by City, the Design Professional nor inspections, tests or approvals by 
others will relieve Contractor from their obligations to perform the Work in accordance with 
the Agreement Documents.

General Conditions
Revised: 7/20/22
GC-16 of 75
4.4.14
Uncovering Work.  If any Work that is to be observed, inspected, tested or approved is 
covered without written concurrence of City, it must, if requested by City be uncovered for 
observation. Unless Contractor has given City timely notice of Contractor's intention to 
cover such Work and City has not acted with reasonable promptness in response to such 
notice, Contractor must furnish all necessary labor, material and bear all the expenses of 
such uncovering, exposure, observation, inspection and testing and of satisfactory 
reconstruction, including compensation for additional professional services, and an 
appropriate deductive Change Order will be issued.
4.4.15
In all cases of interconnection of its Work with existing or other Work, Contractor must verify
at the
Site all dimensions relating to such existing or other Work.  Any errors due to
to so verify all such grades, elevations, locations or dimensions must
be promptly rectified by
Contractor without any increase in the Agreement Price. Any
design errors or omissions noted by
Contractor during this review must be reported
promptly to City.
4.4.16
Contractor must establish and maintain all construction grades, lines, levels, and
benchmarks, and will be responsible for accuracy and protection of same. This Work
must be performed or supervised by a licensed civil engineer or surveyor in the State of
Arizona.
4.4.17
Contractor must photograph all buried piping of greater than four (4) inches in diameter 
prior to backfill. 
4.4.18
Contractor is responsible for the proper performance of the work of Subcontractors and any
acts and omissions in connection with such performance.
Nothing in the Agreement
Documents is intended or deemed to create any legal or contractual relationship
between City and any Subcontractor or Sub-Subcontractor, including but not limited to any
third-party beneficiary rights.
4.4.19
Contractor
must
coordinate
the
activities
of
all
Subcontractors. Contractor
must
coordinate performance of the Work with
Public Works & Utilities Department and
other departments or agencies within City. The Design Professional and other contractors
or parties involved in the Project. If Cityperforms otherwork ontheProjector at theSitewith
separate contractors under
control, Contractor agrees to cooperate and coordinate
its activities with those of such separate contractors so that the Project can be completed
in an orderly and coordinated manner without unreasonable disruption.
4.4.20
Contractor will not substitute or change any Subcontractor or Supplier without the prior
written approval of City. Any substitute or replacement Subcontractor or Supplier must
be required to meet the same qualifications and selection criteria and process as the
original Subcontractor or Supplier. If a Subcontract/Supplier selection plan has been
approved by City, Contractor will
follow that plan unless otherwise approved by City in
writing.
4.4.21
Contractor must not change or replace any members of its Project team, including
Representative, Project Manager, or Superintendent, without an explanation for
the change being given to City, and receiving prior written approval of the change from City,
which approval will not be unreasonably withheld.
4.4.22
Subcontractors whose scope of work has a value greater than 15% of the total Agreement
Price are
required to furnish performance and payment bonds to Contractor, unless

General Conditions
Revised: 7/20/22
GC-17 of 75
otherwise approved in writing by City.
4.4.23
Contractor must comply with MAG Specification § 108.2 (E) unless otherwise specified in 
Agreement Documents.
4.5
CONTROL OF THE PROJECT SITE
4.5.1
Throughout all phases of construction, including suspension of Work, Contractor must keep
the Site reasonably free from debris, trash and construction wastes to permit Contractor to
perform its
construction services efficiently, safely and without interfering with the use of
adjacent land areas.
Prior to Final Acceptance of the Work, or a portion of the Work,
Contractor must remove all debris,
trash, construction wastes, materials, equipment,
machinery and tools arising from the Work or applicable portions thereof to permit City
to occupy the Project or a portion of the Project for its intended use.
4.5.2
Contractor must take whatever steps, procedures or means necessary to prevent dust 
nuisance due to construction operations. The dust control measures must be maintained 
at all times to the satisfaction of City and in accordance with the requirements of the 
Maricopa County Bureau of Air Pollution Control Rules and Regulations.
4.5.3
Contractor must maintain Americans with Disabilities Act (ADA) and American National
Standards
Institute (ANSI)
accessibility requirements during construction activities,
including
without
limitation
compliance
with
the
2010
regulations
governing
implementation of the ADA to the extent
applicable.
ADA and ANSI accessibility
requirements must include, but not be limited to, parking, building access, areas of refuge,
and emergency exit paths of travel. Contractor i s responsible for the coordination of all
Work to minimize disruption to residents and the public.
4.5.4
Only materials and equipment used directly in the Work will be brought to and stored on the
Site by Contractor. When equipment is no longer required for Work, it must be removed
promptly from
the Site. Protection of construction materials and equipment stored at the
Site from weather, theft, damage and all other adversity is solely the responsibility of the
Contractor.
4.5.5
Contractor agrees all persons working on the Site must act at all times in the best interest 
of the Project and will comply with all applicable rules and regulations reasonably set forth 
by City related to the Site. Notwithstanding the foregoing or anything in this Agreement to 
the contrary, City may remove from the Site any individual who City deems in their 
reasonable discretion to be creating a disturbance or causing any problem on the Site.
4.5.6
Contractor will
Subcontractors and their agents and employees, and any other person performing any of 
the Work under an Agreement with Contractor, or claiming by, through or under Contractor, 
for all damages, losses, costs and expenses resulting from such acts or omissions.
4.5.7
City may conduct criminal, drive history, and all other requested background checks of
Contractor
and Subcontractor personnel performing Work or who have access to
information, data, or facilities in accordance with
current background check policies,
or the provisions of the Project Specific Conditions. Any officer, employee or agent that
fails to background check must be replaced immediately.
4.5.8
City will have a final authority, based upon security reasons: (i) to determine when

General Conditions
Revised: 7/20/22
GC-18 of 75
security clearanceof
and
personnelisrequired;(ii)todetermine
the nature of the security clearance, up to and including fingerprinting personnel; and
(iii) to determine whether or not any individual or entity may provide Services or perform
Work under the Agreement.
4.5.9
If City objects to any personnel for any reasonable cause, then Contractor must, upon notice
from City, remove such individual from the Project.
4.6
PROJECT SAFETY
4.6.1
The Project and all Work performed in relation thereto is governed by applicable provisions
of the federal laws, including but not limited to, the latest amendments of the following:
a.
Williams-Steiger Occupational Safety & Health Act of 1970, Public Law, 91-596.
b.
Part 1910 and Part 1926
Occupational Safety and Health Standards,
Chapter XVII of Title 29, Code of Federal Regulations.
c.
Part 1518
Safety and Health Regulations for Construction, Chapter XIII of
Title 29, Code of Federal Regulations.
4.6.2
Contractor is responsible for safety of the job Site for employees of Contractor as well
as for members of the general public and others who may drive or walk through or be at
the Site.
4.6.3
Contractor recognizes the importance of performing the Work in a safe manner so as to
prevent damage, injury or loss to: (i) all individuals at the Site, whether working or visiting;
(ii) the Work, including materials and equipment incorporated into the Work and stored On-
Site or Off-Site; and (iii) all other property at the Site or adjacent thereto, including trees,
shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for
removal, relocation or replacement in the course of construction; and (iv) the owners or
tenants of adjacent property and their patrons, employees and invitees.
4.6.4
Contractor assumes responsibility for implementing and monitoring all safety precautions
and programs related to the performance of the Work.
4.6.5
Contractor must provide a
as required by O.S.H.A regulations. The
must be identified at the Pre-Construction Conference with City
advised in writing of any changes.
4.6.6
must make routine daily inspections of the Site and must hold 
applicable.
4.6.7
Contractor and Subcontractors must comply with all legal and regulatory requirements 
relating to safety, as well as any City specific safety requirements set forth in the Agreement
Documents, provided that such City-specific requirements do not violate any applicable 
legal and regulatory requirements.
4.6.8
Contractor will immediately report in writing any safety-related injury, loss, damage or
accident arising from the Work to Project Manager and, to the extent mandated by Legal
Requirements, to all government or quasi-government authorities having jurisdiction over
safety-related matters involving the Project or the Work.

General Conditions
Revised: 7/20/22
GC-19 of 75
4.6.9
responsibility for safety under this Section is not intended in any way to
relieve Subcontractors and Sub-Subcontractors of their own contractual and legal
obligations and responsibility for (i) complying with all Legal Requirements, including those
related to health and safety matters, and (ii) taking all necessary measures to implement
and monitor all safety precautions and programs to guard against injury, losses, damages
or accidents resulting from their performance of the Work.
4.6.10
As between City and Contractor, Contractor is responsible to City for any and all the safety
issues relating to the Work on the Project. Contractor must administer and manage the
safety program. This will include, but not necessarily be limited to review of the safety
programs
of
each
Subcontractor. Contractor must monitor the establishment and
execution of compliance with all applicable regulatory and advisory agency construction
safety standards.
responsibilityfor review, monitoring, and coordination of the
safety programs will not extend to direct control over execution of the
safety programs. Notwithstanding
safety obligations to City,
it is agreed and understood that each individual Subcontractor will remain controlling
employer responsible for the safety programs and precautions applicable to its own work
and the activities of 
work in areas designated tobecontrolledbysuchSubcontractor
for purposes of workers compensation insurance coverage.
4.6.11
Nothing in this agreement will relieve Contractor of his responsibility to maintain traffic,
structures, etc., as noted on the Plans, Specifications, and Project Specific Conditions.
Contractor is responsible to provide all necessary shoring, bracing and trench support as
is necessary to maintain traffic structures, etc., as stipulated in the Plans, Specifications, and
Special Provisions. If the stability of adjoining building, walls, roadways, etc., is endangered
by
excavation, shoring, bracing, or under pinning must be provided as
necessary to ensure project safety. Cost for shoring, bracing, underpinnings, and trench
support will be included in the appropriate items listed in the Agreement Price, and no
additional payment will be made for this work.
4.7
MATERIALS QUALITY, SUBSTITUTIONS, AND SHOP DRAWINGS
4.7.1
Quality Control and Quality Assurance Testing.
4.7.1.1
All construction materials to be used or incorporated in the Project are subject to
inspection, Quality Control & Quality Assurance Testing, and approval or rejection by City.
Any material rejected by City must be removed immediately and replaced in an acceptable
manner to City at no additional cost to City. When QC/QA tests indicate noncompliance
with the Agreement
Documents, retesting must be performed by the same testing
laboratory that performed the tests that indicated noncompliance.
4.7.1.2
The Contractor must establish, provide, and maintain an effective Quality Control Testing
Program (QCTP). The Contractor must develop his own program or procure the services of
a consultant. In either case, the party performing the tests must be currently certified by the
National Bureau of Standards in the National Voluntary Laboratory Accreditation Program
(NVLAP) for construction
services or the AASHTO
Accreditation Plan (AAP) for Soils,
Asphalt and Concrete. The Contractor must provide all support necessary to perform QC
and QA testing and sampling (i.e.
shoring for testing trench backfill, backhoes, motor
graders, loaders, etc. to facilitate testing and sampling). The City will perform the QA testing.
4.7.1.3
The Contractor must submit a written QCTP to the City as a required submittal. The
Contractor must not begin Work until the Quality Control Program has been reviewed and

General Conditions
Revised: 7/20/22
GC-20 of 75
accepted by the City. Resumes of all personnel that will be associated directly or indirectly
with the QCTP must be included.
4.7.1.4
The QCTP must include, but not be limited to, on-site/field and laboratory testing of all
material delivered to the Site and any existing materials or conditions pertinent to the
project.
4.7.1.5
All testing must be under the direction of a Professional Engineer registered in the State of
Arizona, knowledgeable in Materials Testing. All Test R
forms must be stamped by
said Engineer.
4.7.1.6
The written QCTP will set forth the responsibilities of the engineer, project manager,
supervisory
personnel and each technician assigned to this project. Substitutions or
replacement of personnel mustrequireprior written approvalbythe City. Allpersonnelmust
be proficient within their assigned duties and possess certification(s) commensurate with
their position and responsibilities. The minimum certification(s) for each technician must
be NICET Level II, Arizona Technical Testing Institute, American Concrete Institute, or other
nationally recognized program applicable to the project and approved by the City of 
Chandler.
The written QCTP must include a description of the
required field and
construction materials laboratory tests, including required frequencies that meet
the
minimums established herein.
4.7.1.7
The Contractor must establish a system to record and report all material test results.
The
daily test reports must include, but not be limited to:
a.
Test designation;
b.
Date of test;
c.
Name of tester;
d.
Location of test/sample (station and offset);
e.
Product suppliers and product codes (as applicable);
f.
Depth/elevation of test/sample;
g.
Test result;
h.
Control requirement(s);
i.
Cause of rejection (if applicable);
j.
Results of retests (if applicable); and
k.
Remedial action (if applicable).
4.7.1.8
The Contractor must submit test results to the designated City representative.  
4.7.1.9
The Contractor must also submit a weekly report to the City summarizing the testing
and construction activities completed by emailing the report to the email addresses noted
above. All weekly reports must be submitted simultaneously to the Contractor and the
City of Chandler. The report must include individual summary sheets for each utility line,
structure, and portion of the pavement section. Cores must be numbered sequentially
throughout the Project. Re-cores must reference the original core by number and must
contain the averaged values for thickness and density. Total pavement thickness must be
reported. Vertical location of tests for underground utilities must indicate the depth of the

General Conditions
Revised: 7/20/22
GC-21 of 75
excavation at the location of the test (i.e., cut to flow line [if applicable], depth to bottom
or top of pipe, etc.). Density tests must be numbered sequentially. If the minimum number
of tests has not been performed per the written QCTP, this must be stated in the weekly
summary report with an explanation of the circumstances.
4.7.1.10
The City will maintain a copy of the Project test results and weekly reports in the Project
file. In cases where quality control activities do not comply with the Agreement provisions,
the City may:
a.
Order the Contractor to replace ineffective or unqualified quality control
personnel.
b.
Order the Contractor to stop operations until appropriate corrective action is
taken.
4.7.1.11
Although minimum testing requirements are specified herein, the Contractor bears full
responsibility for the quality of the materials and their installation and may elect to
perform additional testing beyond the requirements set forth herein to ensure compliance.
4.7.1.12
The Quality Control requirements contained in this Section are in addition to and separate
from
Quality Assurance Testing, which will be performed by the City of Chandler or its
representative. If the Quality Assurance test results are not in agreement with the Quality
Control test results, the Contractor will have the option to retain a third party consultant for
referee tests. The third party
consultant must meet the same requirements as the
consultant performing the Quality Control Testing. The results of the third party will be
binding. All cost incurred by the referee testing will be the
expense. If the
Contractor elects not to retain a third party for referee testing, the City of Chandler test
results will prevail.
4.7.1.13
Except as otherwise noted within this Section, Work or materials required by this Section are
non- pay items. Per MAG Section 101, a non-pay item is an item of Work for which no
separate payment will be made, the cost of which is to be included as an incidental cost
for associated item(s) included on the Bid Schedule or Schedule of Values.
4.7.2
Trade Names and Substitutions.
4.7.2.1
Substitutions prior to bid will only be considered if in compliance with Arizona Revised
Statute § 34-104.
4.7.2.2
Contractor, if requested by City, must submit Samples or any additional information that 
may be necessary to evaluate the acceptability of the substitution.
4.7.2.3
City will make the final decision and will notify Contractor in writing as to whether the 
substitution has been accepted or rejected.
4.7.2.4
If City does not respond within 15 working days, Contractor must continue to perform the 
Work in accordance with the Agreement Documents and the substitution will be considered 
rejected.
4.7.3
Shop Drawings.
4.7.3.1
Contractor must prepare and submit Shop Drawings which show details of all Work to insure
proper installation of the Work using those materials and equipment specified under the
approved Plans and Specifications.

General Conditions
Revised: 7/20/22
GC-22 of 75
4.7.3.2
Contractor must submit a schedule of Shop Drawing submissions, which avoids bulk
submissions to the extent reasonably possible, with the Project Schedule for City approval.
The schedule of Shop Drawing submissions must include all of the items for which Shop
Drawings are required by the Agreement Documents, including the Specifications. Unless
otherwise noted, Shop Drawings will not be required for items specified or detailed in
the Uniform Standard Specifications and Details or the Technical Specifications.
4.7.3.3
Shop Drawings must be numbered consecutively for each Specification section and must
accurately and distinctly present the following:
a.
All working and erection dimensions.
b.
Arrangements and sectional views.
c.
Necessary details, including complete information for making connections
between work under this Agreement and work under other Agreements.
d.
Kinds of materials and finishes.
e.
Parts list and description thereof.
4.7.3.4
Each Drawing or page must include:
a.
Project Name, City of Chandler Project Number and descriptions.
b.
Submittal date and space for revision dates.
c.
Identification of equipment, product or material.
d.
Name of Contractor and Subcontractor.
e.
Name of Supplier and Manufacturer.
f.
Relation to adjacent structure of material.
g.
Physical dimensions clearly identified.
h.
ASTM and Federal Specifications references.
i.
Identification of and justification for deviations from the Agreement
Documents.
j.
stamp, initialed or signed, dated and certifying the review
of
submittal,
certification of field measurements and compliance with
Agreement.
k.
Location at which the equipment or materials are to be installed.
4.7.3.5
Location will mean both physical location and location relative to other connected or
attached
material. City will return unchecked any submittal, which does not contain
complete data on the Work and full information on related matters.
4.7.3.6
Stock or standard drawings will not be accepted for review unless full identification and
supplementary information is shown thereon in ink or typewritten form.
4.7.3.7
Contractor must schedule, prepare and submit all Shop Drawings in accordance with a time-
table
that will allow its suppliers and manufacturers sufficient time to fabricate,
manufacture, inspect,
test and deliver their respective products to the project Site in a
timely manner so as to not delay the complete performance of the Work.

General Conditions
Revised: 7/20/22
GC-23 of 75
4.7.3.8
If the Shop Drawings show departures from the Agreement requirements, Contractor
must make specific mention thereof in the Letter of Transmittal; otherwise review of such
submittals by City will not constitute review of the departure. Review of the Drawings will
constitute review of the specific subject matter for which the Drawings were submitted
and not of any other structure, material, equipment, or apparatus shown on the Drawings.
4.7.3.9
The review of Shop Drawings will be general and will not relieve Contractor of responsibility
for the accuracy of such Drawings, nor for the proper fitting and construction of the Work,
nor for the furnishing of materials or Work required by the Agreement. No construction
called for by Shop Drawings will be initiated until such Drawings have been reviewed and
approved by City.
4.7.3.10
The procedure in seeking review of the Shop Drawings will be as follows:
a.
Contractor must submit complete sets of Shop Drawings and other
descriptive data as specified in this Section.
b.
After
submittal or resubmittal of Shop Drawings, if Contractor
has submitted
Shop Drawings in accordance with the City-approved
submittal schedule, or upon resubmission, City will be provided with three
(3) calendar weeks for review. Should City
require additional review time
above and beyond the three (3) calendar weeks, Contractor may ask for a
time extension or monetary compensation, if they can present valid, factual
evidence that actual damages were incurred by Contractor. City will
determine
the
amount
of
the
time
extension
or
the
monetary
compensation to be awarded Contractor, if any, in accordance with
Policy Statement for Calculating Delays and Damages, Appendix 1.
4.7.3.11
Contractor will be responsible for all extra costs incurred by City caused by
failure to comply with the procedure outline above.
4.7.4
Long Lead Time Items. Contractor must submit Shop Drawings, as required by the Engineer,
on all long lead items to be furnished and installed as part of the project within 10 Days
after
the date of the executed Agreement letter issued by City. In addition,
Contractor must order all long lead items to be furnished and installed as part of this
Project within 3 Days after receiving approved Shop Drawings. For all long lead times for
which Shop Drawings are not required, Contractor must order said long lead items within
15 Days after the date of the executed Agreement letter issued by City. Within 2 Days
after ordering long lead items, Contractor must supply copies of all purchase orders,
along with an accurate delivery schedule from the supplier.
4.7.5
Construction Water. If Contractor uses water from
water system for construction
water,
Contractor must obtain a fire hydrant meter from City of Chandler Utility Services 
(480-782-2280) and all construction water must be obtained through the hydrant meter.
Contractor must pay all fees related to the hydrant meter and all water bills for construction
water. All cost for meters and construction water will be included in the Agreement Price.
4.8
PROJECT RECORD DOCUMENTS
4.8.1
During the construction period, Contractor must maintain at the jobsite a full-size set of
prints of
the Construction Document Drawings and Shop Drawings for Project Record
Document purposes.

General Conditions
Revised: 7/20/22
GC-24 of 75
4.8.2
Contractor must mark these Drawings to indicate theactual installation wherethe installation
varies from the original Construction Documents. Contractor must give particular attention
to information
on elements that will be concealed, which would be difficult to identify or
measure and record later. Items required to be marked include but are not limited to:
a.
Dimensional changes to the Drawings.
b.
Revisions to details shown on Drawings.
c.
Locations and depths of underground utilities.
d.
Revisions to routing of piping and conduits.
e.
Actual equipment locations.
f.
Changes made by Change Order or Addendum.
g.
Details not on original Agreement Drawings.
4.8.3
Contractor must mark completely and accurately Project Record Drawing sets of 
Construction Documents.
4.8.4
Contractor must mark Project Record Drawings sets with red erasable colored pencil.
4.8.5
Contractor must note Request for Information (RFI) Numbers and Change Order numbers, 
etc., as required to identify the source of the change to the Construction Documents.
4.8.6
Contractor must submit Project Record Drawing sets and Shop Drawings to City or its 
representative for review and comment.
4.8.7
Upon receipt of the reviewed Project Record Drawings from City, Contractor must correct 
any deficiencies and omissions to the Drawings and submit the final original of the Project 
Record Drawings to City prior to Final Payment.
4.8.8
Project Manager will review the Project Record Drawings monthly prior to the date 
established for the Payment Request and will be the sole judge of acceptance of these 
Drawings.
4.9
WARRANTY AND CORRECTION OF DEFECTIVE WORK
4.9.1
Contractor warrants to City that the construction, including all materials and equipment 
furnished as part of the Work, will be new unless otherwise specified in the Agreement
warranty obligation excludes defects caused by abuse, alterations, or unreasonable failure 
to maintain the construction by persons other than Contractor, subcontractors, or others 
which provides City with greater warranty rights than set forth herein or in the Agreement.  
must be for one (1) year, in accordance with MAG Specification § 108.8, and will commence 
for all portions of the Work upon Final Acceptance of the entire Work as determined by City 
under the Agreement.  All statutory or other warranties, express or implied, related to latent 
defects will remain in force and are not limited by this provision.
4.9.2
City May Stop the Work.  If the Work is defective, or Contractor fails to supply sufficient 
skilled workmen or suitable materials or equipment, City may order Contractor to stop the

General Conditions
Revised: 7/20/22
GC-25 of 75
Work without cost to City, or any portion thereof, until the cause for such order has been 
eliminated; however, this right of City to stop the Work will not give rise to any duty on the 
part of City to exercise this right for the benefit of Contractor or any other party.
4.9.3
Correction or Removal of Defective Work.
4.9.3.1
If required by City, Contractor must promptly, without cost to City and as specified by City, 
either correct any defective Work, whether or not fabricated, installed or completed, or, if 
the Work has been rejected by City, remove it from the Site and replace it with non-defective 
Work. Contractor must correct any Work which may be displaced in correcting, removing or 
replacing defective Work. No compensation will be allowed Contractor for such removal, 
replacement or remedial Work.  Contractor must reimburse City for costs incurred by City 
due to such correction or removal including but not limited to additional expenses for 
inspection, testing or observation and for repeated reviews by the City or Design 
Professional.  
4.9.3.2
Upon failure on the part of the Contractor to comply within a reasonably prompt time with 
any written order of City to correct or remove defective Work, City has authority to cause 
nonconforming materials or rejected Work to be remedied, removed, or replaced at the 
Contractor's expense and to deduct the costs from any moneys due or to become due the 
Contractor.
4.9.4
City May Correct Defective Work.  If Contractor fails within a reasonable time after written 
notice of City to proceed to correct defective Work or to remove and replace rejected Work 
as required by City or if Contractor fails to perform the Work in accordance with the 
Agreement Documents (including any requirements of the progress schedule), City may, 
after 7 Days' written notice to Contractor, correct and remedy any such deficiency.  To the 
extent necessary to complete corrective and remedial action, City may exclude Contractor 
from all or part of the Work, and suspend Contractor's services related thereto, take 
possession of Contractor's tools, appliances, construction equipment and machinery at the 
Site and incorporate in the Work all materials and equipment stored at the Site or for which 
City has paid Contractor, but which are stored elsewhere. Contractor must allow City, city 
representatives, agents and employees such access to the Site as may be necessary to 
Section.  All direct and indirect costs of City in 
exercising such rights will be charged against Contractor in an amount verified by City 
representative, and a Change Order will be issued incorporating the necessary revisions in 
the Agreement Documents and a reduction in the Agreement Price.  Such direct and indirect 
costs will include, in particular but without limitation, compensation for additional 
professional services required and all costs of repair and replacement of Work or others 
destroyed or damaged by correction, removal or replacement of Contractor's defective 
Work. Contractor will not be allowed an extension of the Agreement Time because of any 
rights hereunder.
4.9.5
Correction or Removal of Unauthorized Work.
4.9.5.1
Any Work done beyond the lines and grades shown on the Drawings or established by the 
Design Professional or any changes in, additions to, or deductions from the Work done 
without written authority will be considered as unauthorized and will not be paid for. Work 
so done may be ordered remedied, removed, or replaced at the Contractor's expense.
4.9.5.2
Upon failure on the part of the Contractor to comply promptly with any order of the City,

General Conditions
Revised: 7/20/22
GC-26 of 75
City will have authority to cause unauthorized Work to be remedied, removed, or replaced 
at the Contractor's expense and to deduct the costs from any moneys due or to become 
due the Contractor.
4.9.6
Correction Period - One Year Guarantee.
4.9.6.1
If, within one year after the date of Final Acceptance, or such longer period of time as may 
be prescribed by law or by the terms of any applicable special guarantee required by the 
Agreement Documents, or by any specific provision of the Agreement Documents, any Work 
is found to be defective, Contractor must promptly, without cost to City and in accordance 
with City's written instructions, either correct such defective Work, or, if it has been rejected 
by City, remove it from the Site and replace it with non-defective Work. If Contractor does 
not promptly comply with the terms of such instructions, or in an emergency where delay 
would cause serious risk of loss or damage, City may have the defective Work corrected or 
the rejected Work removed and replaced, and all direct and indirect costs of such removal 
and replacement, including compensation for additional professional services, must be paid 
by Contractor. Such action by the City will not relieve the Contractor of the guarantees 
required by this Section or elsewhere in the Agreement Documents. 
4.9.6.2
If, in the opinion of the City, defective Work creates a dangerous condition or requires 
immediate correction or attention to prevent further loss to the City or to prevent 
interruption of operation of the City, the City will attempt to give the notice required by this 
Section.  If the Contractor cannot be contacted or does not comply with the City's request 
for correction within a reasonable time as determined by the City, the City may, 
notwithstanding the provisions of this Section, proceed to make such correction or provide 
such attention; and the costs of such correction or attention will be charged against the 
Contractor.  Such action by the City will not relieve the Contractor of the guarantees 
required by this Section or elsewhere in the Agreement Documents.
4.9.6.3
This Section does not in any way limit the guarantee on any items for which a longer 
guarantee is specified or on any items for which a manufacturer or supplier gives a 
guarantee for a longer period. The Contractor agrees to act as co-guarantor with such 
manufacturer or supplier and must furnish the City all appropriate guarantee or warranty 
certificates upon completion of the Project.  No guarantee period, whether provided for in 
this Section or elsewhere, will in any way limit the liability of Contractor or their sureties or 
insurers under the indemnity or insurance provisions of these General Conditions and the 
Project Specific Special Conditions.
4.9.7
Acceptance of Defective Work.
4.9.7.1
If, instead of requiring correction or removal and replacement of defective Work, City may 
accept Work when in the best interest of the City to do so with appropriate monetary credit 
from Contractor. If any such acceptance occurs prior to final payment, a Change Order will
be issued incorporating the necessary revisions in the Agreement Documents, including 
appropriate reduction in the Agreement Price; or, if the acceptance occurs after final 
payment, an appropriate amount must be paid by Contractor to City.
4.9.7.2
Alternatively, City may require Contractor to furnish at Contractor's expense, a special 
performance guarantee or other surety prior to acceptance of defective work.
4.9.8
The Warranty period begins on the Final Acceptance date noted in the Certificate of 
Completion, irrespective of early completion by some Subcontractors of their work.

General Conditions
Revised: 7/20/22
GC-27 of 75
4.9.9
warranty obligation must be in accordance with MAG Specifications.
4.9.10
Nothing in the warranties contained in the Agreement Documents are intended to limit any
warranty which provides City with greater warranty rights than set forth
in
this
Section or the Agreement Documents.
Contractor must provide City with all
warranties
prior to Substantial Completion, if applicable, or Final
Acceptance.
4.9.11
Contractor agrees that it will be responsible to manage and administer the correction of any
Work that is not in conformance with the Agreement Documents during the warranty 
periods set forth in this Section, or during any longer periods to the extent required by the
Agreement Documents. A progress payment, or partial or entire use or occupancy of the
Project by City, will not constitute acceptance of Work not in accordance with the Agreement
Documents.
4.9.12
When notified of a warranty issue, Contractor must respond in writing within 48-hours and
must
perform warranty Work as soon as material for said repairs are available (as judged
solely by City), and in any event Contractor must, take immediate steps to commence and
complete correction of nonconforming Work no later than the time period set forth in
written notification in accordance with the Agreement Documents. This includes the 
correction, removal or replacement of the nonconforming Work and any damage caused
to other parts of the Work affected by the nonconforming Work. If defects develop which
are determined by City to be an emergency, City
will notify Contractor, via the most
expeditious means regarding the nature and condition of the defects. In turn, Contractor
must immediately dispatch necessary forces to correct the defect or
the emergency
condition in accordance with Agreement Documents.
4.9.13
The time periods referenced in this Section apply only to
obligation to
correct nonconforming Work and is not intended to constitute a period of limitations for any
other rights or remedies that City may have regarding
other obligations under
the Agreement Documents.
4.9.14
Without limiting the foregoing or anything in these General Conditions or the Agreement
to the contrary, Contractor must obtain and provide to City all warranties for any portion
of the Project offered by the manufacturer, installer or provider thereof. City and the user
of the facility will
have the right to the full value and benefit of all such warranties.
Contractor must ensure all such warranties are fully transferrable to facilitate the full value
of this Section.
4.9.15
warranty excludes damages or defects caused by abuse, alterations to the Work
not executed by or through Contractor, improper or insufficient maintenance, improper
operation, or normal wear and tear and normal usage.
4.9.16
In the event of any noncompliance with this entire Section 4, City may require Contractor to 
stop or suspend the Work in whole or in part.
SECTION 5 - CITY RESPONSIBILITIES
5.1
CITY PROJECT MANAGER AND INSPECTORS
5.1.1
Project Manager is responsible for providing City-supplied information and approvals in a
timely manner to assist Contractor to fulfill its obligations under the Agreement Documents.

General Conditions
Revised: 7/20/22
GC-28 of 75
5.1.2
Project Manager will also provide Contractor with prompt notice when it observes any 
failure on the part of Contractor to fulfill its contractual obligations, including any default
or defect in the Project or non-conformance with the Drawings and Specifications.
5.1.3
City may utilize Field Inspectors to assist Project Manager during construction in
observing performance of Contractor.
use of Inspectors is for the purpose of assisting
Project Manager.
5.1.4
The Inspectors are authorized to inspect all Work and materials furnished. Such inspections
may extend to all or part of the Work and to preparation, fabrication or manufacture of the
materials to be used.  The Inspectors have the authority to issue instructions contrary to
the Construction
Documents if approved and coordinated with the directions of Project
Manager.
5.1.5
The Inspectors have the authority to reject work or materials until any questions at issue can
be decided by Project Manager.
5.1.6
The use of Inspectors by City will not make City responsible for or give City control
over
construction means, methods, techniques, sequences or procedures or for safety
precautions or programs or responsibility for
failure to perform the Work in
accordance with Agreement Documents. The Inspectors are not authorized to direct any of
activities, employees or Subcontractors.
5.2
DESIGN PROFESSIONAL SERVICES
City may contract separately with one or
more
Design Professionals to provide
construction administration of the Project. The Design
Agreement, as well as
other firms hired by City may be furnished to Contractor. Contractor does not have the right
to limit or restrict or reject any Agreement modifications that are mutually acceptable to City
and Design Professional.
5.3
CITY
SEPARATE CONTRACTORS
City is responsible for all work performed on the Project or at the Site by separate
contractors
retained by City. City will contractually require its separate contractors to
reasonablycooperate with, and reasonably coordinate their activities so as not to interfere
with Contractor in order to enable Contractor to timely complete the Work consistent with
the Agreement Documents.
Contractor must immediately notify the Project manager,
and address the matter in the next monthly status report, if any activities of such separate
contractors are
expected to interfere, or are interfering, with Contractor and such
interference will or could result in any delay in
performance of the Work.
5.4
PERMIT REVIEW AND INSPECTIONS
5.4.1
If requested by Contractor, Project Manager will provide assistance and guidance in
obtaining necessary reviews, permits and inspections.
5.4.2
The regulating agencies of City, such as Development and Sustainability, Fire and
Planning Departments, enforce legal requirements. The enforcement activities of City are
independent and separate from this Agreement.
5.5
PLANS AND SPECIFICATIONS TO THE CONTRACTOR.  
Contractor will be provided up to five copies of the Agreement Documents as are 
reasonably necessary for the execution of the Work.  Additional copies will be furnished,

General Conditions
Revised: 7/20/22
GC-29 of 75
upon request, at the cost of reproduction.  
SECTION 6 - AGREEMENT TIME
6.1
AGREEMENT TIME
6.1.1
The Agreement Time will start with the Notice to Proceed
and end with Final
Acceptance. 
6.1.2
Beginning on the date of the NTP, Contractor must begin to fulfill
obligations
under
the
Agreement.
obligations
include
providing
City
and
other
agencies with any submittals required by the Project Specific Special Provisions, including
but not limited to, an approved Project Schedule, Traffic Control Plans, and a Stormwater
Pollution Prevention Plan. Contractor
must submit all such required submittals before
any physical construction work commences on
the
Site. NTP
does
not
authorize
construction work until all a greement insurance, bonds, and schedules are submitted to
and accepted by the City.
6.1.3
The Agreement Time will be as set forth in the Project Schedule. Contractor agrees that
it will
commence performance of the Work and complete the Project through both
Substantial Completion and Final Acceptance within the Agreement Time.
6.1.4
Time is of the essence of this Agreement, for the Project, for the Work, and for each phase
and designated Milestone thereof.
6.1.5
Failure of Contractor to perform any covenant or condition contained in the Agreement
Documents within the time periods specified herein, will constitute a material breach of this 
Agreement entitling City to terminate the Agreement unless Contractor applies for and 
receives an extension of time, in accordance with the procedures set forth in the Agreement
Documents.
6.1.6
Failure of City to insist upon the performance of any covenant or condition within the time 
periods specified herein, will
other covenant or condition within the designated periods, unless a specific waiver is 
granted in writing for each such covenant or condition.
6.1.7
will not constitute a waiver of any other time provisions contained in the Agreement
Documents.  Failure of Contractor to complete performance promptly within the additional 
time authorized in the waiver or extension of time agreement constitutes a material breach 
of this Agreement entitling City to all the remedies set forth herein or provided by law.
6.2
PROJECT SCHEDULE
6.2.1
The Project Schedule must be in Microsoft Project standard file format, must be updated and
maintained throughout the Agreement Time, and must contain the following:
6.2.1.1
Detailed representation of all activities for the project, both on-site construction and major 
procurement.  All significant activities together with the resource loading requirements for 
each and all items appearing on the schedule of values or bid schedule for progress 
payments must be shown on the Project Schedule or in attached transmittal letter as 
described in Section 6.2.8.

General Conditions
Revised: 7/20/22
GC-30 of 75
6.2.1.2
Dependencies between activities must be indicated so that it may establish as to the effect 
the progress of any one activity would have on other activities and on the Schedule.
6.2.1.3
Activities for submission, review, and approval of all required submittals.
6.2.1.4
An amount of time will
will be scheduled during this period.  Punch list and cleanup 
must be shown on the Project Schedule and must be entirely completed prior to the 
expiration of the Agreement Time.
6.2.2
Within 10 D
must make all required 
corrections, adjustments, and additions to complete the Project Schedule and resubmit to 
review of and response to the Project Schedule is for the purpose of:
(1) City planning and staffing for the Project as may be required from time to time; (2)
ensuring
general
conformance with the scheduling requirements of the
Agreement Documents and completion of the Project within the Agreement Time; and (3)
monitoring and evaluating the construction status for
purposes of approving monthly
progress payments.
Acceptance of a submitted schedule by City
should in no way be 
construed as an affirmation or admission that the schedule is reasonable or workable by
Contractor.
The responsibility for completing the Work on the Project within the
Agreement Time remains the obligation of Contractor.
review
does not relieve
Contractor from
compliance with the requirements of the Agreement Documents or
be construed as relieving Contractor of its complete and exclusive control over the
means, methods, sequences and techniques for executing the work.
6.2.3
The Project Schedule must show milestones, including milestones for City-furnished
information, and must include activities for City-furnished material and construction by
other contractors when those activities are interrelated with Contractor activities.
6.2.4
The Project Schedule must be revised as required by conditions and progress of the Work,
but such revisions do not relieve Contractor of its obligations to complete the Work
within the Agreement Time, as adjusted in accordance with the Agreement Documents.
No modification to the Agreement Documents or the Agreement Time will be effective
unless approved in advance by City.
6.2.5
For all items of materials and equipment that are critical or may require long lead times to 
acquire, the Project Schedule must show dates for submission, review and approval of 
submittals, ordering, and delivery.
6.2.6
An updated Project Schedule must be submitted monthly to City as part of the Payment
Request. The monthly submittal must include one full size plot of the entire schedule and 
one electronic copy containing the schedule in Microsoft Project standard file format. In
addition, Contractor must, upon request by City, provide a copy of all submitted schedule
data in electronic
format which must be clearly labeled with the Project description,
scheduling program name and version number, and schedule print/data date.
6.2.7
Contractor must provide City with a monthly status report with each Project Schedule
detailing the progress of the Work, including: (i) if the Work is proceeding according to
schedule, (ii) any discrepancies, conflicts, or ambiguities found to exist in the Agreement
Documents that require resolution, and (iii) other information detailing items that require
resolution so as not to jeopardize the ability to complete the Work in the Agreement Time.

General Conditions
Revised: 7/20/22
GC-31 of 75
6.2.8
With each Project Schedule submittal, Contractor must include a transmittal letter
including the following:
a.
Description of problem tasks, referenced to field instructions or requests
for information
as appropriate.
b.
Current and anticipated delays including:
(i)
Cause of the delay.
(ii)
Corrective action and schedule adjustments to correct the delay.
(iii)
Known or potential impacts and their delay on other activities,
milestones, and their impact on the Substantial Completion and
Final Acceptance dates.
(iv)
Changes in construction sequence.
c.
Pending items and status thereof including but not limited to:
(i)
Time Extension requests;
(ii)
Substantial Completion date status;
(iii)
Final Acceptance date status.
d.
If ahead of schedule, the number of calendar Days ahead.
e.
If behind schedule, the number of calendar Days behind.
f.
Other Project or scheduling concerns.
6.2.9
Critical Path Method (CPM).
6.2.9.1
Unless otherwise specified in the Agreement, the Project Schedule must include a Critical
Path
Method
(CPM)
diagram
schedule
showing
the
sequence
of
activities,
the
interdependence of each activity and identifies the Critical Path.
6.2.9.2
The CPM diagram schedule must be in calendar Days and indicate duration, earliest and
latest
start and finish dates for all activities, and total Float Times for all activities except
critical activities.
The CPM diagram must be presented in a time scaled graphical format for
the Project as a whole.
6.2.9.3
The CPM diagram schedule must indicate all relationships between activities.
6.2.9.4
The activities making the Project Schedule must contain sufficient detail to assure that
adequate planning has been done for proper execution of the Work and such that it provides
an appropriate
basis for monitoring and evaluation the progress of the Work. Individual
activities must not exceed 30 Days in length, in most cases.
6.2.9.5
The CPM diagram schedule must be based upon activities, which coincide with the Schedule
of Values.
6.2.9.6
The CPM diagram schedule must show all submittals associated with each work activity and
the review time for each submittal.
6.2.10
Float Time.
6.2.10.1
The total Float Time within the overall schedule is for the exclusive use of City, but City
may approve
use of Float as needed to meet Agreement Milestones and

General Conditions
Revised: 7/20/22
GC-32 of 75
the Project completion date.
6.2.10.2
Contractor will not be allowed to sequence, hide, or reallocate Float Time through
such strategies, as extending activity duration estimates to consume available Float, using
preferential logic, or using extensive crew/resource sequencing, tec. No time extensions
will be granted nor delay damages paid until a delay occurs which extends the Work beyond
the Agreement Time.
6.2.11
City-Caused Delays.  City-caused delays on the Project, if any, may be offset by City-caused
time
savings (i.e., Critical Path submittals returned in less time than allowed by the
Agreement, approval of substitution requests and credit changes which result in savings of
time to Contractor, etc.) In such an event, Contractor will not be entitled to receive a time
extension or delay damages until
all City-caused time savings are exceeded and the
Agreement Time is also exceeded.
6.2.12
Rain-Related Delays. Contractor is required, in preparing the Project Schedule to take into
account all relevant weather conditions, including normal rainfall and distribution. No
additional compensation will be given for any rain-related delays or impacts on the Work
or the Project Schedule. No time extension will be granted in the Project Schedule unless
the rainfall during the construction of Work is unusually severe, was not reasonably
anticipated, and the total rainfall was significantly in excess of the normal rainfall for the
Project Site location. Normal rainfall for the Project will be determined from the 10-year
average rainfall for the Site as measured by the
National Oceanic and Atmospheric
Administration or comparable source of reliable information for
rainfall in Chandler,
Arizona. In addition, the excessive rainfall must have actually impacted Work activities on
the Critical Path and caused delay beyond any remaining Float at the time of the rain- caused
delay. The burden of documenting normal rainfall, the excessive rainfall and the impact on
Critical Path activities is on Contractor. All other provisions in the Agreement Documents
relating to claims, including without limitation notice requirements, apply to any claim by
Contractor for a rain delay.
6.2.13
Statement for Calculating Delays and
Appendix 1 to these
General Conditions, will apply to all claims of delay and delay damages.
6.2.14
Force Majeure.  If Contractor is delayed or prevented from the performance of any Work 
required under this Agreement by reason of acts of God or other causes beyond the control 
and without fault of Contractor (financial inability excepted), performance of that Work will
be excused, but only for the period of the delay.  The time for performance of the Work will 
be extended for a period equivalent to the period of delay. In addition, the parties agree if 
from the COVID-
excused as set forth in this clause. Provided, however; Contractor must give the City written 
notice within 30 days of the occurrence of the event giving rise to COVID-19 pandemic 
related delayed or suspended performance. For COVID-19 pandemic related delay or 
suspended performance, the parties must agree in writing to the length of the excused 
approval to use any allowance established as part of the project for delays and costs related 
to the COVID-19 pandemic.
6.3
SUBSTANTIALCOMPLETION
6.3.1
When Contractor considers that the Work, phase or a portion thereof, which City agrees in

General Conditions
Revised: 7/20/22
GC-33 of 75
writing to accept separately, is substantially complete, City will prepare and submit to 
Contractor a comprehensive Punch List of items to be completed or corrected prior to Final 
Acceptance and Final Payment. Failure to include an item on such Punch List does not alter 
the responsibility of Contractor to complete all Work in accordance with the Agreement
Documents.
6.3.2
Upon receipt of
Punch List, Project Manager will make an inspection to
determine
whether the Work or designated portion thereof is substantially complete.
Project Manager may, at Project
sole option, be assisted in such inspection by
the Design Professional for the Project. If the inspection by the Project Manager discloses
any item, whether or not included
on
Punch List, which is not sufficiently
completed in accordance with the Agreement Documents so that City can occupy or utilize
the Work, phase or designated portion thereof for its
intended use, Contractor must,
before issuance of the Certificate of Substantial Completion, complete or correct such
item upon notification by Project Manager. In such case, Contractor must then submit a
request for another inspection by Project Manager to determine Substantial Completion.
6.3.3
Certificate of Substantial Completion.
6.3.3.1
The Project Manager will not issue a Certificate of Substantial Completion unless and until
the Work (or separable units or Phases as provided in the Agreement Documents) is
essentially and satisfactorily complete in accordance with the Agreement Documents, such
that the Project is ready for use by City for its intended purpose, opening to the general
public, full occupancy or use by City (including, without limitation, all separate units, or
rooms,facilities,access,income-generating areas, and all areas serving the general public,
as applicable, must be ready for full-operation
without material inconvenience or
discomfort), including, to the extent applicable to the Work, the
following: all materials,
equipment, systems, controls, features, facilities, accessories and similar
elements are
installed in the proper manner and in operating condition, inspected and approved;
surfaces have been painted; masonry and concrete cleaned with any sealer or other finish
applied; utilities and systems connected and functioning; site work complete; permanent
heating,
ventilation, air condition, vertical transportation and other systems properly
operating with proper controls; lighting and electrical systems installed, operable and
controlled; paving completed, signage installed, and other Work as applicable, has
been performed to a similar state of essential and satisfactory completion. A minor
amount of Work, as determined by and at the discretion of the Project Manager, such
as installation of minor accessories or items, a minor
amount of painting, minor
replacement of defective work, minor adjustment of controls or sound
systems, or 
completion or correction of minor exterior work that cannot be completed as a result of
weather conditions, will not delay determination of Substantial Completion. If prior
written
approval is obtained from City for purposes of Substantial Completion, specified
areas of the entire Work
or
Project may be
individually certified as
Substantially
Complete. In no event will Substantial Completion be deemed to have occurred unless
and until: (i) a temporary certificate of occupancy has been issued by the appropriate
Governmental Authorities (as applicable) and (ii) all terms and Work required under this
Agreement have been fulfilled by Contractor and same will have also been approved and
accepted by City, subject only to the Punch List items.
6.3.3.2
If requested by City, Contractor must complete and turn-over to City the Project on a phased
basis. Each phase will have a separate inspection by the Project Manager, a Punch List
generated, and then an inspection by City with final approval and acceptance only after the

General Conditions
Revised: 7/20/22
GC-34 of 75
Project
Punch List.
6.4
PARTIAL UTILIZATION
6.4.1
which has specifically been identified in the Agreement Documents, or which City, the 
Design Professional and Contractor agree constitutes a separately functioning and usable 
part of the Work that can be used by City for its intended purpose, without significant 
however, if the portion of the Work to be used or occupied has not been found to be 
substantially complete, City must do so in accordance with Section 6.3 prior to such 
occupancy.  
6.4.2
In lieu of the issuance of a Certificate of Substantial Completion as to part of the Work, City 
may take over operation of a facility constituting part of the Work whether or not it is 
substantially complete if such facility is functionally and separately usable; provided that 
prior to any such takeover, City and Contractor agree in writing as to the division of 
responsibilities between City and Contractor for security, operation, safety, maintenance, 
correction period, heat, utilities and insurance with respect to such facility.
6.4.3
Substantial Completion of or City's beneficial occupancy of a part of the Project will not alter 
the fact that the one-year warranty for the whole Project starts at the date of Final 
Completion of the whole Project.
6.5
FINAL ACCEPTANCE
6.5.1
Unless otherwise expressly agreed to in writing by City, Final Acceptance must be obtained
by no later than 30 Days (60Days for federally funded agreements) after the date of Substantial
Completion. Failure to timely obtain Final Acceptance will be a material breach of the
Agreement.
6.5.2
Upon receipt of written notice that the Work is ready for final inspection and acceptance, City
and Contractor will jointly inspect to verify that the remaining items of Work have been
completed. There will be no partial acceptance. Final Acceptance will not occur until all
items of Work, including Punch List Items, have been completed to 
satisfaction as
reflected in the written Final Acceptance.
6.5.3
Final Payment will not be due, owing, or paid by City until Final Acceptance is issued.
6.5.4
Landscape Establishment Period. Unless otherwise expressly agreed to in writing by City, the 
Landscape Establishment Period will begin on the date of Final Acceptance of the Project and 
will run 90 Calendar Days thereafter. Landscape Establishment Period requirements are 
detailed in General Conditions Appendices, attached herein.
6.6
CONTINUATION OF WORK
6.6.1
Permitting Contractor to continue and finish the Work or any part of it after the time fixed
for its completion (whether milestone, phase, Substantial Completion or Final Acceptance)
or after the date to which the time fixed for any completion may have been extended, does 
not operate as a waiver by City of any rights under the Agreement Documents, law or equity.
6.6.2
Furthermore, the timely completion of the Work being of the utmost importance under
this Agreement, notwithstanding the existence of one or more disputes between the parties

General Conditions
Revised: 7/20/22
GC-35 of 75
concerning the scope of the Work, the Project Schedule, Agreement Time, payments or any 
other matter, and further notwithstanding a
invocation of the Dispute Resolution
provisions specified in Appendix 6 of these General Conditions, unless City suspends
the Agreement or
performance pursuant to Section 10 of these General
Conditions, Contractor will continue to prosecute the Work, including any Change Order
work or Extra Work Orders, in a diligent and timely manner and not stop, slow down or
impede by action or inaction the progress of the Work, including commencing performance
of and thereafter completing any additional work called out in any Change Order or Extra
Work Order issued by Project Manager with the approval of City, so long as City makes
payment to Contractor in accordance with Section 8 of these General Conditions.
SECTION 7 - AGREEMENT PRICE
7.1
UNIT PRICE AGREEMENTS
7.1.1
The Agreement Price for all Unit Price Agreements will be the amount set forth in the
Agreement or Change Order multiplied by the verified quantity provided.
7.1.2
Measurements of quantities to determine the total Agreement Price must be in accordance
with MAG Specification §§ 109.1 and 109.2.
7.1.3
The Unit Price may only be changed as set forth in Section 9 below.
7.2
CHANGE ORDERS
7.2.1
Unit Price Change Orders. The Change Order Price for all Unit Price Change Orders will be
the amount set forth in the Change Order multiplied by the verified quantity provided.
7.2.2
Measurements of quantities to determine the total Change Order Price must be in
accordance with MAG Specifications §§ 109.1 and 109.2.
7.2.3
The Unit Price may only be changed as set forth in Section 9 below.
7.2.4
MAG Specification § 109.4.1 is modified as follows: Before § 109.4.1, the following is added:  
Any deduction or increase in the Agreement Price must be supported by a signed,
written Change Order fully executed by City, and supported by such backup as the Project
Manager may require.
7.3
SALES TAX
Contractor is required to pay all applicable sales tax in accordance with the law of the state of 
Arizona and this cost must be included in all Agreement Prices.  When equipment, materials 
or supplies generally taxable to Contractor are eligible for a tax exemption due to the nature 
of the Project, Contractor must assist City in applying for and obtaining such tax credits and 
exemptions which will be paid or credited to City.  
SECTION 8 - PAYMENT
8.1
PAYMENT FOR CONSTRUCTION SERVICES
8.1.1
Payment for the Work will be made in accordance with MAG Standard Specification § 109
as amended below.
8.1.2
Contractor must submit to City for review a completed Contractor Payment Request signed

General Conditions
Revised: 7/20/22
GC-36 of 75
by Contractor, covering the Work completed as of the date of the Request and accompanied 
by such supporting documentation as is required by the Agreement Documents and also 
as City may reasonably require. A Contractor Payment Request will not be considered 
complete unless it is accompanied by an updated Project Schedule and a certification that 
the on-site, red lined, as built Drawings are up to date.  If payment is requested on the basis 
of materials and equipment not incorporated in the Work but delivered and suitably, 
securely stored at the Site or at another location (such as a bonded warehouse) agreed to 
in writing, the Contractor Payment Request must also be accompanied by such data, 
satisfactory to City, as will establish City's title to the material and equipment and protect 
City's interest therein, including applicable insurance. Each subsequent Contractor Payment 
Request must include an affidavit of Contractor stating that all previous progress payments 
received on account of the Work have been applied to discharge in full all of Contractor's
obligations reflected in prior Contractor Payment Requests. 
8.1.3
Except for Work performed under a JOC Agreement, the Contracting Agency will retain 10 
percent of all estimates as a guarantee for complete performance of the Agreement in 
accordance with Arizona Revised Statutes Section 34-221 or 34-607. The Contractor may 
elect to deposit securities in lieu of retention in accordance with Arizona Revised Statutes 
Section 34-221, Paragraph C.5. or 34-607, Paragraph B.5.
8.1.4
The payment process functions as follows: Prior to the payment cycle date, Contractor must
send a draft Contractor Payment Request to Project Manager.  The Project Team will review 
the Request and agree upon any necessary adjustments.  Contractor must certify the final 
Request by signing and returning to Project Manager.
8.1.5
When construction of the Project is fifty percent (50%) completed, Contractor may
request payment of one-half of the retention pursuant to A.R.S. § 34-609(B)(3), subject to all
of
rights to withhold or offset payments, and other rights of City, under the Agreement.
8.1.6
City reserves the right under A.R.S. § 34-609(B)(3) to reinstate the ten percent (10%) retention
if City determines that satisfactory progress is not being made.
8.1.7
.
8.1.7.1
Contractor warrants and guarantees that title to all Work, materials and equipment covered 
by any Contractor Payment Request, whether incorporated in the Project or not, will pass 
to City at the time of payment, free and clear of all liens, claims, security interests, and 
encumbrances, provided that this will not preclude the Contractor from installing metering 
devices or other equipment of utility companies or municipalities, the title of which is 
commonly retained by the utility company or municipality.
8.1.7.2
No materials, supplies, or equipment for the Work under this Agreement will be purchased 
subject to any chattel mortgage or under a conditional sale contract or other agreement by 
which an interest therein, or any part thereof, is retained by the seller or supplier.
8.1.7.3
Nothing contained in this Section will defeat or impair the right of such persons furnishing 
materials or labor under any bond given by the Contractor for their protection, or any right 
under any law permitting such persons to look to funds due the Contractor in the hands of 
the City. The provisions of this Section must be inserted in all subcontracts and material 
agreements, and notices of its provision must be given to all persons furnishing materials 
for the Work when no formal agreement is entered into for such materials.

General Conditions
Revised: 7/20/22
GC-37 of 75
8.2
PAYMENT UPON SUBSTANTIAL COMPLETION
8.2.1
No payment will be made upon Substantial Completion, except for a regularly-scheduled
monthly progress payment, as allowed by Section 8.2.2.
8.2.2
No further payments will be made to Contractor until Final Acceptance.
8.3
FINAL PAYMENT
8.3.1
Subject to all of
rights to withhold or offset payment, and other rights under the
Agreement, Final Payment including remaining retainage will be paid only after:
a.
Work has been fully completed (including completion of all incorrect or
incomplete work items) and the written Final Acceptance has been issued by
City;
b.
Necessary operating manuals, any excess materials and supplies necessary
for matching
materials
and
supplies
incorporated
into
the
Work,
acceptable sewer video results
(if applicable), and complete
-
Drawings (including the Building Information Model, if required by the
Agreement Documents) have been delivered to City, as specified in this
Section 8.3;
c.
Full and unconditional lien waivers and releases by Contractor and any
person performing labor or supplying material, machinery, fixtures, or tools
for the Work have been delivered to Contractor;
d.
All conditions and requirements imposed by City or any financing entity
for the corresponding disbursement have been met; and
e.
Contractor delivers to City a Contractor Payment Request requesting Final
Payment.
8.3.2
Contractor must also submit a signed copy of
Affidavit Regarding Settlement
of Claims, Appendix 3 to these General Conditions, and Certificate of Completion, Appendix 7 
to these General Conditions, prior to Final Payment.
8.3.3
In addition, if required under the Project Specific Special Provisions, Contractor must
compile a complete equipment list and maintenance manual to be submitted to City
as a precondition to Final Payment. The list must include the following items for all
equipment supplied under the Plumbing, Electrical, Air Conditioning, Elevator, and other
Special Equipment Specifications:
a.
Name, Model and Manufacturer.
b.
Complete parts lists and Drawings.
c.
Local source of supply for replacement parts along with
telephone
numbers.
d.
Local service organizations serving the equipment and their telephone
numbers.
e.
All
tags,
inspection
slips,
instruction
packages,
etc.,
removed
from
equipment must be
properly identified as to pieces of equipment from
which they were taken.

General Conditions
Revised: 7/20/22
GC-38 of 75
8.3.4
Contractor must also deliver to City, prior to Final Payment, one (1)
digital (in the format
specified by City), and if requested by City, one (1) hard copy, of any
applicable
Maintenance manuals. Each manual must include all
operation and
maintenance instructions and
-
Drawings with the list herein specified. It must also
include all other diagrams and instructions necessary to properly operate and maintain the
equipment, the name, address and telephone number of Contractor and all Subcontractors
involved.
8.4
CITY
RIGHT TO WITHHOLD PAYMENT
City may withhold payment to such extent as may be necessary in
opinion to protect
City from loss for which Contractor is responsible, including, without limitation, if any of
the following conditions exist:
a.
Defective Work not remedied;
b.
Third party claims filed or reasonable evidence indicating probable filing of
such claims unless security acceptable to City is provided by Contractor;
c.
Failure of Contractor to make payments properly to Subcontractors or for
labor, materials or equipment;
d.
Reasonable evidence that the Work cannot be completed for the unpaid
balance of the Agreement Price;
e.
Damage to City or another Contractor;
f.
Reasonable evidence that the Work will not be completed within the 
Agreement Time, and that the unpaid balance would not be adequate to
cover actual or liquidated damages for the anticipated delay;
g.
Failure to carry out the Work in accordance with the Agreement Documents;
or
h.
Contractor is in default of any of its other obligations under the Agreement
Documents.
8.5
JOINT/DIRECT CHECKS
To promote the timely completion and progress of the Work or when appropriate and 
necessary, payments to Contractor may be made jointly to Contractor and its employees, 
agents, Subcontractors and suppliers, or any of them. For federally funded agreements, 
see federal provisions for additional requirements for the joint check process.
8.6
PAYMENT NOT A WAIVER
No payment (nor use or occupancy of the Project by City) will be deemed acceptance or
approval of the Work or as a waiver of any claims, rights, or remedies of City.
8.7
LIENS AND BOND CLAIMS
Contractor must make all payments, in the time required, of all labor and materials
furnished to Contractor in the course of the Work and must promptly furnish evidence of
such payments as City may require. Contractor must pay when due all claims arising out of
performance of the Work covered by this Agreement for which a lien may be filed either
against the real estate or leasehold interest of City, or against payments due from City to
Contractor, or for which a claim may be made against any payment or performance bond
or both. To the fullest extent permitted by law, Contractor agrees that no liens or other
claims in the nature of a lien against the real estate, leasehold, or other interest of City,

General Conditions
Revised: 7/20/22
GC-39 of 75
against payment due from City to Contractor, or against any payment or performance
bond, must be filed or made in connection with the Work by any party
who has supplied
professional services, labor, materials, machinery, fixtures, tools, or equipment used in or
in connection with the performance of this Agreement, and Contractor agrees to remove or
to cause to be removed any such liens or claims in the nature of a lien or bond claim within
10 Days upon receiving notice or obtaining actual knowledge of the existence of such liens
or claim. In addition, Contractor agrees to defend, indemnify, and hold harmless City
from and against any and all such liens and claims. This paragraph does not apply to claims
and liens of Contractor due to non-payment for work performed.
8.8
FINANCIAL RECORDKEEPING AND CITY
AUDIT RIGHT
8.8.1
Records for all Agreements between City and Contractor must, upon reasonable notice, be
open to inspection and subject to audit, scanning, and reproduction during normal
business working hours. Such audits may be performed by any
representative or any
outside representative engaged by City for the purpose of examining such records. City or
its designee may conduct such audits or inspections throughout the term of this Agreement
and for a period of five years after
Final Payment or longer if required by law.
representatives may (without limitation) conduct verifications such as counting employees
at the Site, witnessing the distribution of payroll, verifying information and amounts through
interviews and written confirmations with Contractor employees,
field and agency labor,
Subcontractors, and vendors.
8.8.2
must include any and all information, materials and data of every kind
and
character,
including
without
limitation,
records,
books,
papers,
documents,
subscriptions, recordings, agreements, purchase orders, leases, contracts, commitments,
arrangements, notes daily diaries, superintendent reports, drawings, receipts, vouchers and
memoranda, and any and all other agreements, sources of information and matters that
may in
judgment have any
bearing on or pertain to any matters, rights, duties or
obligations under or covered by anyAgreement Document. Such records must include (hard
copy, as well as computer readable data if it can be made available), written policies and
procedures; time sheets; payroll registers; payroll records;
cancelled payroll checks;
subcontract files (including proposals of successful and unsuccessful bidders, bid recaps,
negotiation notes, etc.); original bid estimates; estimating work sheets; correspondence;
Change Order files (including documentation covering negotiated settlements);
back-
charge logs and supporting documentation; invoices and related payment documentation;
general ledger, information detailing cash and trade discounts earned, insurance rebates
and dividends; and any other Contractor records which may have a bearing on matters of
interest to City or the Project in connection with
dealings with City or the
Project (all foregoing
hereinafter referred to as
to the extent necessary to
adequately permit evaluation and verification of any or all of the following:
a.
Compliance with Agreement requirements for deliverables;
b.
Compliance with approved Plans and Specifications;
c.
Compliance with § 14.9 below;
d.
Compliance with Agreement provisions regarding the pricing of Change
Orders;
e.
Accuracy of Contractor representations regarding the pricing of invoices; or
f.
Accuracy of Contractor representations related to claims submitted by

General Conditions
Revised: 7/20/22
GC-40 of 75
Contractor or any of their employees.
8.8.3
Contractor must require all payees (examples of payees include Subcontractors, Suppliers, 
Insurance Carriers, etc.) to comply with the provisions of this Section by including the 
requirements hereof in a written agreement between Contractor and payee. Contractor will 
ensure that all payees (including those entering into lump sum agreements) have the same 
right to audit provisions contained in this Agreement included in their agreements with 
Contractor.
8.8.4
must have 
must be allowed to interview all current or former 
employees to discuss matters pertinent to the performance of this Agreement and must be 
provided adequate and appropriate work space, in order to conduct audits in compliance 
with this Section.
8.8.5
If an audit inspection or examination in accordance with this Section, discloses overpricing
or overcharges to City (of any nature) by Contractor or
Subcontractors in excess
of $100,000 in addition to making adjustments for the overcharges, the reasonable actual
cost of
audit must be reimbursed to City by Contractor. Any adjustments or payments
which must be made as a result of any such audit or inspection of
invoices or 
records must be made within a reasonable amount of time (not to exceed 90 Days) from
presentation of
findings to Contractor.
8.8.6
In addition to the normal paperwork documentation Contractor typically furnishes to City, 
Contractor agrees to furnish, upon written request from City, any of the documentation 
necessary for City to exercise its audit rights under this Section 8.8 in computer readable file 
formats (Word, Excel, or .pdf), as City may designate.
8.8.7
City, its authorized representative, and the appropriate agency, reserve the right to
audit
records in compliance with local, state or federal policies, statutes
or at
discretion, within three (3) years of Final Acceptance of the Work.
SECTION 9 - CHANGES TO THE AGREEMENT
9.1
FIELD ORDERS
City may authorize minor changes in the Work not involving an adjustment in the 
Agreement Price or the Agreement Times, which are consistent with the overall intent of 
the Agreement Documents.  These may be accomplished by a written Field Order on the 
standard form approved and executed by City.  Such Field Orders must be binding and 
Contractor must perform the change promptly. If Contractor believes that a Field Order 
justifies an increase in the Agreement Price or Agreement Time, Contractor may make a 
claim therefor as provided in Section 7.2.
9.2
EXTRA WORK/CHANGES IN THE WORK
9.2.1
City reserves the right to make such changes in the Plans and Specifications for the Work,
as it may deem appropriate and any such change as set forth in a written Change Order
must be deemed a part of this Agreement as if originally incorporated herein.
9.2.2
In the event City and Contractor cannot agree on the terms of a Change Order, or
when circumstances otherwise require, the Project Manager has the authority to direct the
Contractor to perform extra work, if the work in question is an item not provided for in the

General Conditions
Revised: 7/20/22
GC-41 of 75
Agreement as awarded. The Project Manager will have the authority to determine, based
upon factual evidence presented by the Contractor, whether the work in question is an
item not provided for in the Agreement as awarded. If the Project Manager directs the
Contractor to perform extra work, the Project
instructions will include a price
that the Contractor cannot exceed in charging the City for the extra work. Upon receipt of
the Project
directions to perform extra work,
the Contractor must promptly
proceed with the extra work and document the actual cost thereof.
right to
payment for extra work will be determined under Subsection 9.2.4 below. The Contractor is
responsible to manage the extra work to ensure that the price limits set by the Project
Manager are not exceeded. Contractor must perform the extra work and submit
documentation for the actual cost of the extra work to the City. A Change Order will be
issued to cover this work.
9.2.3
Contractor will not be entitled to payment for extra work unless a written Change Order, in
form and content prescribed by City, has been executed by City. On all requests for Change
Orders, Contractor must specify the increased or decreased costs and whether it
believes any extensions of time will be necessary to complete its Work as modified by the
Change Order. If extra work is performed under Subsection 9.2.2 above, a corresponding
Change Order will be prepared, approved and processed by City before payment can be
made to Contractor.
9.2.4
In general, pricing for Change Orders will include the same mark-up percentages that were
in effect when the Agreement was awarded. The cost or credit to the City resulting from a
change in the Work is subject to Appendix 1 (Policy Statement for Calculating Delays and
Damages) and will be determined, based on the type of pricing for the Agreement involved,
as follows:
a.
By mutual acceptance of a lump sum properly itemized in a form acceptable
to City;
b.
By unit prices stated in the Agreement Documents;
c.
When the City determines that a Unit Price Book Job Order associated with
a Job Order Agreement requires a Change Order, by using the same Total
Cost Data and CCI that are in effect when the Change Order is anticipated to
be issued; or
d.
By actual cost and a percentage fee covering overhead and profit, as follows:
(i)
Contractor will perform the extra work and be compensated for actual
cost of labor, materials and equipment.
(ii)
Contractor will have the right to add the fee percentage applicable
to the Work under the Agreement, or if no such fee has been agreed
to by the parties, not more
than
five
percent
(5%)
to
the
prices for authorized extra work performed solely
by Subcontractors. Such percentage will include all of
charges for overhead, profit, administration and supervision.
(iii)
Contractor or Subcontractor will have the right to add the fee
percentage applicable
to Work under the Agreement for self-
performed extra work, or if no such fee has been agreed to by the
parties,
or
maximum total allowable
additions for overhead, profit, administration and supervision will

General Conditions
Revised: 7/20/22
GC-42 of 75
not exceed ten percent (10%) of actual verifiable labor, materials
and equipment for such self- performed extra work.
9.2.5
Any agreement which modifies the terms of the Agreement (including Change Orders)
will be approved in writing by the Project Manager. Once properly executed by both
parties, these modifications to the Agreement will have the same effect as if they had been
included in the original Agreement.
9.3
ACCURACY OF CHANGE ORDER PRICING INFORMATION
9.3.1
Subject to Sections 9.3.2 through 9.3.4, signature by the contracting parties constitutes full 
accord and satisfaction between City and Contractor for all costs, damages, and expenses
of whatever kind of nature, including delay, impact or acceleration damages, which may be
occasioned by a Change Order of other modification of the Agreement agreed to in writing.
9.3.2
Accurate Change Order Pricing Information: Contractor agrees that it is responsible for
submitting accurate cost and pricing data to City to support its Fixed Price, Unit Price, or
Cost Plus Change Order Proposals or other Agreement Price adjustments under the
Agreement. Contractor further agrees to submit Change Order proposals with cost and
pricing data which is accurate, complete, current, and in accordance with the terms of
the Agreement with respect to pricing of change orders. Contractor agrees that any
-
out
on Change Orders will accrue 100% to Owner.
-out
are defined
as any savings negotiated by the Contractor with
a Subcontractor or a Material Supplier
after receiving approval of a Change Order amount that was designated to be paid to a
specific Subcontractor or Supplier for the Approved Change Order work.
9.3.3
Right to Verify Change Order Pricing Information: Contractor agrees that City, through
its designated representative, will have the right to examine, copy, and scan the records
of the Contractor, Subcontractor or Sub-
records (during the Agreement
period and up to three years after final payment is made on the Agreement) to verify
the accuracy and appropriateness of the pricing data used to price all Change Order
proposals or claims. Contractor agrees that if City determines the cost and pricing data
submitted (whether approved
or not) was inaccurate, incomplete, not current, or not in
compliance with the terms of the Agreement
regarding pricing of Change Orders, an
appropriate Agreement Price adjustment will be made. Such post-approval Contact Price
adjustments will apply to all levels of contractors and Subcontractors and to all types of
Change Order proposals, specifically including Fixed Price, Unit Price, and Cost Plus Change
Orders.
9.3.4
Requirements for Detailed Change Order Pricing Information: Contractor agrees to
provide a detailed breakdown of allowable labor and labor burden cost (i.e., base wage
rate of applicable classifications of workers, payroll taxes, and insurance and benefits
costs).  This information will be used to evaluate the potential cost of labor and labor burden
related to Change Order work. It is intended that this information represent an accurate
estimate of the
actual labor and labor burden cost components. Information
is not intended to establish fixed billing or Change Order pricing labor rates. However, at the
time Change Orders are priced, the submitted cost data for labor rates may be used to price
Change Order work. The accuracy of any such agreed upon labor rate cost components
used to price Change Orders will be subject to later audit.
Approved
Change Order
amounts
may be adjusted
later
to
correct
the
impact
of
inaccurate labor
cost
components if the agreed upon labor cost components are determined to be inaccurate.

General Conditions
Revised: 7/20/22
GC-43 of 75
9.4
EMERGENCIES
In any emergency affecting the safety of persons or property, Contractor will act, at its
discretion, to prevent threatened damage, injury or loss. Any change in the Agreement Price
or Agreement Time resulting from emergency work will be determined as provided in this
Section.
9.5
DIFFERING SITE CONDITIONS
9.5.1
If Differing Site Conditions are encountered at the Project Site, then notice by the observing
party mustbegiventothe otherpartypromptlybefore conditions are disturbed(tothe extent
practicable) and in no event later than 14 Days after first observance of the conditions.
City will promptly investigate such conditions and, if City determines that Differing Site
Conditions exist and they materially cause an increase in the cost of, or time required for,
performance of any part of the Work, Contractor will be entitled to equitable adjustment
in the Agreement Price or Construction Schedule (and other time requirements), or both.
If it is determined by City that the conditions at the Project Site are not Differing Site
Conditions and no change is justified, then City will sonotifyContractor in writing,stating the
reasons. Claims in opposition to such determination
must be made within 14 Days after
City has given notice of its decision. If City and Contractor cannot agree on an adjustment
in the Agreement Price or Construction Schedule (and other time requirements), the
adjustment may be submitted to dispute resolution as provided these GeneralConditions.
9.6
CHANGES IN LAWS, REGULATIONS, OR LEGAL REQUIREMENTS OR TAXES
In the event of a material change in applicable Laws, Regulations, or Legal Requirements, or
taxes subsequent to the date of the Agreement by the parties, Contractor may be entitled
to a Change Order, in
discretion, to the extent Contractor can document to the
satisfaction of City that
such change significantly increases
actual cost of
performance of the Work.
SECTION 10 -SUSPENSION AND TERMINATION
10.1
SUSPENSION
City may suspend the Agreement
Specifications § 105.1 and 108.7.
10.2
TERMINATION BY THE CITY FOR CAUSE
10.2.1
MAG Specifications § 108.11 applies to the Agreement.
10.2.2
City may also terminate the Agreement if City determines, in its sole discretion that
Contractor has:
a.
After prior written notice, refused or failed to supply enough properly skilled
workers or proper materials;
b.
After prior written notice, failed to make payment to Subcontractors for
materials or labor in accordance with the
respective agreements between
Contractor and the Subcontractors;
c.
After prior written notice, disregards laws, ordinances, or rules, regulations or
orders of a public authority having jurisdiction;
d.
After prior written notice, repeatedly failed to comply with written directives 
from City;

General Conditions
Revised: 7/20/22
GC-44 of 75
e.
Is adjudged as bankrupt or insolvent;
f.
Made a general assignment for the benefit of creditors;
g.
Appointed a trustee or receiver for itself or any of its property;
h.
Filed a petition to take advantage of any debtor's act, or to reorganize under 
the bankruptcy or similar laws; or
i.
Otherwise breached a provision of the Agreement Documents or any other
Agreement between City and Contractor.
10.2.3
When any of the above reasons exist, City may terminate the Agreement, without prejudice
to any other rights or remedies of City, after giving Contractor and
surety, if
any, 7
Days written notice of
intent to terminate the Agreement and
failure to cure any such reasons. Upon such termination, City may: (1) take possession of
the Site and of all materials thereon owned by Contractor; or (2) finish theWork bywhatever
reasonable method City may deem expedient. When City terminates the Agreement for one
of the reasons state above, Contractor will not be entitled to receive further payment until
the Work is finished. If the unpaid balance of the Agreement Price existing at the time of
such termination exceeds the costs and expenses of finishing the Work and any other
damages incurred by City, such excess will be paid to Contractor. If such costs, expenses
and damages exceedsuchunpaid balance,Contractor must pay the difference to City. This
obligation for payment will survive termination of the Agreement.
10.3
TERMINATION BY CITY FOR CONVENIENCE
City may also terminate the Agreement at any time for its convenience upon 7 Days written
notice to Contractor specifying the termination date. In the event of termination which is
not the fault, in whole or in part, of Contractor, City will pay to Contractor only such
compensation, including reimbursable expenses, due for Work properly performed on
the Project prior to the termination date. Upon any termination of the Agreement, no
further payments will be due from City to Contractor.
10.4
A.R.S. § 38-511
The Agreement is subject to, and may be terminated by City in accordance with, the
provisions of A.R.S. § 38-511.
SECTION 11 -INSURANCE AND BONDS
11.1
INSURANCEREQUIREMENTS
11.1.1
After Agreement award, the Contractor must furnish the City a certificate of insurance on a 
standard insurance industry ACORD form.  The ACORD form must be issued by an insurance 
company authorized to transact business in the State of Arizona possessing a current A.M. 
Best, Inc. rating of A-7, or better and legally authorized to do business in the State of Arizona 
with policies and forms satisfactory to City.  Provided, however, the A.M. Best rating 
requirement may
11.1.2
The Contractor and any of its Subcontractors must procure and maintain, until all of their 
obligations have been discharged, including any warranty periods under this Agreement are 
satisfied, the insurances set forth below.
11.1.3
The insurance requirements set forth below are minimum requirements for this Agreement
and in no way limit the indemnity covenants contained in this Agreement.

General Conditions
Revised: 7/20/22
GC-45 of 75
11.1.4
The City in no way warrants that the minimum insurance limits contained in this Agreement
are sufficient to protect Contractor from liabilities that might arise out of the performance 
of the Agreement services under this Agreement by Contractor, its agents, representatives, 
employees, or Subcontractors and the Contractor is free to purchase any additional 
insurance as may be determined necessary.
11.1.5
Failure to demand evidence of full compliance with the insurance requirements in this 
Agreement or failure to identify any insurance deficiency will not relieve the Contractor
from, nor will it be considered a waiver of its obligation to maintain the required insurance 
at all times during the performance of this Agreement.
11.1.6
Use of Subcontractors:  If any Work is subcontracted in any way, the Contractor must
execute a written agreement with Subcontractor containing the same Indemnification 
Clause and Insurance Requirements as the City requires of the Contractor in this 
Agreement.  The Contractor is responsible for executing the Agreement with the 
Subcontractor and obtaining Certificates of Insurance and verifying the insurance 
requirements.
11.2
MINIMUM SCOPE AND LIMITS OF INSURANCE
11.2.1
The Contractor must provide coverage with limits of liability not less than those stated 
below.
11.2.1.1
Commercial General Liability-Occurrence Form.  Contractor 
form Commercial General Liability insurance with a limit of not less than $2,000,000 for each 
occurrence, $4,000,000 aggregate.  Said insurance must also include coverage for products 
and completed operations, independent contractors, personal injury and advertising injury. 
If any Excess insurance is utilized to fulfill the requirements of this paragraph, the Excess 
ge scope than underlying 
insurance.
11.2.1.2
Automobile Liability-Any Automobile or Owned, Hired and Non-Owned Vehicles.  Contractor
must maintain Business/Automobile Liability insurance with a limit of $1,000,000 each 
accident on Contractor owned, hired, and non-owned vehicles assigned to or used in the 
performance under this Agreement.  If any Excess or Umbrella insurance is utilized to fulfill 
11.2.1.3
Workers Compensation and Employers Liability Insurance.  Contractor must maintain 
Workers Compensation insurance to cover obligations imposed by federal and state 
statutes having jurisdiction of Contractor employees engaged in the performance of Work 
under this Agreement and must also
$1,000,000 for each accident and $1,000,000 disease for each employee. 
11.2.1.4
.  The Contractor bears all responsibility for loss 
to all equipment or Work under construction.  Unless waived in writing by the City the 
Contractor 
on the entire Work until completed and accepted by the City.  This insurance will be Special 
Causes of Loss policy form, (minimally including perils of fire, flood, lightning, explosion, 
windstorm and hail, smoke, aircraft and vehicles, riot and civil commotion, theft, vandalism, 
malicious mischief, and collapse), completed value, replacement cost policy form equal to 
the Agreement Price and all subsequent modifications.  The

General Conditions
Revised: 7/20/22
GC-46 of 75
Risk/Installation Floater insurance must be primary and not contributory.
a.
surance must provide coverage from the 
time any covered property comes under the 
control and or 
responsibility, and continue without interruption during course of 
construction, renovation and or installation, including any time during which 
any Project property or equipment is in transit, off Site, or while on Site for 
future use or installation.  Insured property must include, but not be limited 
to, scaffolding, false work, and temporary buildings at the Site.  This 
insurance must also cover the cost of removing debris, including demolition 
as may be legally required by operation of any law, ordinance, regulation or 
code.
b.
The Contractor must also purchase and maintain Boiler and Machinery 
insurance cited above if the Work to be performed involves any exposures 
or insurable property normally covered under a Boiler and Machinery 
insurance policy or made necessary as required by law or testing 
requirements in the performance of this Agreement.  The Contractor will be 
responsible for any and all deductibles under these policies and the 
Contractor waives all rights of recovery and subrogation against the City 
under the Contractor-
herein.
c.
whichever of the following first occurs: (i) final payment has been made; or, 
(ii) until no person or entity, other than the City, has an insurable interest in 
the property required to be covered.
d.
the insurance will not be canceled or lapse because of any partial use or 
occupancy by the City.
e.
The Builders Risk/Installation Floater insurance must include as named 
insureds, the City, the Contractor, and all tiers of Subcontractors and others 
with an insurable interest in the Work who will be named as additional 
insureds unless they are able to provide the same level of coverage with the 
City and Contractor named as additional insureds. Certificates must contain 
a provision that the insurance will not be canceled or materially altered 
without at least 30 Days advance notice to the City.  The City must also be 
f.
The Builders Risk/Installation Floater insurance must be written using the 
Special Causes of Loss policy form, replacement cost basis.
g.
All rights of subrogation under the Builders Risk/Installation Floater 
insurance are, by this Agreement, waived against the City, its officers, 
officials, agents and employees.
h.
The Contractor is responsible for payment of all deductibles under the

General Conditions
Revised: 7/20/22
GC-47 of 75
11.2.1.5
Pollution Liability Insurance (Including Errors and Omissions).  For Job Orders, Pollution 
Liability Insurance is only required if applicable and determined on a project specific basis.  
Contractor must maintain Pollution Liability Insurance with a limit of not less than 
$5,000,000 per loss, $5,000,000 aggregate for losses caused by pollution conditions 
including coverage for bodily injury, property damage, defense costs, clean-up costs, and 
completed operations that arise from the operations of Contractor as described in this 
Agreement. 
a.
The policy must provide for complete professional service coverage, 
including coverage for pollution liability that is a result of a breach of 
professional duties.
b.
The policy must provide for protection again claims for third-party bodily 
injury, property damage, or environmental damage caused for pollution 
conditions resulting from general contracting activities for which Contractor 
is legally liable.
c.
The policy must provide for cleanup costs when mandated by governmental 
entities, when required by law, or as a result of third-party claims.
d.
Completed Operations Coverage must be kept in place for up to the statute 
of repose.
e.
The policy must be endorsed to include the following additional insured 
volunteers must be named as additional insureds with respect to liability 
arising out of the activities perform
f.
If Work under this Agreement requires the transportation of any hazardous 
material or regulated substances, Contractor must carry Auto Liability with a 
CA 9948 endorsement or equivalent.  
g.
If Work under this Agreement requires the disposal of any hazardous 
materials from the job site, Contractor must obtain a certificate of insurance 
for Pollution Legal Liability from the disposal site operator with a limit of not 
less than $5,000,000 per loss, $5,000,000 aggregate.
11.3
ADDITIONAL POLICY PROVISIONS REQUIRED
11.3.1
Self-Insured Retentions or Deductibles.  Any self-insured retentions and deductibles must 
be declared and approved by the City.  If not approved, the City may require that the insurer 
reduce or eliminate any deductible or self-insured retentions with respect to the City, its 
officers, officials, agents, employees, and volunteers.
11.3.2
The Contractor
insurance must contain broad form contractual liability coverage.
11.3.3
The Contractor's insurance coverage must be primary insurance with respect to the City, its 
officers, officials, agents, and employees.  Any insurance or self-insurance maintained by 
the City, its officers, officials, agents, and employees will be in excess of the coverage 
provided by the Contractor and must not contribute to it.
11.3.4
The Contractor's insurance must apply separately to each insured against whom claim is 
made or suit is brought, except with respect to the limits of the insurer's liability.
11.3.5
Coverage provided by the Contractor must not be limited to the liability assumed under the

General Conditions
Revised: 7/20/22
GC-48 of 75
indemnification provisions of this Agreement.
11.3.6
The policies must contain a severability of interest clause and waiver of subrogation against 
the City, its officers, officials, agents, and employees, for losses arising from Work 
performed by the Contractor for the City.
11.3.7
The Contractor, its successors and or assigns, are required to maintain Commercial General 
Liability insurance as specified in this Agreement for a minimum period of 3 years following 
completion and acceptance of the Work.  The Contractor must submit a Certificate of 
Insurance evidencing Commercial General Liability insurance during this 3 year period 
containing all the Agreement insurance requirements, including naming the required 
Additional Insureds set forth herein.
11.3.8
If a Certificate of Insurance is submitted as verification of coverage, the City will reasonably 
rely upon the Certificate of Insurance as evidence of coverage but this acceptance and 
reliance will not waive or alter in any way the insurance requirements or obligations of this 
Agreement.  
11.3.9
Insurance Cancellation During Agreement Term.  
11.3.9.1
If any of the required policies expire during the life of this Agreement, the Contractor must 
forward renewal or replacement Certificates to the City within 10 Days after the renewal 
date containing all the required insurance provisions.
11.3.9.2
Each insurance policy required by the insurance provisions of this Agreement must provide 
the required coverage and must not be suspended, voided or canceled except after 30 Days 
prior written notice has been given to the City, except when cancellation is for non-payment 
of premium, then 10 Days prior notice may be given.  Such notice must be sent directly to 
Chandler Law-Risk Management Department, Post Office Box 4008, Mailstop 628, Chandler, 
Arizona  85225. If any insurance company refuses to provide the require notice, the 
Contractor or its insurance broker must notify the City of any cancellation, suspension, non-
renewal of any insurance within 7 D
11.3.10
City as Additional Insured.  The above-referenced policies are to contain, or be endorsed to 
contain, the following provisions:
11.3.10.1
The Commercial General Liability and Automobile Liability policies are to contain, or be 
endorsed to contain, the following provisions:  The City, its officers, officials, agents, and 
employees are additional insureds with respect to liability arising out of activities performed 
by, or on behalf of, the Contractor including the City's general supervision of the Contractor; 
Products and Completed Operations of the Contractor; and automobiles owned, leased, 
hired, or borrowed by the Contractor.
11.3.10.2
The City, its officers, officials, agents, and employees must be additional insureds to the full 
limits of liability purchased by the Contractor even if those limits of liability are in excess of 
those required by this Agreement.
11.4
BONDS AND OTHER PERFORMANCE SECURITY
11.4.1
After Agreement award, Contractor must provide a Performance Bond and a Payment
Bond, each in an amount equal to the full amount of the Agreement Price.
11.4.2
Each such bond must be executed by a surety company or companies holding a Certificate

General Conditions
Revised: 7/20/22
GC-49 of 75
of Authority to transact surety business in the State of Arizona, issued by the Director of the
Arizona Department of Insurance and must be named in the current list of "Companies 
Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable 
Reinsuring Companies" as published in Circular 570 (amended) by the Audit Staff Bureau of 
Accounts, U.S. Treasury Department. A copy of the Certificate of Authority must accompany
the bonds. The Certificate must have been issued or updated within two (2) years prior to
the execution of this Agreement. The bonds must be written or countersigned by an
authorized representative of the surety who is either a resident of the state of Arizona or
whose principal office is maintained in this state, as by law required.
11.4.3
The bonds must be made payable and be acceptable to City. The bond forms for the
performance and payment bonds must be in the forms required under A.R.S. § 34-221, et.
Seq., as in Appendices 4 and 5 of these General Conditions.
11.4.4
Upon the request of any person or entity appearing to be a potential beneficiary of bonds
covering payment of obligations arising under the Agreement Documents, Contractor must
promptly furnish a copy of the bonds or must permit a copy to be made.
11.4.5
All bonds submitted for this Project must be provided by a company which has been rated AM
Best rating of A- or better for the prior four quarters by the latest edition of the
Key Rating Guide
published by the A.M. Best Company.
11.4.6
Personal or individual bonds are not acceptable.
11.4.7
If the surety on any Bond furnished by Contractor is declared a bankrupt or becomes 
the Project is located, or it ceases to meet the requirements of this Section 11.4, Contractor
must within 5 Days thereafter substitute another Bond and surety, both of which must be 
acceptable to City.
SECTION 12 - INDEMNIFICATION
12.1
To the extent permitted by law, the Contractor and its owners, officers, directors, agents, 
employees, and subconsultants (collectively "lndemnitor") must indemnify, save, and hold 
harmless the City and its officers, officials, agents, and employees (collectively "lndemnitee") 
from any and all claims, actions, liabilities, damages, losses, or expenses (including court 
costs, attorneys' fees, and costs of claim processing, investigation, and litigation) (collectively 
"Claims") caused or alleged to be caused, in whole or in part, by the negligent, reckless, 
wrongful, or willful acts, errors, or omissions of Indemnitor in connection with this 
Agreement. This indemnity includes any Claim or amount arising out of or recovered under 
workers' compensation laws or on account of Indemnitor's failure to conform to any federal, 
state, or local law, statute, ordinance, rule, regulation, or court decree. Indemnitor must 
indemnify lndemnitee from and against any and all Claims, except those arising solely from 
lndemnitee's own negligent, reckless, wrongful, or willful acts, errors, or omissions. 
Indemnitor is responsible for primary loss investigation, defense, and judgment costs where 
this indemnification applies. In consideration of the award of this Agreement, Indemnitor 
agrees to waive all rights of subrogation against lndemnitee for losses arising from or 
related to this Agreement. Indemnitor's obligations under this provision survive the 
termination or expiration of this Agreement.
SECTION 13 -DISPUTE RESOLUTION

General Conditions
Revised: 7/20/22
GC-50 of 75
13.1
All disputes arising out of or relating to the Agreement, the Work or the Project, other than
termination under Section 10, will be resolved pursuant to the Dispute Resolution
process set forth in Appendix 6 of these General Conditions, and not pursuant to MAG
Specifications § 110.
13.2
Contractor agrees that during any dispute between the parties, Contractor will continue to
perform its obligations under the Agreement until such dispute is resolved.
13.3
Notwithstanding any other provision in this Agreement, City has the right to immediately file
in court and pursue an action for a temporary restraining order and injunctive relief against
Contractor if City determines that such action is necessary to protect its interests under the
Agreement, to obtain specific performance of any provision of the Agreement, to advance
the completion of the Project, or to protect health, welfare and safety.
SECTION 14 - MISCELLANEOUS PROVISIONS
14.1
AGREEMENT DOCUMENTS
14.1.1
The Agreement Documents are intended to permit the parties to complete the Work
and all obligations required by the Agreement Documents within the Agreement Times for
the Agreement Price. The Agreement Documents are intended to be complementary and
interpreted in harmony so as to
avoid conflict, with words and phrases interpreted in a
manner consistent with construction and design industry standards.
14.1.2
It is the intent of the Agreement Documents to describe a functionally complete Project (or 
part thereof) to be constructed in accordance with the Agreement Documents.  Any labor, 
documentation, services, materials, or equipment that may reasonably be inferred from the 
Agreement Documents or from prevailing custom or trade usage as being required to 
produce the intended result must be provided by Contractor whether or not specifically 
called for at no additional cost to City.  
14.1.3
The Agreement Documents establish the rights and obligations of the parties and include 
the Agreement, Addenda (which pertain to the Agreement Documents), Contractor's Bid or 
Proposal (including documentation accompanying the Bid and any post-Bid documentation 
submitted prior to Agreement award) when attached as an exhibit to the Agreement, the 
accepted Project Schedule, the Notice to Proceed, the Performance Bond, the Payment 
Bond, Project Design, Engineering and Specifications, these General Conditions, the Project 
Specific Special Provisions, Technical Specifications, Agreement Drawings, as the same may 
be more specifically identified in the Agreement, Change Orders, Work Change Directives, 
Field Orders and the written interpretations and clarifications of the Design Professional or 
City representative and Modifications issued after execution of the Agreement.  Approved 
Shop Drawings and the reports and drawings of subsurface and physical conditions are not 
Agreement Documents.  
14.1.4
In the event of any inconsistency, conflict, or ambiguity between or among the Agreement
Documents, the Agreement Documents will take precedence as follows from highest to 
lowest: Change Orders, Addenda, Agreement, Project Specific Special Provisions, General 
Conditions, Technical Specifications, Drawings/Plans, Chandler Amendments to MAG 
Standard Specifications and Chandler Standard Details, and MAG Uniform Standard 
Specifications and Details for Public Works Construction.  If applicable to this Agreement, 
Federal Provisions prevail.

General Conditions
Revised: 7/20/22
GC-51 of 75
14.1.5
On the Drawings, given dimensions will take precedence over scaled measurements and
large scale drawings over small-scale drawings.
14.1.6
Clarifications and interpretations of the Agreement Documents will be issued by the Design 
Professional through the City.
14.1.7
The headings used in this Agreement or any other Agreement Documents, are for ease of
reference only and must not in any way be construed to limit or alter the meaning of any
provision.
14.1.8
The Agreement Documents form the entire agreement between City and Contractor.
No oral representations or other agreements have been made by the parties except as
specifically stated in the Agreement Documents.
14.1.9
The Agreement Documents may not be changed, altered, or amended in any way except in
writing signed by a duly authorized representative of each party in the form of a Change
Order.
14.1.10
Re-Use of Documents.  Neither Contractor nor any Subcontractor, manufacturer, fabricator, 
supplier or distributor will have or acquire any title to or ownership rights in any of the 
Drawings, Specifications or other documents (or copies of any thereof) prepared by or 
bearing the seal of the Design Professional; and they must not re-use any of them on 
extensions of the Project or any other project without written consent of City and the Design 
Professional and specific written verification or adaptation by the Design Professional.
14.2
REFERENCE STANDARDS
14.2.1
Reference to standards, specifications, manuals, or codes of any technical society, 
organization, or association, or to Laws or Regulations, whether such reference be specific 
or by implication, will mean the standard, specification, manual, code, or Laws or 
Regulations in effect at the time of opening of Bids (or on the Effective Date of the 
Agreement if there were no Bids), except as may be otherwise specifically stated in the 
Agreement Documents.
14.2.2
The provisions of any such standard, specification, manual or code, or any instruction of a 
Supplier will not change the duties or responsibilities of City, Contractor, Design 
Professional or Project Manager, or any of their Subcontractors, consultants, agents, or 
employees from those set forth in the Agreement Documents, nor will any such provision 
or instruction assign to City, Contractor, Design Professional, or any of their agents, or 
employees any duty or authority to supervise or direct the performance of the Work or any 
duty or authority to undertake responsibility inconsistent with the provisions of the 
Agreement Documents.
14.3
COMPLIANCE WITH ARIZONA LAW AND FEDERAL LAW
14.3.1
Compliance with A.R.S. § 41-4401.  Pursuant to the provisions of A.R.S. § 41-4401, the 
Contractor hereby warrants to the City that the Contractor and each of its subcontractors 
s that 
relate to the immigration status of their employees and the requirement to use E-Verify set 
forth in A.R.S. §23-214(A).  
14.3.2
A breach of the Contractor Immigration Warranty constitutes a material breach of this 
Agreement and subject to penalties up to and including termination of this Agreement.

General Conditions
Revised: 7/20/22
GC-52 of 75
14.3.3
The City retains the legal right to inspect the papers of any Contractor or Subcontractor 
employee who works on this Agreement to ensure that the Contractor or Subcontractor is 
complying with the Contractor Immigration Warranty.  The Contractor agrees to assist the 
City in the conduct of any such inspections. 
14.3.4
The City may, at its sole discretion, conduct random verifications of the employment records 
of the Contractor and any Subcontractors to ensure compliance with Contractors 
Immigration Warranty.  The Contractor agrees to assist the City in performing any such 
random verifications. 
14.3.5
The provisions of this Article must be included in any agreement the Contractor enters into 
with any and all of its subcontractors who provide services under this Agreement or any 
by a contractor or subcontractor.  Services include construction or maintenance of any 
structure, building or transportation facility or improvement to real property. 
14.4
HAZARDOUS ENVIRONMENTAL CONDITIONS
14.4.1
Contractor will not be responsible for any Hazardous Environmental Condition uncovered 
or revealed at the Site which was not shown or indicated in Drawings or Specifications or 
identified in the Agreement Document to be within the scope of the Work.  Contractor will
be responsible for a Hazardous Environmental Condition created with any materials 
brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom 
Contractor is responsible.
14.4.2
If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone 
for whom Contractor is responsible creates a Hazardous Environmental Condition. 
Contractor must immediately: 
a.
Secure or otherwise isolate such condition;
b.
Stop all Work in connection with such condition and in any area affected 
thereby; and
c.
Notify City and promptly thereafter confirm such notice in writing.
14.4.3
City will promptly retain a qualified expert to evaluate such condition or take corrective 
action, if any.
14.4.4
Contractor will be responsible for any and all civil or criminal penalties, fines, damages, or 
other charges imposed by any regulatory agency or court for sewage discharges that are in 
violation of applicable statutes and laws and that are a result, direct or indirect, of work 
performed under this Agreement.  Contractor will also be responsible for reimbursement 
to City for administration, reporting, and tracking expenses required as a result of any spill 
event.  In the event the regulatory agency or court imposes a probationary period, 
Contractor must post bond for the probationary period to ensure that all such costs are 
reimbursed to City.  This responsibility will apply whether penalties are imposed directly on 
Contractor or any of its Subcontractors, or the City of Chandler.  Contractor must defend 
and indemnify City against such penalties.  Regulatory agencies may include, but are not 
limited to, the Arizona Department of Environmental Quality (ADEQ) and the United States 
Environmental Protection Agency (USEPA).
14.5
COOPERATION AND FURTHER DOCUMENTATION

General Conditions
Revised: 7/20/22
GC-53 of 75
Contractor agrees to provide City such other duly executed documents as may be
reasonably requested by City to implement the intent of the Agreement Documents.
14.6
ASSIGNMENT
Neither Contractor nor City will, without the written consent of the other assign, transfer or
sublet any portion of this Agreement or part of the Work or the obligations required by
the Agreement Documents, any such assignment will be void, will transfer no rights to the
purported assignee, and would be a material breach of the Agreement.
14.7
SUCCESSORS
Contractor and City intend that the provisions of the Agreement Documents are binding
upon the parties, their employees, agents, heirs, successors and assigns.
14.8
LAWFUL PRESENCE
Pursuant to A.R.S. §§ 1-501 and 1-502, City is prohibited from awarding an agreement to any 
natural person who cannot establish that such person is lawfully present in the United 
States.  To establish lawful presence, a person must produce qualifying identification and 
sign a City-provided affidavit affirming the identification provided is genuine.  This 
requirement will be imposed at the time of agreement award.  This requirement does not 
apply to business organizations such as corporations, partnerships, or limited liability 
companies.
14.9
NO BOYCOTT OF ISRAEL CERTIFICATION
By Contractor's signature on this Agreement, Contractor certifies under A.R.S. § 35-393.01 
that Contractor is not currently engaged in and for the duration of this Agreement will not 
engage in a boycott of Israel.
14.10
NO THIRD PARTY BENEFICIARY
Nothing under the Agreement Documents will be construed to give any rights or benefits
in the Agreement Documents to anyone other than City and Contractor, and all duties and
responsibilities undertaken pursuant to the Agreement Documents will be for the sole and
exclusive benefit of City and Contractor and not for the benefit of any other party, unless
otherwise expressly set forth in the Agreement Documents.
14.11
GOVERNING LAW AND VENUE
The Agreement and all Agreement Documents will be deemed to be made under, and will
be construed in accordance with and governed by the laws of the State of Arizona without 
regard to the conflicts or choice of law provisions thereof.  Any court action to enforce any
provision of the Agreement or to obtain any remedy with respect hereto must be brought
in the Superior Court, Maricopa County, Arizona, and for this purpose, each party hereby
expressly and irrevocably consents to the jurisdiction and venue of such Court.
14.12
SEVERABILITY
If any provision of the Agreement Documents or the application thereof to any person or
circumstance will be invalid, illegal or unenforceable to any extent, the remainder of the
affected provision, the remainder of the Agreement Documents, and the application
thereof will not be affected and will be enforceable to the fullest extent permitted by law.
14.13
LEGALREQUIREMENTS
At all times relevant to its entry into this Agreement and performance of the Services and
the Work, Contractor must fully comply with all Laws, Regulations, or Legal Requirements
applicable to City, the Project, and the Agreement, including, without limitation, those set

General Conditions
Revised: 7/20/22
GC-54 of 75
forth on Exhibit C of the Agreement.
14.14
PARTIAL INVALIDITY
If any provision of the Agreement is held by a court of competent jurisdiction to be invalid, 
void or unenforceable, the remaining provisions will nevertheless continue in full force 
without being impaired or invalidated in any way.
14.15
ATTORNEYS' FEES
Should either party to the Agreement bring an action to enforce any provision of the 
Agreement, the prevailing party will be entitled to recover reasonable attorneys' fees and 
costs in connection therewith.
14.16
CONFLICT OF INTEREST
14.16.1
Contractor agrees to disclose any financial or economic interest with the Project property, 
or any
property affected by the Project, existing prior to the execution of the Agreement.
Further, Contractor agrees to disclose any financial or economic interest with the Project
property, or any property affected by the Project, if Contractor gains such interest during
the course of this Agreement. If Contractor gains financial or economic interest in the
Project during the course of this Agreement,
this may be grounds for terminating this
Agreement. Any decision to terminate the Agreement must be at the sole discretion of City.
14.16.2
Contractor will not engage the services on this Agreement of any present City employee who
was involved as a decision maker in the selection or approval processes, or who negotiated
or approved billings or Agreement Modifications for this Agreement.
14.16.3
Contractor agrees that it will not perform services on this Project for a contractor,
subcontractor, or any supplier, not covered under this Agreement.
14.17
INDEPENDENTCONTRACTOR
Contractor is and must be an independent contractor. Any provisions in the Agreement
Documents that may appear to give City the right to direct Contractor as to the details of
accomplishing the Work or to exercise a measure of control over the Work means that
Contractor must follow the wishes of City as the results of the Work only. These results
must comply with all applicable laws and ordinances.
14.18
NOTICE OF INJURY
Should City or Contractor suffer injury or damage to their person or property because of 
any error, omission or act of the other party or of any of the other party's employees or 
agents or others for whose acts the other party is legally liable, claim must be made in 
writing to the other party within 7 Days of the first observance of such injury or damage.
14.19
CONFIDENTIALITY
Contractor, for the benefit of City, hereby agrees it will not release or cause or permit
to be
released to the public any press notices, publicity (oral or written) or advertising
promotion relating
to, any statement regarding, or any other public announcement or
disclosure or cause or permit to be publicly announced or disclosed, in any manner
whatsoever, the specific terms and conditions of this Agreement or any comment relating
to the Project or the Site. Notwithstanding the foregoing, Contractor will be entitled to
disclose the terms of the Agreement to the extent required by law or in the course of
enforcing or defending a claim or action hereunder. Contractor must give City reasonably
prompt notice of any disclosure or statement made pursuant to this provision.

General Conditions
Revised: 7/20/22
GC-55 of 75
14.20
DATA CONFIDENTIALITY
14.20.1
As used in the Agreement
plans, specifications, renderings, photographs, studies, investigations, audits, analyses, 
samples, reports, calculations, internal memos, meeting minutes, data field notes, work 
product, proposals, correspondence and any other similar documents or information 
prepared by, obtained by, or transmitted to the City in the performance of this Agreement.
14.20.2
Contractor agrees that all data, regardless of form, including originals, images, and 
reproductions, prepared by, obtained by, or transmitted to City in connection with the 
Agreement is confidential and proprietary information 
belonging to City.
14.20.3
Except as specifically provided in this Agreement, Contractor or its Subcontractors must not 
divulge data to any third party without prior written consent of City.  Contractor or its 
Subcontractors must not use data for any purposes except to perform Work required under 
this Agreement.  These prohibitions will not apply to the following data provided Contractor 
has first given the required notice to City:
a.
Data which was known to Contractor or its Subcontractors prior to its 
performance under this Agreement unless such data was acquired in 
connection with Work performed for City;
b.
Data which was acquired by Contractor or its Subcontractors in its 
performance under this Agreement and which was disclosed to Contractor 
or its S
S
disclosure and Contractor or its Subcontractors are not otherwise required 
to hold such data in confidence; or 
c.
Data which is required to be disclosed by virtue of law, regulation, or court 
order, to which the Contractor or its Subcontractors are subject.
14.20.4
In the event the Contractor or its Subcontractors are required or requested to disclose data 
to a third party, or any other information to which the Contractor or its Subcontractors 
became privy as a result of any other agreement with City, the Contractor must first notify 
City as set forth in this Section of the request or demand for the data.  The Contractor or its 
Subcontractors must give City sufficient facts so that City can be given an opportunity to 
first give its consent or take such action that City may deem appropriate to protect such 
data or other information from disclosure.
14.20.5
Unless prohibited by law, within 10 Days after completion of services for a third party on 
real or personal property owned or leased by City, the Contractor must promptly deliver, as 
set forth in this Section, a copy of all data to City.  All data will continue to be subject to the 
confidentiality agreements of this Agreement. 
14.20.6
Contractor or its Subcontractors assume all liability for maintaining the confidentiality of 
the data in its possession and agree to compensate City if any of the provisions of this 
Section are violated by Contractor, its employees, agents, or Subcontractors.  Solely for the 
purposes of seeking injunctive relief, it is agreed that a breach of this Section will be deemed 
to cause irreparable harm that justified injunctive relief in court.  Contractor agrees that the 
requirements of this Section will be incorporated into all subcontracts entered into by 
Contractor.  A violation of this Section may result in immediate termination of this

General Conditions
Revised: 7/20/22
GC-56 of 75
Agreement without notice.  
14.21
SURVIVAL
All warranties, representations and indemnifications by Contractor must survive the
completion or termination of this Agreement.
14.22
COVENANTS AGAINST CONTINGENT FEES
Contractor warrants that no person has been employed or retained to solicit or secure
this
Agreement upon an agreement or understanding for a commission, percentage,
brokerage, or contingent fee, and that no member of City Council, or any employee of
City has any interest, financially, or otherwise, in the firm. For breach or violation of this
warrant, City will have the right to annul the Agreement without liability or at its discretion
to deduct from the Agreement Price or consideration, the full amount of such commission,
percentage, brokerage, or contingent fee.
14.23
NO WAIVER
The failure of either party to enforce any of the provisions of the Agreement Documents or
to require
performance of the other party of any of the provisions hereof must not be
construed to be a waiver of such provisions, nor will it affect the validity of the Agreement
Documents or any part thereof, or the right of either party to thereafter enforce each and
every provision.
14.24
NONEXCLUSIVEREMEDIES
The remedies set forth in this Agreement are cumulative and not exclusive, and failure to
exercise any remedy (including, without limitation, any right to terminate) will not preclude
any party from exercising any other right in seeking any other remedy available to it at law
or in equity.
14.25
PROJECTCOMMUNICATIONS
14.25.1
All communications concerning the performance of the Work or the Project will be provided
to the designated Project Manager and
Representative set forth in Article 1
of the Agreement. City may change the designated Project Manager and, subject to
Section
4.4.20
of
these General Conditions,
Contractor may change Contractor
Representative, by written notice to the other.
14.25.2
Project communications may be exchanged by e-mail, but email communications cannot
change the terms of the Agreement or the Scope of Work, or effectuate any change that
requires a written Change Order.
14.25.3
When any provisions of the Agreement Documents requires Contractor or the Design 
Professional to give written notice to City, it will be deemed to have been validly given if 
delivered in person or if delivered at or sent by registered or certified mail, postage prepaid, 
to the Parties indicated in Agreement Article 1, incorporated by reference.  
14.25.4
When any provisions of the Agreement Documents requires City, Project Manager, or the 
Design Professional to give written notice to Contractor, it will be deemed to have been 
validly given if delivered in person to the person designated in the Agreement Documents 
as 
Resident Superintendent, or if delivered at or sent by registered or certified 
mail, postage prepaid, to Contractor at the last address in the Agreement Documents or 
such substitute address which Contractor designates in writing, or to the business address 
known to the giver of notice.

General Conditions
Revised: 7/20/22
GC-57 of 75
14.26
DRUG FREE WORKPLACE PROGRAM
14.26.1
City has adopted a policy establishing a drug free workplace for itself and as a requirement
for Contractors doing business with City, to ensure the safety and health of employees
working on City projects.
14.26.2
Contractor must require a drug free workplace for all employees working under the
Agreement.
Specifically,
all employees
of
Contractor
who
are
working
under
an
agreement with City must be notified, in writing, by Contractor that they are prohibited
from
the
manufacture,
distribution,
dispensation, possession or unlawful use of a
controlled substance in the workplace.
14.27
Failure to require a drug free workplace in accordance with the
policy may result
in
termination of the Agreement and possible debarment form bidding on future City
projects.
SECTION 15 - PROVISIONS APPLICABLE SOLELY TO GMP AND COST-BASED AGREEMENTS,
CHANGE ORDERS, AND JOB ORDERS
15.1
ADDITIONALDEFINITIONS
The definitions set forth in Section 2 apply to GMP and Cost-Based Agreements, Change
Orders, and Job Orders, together with the additional definitions set forth below.
Baseline Cost Model
A breakdown and estimate of the scope of the Project developed by CM@Risk pursuant to Section 17.5 
of these General Conditions.
CM@Risk or Construction Manager at Risk 
The person or firm selected by City to provide pre-construction and/or construction services as
detailed in a Construction Manager at Risk Agreement with City. In these General Conditions, the
term
includes CM@Risk under both Pre-Construction and Construction Services
Agreements.
CM@Risk Fee or
Fee
An agreed to percentage in an accepted GMP that represents
fee for performance of 
the Work.
Agreement Documents
Where compensation under the Agreement is based upon a GMP accepted by City, the term
Agreement
also includes the accepted GMP Proposal.
Agreement Price
Where compensation under the Agreement based upon a GMP accepted by City, the term
Agreement
refers to the GMP.
Cost-Based Agreement, Change Order, or Job Order
A Agreement, Change Order, or Job Order where the Agreement Price is based upon the actual
cost of
performing the Work, subject to the terms of the Agreement Documents, including this
Section 15. These would include those generally referred to as
of the Work plus a Fee with
a
and
or
Plus a
Cost of the Work
The direct costs necessarily incurred by Contractor in the proper, timely, and complete performance
on the Work. The Cost of the Work will include only those costs set forth in Section 15.2 of these

General Conditions
Revised: 7/20/22
GC-58 of 75
General Conditions.
Deliverables 
The work products prepared by Contractor in performing the scope of work described in the 
Agreement. Some of the major deliverables to be prepared and provided by Contractor during pre-
construction may include but are not limited to: the Baseline Cost Model and Schedule that validate 
Schedule, Schedule of Values, 
alternative system evaluations, procurement strategies and plans, Detailed Cost Estimates, 
construction market surveys, cash flow projections, GMP Proposals, Subcontractor procurement plan, 
Subcontractor agreements, Subcontractor bid packages, Supplier agreements, Constructability 
Review, Cost Control Log, Traffic control and phasing plans and others as indicated in this Agreement
or required by the Project Team.
Pre-Construction Services Agreement
The Agreement entered into between City and the CM@Risk for Pre-Construction Services to be 
provided by the CM@Risk, including, without limitation, the generation of a GMP Proposal. If the GMP 
Proposal is accepted by City and a Construction Agreement is entered into between City and CM@Risk, 
the duties, obligations and warranties of the CM@Risk under the Pre-Construction Services 
Agreement survive and are incorporated into the resulting Construction Agreement.
Pre-Construction Services
The services to be provided under the Pre-Construction Services Agreement, including Section 17 of 
these General Conditions.
Detailed Project Schedule
The Detailed Project Schedule developed by the CM@Risk for the review and approval of the Project 
Manager in accordance with Section 17.3 of these General Conditions, if applicable.
General Conditions Costs
Those costs set forth in Section 4 of Appendix 9 to these General Conditions.
GMP Plans and Specifications
The plan and specifications upon which the Guaranteed Maximum price Proposal is based.
GMP Proposal
The proposal of Contractor submitted pursuant to Section 17.7 of these General Conditions for the 
entire Work and/or portion (phases) of the Work.
Guaranteed Maximum Price or GMP
The Guaranteed Maximum Price set forth in the Agreement, Change Order, or Job Order if applicable.
15.2
AGREEMENT PRICE
15.2.1
The Agreement Price for all Agreements, Change Orders, and Job Orders based upon 
payment of the Cost of the Work plus a Fee with a GMP, time and materials, or cost-plus a 
fee will be the Cost of the Work incurred plus the Fee agreed to in writing by City, limited to 
the amount of the GMP, if agreed to. Unless otherwise expressly provided in the Agreement, 
Change Order, or Job Order, all Cost Based pricing will be subject to and limited to GMP.
15.2.2
The Agreement Price may only be changed as set forth in Section 9 above.

General Conditions
Revised: 7/20/22
GC-59 of 75
15.2.3
Only costs specifically designated as reimbursable costs are eligible for payment by City or 
may be charged against the Agreement Price. All other costs will not be paid by City and will
not be chargeable against the Agreement Price.
15.2.4
Cost-Based Agreements. For Agreements, Change Orders, or Job Orders, reimbursable 
costs must be determined pursuant to Appendix 9 to these General Conditions, Cost of the 
Work, and not by MAG Specifications §109.5.
15.3
ALLOWANCES
15.3.1
Contractor must include in the Agreement Price all Allowances stated in the Agreement
Documents and agreed to in writing by City. Items covered by these Allowances must be 
supplied for such amounts and by such persons as City may direct, provided Contractor will 
not be required to employ persons against whom Contractor makes a reasonable objection. 
Materials, labor, and equipment under an Allowance will be selected by City in accordance 
with a schedule to be mutually agreed upon by City, Design Professional and Contractor or 
otherwise in reasonably sufficient time to avoid delay in the Work.
15.3.2
Unless otherwise provided in the Agreement Documents:
15.3.2.1
These Allowances must cover the cost to Contractor, less any applicable trade discount, of 
the materials, labor, and equipment required by the Allowances, delivered at the Site, and 
all applicable taxes;
15.3.2.2
profit and other expenses relating to materials, labor, and equipment required by the 
Allowance must be included in the Agreement Sum and not in the Allowance; and
15.3.2.3
Whenever the cost is more or less than the Allowance, the Agreement Sum must be 
adjusted accordingly by Change Order, the amount of which will recognize the difference 
between actual costs for an Allowance item and the amount of the Allowance item and 
changes, if any, in handling costs on the Site, labor, installation costs, overhead, profit and 
other expenses.
15.4
CONTINGENCY
An agreed to amount in the GMP that may only be used in accordance with the terms set
forth in these General Conditions and with prior written approval by the City.
15.4.1
Construction Contingency.  This GMP includes a dollar amount listed as a Construction 
Contingency which will be readily available for increased costs for subcontractors, material, 
and equipment subject to prior approval of City, which approval will not be withheld 
unreasonably.  The Construction Contingency may also be used, at the discretion of City, to 
reimburse CM@Risk for unexpected costs due to (a) scope gaps between trade 
subcontractors; (b) agreement default by trade subcontractors; (c) unforeseen field 
conditions, but only as defined in Section 9.5 above; (d) work completed to meet the intent 
of the design, but which was not indicated on the plans; (e) costs overruns not covered by 
allowances; (f) costs of corrective work not provided for elsewhere; and (g) implementation 
of any Recovery Plan.  Cost for which CM@Risk desires to be paid from the Construction 
Contingency must be documented by CM@Risk on a time and materials basis and are 
will be 
executed by both parties authorizing the actual cost of the work to be paid and included in 
the Work Item Direct Costs.  The Construction Contingency is not allocated to any particular

General Conditions
Revised: 7/20/22
GC-60 of 75
item of the Project but may be used for any portion of the work as determined above.  Any 
amount not used in the Construction Contingency will belong to City and will reduce the 
GMP. 
15.4.2
Contingency which may be used only by the City (owner department) for upgrades and 
changes in scope or other changes not already included within the intent of the Project 
Program.  City will provide CM@Risk with a Work Change Directive authorizing CM@Risk to 
Work Item Direct Costs category to be paid with such direct costs.  These additional costs 
will be in an amount mutually agreed upon by CM@Risk and City or will be documented by 
CM@Risk on a time and materials basis and are subject to verification by City.  Any amount 
will belong to the City and will reduce the GMP.
15.5
REDUCTION IN RETENTION
If the Agreement Price is based upon a GMP, in order to receive payment of one-half of the
retention as set forth in Section 8.1.5 above, Contractor must also submit to the Project
Manager a complete accounting of the Actual Reimbursable Cost of the Work to date,
including all such documentation (including, without limitation, invoices, subcontract,
subcontractor change orders, purchaseorders,records ofpayment,etc.) as Citymayrequire,
to establish whether the payments made to Contractor equal, exceed, or are less than the
actual reimbursable Cost of the Work to date. Any excess payments by City, as determined
by the Project Manager, will be deducted from the one-half retention payment to be made
to Contractor, and any additional excess amounts paid to Contractor will be refunded by
Contractor to City. The Project
determinations as to Actual Reimbursable Cost
of the Work will be the basis of payment until final Project Closeout and Final Payment
under the Agreement.
15.6
FINAL PAYMENT
If the Agreement Price is based upon a GMP, as a further condition precedent to Final
Payment by City, Contractor must submit to the Project Manager a complete final
accounting of the Actual Reimbursable Cost of the Work, including all such documentation
(including,
without
limitation,
invoices, subcontracts, subcontractor change orders,
purchase orders, records of payment, etc.) as City may require, to establish whether the
payments made to Contractor equal, exceed, or are less than the Actual Reimbursable Cost
of the Work to date. Any excess payments by City, as determined by the Project Manager,
will be deducted from the one-half retention payment to be made to Contractor, and any 
additional excess amounts paid to Contractor will be refunded by Contractor to City.
Disputes relating to the Final Cost of the Work will be subject to
audit
rights under
Sections 8.8 above and 15.7 below, and the dispute resolution process under Section
13
above.
15.7
OPEN BOOK
On any GMP-based or Cost-Based Agreement, Job Order, or Change Order, City may attend
any and all meetings or discussions pertaining to the Project, including bid openings, and
must have
access to all books, invoices, accounts, memoranda, correspondence, and
written communications or records of any kind pertaining to the Project, including without
limitation, those stored in electronic format.
15.8
DIFFERING SITE CONDITIONS AND/OR CHANGE IN LAWS
A Change Order for increased costs under Section 9.5 or 9.6 above will only be considered

General Conditions
Revised: 7/20/22
GC-61 of 75
or granted by City to the extent such actual, documented costs are justified.
SECTION 16 - PROVISIONS APPLICABLE SOLELY TO JOB ORDER AGREEMENTS (JOC)
16.1
ADDITIONAL DEFINITIONS
The definitions set forth in Sections 2 and below will apply to all Job Order Agreements and
Job Orders. In addition, the definitions set forth in Section 15.1 above will apply to all Cost-
Based Job Orders.
Agreement
Includes the Job Order Master Agreement and Job Order Project Agreements issued and agreed to by City
and JOC Contractor.
JOC 
Coefficient
A numerical factor that represents JOC Contractor total costs (indirect and direct costs, sales tax,
profit, etc.) and other adjustments for market conditions.
Job Order Request for Proposal (RFP)
The Request for Proposals issued by City for each Job Order Project Agreement relating to a specific 
Project.
Job Order Cost Proposal
The Proposal submitted by JOC Contractor in response to a Job Order Request for Proposal (RFP) issued
by City to develop a Job Order Project Agreement for a specific Project.
Guaranteed Maximum Price (GMP) Job Order
Job Order under which JOC Contractor is compensated for actual costs incurred.
Job Order Project Agreement (Job Order) 
The agreement for a specific project, as it may be modified by all Change Orders, executed by the 
Parties, which incorporates the terms and conditions of the Job Order Master Agreement. 
16.2
ORDERING AND PROCESSING PROCEDURES FOR JOB ORDERS
16.2.1
The process for developing and issuing a Job Order for a particular Project consists of three 
(3) procedures: (1) issuance of a RFP by City; (2) JOC Contractor
form of JOC Contractor
Job Order Cost Proposal; and (3) Issuance of a Job Order by City, as 
set for below.
16.2.2
For Job Orders
16.2.2.1
City will provide to JOC Contractor RFP with a Scope of Work (SOW) describing the Work to 
be performed, which may include special instructions and conditions, material submittal 
requirements, and, if applicable, a complete set of sketches, construction drawings and 
specifications for the Job Order.
16.2.2.2
specifications and will rely on JOC Contractor to produce them for City review and approval 
and is considered to be Pre-Construction and incidental design services included in JOC 
Contractor
JOC Contractor will not be 
reimbursed for any Pre-Job Order costs, including proposal preparation, attendance during 
negotiations, or site visits.

General Conditions
Revised: 7/20/22
GC-62 of 75
16.2.3
JOC Contractor
Job Order Cost Proposal
16.2.3.1
JOC Contractor must respond within ten (10) calendar days of the RFP date or site visit,
whichever is
later or as otherwise indicated on a case-by-case basis, by submitting JOC 
Contractor
Job Order Cost Proposal to the City representative.
16.2.3.2
Unless otherwise required under the terms of the RFP, JOC Contractor
Job Order Cost 
Proposal must include the following.
a.
JOC Contractor
Job Order Cost Proposal in PDF and electronic format;
b.
A Project Schedule and schedule of values that reflects the costs of each work 
element on the
schedule. The schedule must show all milestones (e.g.,
permits, submittals, ordering materials, demolition, work phases, closeout
and completion date); and
c.
Necessary documentation will be required to indicate that adequate scoping,
layout, setup and planning to accomplish the Work has been done.
Examples of documentation that might reasonably be expected include
sketches, drawings, calculations, catalog cuts and specifications produced
to a level of detail and skill that could be expected of experienced,
competent Project Managers with five or more periods experience in their
respective trade.
16.2.3.3
JOC Contractor must select Subcontractors based on qualifications alone or on a
combination of
qualifications and price and must not select Subcontractors based on
price alone. A qualifications and price selection may be a one-step selection based on
a combination of qualifications and price or two-step selection. In a two-step selection,
the first step must be based on qualifications alone and the second step may be based or
a combination of qualifications and price or on price alone.
16.2.3.4
Upon request, JOC Contractor must provide City with copies of Subcontractor quotes and
the basis for selection of each Subcontractor.
16.2.3.5
If City objects to a selected Subcontractor, City will make the objection and the reasons for
the
objection known to the JOC Contractor.
JOC Contractor must then present an
acceptable Subcontractor for the applicable discipline. City will not unreasonably object
to or withhold approval of a Subcontractor.
16.2.3.6
For self-performed work, the City retains the right to have the JOC Contractor establish JOC 
Contractor
costs by bidding their costs against at least three (3) other interested trade
Contractors. No self- performed work will be allowed to be performed on a lump sum basis.
16.2.4
Issuance of Job Order
16.2.4.1
City Representative will compare the JOC Contractor
Job Order Cost Proposal with the
estimate,
schedules and other requirements, and then, if the City Representative
determines it is in the best interest of City, arrange a meeting with JOC Contractor, at which
time the JOC Contractor
Job Order Cost Proposal will be discussed and negotiated.
16.2.4.2
If the City Representative determines that it is in the best interest of the City, City will then
issue a Job Order to JOC Contractor for execution.
16.2.4.3
Specific Job Orders may vary, but unless agreed to by City in writing otherwise, the content

General Conditions
Revised: 7/20/22
GC-63 of 75
of Job Orders under the Agreement will generally be as follow, all of which will be signed
and/or initialed by JOC Contractor
designated representative:
a.
The description of the Scope of the Work and Project Schedule (attached as
Exhibit A to the Job Order);
b.
The address or location of the Work;
c.
The Agreement Price for Work (Construction) included in the Project 
(attached as Exhibit B to the Job Order);
d.
The name of the JOC Contractor representative for the Project;
e.
The Drawings and Specifications for the Project;
f.
If any shop drawings, project date and/or samples are required for the Job
Order, the date for delivery of each required item (included in the Project
Schedule, Exhibit A to the Job order); and
g.
Project Specific Provisions, if any, in Exhibit A to the Job Order,
including, without limitation, whether any of the following are required:
Pre-Construction Conference, weekly progress meetings, field office,
storage enclosure, materials and equipment handling facility, submittals,
shop drawings, product data, equipment list, samples, project manual,
schedule of values, Construction progress schedule, narrative reports,
progress report, progress charts, progress photographs, materials status
report, Construction diagram, Construction status report, operation and
maintenance data, operating maintenance instructions and parts list, and
as-build drawings.
16.2.5
Job Order Intent.
Each Job Order will be interpreted to include all items reasonably
necessary to complete the Project under that Job Order as described in the scope of the
Work in that Job
Order. All Work must be performed in a professional manner and all
materials used must be new and of the highest quality and of the type best adapted to
their purpose, unless otherwise specified. The Notice to Proceed date, and the award date
established therein, will be deemed an integral part of the Job Order the same as if set forth
therein.
16.3
INCIDENTAL DESIGN SERVICES
16.3.1
This effort includes all
of
for systems that are typically specified in
a performance oriented manner by consultants and designers. Examples include: fire
sprinkler
systems, fire alarm and sprinkler systems, DDC controls, control systems, 
prefabricated metal
building and similar situations. These designs are normally provided
under submittals as a shop drawing with engineering backup and as appropriate, seals of
registered engineers specializing in the particular system.
16.3.2
Incidental design includes all documents, sketches, schematic diagrams, floor plan
layouts, equipment schedules and other documents produced by the JOC Contractor to
define the work required for projects that the City does not develop formal or abbreviated
designs requiring a seal by a registered engineer. Incidental design does not include
preparation of designs requiring an architect or engineer seal.
16.3.3
JOC Contractor represents, covenants, and agrees, and contractually assumes the
obligation to
furnish, all of the required Design Services through properly licensed and

General Conditions
Revised: 7/20/22
GC-64 of 75
experienced Design Professionals in complete accordance with all of the duties imposed 
on a Design Professional under the Agreement Documents, Laws, Regulations, or Legal
Requirements, and the common law.
16.3.4
All Design Documents (and all other Project-related documents, models, computer
drawings and other electronic expression, photographs and other expressions CADD, and
BIM files and
images included) that JOC Contractor and/or JOC Contractor
Design
Professional(s) prepare in connection with a Job Order and the copyrights therein
(collectively, the
of
will be the property of City. JOC Contractor
covenants and agrees to execute any additional document reasonably requested by City
to confirm such assignment without any additionalcompensation.
16.4
CONSTRUCTION SERVICES
16.4.1
The following subsections of this Section 16.4 set forth requirements beyond those set forth 
in Section 4 above which apply to Construction Services performed under a Job Order.
16.4.2
JOC Contractor must perform the Work using only those firms, team members and 
individuals designated by JOC Contractor consistent with each Job Order or otherwise 
approved by City pursuant to the General Conditions. No other entities or individuals may 
be used without the prior written approval of the Project Manager.
16.4.3
Construction Phasing
16.4.3.1
City use of the facilities is anticipated while the Work is being performed. The Work must
be
planned and accomplished so that there will be a minimum of interference and
inconvenience
to occupants in the building and agencies in the vicinity and to other
craftsmen who may have to do work in the affected facilities. Any blockage of building
exits or driveways must be coordinated in advance.
16.4.3.2
If applicable, furniture, portable office equipment and wall appurtenances not rigidly
fastened to the walls must be moved by JOC Contractor, protected from damage and
replaced to the original position upon completion of the work. If the work required by
the Job Order will not allow furniture and portable office equipment to be replaced to its 
original position, new locations will be designated by City. Incidental costs associated with
moving one-piece furnishings up to approximately 150 pounds to perform such tasks as
painting, carpet or tile replacement, etc.,
are considered a general cost of building
renovation and must be included in the JOC Contractor
Coefficient. Costs for large scale
or wholesale removal and replacement of large quantities of
desks
or
modular
workstations, copiers, multiple full file cabinets, etc. to another location or storage outside
the work space, or disassembly and reassembly of modular furniture is not considered
part of the JOC Contractor
Coefficient and will be priced separately.
16.4.3.3
The work must, so far as practicable, be done in definite sections or divisions and confined
to limited areas which must be completed before work in other sections or divisions are
begun.
16.4.4
Work Site Conflicts. In the event of a conflict between JOC Contractor and others in an
occupied facility or where other Contractors are performing work on the same facility
under other Agreements, City will decide to dispute and that decision will be final.
16.4.5
Ownership of Work Product. Work Product prepared or otherwise created in connection

General Conditions
Revised: 7/20/22
GC-65 of 75
with the performance of this Agreement, including the Work, are to be and remain the
property of City. For purposes of this provision,
will include all designs,
drawings, plans, specifications, ideas, renderings and other information or matter, in
whatever form created (e.g., electronic or printed) and in all media now known or
hereinafter created. All Work Product will be considered Work Made for Hire as defined
in the United States Copyright Act 17 U.S.C. §101 (Copyright Act). If for any reason any such
Work is found not to be a work for hire, JOC Contractor hereby transfers and assigns
ownership of the copyright in such Work to City. The rights in this Section are exclusive to
City in perpetuity.
16.5
OPTIONAL LIQUIDATED DAMAGES
16.5.1
Specific Job Orders. City will have the right to assess liquidated damages in relation to
any specific JOC Project Agreement as set forth below.
16.5.2
Substantial Completion Liquidated Damages. JOC Contractor acknowledges and agrees
that if
JOC Contractor fails to obtain Substantial Completion of the Work within the
Agreement Time, City will sustain extensive damages and serious loss as a result of such
failure. The exact amount of
such damages will be extremely difficult to ascertain.
Therefore, City and JOC Contractor agree that if JOC Contractor fails to achieve Substantial
Completion of the Work within the Agreement Time, City
will
be entitled to retain or
recover from JOC Contractor, as liquidated damages and not as a penalty, the sum per 
calendar day as indicated in MAG § 108.9.
16.5.3
Final Acceptance Liquidated Damages. For the same reasons set forth in Section 16.5.2
above, City and JOC Contractor further agree that if JOC Contractor fails to achieve Final
Acceptance of the Work within the Agreement Time, City will be entitled to retain or recover
from JOC Contractor, as liquidated
damages and not as a penalty, the sum per calendar 
day as indicated in MAG § 108.9 commencing from the actual date
of Substantial
Completion or Final Acceptance as required under any specific JOC Project Agreement.
16.5.4
MAG Liquidated Damages. Liquidated damages provisions in MAG § 108.9 may apply to any 
specific JOC Project Agreement.  
16.5.5
City may deduct liquidated damages assessed pursuant to this Section 16.5 from any
unpaid amounts then or thereafter due JOC Contractor under the Agreement or any
specific JOC Project Agreement between JOC Contractor and City. Any liquidated damages
not so deducted from any unpaid amounts due JOC Contractor must be payable to City
at the demand of City, together with interest from the date of the demand at the highest
lawful rate of interest payable to JOC Contractor.
16.6
PERFORMANCEMEASUREMENT
16.6.1
Performance Assessment. After the Final Acceptance of Work under each Job Order, City
will complete a written evaluation of the performance of JOC Contractor on the Job Order.
16.6.2
Consideration in Assignment of Work. JOC Contractor
record of cost, schedule and
quality performance and comparative assessments will be significant considerations in
determination whether to award future Job Orders. JOC Contractor agrees that any
determination by City not to not award future Job Orders or Option periods based on
performance will be at the sole discretion of City.

General Conditions
Revised: 7/20/22
GC-66 of 75
SECTION 17 - PROVISIONS APPLICABLE SOLELY TO PRE-CONSTRUCTION SERVICES FOR 
CONSTRUCTION MANAGER AT RISK
17.1
ADDITIONALDEFINITIONS
The definitions set forth in Section 2 and 15.1 above will apply to all Pre-Construction
Services Agreements.
17.2
GENERAL
17.2.1
CM@Risk must perform the  Services required by, and in accordance with the Agreement
Documents and as outlined in Exhibit A of the Agreement to the satisfaction of the
Project Manager, exercising the degree of care, skill, diligence and judgment a professional
construction manager experienced in the performance of such services for construction
and/or facilities of similar scope, function, size, quality, complexity and detail to the
Project in urban areas throughout the United States, would exercise at such time, under
similar conditions. CM@Risk must, at all times, perform the required services consistent
with sound and generally accepted engineering principles and construction management
and construction contracting practices.
17.2.2
As a participating member of the Project Team, CM@Risk must provide to City and Design
Professional a written evaluation of
Project Program and budget, each in terms of
the other, with recommendations as to the appropriateness of each. CM@Risk must
prepare a Baseline Cost Model that validates
budget. The Baseline Cost Model must
include all assumptions and basis of estimates in enough detail so that the Project Team
can compare
future detail estimates to the Baseline Cost model for variances. City and
Design Professional will provide all the reasonably required data that is available in
order to reach agreement between the team members that the Baseline Cost Model is an
accurate projection of the costs of the Project.
17.2.3
CM@Risk must attend Project Team meetings, which may include, but are not limited to,
bi- weekly Project management meetings, Project workshops, special Project meetings,
construction document rolling reviews, public meetings and partnering sessions. CM@Risk
attendance at design or other meetings in which CM@Risk is provided the opportunity but
does not actively participate and/or is not properly prepared is not acceptable. Repeated
instances of non-participation and/or lack of preparedness will be grounds for termination
of CM@Risk Agreement for default.
17.2.4
CM@Risk must provide Pre-Construction Services, described herein, in a timely manner
and consistent with the intent of the most current Drawings and Specifications. CM@Risk
must promptly notify City in writing whenever CM@Risk determines any Drawings or
Specifications are inappropriate for the Project and/or cause changes in the scope of Work
that deviates more
than the allowed contingencies within the Baseline Cost Model or
requires an adjustment in the Baseline Cost Model, Detailed Cost Estimate, Detailed
Project Schedule, GMP Proposals and/or in the Agreement Time for the Work, to the extent
such as established.
17.2.5
CM@Risk when requested by City, must attend, make presentations and participate as may
be appropriate in public agency and or community meetings, relevant to the Project.
CM@Risk must provide drawings, schedule diagrams, budget charges and other materials
describing the Project when their use is required or appropriate in any such public agency
meetings.

General Conditions
Revised: 7/20/22
GC-67 of 75
17.2.6
Ownership of Work Product. All Work Product prepared or otherwise created in connection
with
the performance of this Agreement, including the Work, are to be and remain the
property of City. For purposes of this provision,
will include all designs,
drawings, plans, specifications, ideas, renderings and other information or material, in
whatever form created (e.g., electronic or printed) and in all media now know or hereinafter
created. All Work Product will be considered Work Made for Hire as defined in the United
States Copyright Act 17 U.S.C.
§101 (Copyright Act). If for any reason any such Work is found not to be a work for
hire, Contractor hereby transfers and assigns ownership of the copyright in such Work to
City. The rights in this Section are exclusive to City in perpetuity.
17.2.7
CM@Risk represents to City in completing Pre-Construction Services and providing the
reports
and analysis required thereunder, that Work can be properly and timely
constructed within the GMP Proposal, if accepted. CM@Risk does not assume any design
responsibilities unless
specifically called for in the scope of work, but CM@Risk will be
responsible for their errors, omissions or inconsistencies included in the Work.
17.3
DETAILED PROJECT SCHEDULE
17.3.1
The fundamental purpose of the Detailed Project Schedule is to identify, coordinate and
record the tasks and activities to be performed by all of the Project Team members and
then for the
Project Team to utilize that Deliverable as a basis for managing and
monitoring all
compliance with the schedule requirements of the Project.
Each Project Team member is responsible for its compliance with the Detailed Project
Schedule requirements.
CM@Risk
must, however, develop and maintain the Detailed
Project Schedule on behalf of and to be used by the Project Team based on input from the
other Project Team members. The Baseline Project Schedule must be developed as part
of the Baseline Cost Model. The Detailed Project Schedule must use the Critical Path
method
technique, unless required otherwise, in writing by City. CM@Risk must
use scheduling software acceptable to City to develop the Detailed Project Schedule.
The Detailed Project Schedule must be presented in graphical and tabular reports as
agreed upon by the Project Team. If Project phasing as described below is required, the
Detailed
Project
Schedule
must
indicate
milestone
dates
for
the
phases
once
determined.
As part of construction phase, City may require CM@Risk to prepare a
schedule for all work, including work performed by Subcontractors,
detailing each of the project tasks and the required/anticipated number of personnel per
dayfor each task. CM@Risk must also indicate on the schedule its ability to meet said
required/anticipated personnel requirements.
17.3.2
CM@Risk must include and integrate in the Detailed Project Schedule the services and
activities required of City, Design Professional and CM@Risk including all construction
phase activities
based on the input received from City and the Design Professional.
The Detailed Project Schedule must define activities as determined by City to the extent
required to show: (a) the coordination between preliminary design and various pre-
construction documents, (b) any separate long-lead procurements, (c) any permitting
issues, (d) any land, right-of-way, or easement acquisition, (e) bid packaging strategy and
awards to Subcontractors and Suppliers, (f) major stages of construction, (g) start-up and
commissioning, and (h) occupancy of the completed Work by City. The Detailed Project
Schedule must include by example and not limitation, proposed activity sequences and
durations for design, procurement, construction and testing activities, milestone dates for
actions and decisions by the Project Team, preparation and processing of shop drawings

General Conditions
Revised: 7/20/22
GC-68 of 75
and samples, delivery of materials or equipment requiring long-lead time procurement (if
any), milestone dates for various construction phases,
Total Float for all activities to the
extent authorized by City, relationships between the activities,
occupancy
requirements showing portions of the Project having occupancy priority, and proposed
dates for Final Acceptance.
17.3.3
A Baseline Project Schedule must be initiated with the project Baseline Cost Model and
agreed to by the project team at the same time. CM@Risk must update and maintain a
detailed Project
Schedule throughout pre-construction such that it will not require major
changes at the start of
the construction phase to incorporate
plan for the
performance of the construction phase Work. CM@Risk must provide updates and/or
revisions to the Detailed Project Schedule for use by the Project Team, whenever required,
but no less often than at the Project Team meetings. CM@Risk must include with such
submittals a narrative describing its analysis of the
progress achieved to-date vs. the
Baseline Project Schedule, including any concerns regarding delays or potential delays, and
any recommendations regarding mitigating actions.
17.3.4
If phased construction is deemed appropriate at the time of developing the Baseline Cost
Model or during the development of the Detailed Project Schedule, and City approves,
CM@Risk must review the design and make recommendations regarding the phased
issuance of Construction Documents to facilitate phased construction of the Work, with
the objective of reducing the Project Schedule and/or Cost of the Work. CM@Risk must take
into consideration such factors as natural and practical lines of work severability,
sequencing
effectiveness, access and availability constraints, total time for completion,
construction market
conditions, labor and materials availability, and any other factors
pertinent to saving time and cost.
17.3.5
Long Lead Time Items. As part of developing the Detailed Project Schedule, CM@Risk must
identify all long lead time materials, fabrications, equipment, or other items which may
impact the Project Schedule and may require early action on the part of the Project Team.
Dates for selecting and ordering long lead time items will be included and highlighted
in the Detailed Project Schedule
17.3.6
Equipment Plan. Contractor must develop an Equipment Plan that addresses all rental
and
owned equipment, regardless of whether such equipment will be provided by
CM@Risk or subcontractor(s), that will be necessary to construct the Project and the cost
of which will be included as a Cost of the Work in the GMP Proposal. The Equipment Plan
will seek to minimize the cost of the equipment to City and maximize the efficient and
coordinated use of the equipment for completion of the Project. The Equipment Plan will
not only include the costs and allowable lease rates for the equipment, but will also include
an equipment schedule that will be incorporated into the Detailed Project Schedule and the
Schedule of Values submitted with the GMP Proposal.
17.4
DESIGN DOCUMENT REVIEWS
17.4.1
CM@Risk must evaluate periodically the availability of labor, materials/equipment, cost-
sensitive aspects of the design; and other factors that may create an unacceptable variance
to the Baseline Cost Model and/or Baseline Project Schedule.
17.4.2
CM@Risk must recommend, in conjunction with the Project Team, those additional surface
and subsurface investigations that, in its professional opinion, are required to provide the
necessary
information
for
CM@Risk
to
construct
the
Project.
These
additional

General Conditions
Revised: 7/20/22
GC-69 of 75
investigations, if agreed to
be necessary by the Project Manager and the Design
Professional, will be acquired by City and copies of the reports will be provided to CM@Risk.
17.4.3
CM@Risk must meet with the Project Team as required to review
designs during their
development. CM@Risk must familiarize itself with the evolving documents through
pre-
construction.
CM@Risk must proactively advise the Project Team and make
recommendations
on factors related to construction costs, and concerns pertaining to the
feasibility and practicality
of any proposed means and methods, selected materials,
equipment and building systems, and,
labor and material availability. CM@Risk must
furthermore advise the Project Team on proposed site improvements, excavation and
foundation considerations, as well as, concerns that exist with respect to coordination of
the Drawings and Specifications. CM@Risk must use established value analysis principles
in recommending cost effective alternatives.
17.4.4
CM@Risk must routinely conduct constructability and bid-ability reviews of the Drawings
and Specifications as necessary to satisfy the needs of the Project Team. The reviews must
attempt
to identify all discrepancies and inconsistencies in the Construction Documents
especially those related to clarity, consistency, completeness and coordination of Work of
Subcontractors and Suppliers.
17.4.4.1
CM@Risk must evaluate whether: (a) the Drawings and Specifications are configured to
enable efficient construction; (b) design elements are standardized; (c) construction
efficiency
is
properly
considered
in
the
Drawings
and
Specifications;
(d)
module/preassembly design is prepared to facilitate fabrication, transport and installation;
(e) sequences of Work required by or inferable from the Drawings and Specifications are
practicable; (f) the design has taken into consideration efficiency issues concerning access
and entrance to the site, laydown and storage
of materials, staging of site facilities,
construction parking, and other similar pertinent issues; and (g) the design maintains
continued operation of the existing City systems and maintains
traffic on adjacent
roadways. CM@Risk must also review the Drawings and Specifications to ensure that what
is depicted therein can be constructed as designed and must promptly inform the Project
Team of any issues.
17.4.4.2
CM@Risk must check cross-reference and complementary Drawings and sections within
the Specifications and in general evaluate whether: (a) the Drawings and Specifications
are sufficiently clear and detailed to minimize ambiguity and to reduce scope interpretation
discrepancies; (b) named materials and equipment are commercially available and are
performing well, or otherwise, in similar installations; (c) Specifications include alternatives
in the event a requirement cannot be met in the field; and (d) in its professional opinion, the
Project is likely to be subject to Differing Site Conditions.
17.4.4.3
The results of the reviews must be provided to Project Team in formal, written reports
clearly
identifying all reviewed documents and the discovered discrepancies and
inconsistencies in the Drawings and Specifications with notations and recommendations
made on the Drawings, Specifications and other documents. CM@Risk must meet with
Project Team to discuss any findings and review reports.
17.4.4.4
CM@Risk s reviews must be from a
perspective, and though it will serve to
eliminate/reduce the number of RFIs) and changes during the construction phase,
responsibility for the Drawings and Specifications will remain with the Design Professional
and not CM@Risk.

General Conditions
Revised: 7/20/22
GC-70 of 75
17.4.5
It is
responsibility
to assist the Design Professional in ascertaining that, in
professional opinion, the Construction Documents are in accordance with
applicable Laws, Regulations, or Legal Requirements, building codes, sound engineering
rules and regulations. If CM@Risk recognizes that portions of the Construction
Documents are at variance with applicable laws, statutes, ordinances, building codes,
sound engineering
rules and regulations, it must promptly notify the Project Team
in writing, describing the apparent variance of deficiency. However, the Design Professional
is ultimately responsible for the compliance of the Drawings and Specifications with those
laws, statutes, ordinances, building codes, rules and regulations.
17.4.6
The Project Team will routinely identify and evaluate using value analysis principles and
alternate systems, approaches, design changes that have the potential to reduce Project
costs while still delivering a high quality and fully functional Project consistent with
the Project Program. If the Project Team agrees, CM@Risk in cooperation with the Design
Professional,
will perform a cost/benefit analysis of the alternatives and submit such in
writing to the Project Team. City, through the Project Manager, will direct which alternatives
will be incorporated into
the Project.
The Design Professional will have full design
responsibility for the review and incorporation of CM@Risk suggested alternatives into
the Drawings and Specifications. CM@Risk must analyze the costs and schedule impacts of
the
alternatives
against the
Baseline
Cost
Model
and
Schedule
and
provide
a
recommendation for the Project
consideration
and
approval prior to the
establishment of the GMP.
17.5
BASELINE COSTS MODEL, DETAILED COST ESTIMATES, AND SCHEDULE OF VALUES
17.5.1
At the conclusion of the Master Planning and Programming, if required, CM@Risk will
review all available information regarding the design and scope of the Project using
experience in performing similar work, knowledge of similar projects and
current and projected
construction costs and, based upon that review, must develop a
Baseline Cost Model for review by the Project Team and approval by City. Once approved
by City, the Baseline Cost Model will be continually referenced as detailed estimates are
created as the design progresses throughout Pre-Construction until the final GMP for the
entire Project is established. A final GMP for the entire Project must be established and
approved by City prior to the start of construction. It is the responsibility of CM@Risk
to ensure City has sufficient information to evaluate  and  approve  a  final  GMP prior to  
the  time  necessary to start construction  so construction can be completed within the
Agreement Time. The Project Detailed Cost Estimate will be the best representation from
CM@Risk of what the complete functional
construction costs will be as indicated
by the most current available documents and will be
constantly checked against the
Baseline Cost Model. CM@Risk must communicate to the Project Team and assumptions
made in preparing the Baseline Cost Model.
The Baseline Cost
Model must support
Detailed Cost Estimates and may be broken down initially as dictated by the
available information, as required by City.
17.5.2
After receipt of the Design
most current documents from certain specified
pre- construction milestones, CM@Risk must provide a draft Detailed Cost Estimate
including a detailed written report detailing any variances to the Baseline Cost Model and
Baseline Project Schedule. The Design Professional and CM@Risk will reconcile any
disagreements on the estimate to arrive at an agreed upon Detailed Cost Estimate for the
construction costs based on
the scope of the Project through that specified pre-
construction milestone. Pre-Construction milestones applicable to this paragraph are:

General Conditions
Revised: 7/20/22
GC-71 of 75
Master Planning and Programming, Schematic Design, 50% Design Development, 100%
Design Development, and 50% Construction Drawings, If no consensus is reached, City will
make the final determination. If the Project Team
requires additional updates of the
Detailed Cost Estimate beyond that specified in this paragraph, CM@Risk must provide the
requested information in a timely manner.
17.5.3
If at any point the Detailed Cost Estimate submitted to City exceeds the previously
accepted Baseline Cost Model or previously approved Detailed Cost Estimate agreed to as
set forth in Section 17.5.2 above, CM@Risk must make appropriate recommendations to
project Team on means/methods, materials, and or other design elements that it
believes will reduce the estimated construction costs, such that it is equal to or less than
the established Project
Baseline Cost Model.
17.5.4
Unless other levels of completion are agreed to in writing in the Construction Documents,
at 50% Construction Drawings and included with the associated report, CM@Risk must
also submit to the Project Team for review and approval a Schedule of Values that complies
with the following requirements. The Schedule of Values must be based on City standard
bid schedule and highlight significant variances from any previously submitted Schedule
of Values. The Schedule of Values must be directly related to the breakdowns reflected in
the Detailed Project Schedule and
Detailed Cost Estimate. In addition, the
Schedule of Values must:  (a) detail unit prices and quantity take-offs, (b) detail all other
contingencies and unit price Work shown and specified in the detailed design documents.
17.5.5
CM@Risk is to track, estimate/price and address the Project
overall project cost issues
that arise outside of the Baseline Cost Model and the latest approved Detailed Cost
Estimate
such as: City generated changes, Project Team proposed changes, alternate
system analysis, constructability items and value engineering analysis. The system used
to implement this process will be referred to as the Design Evolution Log. This is to be
addressed between the Baseline Cost Model and the Master Planning and Programming
Detailed Cost Estimate, and then (unless other levels of completion are agreed to in writing
in the Construction Documents) between the Detailed Cost Estimates for each of the pre-
construction milestones thereafter, Schematic Design, 50% Design Development, 100%
Design Development, and 50%
Construction Documents, and the bid packages for all
Phases.
17.5.6
Upon request by City, CM@Risk must submit to City a cash flow projection for the Project
based on the current updated/revised Detailed Project Schedule and the anticipated level of
payments for CM@Risk during the design and construction phases. In addition, if requested
by City and based on information provided by City, CM@Risk must prepare a cash flow
projection for the entire Project based on historical records for similar types of projects
to assist City in the financing process.
17.5.7
Construction Water. CM@Risk must estimate the quantity of water to be used and include
the cost thereof in each Detailed Cost Estimate and GMP Proposal provided by City.
17.6
SUBCONTRACTOR AND MAJOR SUPPLIER SELECTIONS
17.6.1
There are two ways to select Subcontractors and major Suppliers prior to submission of a
GMP Proposal: (1) qualifications-based selection; or (2) a combination of qualifications
and price. Except as noted below, the selection of Subcontractors/Suppliers is the sole
responsibility of CM@Risk. In any case, CM@Risk is solely responsible for the performance
of the selected Subcontractors/Suppliers, and for compliance with the requirements of

General Conditions
Revised: 7/20/22
GC-72 of 75
Title 34 of the Arizona Revised Statutes in the selection of a Subcontractors/Suppliers,
to the extent applicable. CM@Risk must comply with its Subcontractor Selection Plan
submitted with its Statement of Qualifications.
17.6.2
City may approve the selection of a Subcontractor(s) or Suppliers(s) based only on their
qualifications when CM@Risk can demonstrate it is in the best interest of the Project. All
Work
that is performed, after such a qualifications-based selection, for a price that is
negotiated by CM@Risk will be billed in accordance with the GMP for actual costs and may
be subject to audit by City.
17.6.2.1
Qualifications based selection of a Subcontractor(s)/Supplier(s) should only occur prior to
the submittal of the GMP Proposal.
17.6.2.2
If a Subcontractor/Supplier selection plan was submitted and agreed to by City, CM@Risk
must apply the plan in the evaluation of the qualifications of a Subcontractor(s) or
Supplier(s) and provide City with its review and recommendations.
17.6.2.3
CM@Risk must receive written City approval for each selected Subcontractor(s) and
Supplier(s).
17.6.2.4
CM@Risk must negotiate costs for services/supplies from each Subcontractor/Supplier
selected under this method.
17.6.3
All Work must be competitively bid unless a Subcontractor or Supplier was selected pursuant
to Section 17.6.2 above.
17.6.3.1
CM@Risk must develop Subcontractor and Supplier interest, submit the names of a
minimum of three qualified Subcontractors or Suppliers for each trade in the Project for
approval by City and solicit bids for the various Work categories. If there are not three
qualified Subcontractors/Suppliers available for a specific trade or there are extenuating
circumstances warranting such, CM@Risk may request approval by City to submit less
than three names. Without prior written notice to City, no change in the recommended
Subcontractors/Supplies will be allowed.
17.6.3.2
If City objects to any nominated Subcontractor/Supplier or to any self-performed Work for
good
reason, CM@Risk must nominate a substitute Subcontractor/Supplier that is
acceptable to City.
17.6.3.3
CM@Risk must distribute Drawings and Specifications, and when appropriate, conduct a
Pre- Bid Conference with prospective Subcontractors and Suppliers.
17.6.3.4
If CM@Risk desires to self-perform certain portions of the Work, it must request to be one of
the approved Subcontractor bidders for those specific bid packages.
bid will
be evaluated in accordance with the process identified below. If events warrant and City
concurs
that it is necessary in order to ensure compliance with the Project Schedule
and/or the most recent Detailed Cost Estimate, CM@Risk may be authorized to self-
perform Work without bidding or rebidding the Work. When CM@Risk self-performs work
without bidding, only the actual costs associated with performing the Work in accordance
with the approved GMP will be billed and may be subject to audit by City.
17.6.3.5
CM@Risk must receive, open, record and evaluate
the bids; provided, however, that if
CM@Risk or one of its affiliates is bidding to self-perform the Work that is the subject of the
bid, then the bids must be received, opened, recorded and evaluated by Project Manager

General Conditions
Revised: 7/20/22
GC-73 of 75
instead of CM@Risk. Bids for each category of Work must be opened and recorded at a
pre-determined
time. The apparent low bidders must be interviewed to determine the
responsiveness of their
proposals. In evaluating the responsiveness of bid proposals
CM@Risk, in addition to bid price,
may consider the following factors: past performance
on
similar
projects,
qualifications
and
experience of personnel assigned, quality
management plan, approach or understanding of the
Work to be performed, and
performance
schedule
to
complete 
the
Work.
The
final
evaluation
of
Subcontractor/Supplier bids must be done with Project Manager in attendance to observe
and witness the process. CM@Risk mustresolve anySubcontractor/Supplier bid withdrawal,
protest or disqualification in connection with the award at no increase in the Cost of Work.
17.6.4
CM@Risk will be required to prepare two different reports on the subcontracting process.
17.6.4.1
Within fifteen days after each major Subcontractor/Supplier bid opening process;
CM@Risk
must
prepare
a
report
for
review
and
approval
identifying
the
recommended Subcontractors/Supplier for each category of Work. The report must detail:
(a) the name of the
recommended Subcontractor/Supplier and the amount of the
Subcontractor/Supplier bid for each sub-agreement; (b) the sum of all recommended
Subcontractor/Supplier bids received; (c) and trade work and its cost that CM@Risk intends
to self-perform, if any.
17.6.4.2
Upon completion of the Subcontractor/Supplier bidding process, CM@Risk must submit
a summary report to City of the entire Subcontractor/Supplier selection process. The report
must indicate, by bid process, all Subcontractors/Suppliers contacted to determine
interest, the Subcontractors/Suppliers solicited, the bids received and costs negotiated,
and the recommended Subcontractors/Suppliers for each category of Work.
17.6.5
The approved Subcontractors/Suppliers will provide a Schedule of Values with their bid
proposals, which will be used to create the overall Project Schedule of Values.
17.6.6
If after receipt of sub-bids or after award to Subcontractors and Suppliers, City objects to
any
nominated Subcontractor/Supplier or to any self-performed Work without any
reasonable basis,
CM@Risk must nominate a substitute Subcontractor or Supplier,
preferably if such option is still available, from those who submitted Subcontractor bids
for the Work affected.  Once such substitute Subcontractors and Suppliers are consented
to by
proposed GMP
for the Work or portion thereof must be
correspondingly adjusted to reflect any higher or lower costs form any such substitution.
17.7
GMP PROPOSAL
17.7.1
When a GMP Proposal is submitted for a phase of the Work, the GMP will have a Detailed Cost
Estimate of the Costs of the Work (as set forth in Section 15.2) in each phase of the Work 
that is being proposed plus the current estimate for all other Work. City will not approve
the GMP for the phase of work without a total estimate for the complete Project. City may
request a GMP
Proposal for all or any portion of the Project and at any time during pre-
construction. Any GMP Proposals submitted by CM@Risk must be based on and consistent
with Baseline Cost Model and the current update/revised Detailed Cost Estimate at the
time of the request and include any clarifications or assumptions upon which the GMP
Proposal(s) are based.
17.7.2
A GMP Proposal for the entire Project will be the sum of the Cost of the Work, CM@Risk Fee,
and General Conditions Cost. CM@Risk guarantees to complete the Project at or less than

General Conditions
Revised: 7/20/22
GC-74 of 75
the final GMP Proposal amount plus approved Change Orders. CM@Risk will be responsible
for any costs for expenses that would cause the Cost of the Work actually incurred,
including the Construction Fee and General Conditions Costs, to exceed the GMP.
17.7.3
CM@Risk must prepare its GMP Proposal in accordance with Ci
request for GMP Proposal
requirements based on the most current completed Drawings and Specifications at that
time, which unless otherwise directed by City in writing, will be at 100% Construction
Drawings. CM@Risk must mark the face of each document of each set upon which its GMP
Proposal is
based.
These documents must be identified as the GMP Plans and
Specifications. CM@Risk
must send one set of those documents to the Project Manager,
keep one set and return the third set to the Design Professional.
17.7.4
An updated/revised Detailed Project Schedule, Equipment Plan, and Schedule of Values
must
be included in any GMP Proposal(s), all of which must reflect the GMP Plans and
Specifications
the Detailed Project Schedule must be shown in relationship to the Project
Schedule and identify any variance to the Baseline Project Schedule. Any such Detailed
Project Schedule updates/revisions must continue to comply with the requirements of
Section 17.3.1 through 17.3.5.
17.7.5
GMP Proposals(s) Review and Approval
17.7.5.1
CM@Risk must meet with the Project Team to review the GMP Proposal(s) and the written
statement of its basis.
In the event the Project Team discovers inconsistencies or
inaccuracies
in the information presented,
CM@Risk
must make adjustments
as
necessary to the GMP Proposal.
17.7.5.2
If during the review and negotiation of GMP Proposals design changes are required, City
may authorize and cause the Design Professional to revise the GMP Plans and Specifications
to the extent necessary to reflect the agreed-upon assumptions and clarifications contained
in the final approved GMP Proposal. Such revised GMP Plans and Specification will be
furnished to CM@Risk. CM@Risk must promptly notify the Project Team in writing if any
such revised
GMP Plans and Specifications are inconsistent with the agreed upon
assumptions and clarifications.
17.7.6
All portions of or items comprising the GMP Proposal are subject to audit by City, as
deemed appropriate by City, including, without limitation, any based upon unit prices or
Work to be self- performed by CM@Risk, or its affiliates.
17.8
PAYMENT PROCEDURE FOR PRE-CONSTRUCTION SERVICES
17.8.1
Requests for monthly payments by CM@Risk for Pre-Construction Services must be
submitted monthly and must be accompanied by a progress report, detailed invoices
and receipts, if
applicable. Any requests for payment must include, as a minimum, a
narrative description of the tasks accomplished during the billing period, a listing of any
Deliverables submitted, and copies of any
requests for payment, plus
similar narrative and listings of Deliverables associated with their Work. Payment for
services negotiated as a lump sum will be made in accordance with the percentage of work
completed during the preceding month.
17.8.2
In no event will City pay more than seventy-five (75%) of the Agreement Price until
acceptance of ALL Pre-Construction Services and award of the final approved Construction
Services Agreement for the entire Project by City Council. If CM@Risk does not prepare a

General Conditions
Revised: 7/20/22
GC-75 of 75
GMP Proposal that is
acceptable to City, or the
GMP Proposal exceeds
Construction Budget, then CM@Risk understands and acknowledges that it will forfeit any
right to receive the 25% of the Agreement Price being retained by City.
17.8.3
CM@Risk agrees that no charges or claims for costs or damages of any type will be made by
it for any delays or hindrances beyond the reasonable control of City during the progress of
any
portion of Pre-Construction Services specified in this Agreement. Such delays or
hindrances, if
any, will be solely compensated for by an extension of time for such
reasonable period and may be mutually agreed between the parties. It is understood
and agreed, however, that permitting CM@Risk to proceed to complete any such Services,
in whole or in part after the date to which the time of completion may have been extended, 
will in no way act as a waiver on the part of City of any of their respective legal rights herein.
17.8.4
No compensation to CM@Risk will be allowed contrary to Article I, Chapter I, Title 34 of the
Arizona Revised Statutes.
17.8.5
If any service(s) executed by CM@Risk is abandoned or suspended in whole or in part, for
a period of more than 180 days through no fault of CM@Risk, CM@Risk is to be paid for
the services performed prior to the abandonment or suspension.
17.9
SURVIVAL OF THE DESIGN SERVICES AGREEMENT, DUTIES, OBLIGATIONS AND
WARRANTIES
If the GMP Proposal is accepted by City and a Construction Agreement is entered into
between City and CM@Risk, the duties, obligations and warranties of CM@Risk under the
Pre- Construction Services Agreement survive and are incorporated into the resulting
Construction Agreement.

7/20/2022
APP-1 of 33 
General Conditions Appendices 
 
SECTION 15  APPENDICES 
The following Appendices attached hereto are referenced in the General Conditions and 
are incorporated herein. 
 
Appendix 1  Policy Statement for Calculating Delays and Damages 
Appendix 2  Cost Reduction Incentive Proposals for Design Bid Build Agreements 
Appendix 3  Contractor s Affidavit Regarding Settlement of Claims 
Appendix 4  Forms of Performance Bond 
Appendix 5  Forms of Payment Bond 
Appendix 6  Dispute Resolution 
Appendix 7  Certificate of Completion 
Appendix 8  Construction Sign Detail 
Appendix 9  Cost of the Work (Applicable solely to Construction Manager at Risk and 
Job Order Contracting) 
Appendix 10 Landscape Establishment Period

7/20/2022
APP-2 of 33 
General Conditions 
Appendix 1 
CALCULATING DELAYS AND DAMAGES 
The purpose of this policy statement is to establish guidelines and procedures for negotiation between 
the Contractor and City of Chandler relating to compensation for delays pursuant to Arizona Revised 
Statutes (A.R.S.) 34-221(F). This policy statement contains notice requirements in addition to those set 
forth in the Agreement Documents, and will be the Agreement Provision contemplated by that statute. 
NOTE: As used herein, the term Engine
 will refer to the City of Chandler City Engineer or 
his/her designated representative. Nothing in this Policy Statement will be construed to void any 
provision in the Agreement which requires timely notice of delays or provides for arbitration or 
any other procedure for settlement or provides for liquidated damages. 
I. 
TYPES OF DELAYS: 
For the purposes of this document, there are essentially four types of delays encountered by 
City of Chandler Construction Contractors; excusable/compensable, excusable/non-
compensable, non- excusable, and concurrent. Only delays that extend Agreement 
Completion Time set forth in the Agreement Document will be considered for issues 
relating to Agreement extensions or additional compensation. All other delays are 
considered to be activity delays and do not entitle the Contractor to either time extensions 
or additional compensation. Agreement Completion Time will be defined as the date set forth 
in Maricopa Association of Governments (MAG) Uniform Standard Specification Section 101 
and as may be modified by the Agreement Documents. 
A. 
Excusable/Compensable: 
These are delays caused solely by the City s actions or inactions, are unreasonable 
under the circumstances, and which were not within the contemplation of the 
parties to the Agreement at or prior to the time of execution of the Agreement. 
Since the Contractor presumably has no control over the events causing the delay, 
he may be entitled to both Agreement time extensions and additional compensation 
for delay damages. Further, he/she may be entitled to additional compensation from 
the impact of that delay on other work. Examples of excusable/compensable (E/C) 
delays include: failure to properly locate an underground City-owned utility within 2 
feet of the actual location; failure to relocate City-owned utilities far enough in 
advance of construction in an area where the Contractor is scheduled to work that 
it delays start or completion of the Contractor s regularly scheduled work; failure 
to provide City-furnished equipment or materials in a timely manner if required by 
the Agreement; failure to acquire necessary Right-of-Way or Public Utility Easements 
prior to the Contractor beginning Work in the area; failure to timely return Shop 
Drawings or other Agreement Submittals in accordance with the Agreement; 
unreasonable delay by the City in making decisions which affect critical activities; 
surveying errors when the City is contractually responsible for providing Project 
Surveying. This list is not meant to be all inclusive, but is intended merely as examples 
of the type of City action or inaction which can result in a Contractor s claim for 
additional time and compensation.

7/20/2022
APP-3 of 33 
General Conditions 
Appendix 1 
B. 
Excusable/Non-compensable: 
These are delays over which neither the City nor the Contractor had control. Since 
both parties to the Agreement have been potentially damaged by the delay, but 
neither have caused it, only Time Extensions are warranted. Examples of excusable, 
non-compensable (E/N) delays include: unusually severe weather; fire; acts of God; 
failure of non-City owned utilities (SRP, CenturyLink, Cable TV, Southern Pacific 
Railroad, and Southwest Gas, etc.) to properly or timely locate accurately; failure of 
non-City owned utilities to relocate in advance of construction; the voluntary or 
involuntary filing for Bankruptcy protection by a Supplier or Subcontractor which 
causes the Supplier/Subcontractor to fail to meet a contractual deadline provided the 
Contractor can provide documentation that he/she executed the required Purchase 
Orders/Subcontract Agreements and received delivery schedules which, if met, 
would have eliminated the delay; delays as a result of an incomplete shutdown of a 
City or non-City owned utility main (the City does not guarantee a complete 
shutdown). This list also is not necessarily all inclusive but merely indicative of type 
and class of E/N delays. 
C. 
Non-excusable/Non-compensable: 
These are delays caused by the actions or inactions of Contractor or an officer, 
employee, agent, Subcontractor, Supplier or any other party for whom the Contractor 
is responsible. Since the Contractor has assumed responsibility for the risks 
associated with the events that caused the delay, he/she are not entitled to either time 
extensions or monetary delay damages. All non-excusable delays are also non-
compensable. Examples of non- excusable, non-compensable (N/N) delays include: 
failure to perform by the Contractor, its Subcontractors and/or Suppliers (except as 
noted in section I.B above); failure to provide adequate labor, materials, and/or 
equipment on the Project; failure to perform contractually-required coordination 
with utilities, agencies and other Contractors; failure to notify the Engineer, in writing, 
of delay impacts within two working days, as required by MAG 104.2.3, or the next 
work day, as required by MAG 109.8.2; failure to timely submit Shop Drawings; failure 
to pothole or otherwise visually locate utilities sufficiently ahead of the Work to allow 
the Engineer to direct corrective action when necessary; delays due to retesting of 
previously failed work, re-inspection, and/or restaking resulting from faulty 
workmanship, poor quality control, or lack of compliance with Agreement 
Specifications. Again, this list is not necessarily all inclusive. 
D. 
Concurrent: 
When two or more delays occur simultaneously or overlap, each delay is analyzed 
separately to determine its impact on the overall project completion date based on 
when that delay started. Once again, only those delays which actually extend the 
Agreement completion time are considered as delays. The concurrent delay is 
considered an additional delay only to the extent it prolongs the delay to the 
Agreement Completion Time beyond the date that the one it is concurrent with had 
already delayed that date. For example, if two delays are concurrent, and one is five 
days long and the second is seven days long, the second concurrent delay will only 
extend the Agreement Completion Time by two days. The same method of analysis is

7/20/2022
APP-4 of 33 
General Conditions 
Appendix 1 
used when there are multiple concurrent delays. Only those extending the Project 
Completion Date are considered to be delays for the purposes of this policy. The 
portion of each concurrent delay that delays the completion of the work is classified 
in the same manner as described previously for individual delays and being either E/C, 
E/N or N/N. 
An example of a concurrent delay is where the City delays furnishing material, but 
the Contractor could not have installed it anyway due to unusually severe weather. The 
effect of the first delaying activity will extend for the full duration and will be 
considered controlling on the Contractor s schedule. A subsequent, concurrent delay 
will thereafter only be considered to effect the project completion (if at all) once the 
first delaying activity has ceased to impact the project completion. In this case, if the 
unusually severe weather continued and delayed the work after the material was 
delivered, the first portion of the delay would be classified E/C (delay for material) 
and the second as E/N (delay due to unusually severe weather). Using the procedure 
set forth above, the entire concurrent portion would be considered E/C as shown in 
the chart which follows. 
Example of a Concurrent Delay: 
E/C Delay 
E/N Delay 
City Related Material Delay 
Rain Delay 
II. 
ANALYZING THE DELAY: 
The Contractor must provide all documents required or requested by the Engineer to analyze the 
delay(s). It is important to understand that, prior to the delay analysis, delays and their impacts are 
alleged issues. The information the Contractor provides will be compared with the Inspector s Daily 
Log, Schedules and other available Project information and together they will support or refute that 
delays occurred and, if so, how they impact other work and the overall project completion. The 
Contract
 delay in providing these documents will be considered prima facie evidence that either 
the delay did not occur or it did not impact the Project Completion Date and any claim for time 
extension or damages will be denied. 
The Engineer will accept delay analyses in CPM format, as these may demonstrate to his/her 
satisfaction whether or not Project Completion has been impacted by a specific event. If the Contractor 
chooses not to use CPM scheduling procedures, then the burden will be on the Contractor to prove 
to the Engine
 satisfaction that the Project Completion has been impacted. The procedures

7/20/2022
APP-5 of 33 
General Conditions 
Appendix 1 
below assume that the Contractor is using CPM scheduling methods. As a minimum the Contractor 
must provide the following materials to the Engineer: 
A. 
As-Planned Schedule. The initial construction schedule, required by the Agreement 
Documents, will be considered the baseline schedule. It is to the Contractor s 
advantage that the As-Planned (baseline) Schedule be as detailed as possible in order 
for delays, as they occur, to be incorporated into the schedule in representative 
locations. It is also to the Contractor s advantage to use a computer software program 
to generate the schedule since updated schedules are required monthly by the 
Agreement Documents and since updated schedules are required to support 
delays and requests for additional compensation for delays. The As-Planned 
(baseline) Schedule must be presented in network format which clearly shows the 
interrelationships of the activities. The Contractor must also provide a printout of the 
activities showing early start, early finish, late start, late finish, duration and float. The 
activity list printout must also indicate predecessor and successor activities. 
B. 
As-Built Schedules. The as planned (baseline) schedule must be updated with 
complete progress-to-date information (actualized) up to the date of the start of the 
alleged delay. Each updated schedule will serve as the as-built schedule for analyzing 
the alleged delay and provide a new baseline as-planned schedule for the next delay. 
This process must be repeated for each alleged delay as it occurs. In updating the 
baseline schedule, the alleged delay must be treated as an activity and inserted into the 
schedule as a predecessor to the impacted activity (ies). When an activity that has 
already started is impacted, it is preferable to divide this activity into two parts and 
show the impact affecting the second part. For schedules which incorporate a time 
line (or data date), the delay activity must be inserted at the time it actually occurred. 
Some software scheduling programs have a PAUSE-RESUME feature that can be 
used to facilitate the requirements. The updated schedule must also be accompanied 
by a listing of activities as with the baseline schedule. This activities list must contain 
the alleged delay as an activity showing the duration and the activities which are 
predecessors and successors to it. When computer generated schedules are used, 
the Contractor must provide, in electronic media format, the complete data files for 
the updated schedule that included the delay activity, preferably either in Suretrak 
or in Microsoft Project. Each electronic media must contain a label identifying the 
Project name, Contractor s name, program name and version number, data date 
and project finish date. 
C. 
Other Documents: In order to determine the amount of the alleged delay and if it 
is compensable, the Contractor must provide all backup documentation relevant to the 
issue and as required by the Engineer. This documentation must include copies of 
such items as: purchase orders; delivery schedules; correspondence; memoranda of 
telephone calls; force account daily worksheets (initialed by the Inspector); payroll 
data; estimating (bid) worksheets; and any other materials which may be requested 
by the Engineer. 
D. 
Procedure: Only after receipt of sufficient documentation will the Engineer analyze 
each alleged delay and determine if it is supported or refuted. If supported, the 
Engineer will determine if it is excusable or non-excusable, compensable or non-

7/20/2022
APP-6 of 33 
General Conditions 
Appendix 1 
compensable. If the Engineer determines that the delay did not affect the Project 
Completion, the as-planned schedule, which has been updated to the date of the 
alleged delay, must be revised to indicate this. If the Engineer determines the delay 
did occur but was N/N, then no time extension will be granted. It is imperative that 
an actualized schedule be submitted as soon as the occurrence of the alleged delay 
is known. In no event will the Contractor submit an actualized updated schedule 
later than 60 days after the occurrence of the alleged delay becomes known. 
If the Engineer determines the delay did occur and was excusable but, due to a 
reason listed in section I.B. is non-compensable, he/she will determine the length of 
the E/N delay and prepare a Change Order to add that time to the Agreement. The 
Engineer s decision will be final. 
If the Engineer determines the delay was excusable and compensable, he/she will 
determine the length of the E/C delay and proceed to review the Contract
 damage 
calculations in accordance with Section III. The Engineer will check the Contractor s 
calculations, review the backup documentation provided, and prepare a Change 
Order to cover both the additional compensation and the time extension. The 
Engineer s decision on both the time extension and additional compensation for the 
delay will be final. 
If the issue involves a concurrent delay, the Engineer will analyze available data 
to determine the portions which are E/C, E/N, and/or N/N as described above. The 
Engineer will proceed to determine the length of E/C delay and verify the Contractor s 
delay damage calculations, if any are provided. Upon completion of this review, the 
Engineer will prepare a Change Order for the Contractor s review and signature. 
The Engine
 decision regarding excusable delay and additional compensation for 
the delay is final. 
The amount of time the Engineer will require to analyze the alleged delay(s) will 
depend upon the Engineer s workload, the complexity of the delay analysis, 
availability of supporting data, extent of cooperation by the Contractor, and other 
factors beyond the Engineer s control. It is entirely possible other delay(s) may occur 
while the Engineer is analyzing particular claim for delay(s). The Engine
 failure to 
respond to the Contractor in a set period of time will not be used as the basis for 
a further delay claim or as justification for extending and existing delay claim. The 
time required for delay analysis by the Engineer will not be counted against the time 
allotted for processing Final Payment as required by (MAG Section 109.7(B)) or the 
release of retention and Final Payment as prescribed by A.R.S. Arizona Revised 
Statutes §34-221. 
III. 
CALCULATING MONETARY DELAY DAMAGES: 
Additional compensation for delay, when authorized by the Engineer, will be calculated in accordance 
with MAG Section 109.5 ACTUAL COST WORK with the following exceptions: 
A. 
No additional compensation or other monetary damages will be awarded or paid for 
any loss of anticipated profits by the Contractor, Subcontractors or Suppliers.

7/20/2022
APP-7 of 33 
General Conditions 
Appendix 1 
B. 
No additional compensation or other monetary damages will be awarded for home 
office overhead or non-project general conditions of the Contractor, Subcontractors 
or Suppliers. 
C. 
Equipment: 
1. 
Contractor-owned equipment rate calculations must be computed in 
accordance with Section 109.04(D)(3), Arizona Department of Transportation 
Standard Specifications for Road and Bridge Construction  2008 or latest 
edition and as modified herein. Year and regional adjustment factors must be 
based on the most recent publications of the Rental Rate Blue Book for 
Construction 
Equipment, published 
by 
the 
Equipment 
Guide-Book 
Company, San Jose, CA, same as provided by ADOT and in print as of the 
date of alleged delay. In no event will the compensation for Contractor-
owned equipment exceed the purchase price, including tax, paid by the 
Contractor for the equipment. Compensation will not be allowed for small tools 
or equipment that show a daily equipment rental rate of less than $5.00 per 
day or for unlisted equipment that has a value of less than for hundred 
dollars ($400.00). 
2. 
For leased and rented equipment or equipment not otherwise listed in the 
Blue Book, rental contracts, or other supporting data will be used to establish 
the hourly rate. No hourly operating expense will be allowed for delay on 
standby equipment. In no case will equipment be considered for rental which 
exceeds the hourly rate for the first eight hours and the daily rate divided 
by eight for all additional hours as compared with similar equipment listed in 
the Blue Book. The hourly standby rate must be computed as the lesser of: 
a. 
Dividing the monthly invoice or rental value by 176 hours 
per month when the equipment is utilized by the Contractor 
for more than three weeks; 
b. 
Dividing the monthly invoice or rental value by 40 hours per 
week when the equipment is utilized by the Contractor for 
more than three days. 
In no event will compensation be paid for delay at more than 
8 hours per day or 40 hours per week. 
3. 
Except for vehicles used by supervisory personnel, all equipment will be paid 
at the standby  rate during the delay period. 
4. 
Equipment brought solely to mitigate the delay (such as pumps, light plants, 
etc.) may be paid in accordance with ADOT section 109.04(D) (3). 
5. 
The Blue Book regional adjustment will apply in determining rental rates. 
D. 
Material: 
Allowable material charges may include, in addition to material incorporated in the

7/20/2022
APP-8 of 33 
General Conditions 
Appendix 1 
work material used to mitigate the delay such as barricades, plates, shoring, cold 
mix, etc. Except in emergencies the Contractor will not employ such material 
without the prior written approval of the Engineer. 
E. 
Labor: 
1. 
Except for Supervisory Personnel (Superintendent, Project Engineer, and 
Foremen), labor wages will not be paid after the first one-half day of claimed 
delay or impact. It is expected the Contractor will reassign or layoff 
unneeded employees. 
2. 
For Foreman wages to be included, that Foreman must have been actively 
employed on the project prior to the commencement of the delay and be 
directly responsible for the activity being delayed. 
3. 
Labor burden must be actual amounts incurred but must not exceed the 
ADOT approved rate. 
F. 
All costs (equipment, material, and labor) must be substantiated by the City of 
Chandler s Daily Work Reports. 
IV. 
DOCUMENT REQUIRED FOR CLAIM ANALYSIS: 
For purposes of reviewing the Contractor s request for additional compensation, it will be required 
that the Contractor submit the following listed information. Information requested must be prepared 
on forms which are substantially similar to the City of Chandler s Daily Work Report form, a copy of 
which is attached as an exhibit. 
A. 
Labor: 
For each employee, laborer, and foreman, for which compensation is requested: 
Name, classification, dates of work performed, daily hours worked, total hours worked, 
labor rates, labor burden rates, overtime or premium time charges. Further, the 
Contractor must make available for inspection and copying to the Engineer the 
following listed documentation. 
1. 
Certified payroll reports for the period of work claimed. 
2. 
Accounting of Fringe Benefits  certified by a CPA. 
3. 
Contractor s and Subcontractor s daily field reports and daily diaries. 
B. 
Materials: 
For all materials for which compensation is requested, if any, total quantities of 
materials, prices, extensions and transportation costs must be provided on a daily 
basis. Further, the Contractor must make available for inspection and copying to the 
Engineer the following listed documentation. 
1. 
Invoices for all materials incorporated. 
2. 
Weigh tickets. 
3. 
Purchase orders.

7/20/2022
APP-9 of 33 
General Conditions 
Appendix 1 
4. 
Delivery schedules. 
5. 
Quotes or proposals from manufacturers or supplier. 
6. 
Freight bills, Bills of Lading, or other documentation to show transportation 
costs. 
7. 
Restocking charges-invoices from vendor. 
C. 
Equipment: 
For all equipment, the Contractor must provide the Engineer with the designation, 
dates and hours of usage, dates and hours of standby, if any, daily hours, total hours, 
rental rates and extension for each unit of equipment and machinery. Rental 
rates will be as established in Section III. Further, the Contractor must make available 
for inspection and copying to the Engineer the following listed documentation. 
1. 
Owned: 
a. 
Purchase contracts(s). 
b. 
Depreciation schedule(s). 
c. 
Invoices for fuel, lube, repairs and other operating costs. 
2. 
Leased: 
a. 
Lease agreement with hourly rate, overtime rate, double shift rate, etc. 
b. 
Invoices or other documentation showing hours worked on a daily 
basis. 
D. 
Subcontractors/Owner-Operators: 
In the event the Contractor submits a claim which includes requests for compensation 
for Subcontractors of Owner-Operators, the same information requested of the 
Contractor must be provided by the Subcontractor/Owner-Operator. Further, the 
Contractor must make available for inspection and copying to the Engineer the 
following listed documentation. 
1. 
Bid/Estimate work sheets and/or spreadsheets. 
2. 
Subcontract Agreements or Agreements with Owner-Operator. 
3. 
All invoices and billing statements received from the Subcontractor/Owner- 
Operator which relates to the amount requested. 
E. 
Miscellaneous: 
Further, the Contractor must make available for inspection and copying to the Engineer 
the following listed documentation. 
1. 
Evidence of payment for bonds and insurance premiums (MAG 109.5.6). 
2. 
Taxes  unless the Contractor can show otherwise, taxes are reimbursable at 
65% of the total cost (less bonds and insurance). 
V. 
TIME LIMIT ON SUBMISSIONS OF CLAIM FOR DELAY OR IMPACT DAMAGES: 
No claims for delay or impact damages will be considered or allowed more than 45 days after the 
event or occurrence which the Contractor claims gives rise to the delay or impact. In no event will a

7/20/2022
APP-10 of 33 
General Conditions 
Appendix 1 
claim for delay or impact damages be considered after submission by the Contractor of the Final 
Payment Request.

7/20/2022
APP-11 of 33 
General Conditions 
Appendix 2
 
COST REDUCTION INCENTIVE PROPOSALS 
FOR DESIGN BID BUILD AGREEMENTS 
 
The Contractor may submit to the Engineer proposals for modifying the Plans, Specifications, or 
other requirements of the Agreement for the sole purpose of reducing the total cost of Project 
construction. The proposals must not impair in any manner the essential functions or characteristics 
of the project; including but not limited to service life, economy of operations, ease of maintenance, 
desired appearance, compatibility with existing or planned equipment, standardization of systems, 
or  design and safety standards. 
It must not be inferred from this Policy that the Engineer is required to consider any proposal 
submitted. 
Submissions that propose changes in the basic design of a bridge, propose changes in pipe line 
size, materials, bedding conditions, pipe specifications; or that propose any change in pavement design 
will not be considered. 
Proposals submitted pursuant to this Policy will be identified as Cost Reduction Incentive Proposals. 
They must be submitted in writing and, at a minimum, contain the following. 
1. 
Complete the attached or similar cost reduction incentive proposal form. 
2. 
A description of both the existing Agreement Requirements for performing the work 
and the proposed changes. 
3. 
All Engineering Drawings and computations necessary for the thorough and 
expeditious evaluation. 
4. 
An itemization of the existing Agreement Requirements that must be changed if the 
Proposal is adopted and a recommendation as to the manner in which the change 
should be made. 
5. 
A detailed estimate of the cost of performing the Work under the existing 
Agreement and under the proposed changes, including the cost of developing and 
implementing the changes. 
6. 
The Agreement items affected by the proposed changes and any variations in 
quantities resulting from the changes. 
7. 
An objective estimate of any effects the proposal will have on collateral cost to the 
City, costs of related items, and cost of maintenance and operation. 
8. 
A statement as to the effect that the Proposal will have on the time for the completion 
of the Project. 
9. 
A statement as to the time by which a Change Order adopting the Proposal must 
be executed or when the Engineer must have given verbal approval.

7/20/2022
APP-12 of 33 
General Conditions 
Appendix 2
 
Proposals will be processed expeditiously; however, the City will not be liable for any delay in acting 
upon any Proposal nor for any failure to accept any Proposal pursuant to this Special Provision. 
The Engineer will be the sole judge of the acceptability of a Proposal and of the estimated net savings 
in construction costs from the adoption of all or any part of the Proposal. The Contractor will be 
notified in writing by the Engineer as to whether his/her Proposal has been accepted. The decision by 
the Engineer is final. 
When the City deems such action to be appropriate, it reserves the right to require the Contractor to 
share equally in the cost to the City of investigating, evaluating, and processing the proposal as a 
condition for the consideration of such Proposal. Such cost must be shared whether the Proposal is 
accepted or rejected. When such a condition is imposed, the City will estimate these costs and the 
Contractor must indicate his acceptance thereof in writing. Such acceptance will authorize the City to 
deduct the Contract
 share of the costs from any monies due or that may become due to the 
Contractor under the Agreement. 
If the Contractor s Proposal is accepted in whole or in part, the necessary Agreement Modifications 
and Agreement Price Adjustments will be affected by the execution of a Change Order which will 
specifically state that it is executed pursuant to this Special Provision. 
The Contractor must continue to perform the work in accordance with the requirements of the 
Agreement until a Change Order incorporating the Proposal has been executed or until he/she has 
been given verbal approval by the Engineer that his/her Proposal has been accepted. If the Change 
Order has not been executed or he/she has not been given verbal approval on or before the date 
specified on the attached cost reduction incentive proposal form or on or before such other date as the 
Contractor may have subsequently specified in writing, the Proposal may be deemed to be rejected. 
The executed Change Order will incorporate the changes in the Plans, Specifications, or other 
requirements of the Agreement which are necessary to permit the Proposal, or such part of it which 
has been accepted, to be put into effect, and will include any condition  upon which the Citys 
approval thereof is based, if such approval is conditional. The executed Change Order may also 
extend the time for the completion of the Agreement if such an extension has been deemed to be 
warranted by the Engineer as a result of his evaluation of the Proposal. 
The executed Change Order will also establish the estimated net savings in the cost of performing 
the Work attributable to the Proposal effectuated by the Change Order. In determining the net 
savings, the right is reserved to the Engineer to disregard the Agreement bid prices if, in his/her 
judgment, such prices do not represent a fair measure of the value of the Work to be performed or 
to be deleted. The net savings will be established by determining the Contract
 cost of performing 
the Work, taking into account his/her cost of developing the Proposal and implementing the change, 
and reducing  this amount by any ascertainable collateral costs to the City. The executed Change 
Order may provide that the Contractor be paid 50 percent of the estimated net savings amount. 
The executed Change Order may also provide for the adjustment in Agreement prices. Agreement 
prices may be adjusted by subtracting the City s share of the accrued net savings. 
The amount specified to be paid to the Contractor in the executed Change Order which effectuates a 
Cost Reduction Proposal will constitute full compensation to the Contractor for the Cost Reduction

7/20/2022
APP-13 of 33 
General Conditions 
Appendix 2
 
Proposal and the performance of the work thereof pursuant to the said Change Order. 
Upon acceptance of a Cost Reduction Incentive Proposal, any restrictions imposed by the 
Contractor on its use or on disclosure of the information will become void, and the City thereafter 
will have the right to use all or any part of the Proposal without obligation or compensation of any 
kind to the Contractor.

7/20/2022
APP-14 of 33 
General Conditions 
Appendix 2
 
COST REDUCTION INCENTIVE PROPOSAL FORM
TO: 
CIP City Engineer 
FROM: 
 
PROJECT NAME: 
Taxiway B Improvements Phase 1 
CITY PROJECT NUMBER: 
AI2302.401; ADOT No.: E3S4C 
DATE: 
 
Summary of Change (Brief description of proposed change including advantages and disadvantages): 
ESTIMATED COST SUMMARY (Attached detailed estimate): 
 
A.
 
Original Cost:
 
 
 
$
B.
Proposed Cost:
$
C.
Construction Savings (A-B):
$
D.
Gross Savings (Included OH
%, Bond
%)
$
E.
Contractor Implementing
$_
F.
City Implementing Cost:
$_
Reduction in Agreement Price (C+D-E-F) x 50%: 
$   
 
Date by which a Change Order must be issued so as to obtain maximum cost reduction:

7/20/2022
APP-15 of 33 
General Conditions 
Appendix 3 
CITY OF CHANDLER, ARIZONA 
PUBLIC WORKS & UTILITIES DEPARTMENT 
CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS 
________________________, Arizona 
Date ____________________________ 
Project Name:  Taxiway B Improvements Phase 1 
City Project No.:  AI2302.401; ADOT No.: E3S4C 
To the City of Chandler, Arizona 
Gentlemen: 
This is to certify that all lawful claims for materials, rental of equipment and labor used in connection 
with the construction of the above project, whether by subcontractor or claimant in person, have been 
duly discharged. 
The undersigned, for the total compensation of $________________________, as set out in the final pay 
application, as full and complete payment under the terms of the Agreement, hereby waives and 
relinquishes any and all further claims or right of lien under, in connection with, or as a result of the 
above described project.  The undersigned further agrees to indemnify and save harmless the City of 
Chandler against any and all liens, claims or liens, suits, actions, damages, charges and expenses 
whatsoever, which said City may suffer arising out of the failure of the undersigned to pay for all labor 
performances and materials furnished for the performance of said installation. 
Signed and dated at ________________, this _________ day of _______________ 20_____. 
__________________________________ 
CONTRACTOR 
By _______________________________ 
STATE OF ARIZONA 
 
) 
) SS 
COUNTY OF MARICOPA 
) 
The foregoing instrument was subscribed and sworn to before me this __________ day of 
__________________ 20 _________. 
___________________________________ 
 
 
 
 
Notary Public 
___________________________________ 
 
 
 
 
My Commission Expires

7/20/2022
APP-16 of 33 
General Conditions 
Appendix 4 
PERFORMANCE BOND
ARIZONA STATUTORY PERFORMANCE BOND 
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES 
(Penalty of this bond must be 100% of the Agreement amount) 
KNOW ALL MEN BY THESE PRESENTS THAT:___________________________________________________ 
(hereinafter "Principal"), and __________________________________________________________ (hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of ______________ with its principal office in the City 
of _____________________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
__________________________(hereinafter "Obligee") in the amount of __________________________________________ (Dollars) 
($___________), for the payment whereof, Principal and Surety bind themselves, and their heirs, administrators, 
executors, successors and assigns, jointly and severally, firmly by these presents. 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated  
the ____________ day of _______________________, 20___ for construction of Taxiway B Improvements Phase 1, 
City Project No.: AI2302.401; ADOT No.: E3S4C which Agreement is hereby referred to and made a part 
hereof as fully and to the same extent as if copies at length herein. 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs 
and fulfills all the undertakings, covenants, terms, and conditions of the Agreement during the original term of the 
Agreement and any extension of the Agreement, with or without notice of the Surety, and during the life of any 
guaranty required under the Agreement, and also performs and fulfills all the undertakings, covenants, terms, 
conditions, and agreements of all duly authorized modifications of the Agreement that may hereafter be made, 
notice of which modifications to the Surety being hereby waived, the above obligation is void.  Otherwise it remains 
in full force and effect. 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2, 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of Title 
34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this Agreement. 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees 
that may be fixed by a judge of the court. 
Witness our hands this ________________ day of ____________________, 20__. 
 
 
 
 
____________________________________ 
PRINCIPAL          
SEAL 
___________________________________ 
AGENT OF RECORD 
 
 
 
By _________________________________ 
 
 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
AGENT ADDRESS

7/20/2022
APP-17 of 33 
General Conditions 
Appendix 5 
PAYMENT BOND
 
 
ARIZONA STATUTORY PAYMENT BOND 
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES 
(Penalty of this Bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:________________________________________________  
(hereinafter "Principal"), as Principal, and _________________________________________(hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of __________________   with its principal office in the 
City of __________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of the Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly 
bound 
unto 
________________________ 
 
(hereinafter 
"Obligee") 
in 
the 
amount 
of 
______________________________________________ (Dollars) ($___________), for the payment whereof, the Principal and 
Surety bind themselves, and their heirs, administrators, executors, successors and assigns, jointly and severally, 
firmly by these presents. 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated the _________ day of 
_______________________, 20___ for construction of Taxiway B Improvements Phase 1, City Project No.: 
AI2302.401; ADOT No.: E3S4C which Agreement is hereby referred to and made a part hereof as fully and to the 
same extent as if copied at length herein. 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all 
moneys due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the 
prosecution of the work provided for in said Agreement, this obligation is void. Otherwise it remains in full force 
and effect. 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, 
conditions and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were 
copied at length in this Agreement. 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees 
that may be fixed by a judge of the court. 
Witness our hands this ________________ day of ____________________, 20__. 
 
 
 
____________________________________ 
PRINCIPAL          
SEAL 
___________________________________ 
AGENT OF RECORD 
 
 
 
By _________________________________ 
 
 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
AGENT ADDRESS

7/20/2022
APP-18 of 33 
General Conditions 
Appendix 6
DISPUTE RESOLUTION 
A. 
INFORMAL DISPUTE RESOLUTION 
The parties to the Agreement agree that time is of the essence in relation to 
performance of the Agreement and completion of the Project, therefore any and all 
disputes in relation to the Agreement will initially be referred to the Project Manager, 
the Design Professional Representative and/or the Contractor Representative as 
applicable to the dispute, for immediate resolution. If, after good faith efforts to reach 
a resolution, none is reached, any party to the dispute may submit the dispute to 
the Dispute Resolution Representative 
) process set forth below, which is 
intended to be an expedited process. 
B. 
DISPUTE RESOLUTION REPRESENTATIVE 
) PROCESS 
1. 
The Parties under the Agreement agree that all claims and disputes in relation 
to the Project which are not resolved in the ordinary course of the Project 
laim  or 
laims  will, as a prerequisite to any mediation, or litigation of 
the Claim, first be submitted for resolution between the designated 
Dispute Resolution Representatives of the Parties as set forth herein (the 
 
Process
 
2. 
The DRR Process will be initiated through service of a DRR Notice as set forth 
below: 
a. 
For claims by the Contractor or the Design Professional, the DRR 
Process will be initiated by the party asserting the claim serving written 
notice on the City setting forth in detail: (i) the basis for the claim; (ii) the 
effect of the Claim upon the construction of, and/or Project Schedule 
for, the Project; 
(iii) the specific relief requested, the amount thereof, and how such 
was calculated; (iv) the parties involved in the Claim, and how they 
are involved; (v) the specific Agreement provisions in the Agreement 
Documents (including, if applicable, drawings and specifications) which 
apply; and (vi) efforts made to date to resolve the Claim. 
b. 
For claims by the City, the DRR process will be initiated by the City 
providing written notice to the other parties of the basis and amount 
of its claim, the parties involved in the Claim, and how they are 
involved, the provisions in the Agreement Documents that apply, and 
the relief requested. 
c. 
The DRR Notice will be hand-delivered and e-mailed to the other 
parti
 designated Dispute Resolution Representatives. 
3. 
The other parties will respond in writing to the DRR Notice 
 Respons
 
within ten (10) calendar days of receipt of the DRR Notice, setting forth those 
items set forth in the DRR Notice that they agree with, dispute, and/or have 
questions concerning. The DRR Response will be hand-delivered and e-mailed 
to the other parties  Dispute Resolution Representatives.

7/20/2022
APP-19 of 33 
General Conditions 
Appendix 6
4. 
The designated Dispute Resolution Representatives for the Parties to the 
claim will then meet as soon as possible and in any event within twenty (20) 
calendar days of submission of the DRR Notice (regardless of whether a DRR 
Response has been submitted by all parties involved in the dispute), at a 
mutually agreed upon time and place, to attempt to resolve the Claim based 
upon the DRR Notice and DRR Response. 
5. 
At any time after the first meeting required above, either party may terminate 
the DRR Process by written notice to the other party. 
6. 
The parties may agree, in writing, to extend or modify the time limits or 
other provisions of the DRR process in relation to a specific pending Claim. 
7. 
Unless otherwise designated in a written notice to the other parties, the City 
and the representatives of the Contractor and of the Design Professional will 
act as the parti
 designated Dispute Resolution Representatives. 
8. 
If a resolution of the Claim is reached, that resolution must be set forth in 
writing and must be signed by the Parti
 designated Dispute Resolution 
Representative. If the resolution involves a change in any Agreement 
Documents, the Agreement Price, the Project Schedule, or any other change 
requiring a written Change Order or Amendment, the parties must execute 
an appropriate written Change Order or Amendment pursuant to the terms 
of the Agreement Documents. 
C. 
MEDIATION 
1. 
Unless extended by written agreement of the parties involved in the dispute, 
any Claim not resolved through the DRR process set forth above within 
five (5) calendar days after the meeting required under B (4) above, or after 
the DRR is terminated pursuant to B (5) above, whichever is earlier, will be 
submitted to mediation as a condition precedent to litigation by either party. 
2. 
The mediation will be commenced by written demand upon the other party 
for mediation. If the parties cannot agree upon a mediator within ten (10) 
calendar days of the written demand, either party may make a request to the 
Civil Presiding Judge of the Maricopa County Superior Court to appoint a 
mediator. The mediation will occur within forth (40) calendar days of the 
written demand for mediation, unless the parties agree, in writing, to a longer 
period of time. 
3. 
The qualifications for the mediator will be that he/she be: (a) an experienced 
mediator, arbitrator or litigator of construction disputes; and (b) having 
engaged a significant portion of his/her time involving and/or resolving 
construction disputes for at least the past five (5) years. 
4. 
Each party will provide to the other party and the mediator all of the 
information and documentation required under B(1) and (2) above, together 
with any additional information and documentation which the party believes 
relevant. In addition, the parties will exchange, and provide to the mediator 
such additional memoranda, information and/or documentation, as the

7/20/2022
APP-20 of 33 
General Conditions 
Appendix 6
mediator may request, and in the form and at such times, as the mediator may 
direct. 
5. 
The parties will share the mediator s fee and any filing fees equally. The 
mediation will be held in Chandler, Arizona, unless another location is 
mutually agreed upon.  Agreements reached in mediation will be specifically 
enforceable in any court having jurisdiction thereof. 
D. 
LITIGATION 
Any claim arising out of or related to the Agreement, except Claims relating to aesthetic 
effect and except those claims waived as provided for in the Agreement 
Documents, must be resolved through litigation in the Maricopa County, Arizona 
Superior Court.

7/20/2022
APP-21 of 33 
General Conditions 
Appendix 7
CITY OF CHANDLER, ARIZONA
PUBLIC WORKS & UTILITIES DEPARTMENT 
 
CERTIFICATE OF COMPLETION 
 
PROJECT NAME: 
Taxiway B Improvements Phase 1 
CITY PROJECT NO.: 
AI2302.401; ADOT No.: E3S4C 
If Federally Funded: 
 
FEDERAL NO.: 
 
ADOT NO: 
 
(This section to be completed by Prime) 
I HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER FOR THIS 
PROJECT HAVE BEEN DELIVERED IN ACCORDANCE WITH THE AGREEMENT DOCUMENTS AND BID 
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE AGREEMENTOR UNDER THE AGREEMENT HAVE 
BEEN COMPLETED AS OF THE COMPLETION DATE LISTED HERE: 
FINAL ACCEPTANCE DATE: 
 
PRIME CONTRACTOR: 
FIRM NAME: 
 
PRINCIPAL: 
 
TITLE: 
 
SIGNATURE: 
 
DATE: 
 
CERTIFIED BY [INSERT NAME AND TITLE OF PARTY THAT OVERSEES CONSTRUCTION]: 
FIRM NAME: 
 
SIGNATURE: 
 
DATE: 
 
PROJECT ACCEPTED BY CITY OF CHANDLER: 
NAME: 
 
SIGNATURE: 
 
DATE:

7/20/2022
APP-22 of 33 
General Conditions 
Appendix 8
CONSTRUCTION SIGN DETAIL 
 
8' 
 
 
 
  3"  
 
 
 
 
CITY OF CHANDLER 
  5"   
 
 
  3"   
 
 
PUTTING YOUR FUNDS TO WORK 
  5"   
 
 
  3"   
 
 
PROJECT TITLE: 
  5"   
 
4' 
 
 
  3"   
 
 
PROJECT NUMBER: 
  3"   
 
 
 
  2"   
 
 
PROJECT COST: 
  3"   
 
 
 
  2"   
 
 
CONTRACTOR: 
  3"   
 
 
 
  2"   
 
 
MANAGED BY: 
PUBLIC WORKS & UTILITIES DEPARTMENT 
  3"   
 
 
 
CAPITAL PROJECTS DIVISION 
  3"   
 
 
 
 
 
                             <--- 4" X 4" POSTS --->
NOTES: 
SIGN(S) MUST BE FURNISHED AND ERECTED PRIOR TO COMMENCEMENT OF CONSTRUCTION.  POSTS 
MUST BE ANCHORED A MINIMUM OF TWO FEET INTO THE GROUND. BOTTOM OF SIGN MUST BE A 
MINIMUM OF FOUR FEET ABOVE THE GROUND. 
TYPICAL PROJECT IDENTIFICATION SIGN FOR GENERAL PROJECTS MUST BE NON-REFLECTORIZED GREEN 
BACKGROUND, AND NON-REFLECTORIZED WHITE LETTERS AND NUMERALS. 
ONE SIGN MUST BE ERECTED FOR BUILDINGS AND OTHER LIMITED AREA SINGLE SITES.  FOR MULTIPLE 
SITES, ONE SIGN MUST BE ERECTED AT EACH SITE. 
FOR LINEAR PROJECTS ONE HALF MILE OR LONGER, PLACE ONE SIGN AT EACH END OF THE PROJECT.

7/20/2022
APP-23 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
COST OF THE WORK 
(APPLICABLE SOLELY TO CONSTRUCTION MANAGER AT RISK AND JOB ORDER CONTRACTING) 
SECTION 1  COSTS TO BE REIMBURSED 
1.1 Cost of the Work 
The term Cost of the Work will mean costs necessarily incurred by Contractor in the proper 
performance of the Work. Such costs must be at rates not higher than the standard paid at the place 
of the Project except with prior consent of City. The Cost of the Work will include only the items set 
forth in this Section 1. 
1.2 Labor Costs 
1.2.1 
Wages of construction workers directly employed by the Contractor to perform the 
construction of the Work at the site or, with 
 approval, at off-site workshops. Cost to 
be reimbursed will be the actual wages paid to the individuals performing the work. 
1.2.2 
Wages or salaries of the 
 supervisory and administrative personnel when 
stationed at 
the site with 
 approval. No Contractor personnel stationed at the 
 home or branch offices will be charged to the Cost of the Work. Non-field office 
based Contractor management and support personnel are expected to provide service and 
advice from time to time throughout the job and his/her time devoted to Project matters is 
considered to be covered by the 
 Fee. 
1.2.3 
Wages and salaries of 
 supervisory or administrative personnel who would 
normally be stationed at the field office in accordance with Section 1.2.2 but who become 
engaged, at factories, 
workshops or on the road, in expediting the production or 
transportation of materials or equipment required for the Work, but only for that portion of 
his/her time required for the Work. Employee 
bonuses and/or costs associated with 
Employee Stock Ownership Plans 
 will not be considered reimbursable labor or 
labor burden costs and will be considered non-reimbursable costs considered to be covered 
by the 
 Fee. 
1.2.4 
Costs paid or incurred by Contractor for taxes, insurance, contributions, assessments and 
benefits required by law or collective bargaining agreements and, for personnel not 
covered by such agreements, customary benefits such as sick leave, medical and health 
benefits, holiday, vacations and pensions, provided such costs are based on wages and 
salaries included in the Cost of the Work under Subparagraphs 1.2.1 through 1.2.3. 
1.2.4.1 Cost of the Work will include the actual net cost to Contractor for 
 compensation 
insurance attributable to the wages chargeable to the Cost of Work per this Agreement. The 
actual 
net cost of 
 compensation must take into consideration all cost 
adjustments due 
to 
experience modifiers, premium discounts, policy dividends, 
retrospective rating plan premium adjustments, assigned risk pool rebates, any applicable 
weekly maximums, etc. Contractor may 
charge an estimated amount for 
 
compensation insurance costs, but will make appropriate cost adjustments to actual costs 
within 45 days of receipt of actual cost adjustments from the insurance carrier.

7/20/2022
APP-24 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
1.2.4.3 Overtime wages paid to salaried personnel (if approved in advance in writing by City) will 
be reimbursed at the actual rate of overtime pay paid to the individual. No time charges for 
overtime hours worked on the Project will be allowed if the individual is not paid for the 
overtime worked. 
1.2.4.4 Any overtime premium or shift differential expense to be incurred by Contractor for hourly 
workers will require 
 advance written approval before the incremental cost of the 
overtime premium or shift differential will be considered a reimbursable cost. If the 
Contractor is required to work overtime as a result of an inexcusable delay or other 
coordination problems caused by the Contractor or anyone he/she is responsible for, 
the overtime premium and/or shift differential expense portion of the payroll expense and 
related labor burden costs will be considered as cost not to be reimbursed. 
1.2.4.5 Reimbursable labor burden costs will be limited to payroll taxes, 
 compensation 
insurance, the 
 of union benefit costs for union employees working on the 
Project, and the actual verifiable fringe benefit costs incurred by Contractor for non-union 
individuals working on the Project subject to the following maximum percentages for the 
following reimbursable non-union fringe benefit costs. The following maximums (as a 
percentage of reimbursable actual wages by individual) will apply for each of the following 
types of fringe benefit costs specifically attributable to each of the non-union personnel 
working on the Project: 
 
Medical Insurance, Dental, Life & AD&D Insurance:
12.00%
 
Holiday, vacation and other paid time not worked:
10.00%
 Pension Plan Contributions to Vested Employee Account,
Simplified Employee Pension Plans, or 401K matching plans 
(Note: ESOP related costs are covered by the Contractor Fee) 
 
 
10.00%
For non-union personnel, no other fringe benefit costs (other than the three specific 
categories listed immediately above, will be considered reimbursable Cost of Work. Any labor 
burden costs that are in excess of the amounts considered reimbursable or are otherwise 
not considered reimbursable under the terms of this agreement are intended to be covered 
by the Contractor Fee. 
1.3 
Subcontract Costs 
1.3.1 
Payments made by Contractor to Subcontractors in accordance with the requirements of 
the subcontracts. 
1.3.2 
For Scope of Work Bid Packages typically performed by Subcontractors, Contractor may 
- 
 such work on an actual cost basis subject to an agreed upon Guaranteed 
Maximum Price for the 
-performed 
 The Contractor must, unless agreed to by City 
in writing, bid his/her proposed guaranteed Maximum Price for the work to be 
-
 against at least three other interested trade Contractors. All savings under any 
such Subcontract for 
-performed 
 must be applied to reduce the Cost of Work under 
the Agreement and the Guaranteed Maximum Price. For purposes of defining 
-
performed 
 subject to this provision, any division of Contractor, or any separate 
Contractor or Subcontractor that is partially owned or wholly owned by the Contractor or any 
of his/her employees or 
 relatives will be considered a related party entity and 
will be subject to this provision regarding 
-performed 
 No self-performed work will

7/20/2022
APP-25 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
be allowed to be performed on a Fixed Price basis. 
1.3.3 
Contractor (with respect to its Suppliers, Subcontractors and all lower tier Subcontractors) 
must provide City advance written notice and must obtain 
 approval for any proposed 
Subcontract Change Order, Material Purchase Order, or other financial commitment in an 
amount in excess of $5,000 prior to placing such order or entering into such agreement 
(regardless of whether or not any such commitment will affect the prime Agreement 
Guaranteed Maximum Cost). It is agreed that sums applicable to any Subcontract Change 
Order, Purchase Order or other financial commitment entered into in violation of the above 
notice and approval requirement will not be included in the amounts owning to Contractor, 
Subcontractors or Suppliers whether as Costs of the Work or as reasonable termination costs 
in the event of termination. 
1.4 
Costs of Material and Equipment Incorporated in the Completed Construction 
1.4.1 
Costs, including transportation and storage, of materials and equipment incorporated or 
to be incorporated in the completed construction. 
1.4.2 
Costs of materials described in the preceding Subparagraph 1.4.1 in excess of those 
actually installed to allow for reasonable waste and spoilage. Unused excess materials, in 
any, will become 
 property at the completion of the Work or, at 
 option, may be 
sold by the Contractor. Any amounts realized from such sales must be credited to City as a 
deduction from the Cost of Work. 
1.4.3 
Proceeds from the sale of recyclable materials, scrap, waste, etc. will be credited to job cost. 
1.5 
Costs of Other materials and Equipment, Temporary Facilities and Related Items 
1.5.1 
Costs, including transportation and storage, installation, maintenance, dismantling and 
removal of materials, supplies, temporary facilities, machinery, equipment and hand tools 
not customarily owned by construction workers, that are provided by the Contractor at the 
site and fully consumed in the performance of the Work; and cost (less salvage value) of such 
items if not fully consumed, whether sold to others or retained by Contractor. Cost for items 
previously used by Contractor will mean fair market value. 
1.5.2 
Rental charges for temporary facilities, machinery, equipment, and hand tools not 
customarily owned by construction workers that are provided by Contractor at the site, 
whether rented from Contractor or others, and costs of transportation, installation, minor 
repairs and replacements, 
dismantling and removal thereof. Rates and quantities of 
equipment rented will be subject to 
 prior written approval. 
1.5.2.1 The Projected usage for each piece of equipment to be rented for use on the Project and 
the estimated total rentals must be considered by Contractor before the piece of equipment 
is rented so that an appropriate rent versus buy decision can be made. Purchased 
equipment must be considered 
 
 At the completion of the Project, Contractor 
must transfer title and possession of all remaining job-owned equipment to City, or 
Contractor may keep any such equipment for an appropriate fair market value credit to job 
cost, which will be mutually agreed to by City and Contractor. 
1.5.2.2 Each piece of equipment to be rented must have hourly, daily, weekly and monthly rates and

7/20/2022
APP-26 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
the most economical rate available will be reimbursed based on the circumstances of actual 
need and usage of the piece of equipment while it is stationed at the jobsite. When the 
piece of equipment is no longer needed for the work, no rental charges will be reimbursed 
if the piece of equipment remains at the jobsite for the convenience of Contractor. 
1.5.2.3 Equipment Rental Rates 
1.5.2.3.1 Compensation for equipment used on the Project will be paid in accordance with the 
Equipment Plan submitted by Contractor in the accepted GMP Proposal and no payments 
will be made in excess of the rates set forth in the Equipment Plan, or actual documented 
costs, whichever is less. 
 
1.5.2.3.2 All equipment rental rates and costs are subject to 
 right to audit when submitted as 
part of Equipment Plan and/or at any time during the Project. 
1.5.2.4 The aggregate rentals chargeable for each piece of Contractor owned tools or equipment must 
not exceed 50% of the fair market value of such equipment at the time of its commitment to 
the Work. The original purchase price and date of purchase of the equipment will be 
documented with a copy of the purchase invoice for the piece of equipment. Such aggregate 
limitations will apply and no further rentals will be charged even if a piece of equipment is taken 
off the job and is later replaced by a similar piece of equipment. For purposes of computing 
the aggregate rentals applicable to aggregate rental limitations, rental charges for similar 
pieces of equipment will be combined if the pieces of equipment were not used at the same 
time. 
1.5.2.5 Fair market value for used material and equipment as referred to in the Agreement 
Documents will mean the estimated price a reasonable purchaser would pay to purchase 
the used material or equipment at the time it was initially needed for the job. Note: This is 
usually lower than the price a reasonable purchaser would pay for similar new construction 
material or construction equipment. 
1.5.2.6 All losses resulting from lost, damaged or stolen tools and equipment will be the sole 
responsibility of Contractor, and not City, and the cost of such losses will not be reimbursable 
under the Agreement. 
1.5.2.7 Contractor will be required to maintain a detailed equipment inventory of all job-owned 
equipment (either purchased and charged to job cost or job-owned through aggregate 
rentals) and such inventory must be submitted to City each month. For each piece of 
equipment, such inventory should contain at a minimum (1) original purchase price or 
acquisition cost (2) acquisition date (3) approved Fair Market Value at the time the piece of 
equipment was first used on the job and (4) final disposition. 
1.5.2.8 All costs incurred for minor maintenance and repairs will be reimbursed at actual cost. Such 
costs include routine and preventative maintenance, minor repairs and other incidental costs. 
Repairs and/or replacement of a capital nature are considered to be covered by the rental 
rates. Major repairs and overhauls are not considered routine and ordinary; consequently 
such costs are not reimbursable and are intended to be covered by the rental rates. 
1.5.3 
Costs of removal of debris from the Site.

7/20/2022
APP-27 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
1.5.4 
Costs of document reproductions, facsimile transmissions and long-distance telephone 
calls, postage and parcel delivery charges, telephone service at the site and reasonable 
petty cash expenses of the site office. 
1.5.5 
That portion of the reasonable expenses of 
 personnel incurred while traveling 
in discharge of duties connected with the Work. 
1.5.5.1 No travel expenses will be reimbursed to 
 representatives unless Project related 
travel required them to travel to a destination more than 100 miles from the Project location. 
Any travel 
involving airfare will require advance written approval by an authorized 
 
representative. 
1.5.6 
Costs of materials and equipment suitably stored off the site at a mutually acceptable 
location, if approved in advance by the City. 
1.5.7 
Reproduction costs will be the actual costs of reproduction subject to a maximum of five 
cents ($.05) per square foot for prints and a maximum of five cents ($.05) per 8 ½ by 11-inch 
page for offset print or photo copied agreement documents, specifications, etc. Telephone 
costs will be the actual costs paid to the third party telephone company for the field office 
telephone. 
1.6 
Miscellaneous Costs 
1.6.1 
That portion of insurance and bond premiums that can be directly attributed to the Agreement. 
The City will reimburse Contractor for contractually required bond at time of first pay 
application for GMP and Cost-Based Agreements upon receipt of proof of payment from 
the Contractor. If the Contractor completes Work for less than the Agreement Price, 
Contractor must credit the City a pro- rated amount for the unused portion of the bond 
payment 
1.6.1.1 
 actual cost for insurance will be considered to be included within the Maximum 
limit for General Conditions Costs. All premiums for any insurance and bonds required for 
the Project must reflect the net actual costs to Contractor after taking into consideration cost 
adjustments due to experience modifiers, premium discounts, policy dividends, retrospective 
rating plan premium adjustments, assigned risk pool rebates, refunds, etc. 
1.6.1.2 The amount to be reimbursed to Contractor for all contractually required insurance will be 
actual costs not to exceed a total of 2% of the Agreement Value, unless Contractor 
establishes to 
 satisfaction that the actual cost is higher and City agrees to such actual 
higher cost in writing. If 
 cost of contractually required insurance is greater 
than the amount agreed to be reimbursed per this Agreement Provision, the difference will 
be considered to be covered by the 
 Fee.  The City will reimburse Contractor 
for contractually required insurance on a monthly basis for GMP and Cost-Based 
Agreements. If Contractor can demonstrate substantial savings by paying for all insurance in 
advance, the City may agree to reimburse all insurance costs at time of first pay application 
for GMP and Cost-Based Agreements with proof of payment from Contractor. 
1.6.2 
Sales, use or similar taxes imposed by a governmental authority that are related to the Work.

7/20/2022
APP-28 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
1.6.3 
Fees and assessments for the building permit and for other permits, licenses and inspections 
for which Contractor is required by the Agreement Documents to pay. 
1.6.4 
Fees of laboratories for tests required by the Agreement Documents, except those related to 
defective or nonconforming Work and which do not fall within the scope of ¶ 1.7.3 below. 
1.6.5 
Royalties and license fees paid for the use of a particular design, process or product required 
by the Agreement Documents; the cost of defending suites or claims for infringement of 
patent rights arising from such requirement of the Agreement Documents; and payments 
made in accordance with legal judgments against Contractor resulting from such suites or 
claims and payments of settlements made with 
defenses, judgments and settlements must not be included in the calculation of the 
 
1.6.6 
Data processing costs related to the Work. However, any such data processing costs will be 
limited to the cost of personal computer hardware used at the field office in the normal 
day to day administration, management and control of the Project. The aggregate charges 
for any such hardware must not exceed the Fair Market Value of the hardware at the time it 
was brought to the field office. If the total charges for any particular piece of hardware reach 
an amount equal to the Fair Market Value, that particular piece of hardware must be turned 
over to City whenever it is no longer needed for the Project. If Contractor elects to keep the 
particular piece of hardware, the job costs must be credited with a mutually agreeable 
amount which will represent the Fair Market Value of the particular piece of hardware at the 
time it was no longer needed for the job. Software or other costs associated with the use of 
computer programs will not be considered to be a reimbursable cost and will be considered 
to be covered by the 
 Fee. 
1.6.7 
Deposits lost for causes other than 
 negligence or failure to fulfill a specific 
responsibility to City as set forth in the Agreement Documents. 
1.6.8 
Legal, mediation and arbitration costs, including 
 fees, other than those arising 
from 
disputes between City and Contractor, reasonably incurred by Contractor in the 
performance of the Work and with 
 prior written approval; which approval will not be 
unreasonably withheld. 
1.6.9 
Expenses incurred in accordance with 
 standard personnel policy for relocation 
and temporary living allowances of personnel required for the Work, if pre-approved by City 
in writing. 
If City authorizes the reimbursement of relocation costs, the reimbursable 
relocation expenses will be limited to a maximum of $50,000 per person. Any relocation 
cost incurred by Contractor in excess of the amount reimbursed by City will be considered to 
be covered by the 
 Fee. 
1.7 
Other Costs and Emergencies 
1.7.1 
Other costs incurred in the performance of the Work if and to the extent approved in advance 
in writing by City. 
1.7.2 
Costs due to emergencies incurred in taking action to prevent threatened damage, injury or

7/20/2022
APP-29 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
loss in case of an emergency affecting the safety of persons and property. 
1.7.3 
Costs of repairing or correcting damaged or nonconforming Work executed by Contractor, 
Subcontractors or Suppliers, provided that such damaged or nonconforming Work was not 
caused by negligence or failure to fulfill a specific responsibility of Contractor and only to the 
extent that the cost of repair or correction is not recoverable by Contractor from insurance, 
sureties, Subcontractors or Suppliers. 
1.8 
Related Party Transactions 
1.8.1 
The term 
 
 will mean a parent, subsidiary, affiliate or other entity having 
common ownership or management with Contractor; any entity in which any stockholder in, 
or management employee of, Contractor owns any interest in excess of ten percent in the 
aggregate; or any person or entity which has the right to control the business or affairs of 
Contractor. The term 
 
 includes any member of the immediate family of any 
person identified above. 
1.8.2 
If any of the costs to be reimbursed arise from a transaction between Contractor and a 
related party, Contractor must notify City in writing of the specific nature of the contemplated 
transaction, including the identity of the related party and the anticipated cost to be incurred, 
before any such transaction is consummated or cost incurred. If City, after such notification, 
authorizes in writing the proposed transaction, then the cost incurred will be included as a 
cost to be reimbursed, and Contractor must procure the Work, equipment, goods or service 
from the related party, as a Subcontractor. If City fails to authorize the transaction, 
Contractor must procure the Work, equipment, goods or service from some person or entity 
other than a related party. 
SECTION 2  COSTS NOT TO BE REIMBURSED 
2.1 
The Cost of Work must not include: 
2.1.1 
Salaries and other compensation of 
 personnel stationed at 
 principal 
office or offices other than the site office, except as specifically provided in Subparagraphs 
1.2.2 and 1.2.3. 
2.1.2 
Expenses of 
 principal office and offices other than the site office. 
2.1.3 
Overhead and general expenses, except as may be expressly included in Section 1. 
2.1.3.1 Costs of 
 home office computer services or other outside computer processing 
services will be considered overhead and general expense. Accordingly, Contractor should 
not plan to perform any such computer related services or alternatives at the field office when 
such services or functions can be performed at 
 home or branch offices, or 
other outside service locations. 
2.1.4 
 capital expenses, including interest on 
 capital employed for the Work. 
2.1.5 
Rental costs of machinery and equipment, except as specifically provided in subparagraph 
1.5.2.

7/20/2022
APP-30 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
2.1.6 
Except as provided in Subparagraph 1.7.3 of the Agreement, costs due to the negligence or 
failure to fulfill a specific responsibility of Contractor, Subcontractors and Suppliers or anyone 
directly or indirectly employed by any of them or for whose acts of them may be liable. 
2.1.7 
Any cost not specifically and expressly described in Section 1. 
2.1.8 
Costs, other than costs included in Change Orders approved by City that would cause the GMP 
to be exceeded. 
SECTION 3  DISCOUNTS, REBATES, REFUNDS AND SAVINGS 
3.1 
Cash discounts obtained on payments made by Contractor will accrue to City if (1) before 
making the payment, Contractor included them in an Application for Payment and 
received payment therefore from City, or (2) City has deposited funds with Contractor with 
which to make payments; otherwise, cash discounts will accrue to Contractor. Trade discounts, 
rebates, refunds and amounts received from sales or surplus materials and equipment will 
accrue to City, and Contractor must make provisions so that they can be secured. 
3.1.1 
Cost of the Work will be credited with all insurance policy discounts, performance and 
payment bond rebates or refunds, refunds or return premiums from any Subcontractor 
default insurance, refunds or rebates from any Contractor controlled insurance programs 
applicable to the Project, 
merchandise rebates of any nature, refunds of any nature, 
insurance dividends; and a portion of any volume rebates or free material credits earned with 
purchase of material or other goods and services charged to the job. 
3.1.2 
 discounts which may accrue to Contractor will be limited to a maximum of 1.5% of 
invoice cost. Any portion of 
 discounts greater than 1.5% will automatically accrue 
to City if Contractor is eligible to take advantage of the discounts. 
3.2 
Amounts that accrue to City in accordance with the provisions of Paragraph 3.1 will be 
credited to City as a deduction from the Cost of the Work. 
3.3 
Any and all savings on the GMP, or any separately guaranteed items comprising the GMP, will 
belong to City, subject to any express right in the Agreement for Contractor to share in 
savings. Savings are subject to 
 right to audit, and may be audited separately. 
SECTION 4  GENERAL CONDITIONS COSTS 
4.1 
General Conditions Costs may include, but are not limited to, the following types of costs 
incurred by Contractor during construction of the Work to the extent they are reimbursable 
Costs of the Work as delineated above: payroll costs for Work conducted at the site, payroll 
costs for the superintendent and full-time general foremen, payroll costs for management 
personnel resident and working on the site workers not included as direct labor costs 
engaged in support (e.g. loading/unloading, clean-up, etc.), administrative office personnel, 
costs of offices and temporary facilities including office materials, office supplies, office 
equipment, minor expenses, utilities, fuel, sanitary facilities and telephone services at the 
site, costs of liability insurance premiums not included in labor burdens for direct labor

7/20/2022
APP-31 of 33 
General Conditions 
Appendix 9  CM@Risk & JOC 
costs, costs of bond premiums, costs of consultants not in the direct employ of Contractor or 
Subcontractors, fees for permits and licenses. 
4.2 
General Conditions Costs may be paid on a percentage of the Agreement Price or on a 
lump/stipulate sum basis as set forth in the Agreement. All costs included in the General 
Conditions Costs will not be separately invoiced to or paid by City. 
4.3 
The total amount of General Conditions Costs for the Work may be divided by the number of 
days allowed for performance of the Work, to determine a fixed daily rate for General 
Conditions Costs that may be used in computing the General Conditions Costs allocated to any 
period of time, or for any adjustments in the General Conditions Costs agreed to in  
 
writing by City.

7/20/2022
APP-32 of 33 
General Conditions 
Appendix 10 
LANDSCAPE ESTABLISHMENT PERIOD 
Section 1  Description and General 
Contractor is in direct control of work performed under the Landscape Establishment Period. If work is 
subcontracted, a representative of the Contractor will be present at the site of the work for all hours 
that the subcontractor works. Subcontracting of Landscape Establishment work will be permitted for 
weed eradication with herbicides, because of special licensing. A licensed temporary service may be 
used to supply labor to Contractor if Contractor has received approval from City Representatives.  
Contractor will submit the required subcontract documentation. 
 
Contractor must provide adequate personnel to accomplish the required maintenance of the plant 
materials at intervals acceptable to City Representatives. 
 
If not healthy at the end of the maintenance period, the maintenance must be continued until the plant 
material is approved by City. 
 
1.1 Time and Schedule 
Unless otherwise expressly agreed to in writing by City, the Landscape Establishment Period will be 
per General Conditions Section 6.5.4.   
 
1.2 Planted Stock and Seeding Establishment 
1.2.1 
Tree planting and staking must be per City of Chandler Standard Detail C-801.  
1.2.2 
All trees will stand erect on their own without stakes when brought to this site. If the tree 
cannot stand on its own when nursery stakes are removed, the tree will be removed and 
replaced. 
 
1.3 Pre-Emergent Herbicide and Weed Control 
1.3.1 
Contractor will provide three applications of an approved pre-emergent herbicide on all 
unpaved areas of the project, as directed by City Representatives, to control weed growth in 
all areas of the project. The number of applications may be increased as directed by the City 
Representative, and at no additional cost to City, if the City Representative deems additional 
applications are required to control weed growth. 
1.3.2 
Application sequence will be approved in advance by City. The first application of pre-
emergent will be completed prior to the application of Decomposed Granite and will be 
included with the cost of the Decomposed Granite as specified and part of the Construction 
Phase portion of work. The second application of pre-emergent will be completed after 
installation of the Decomposed Granit and no later than half-way through the Landscape 
Establishment Period. The third and final application of pre-emergent will be applied 15 days 
prior to completion of the Landscape Establishment portion of the project. The second and 
third pre-emergent applications will be included with the cost of Landscape Establishment. 
Watering will be completed in accordance with the manufa
included and as related to each application. 
1.3.3 
The pre-emergent herbicide will be applied in accordance with the Technical Specifications 
and the recommendations of the pre-emergent herbicide manufacturer, as approved by City 
Representatives.

7/20/2022
APP-33 of 33 
General Conditions 
Appendix 10 
1.3.4 
The control of weeds will be accomplished by the use of herbicides. Manual removal of weeds 
will be required, after herbicides have taken affect. 
1.3.5 
Contractor is responsible for the removal and disposal of all trash and debris that during the 
Landscape Establishment Period. Contractor will keep the project in a neat and orderly 
manner during the duration of the Landscape Establishment Period. 
 
1.4 Water 
The water used during Landscape Establishment to properly maintain the plant material will be 
furnished by City, at designated sources from within the project limits, at no charge to Contractor. 
Contractor will be responsible for all equipment, materials and labor necessary to load, transport and 
unload water for watering purposes. 
 
1.5 Plant Material Replacements 
The plant material replacement will be considered as included in the work for Landscape 
Establishment, and will be made at no charge to the City. 
1.5.1 
Shrub and Plant Replacement - During the second half of the Landscaping Establishment 
period, Contractor will provide, where required, plant replacements as follows: 
 
Original Size 
Replacement Size 
1 gallon 
5 gallon 
5 gallon 
15 gallon 
15 gallon 
24-inch box 
36-inch box 
48-inch box 
 
1.5.2 
Tree Replacement 
 During the second half of the Landscape Establishment Period, 
Contractor will provide plant material replacements for existing plants that die as follows: 
 
Existing Plant Material Sizes 
Replacement Size 
Trees: 
 
2-inch Caliper 
24-inch box 
4-inch Caliper 
36-inch box 
6-inch Caliper and greater 
54-inch box 
Shrubs: 
 
All Existing Shrubs 
15 gallon 
 
1.6 Measurement and Payment 
See Technical Specifications for Measurement Payment provisions.

EXHIBIT C
 
Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
 
C-1 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev. 10/23/23 
 
TECHNICAL SPECIFICATIONS

09/27/2024

09/27/2024

09/27/2024

09/27/2024

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers Inc.
September 2024
TS-i  
Technical Specifications
DIVISION III
FEDERAL TECHNICAL SPECIFICATIONS TABLE OF CONTENTS
DESCRIPTION
   PAGE
L-100
Electrical General Requirements ....................................................................................
L-100-1
L-108
Underground Power Cable for Airports..........................................................................
L-108-1
L-110 
Airport Underground 
L-110-1
L-115
Electrical Manholes and Junction Structures ................................................................
L-115-1
L-125
Installation of Airport Lighting Systems ........................................................................
L-125-1

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers Inc.
September 2024
TS-ii  
Technical Specifications
PAGE INTENTIONALLY LEFT BLANK

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-1   
Electrical General Requirements
Item L-100 Electrical General Requirements
DESCRIPTION
100-1.1
General.  This Item includes furnishing and installing all material, equipment and apparatus, 
and all labor, tools, services, and equipment required for the removal of portions of the airfield lighting 
system as shown on the drawings and as follows:
a. The demolition, removal and/or salvage of portions of the existing airfield lighting systems 
including cable, signs and sign bases, and edge lights.
b. Temporary Airfield lighting power systems to maintain operation of airfield lighting circuit.
Installation shall be in accordance with Specifications FAA-C-1217 and FAA-C-1391, or as noted on the 
plans.  Perform all work not included in the FAA Specifications in accordance with the National Electrical 
Code, applicable local and Airport standards, and regulations.
100-1.2
Demolition and salvage
a.
Removal and salvage of airfield electrical elements is included under this item shall include the 
intent, but not limited to the specific elements, of the following:
(1)
Remove and salvage existing base mounted taxiway edge lights. 
b.
Any fixtures damaged that are to remain in-place or identified as remove and salvage to Airport on 
c.
Demolition (removal and non-return to Owner or for re-installation) of other airfield electrical 
system elements shall include the intent, but not limited to the specific elements, of the following:
(1)
Power Cables; direct buried or in conduit.
d.
Demolition (removal and non-return) of other elements associated with the airfield electrical 
system may also be included under other Items of this project. Elements covered within this specification 
shall include the intent, but not be limited to the specific elements, of the following:
(1)
Underground conduits and duct banks, both concrete encased and direct earth buried.
(2)
Grading and backfill associated with removal of the foregoing elements shall be covered 
under P-
100-1.3
New construction grading and backfill.
Grading and backfill associated with the removal of existing items or construction of the new ducts and 
conduits shall be installed in accordance with P-
GTP 30.03, 
Concrete for Structures. There will be no separate measurement or payment for any backfill, compaction, 
restoration or materials for slurry or concrete encased conduits and duct banks but shall be considered 
incidental to the associated item being installed.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-2   
Electrical General Requirements
100-1.4
Related documents.  The General Provisions of the Contract, including General and 
Special Conditions, apply to work specified in this item.
a.
Conflicts between Drawing and Specifications (Contract Documents) and between Contract 
Documents and references within the Contract Documents: Drawings and specifications are 
complementary. Work called for by one is binding as if called for by both. Prospective Contractors shall, as 
part of their proposals, enumerate, identify and list conflicts they find to exist within the Contract 
Documents, and between these Documents and the rules, regulations, standards and codes of the authority 
having jurisdiction (Airport Authority, City, County) local Utility companies and local County or State 
governing bodies. No Allowance shall subsequently be made to the Contractor by reason of his/her failure 
to have brought said discrepancies to the attention of the Consultant during the bidding period or by reason 
b.
Execution of Contract is evidence that Contractor has examined all existing conditions, drawings 
and specifications related to work, and is informed to extent and character of work. Claims made during 
construction for labor and materials required due to di
inattention to this issue, which could have been clarified prior to bid had examination been made, will be 
denied.
100-1.5
Temporary lighting and circuits.
a.
Contractor shall coordinate with Airport Maintenance or Operations before the end of each 
work shift to verify that all airfield lighting circuits are operational.  Contractor shall provide all 
labor and material for this work, non-pay item (NPI).
b.
Contractor shall provide and maintain on site, sufficient equipment required to provide 
temporary lighting and circuit extensions. 
c.
Work associated with taxiway shall be performed during coordinated taxiway closures in 
segments, reconnected to remaining existing circuit segments and tested for operation prior to the 
end of each shift before re-opening taxiway if required to prevent the need for excessive temporary 
cabling.
100-1.6
Specifications and standards.  As a supplement to the installation requirements of this 
item, the following standard specifications and regulations of the issues in effect on the date of this 
solicitation are incorporated herein by reference and are made a part hereof for electrical work and 
installation and splicing of underground cables.
NEC National Electrical Code 
FAA-STD-019e 
Lightning Protection, Grounding, Bonding and Shielding Requirements for Facilities
FAA-C-1391c
Installation and Splicing of Underground Cables
Local Governing Bodies' Public Works Department, City of Chandler
Codes and Regulations Maricopa Association of Governments (MAG)

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-3   
Electrical General Requirements
American Association of State Highway and Transportation Officials (AASHTO)
(1)
AASHTO LTS-5 (2009: Errata 2009: Amendment 2010) Standard Specifications for 
Structural Supports for Highway Signs, Luminaries and Traffic Signals.
ASTM International (ASTM)
(1)
ASTM A123/A123M (2009) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings 
on Iron and Steel Products
(2)
ASTM A153/A153M (2009) Standard Specification for Zinc Coating (Hot-Dip) on Iron and 
Steel Hardware
(3)
ASTM A575 (1996; R 2007) Standard Specification for Steel Bars, Carbon, Merchant 
Quality, M-Grades
(4)
ASTM A576 (1900b; R 2006) Standard Specification for Steel Bars, Carbon, Hot-Wrought, 
Special Quality
Illuminating Engineering Society of North America (IESNA)
(1)
IESNA HB-9 (2000: Errata 2004: Errata 2005: Errata 2006) IES Lighting Handbook.
Institute of Electrical and Electronics Engineers (IEEE)
(1) IEEE 81 (1983) Guide for Measuring Earth Resistivity, Ground Impedance, and Earth 
Surface Potentials of a Ground System.
(2) IEEE C135.1 (1999) Standard for Zinc-Coated Steel Bolts and Nuts for Overhead Line 
Construction.
(3) IEEE C2 (2007; Errata 06-1; TIA 07-1: TIA 07-3, Errata 07-2; TIA 08-4; TIA 08-6; TIA 08-
7; TIA 08-8; TIA 08-9; TIA 08-10; TIA 08-11; TIA 09-12; TIA 09-13; TIA 09-14; Errata 09-
3; TIA 09-15; TIA 09-16; TIA 10-17) National Electrical Safety Code
(4) IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of Terms & Definitions
National Electrical Manufacturers Association (NEMA)
(1)
ANSI C136.3 (2005; R 2009) American National Standard for Roadway and Area Lighting 
Equipment Luminaire Attachments
National Fire Protection Association (NFPA)
(1)
NFPA 70 (2011; TIA 11-1; Errata 2011) National Electrical Code
ASHRAE/IESNA 90.1, 2004
American Welding Society (AWS)
Factory Mutual Institute Association (FM)
Lightning Protection Institute

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-4   
Electrical General Requirements
International Electrical Testing Association
Underwriters Laboratories (UL)
(1)
UL 467(2007) Grounding and Bonding Equipment
When required by law or regulations, the government agency having jurisdiction for inspections shall be 
given reasonable notice and opportunity to inspect the work. Any work that is enclosed or covered up before 
such inspection and test shall be uncovered 
Contractor shall restore the work to its original condition at his own expense.
100-1.7
Shop drawings and material lists.  Prior to the installation of any material and 
equipment and within 30 days of contract award, the Contractor shall submit to the Owner for approval 
electronic PDF copies of manufacturers' brochures containing complete dimensional and performance 
characteristics, wiring diagrams, installation, and operation instructions, etc., for the equipment listed in 
the individual L-Series specification Items. Each submittal shall be titled and include the corresponding 
specification section(s).
A materials list shall be submitted listing each specification paragraph number and stating whether the 
materials proposed are as specified or are substitutions. If the item is a substitute item, a complete submittal 
as described in the above paragraph shall be provided for that item.
Submittal data shall be presented in a clear, precise, and thorough manner. Original catalog sheets are 
preferred. Photocopies are acceptable provide they are as a good quality as the original. Clearly and boldly 
mark each copy to identify pertinent products or models applicable to this project. Indicate all optional 
equipment and delete non-pertinent data. Submittals for components of electrical equipment and systems 
shall identify the equipment for which they apply on each submittal sheet. Markings shall be boldly and 
clearly made with arrows or circles (highlighting is not acceptable). Contractor is solely responsible for 
delays in project accruing directly or indirectly from late submissions or resubmissions of submittals.
The data submitted shall be sufficient, in the opinion of the Engineer, to determine compliance with the 
The Engineer reserves the right to reject any and all equipment, materials or procedures, which, in the 
EQUIPMENT AND MATERIALS
100-2.1
Equipment.  Conduits, conduit fittings, conductors, connectors, boxes, and wiring devices 
shall meet requirements of Specification FAA-C-1217 and Item L-110.
100-2.2
Conduit, underground.  Conduits run underground are specified in Item L-110 of these 
specifications. Existing conduit will remain for reuse and installation of new cables as indicated in plans.
100-2.3
Conduit fittings.
Each conduit and nipple entrance to duct and other such electrical 
enclosures shall be fitted with double locknuts (one each side of metal penetrated) and insulating bushing.  
Bushings on 1-1/4 inch and larger conduits shall be insulated metallic, type OZ/Gedney Cat. No. IBC Series, 
or equal; bushings for 3/4 inch and 1 inch shall be plastic insulated T&B rated for 150 C, or equal.  All

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-5   
Electrical General Requirements
insulated bonding and grounding bushings of conduits for 2400 volts or higher voltages, for conduit going 
underground, and for conduits going into concrete slabs shall be OZ/Gedney Cat. No. IBC-xxL (fitted with 
grounding lug), or equal.  The bushings shall be connected to the grounding system within the terminating 
enclosure and not on the underground end.  The buried end of each conduit shall be fitted with a 
thermosetting, plastic-insulated, metallic bushing.  All openings where conduits enter junction boxes, other 
enclosures and shelters shall be sealed weather tight.  The conduit shall be capped, if left empty, or sealed 
with Ducseal, or equal, around the conductors for exterior conduits.
100-2.4
Concrete-encased duct.  Concrete-encased PVC duct shall be as specified in Item L-110.
100-2.5
Concrete duct markers.  Markers shall be as specified in Item L-110 and as detailed on 
drawings.
100-2.6
Concrete handholes.  Hand holes shall be as specified in Item L-115 and as detailed on 
drawings.
100-2.7
Light bases and transformer housing.  New light bases, transformer housings, 
junction cans and covers shall be as specified in AC 150/5345-42, Item L-115 and L-125 and as detailed on 
drawings. 
CONSTRUCTION METHODS
100-3.1
Existing utilities.  Prior to any excavation or trenching, Contractor shall provide utility 
locator or contact Blue Stake to locate any existing cables and utilities, which will be crossed by the trench. 
Where existing underground utilities are shown on plans to conflict with existing conduit removal and / or 
new conduit installation, Contractor shall pothole to verify the location and depth.  Ensure these utilities 
are permanently disconnected if they are going to be demolished.  The existing service lines shall be exposed 
by hand digging in those areas that will be crossed and shall be protected from any possible damage.  If any 
damage occurs, it shall be the Contractor's responsibility to immediately repair such damage with materials 
and methods approved by the Owner and in compliance with applicable codes and standards, at 
on the drawings.
100-3.2
Demolition. Airfield Lighting and Signage.
a. Removal of existing conductors associated with taxiway(s) that are required to remain 
active during daytime operations (or as required by Airport) shall be performed in segments during 
each shift or construction phase, immediately followed by installation of new cable or temporary 
airfield circuit jumpers, reconnection and testing prior to end of shift to maintain operation of 
lighting during hours when construction is not occurring.
b. Removal of cables associated with lighting or signage that is to remain operational during 
construction shall be coordinated with Airport. Existing cables may be removed from underground 
conduits and sleeved with PVC conduit, secured with sandbags to provide temporary power during 
construction as required for facilitating removal of existing and construction of new duct banks, 
light bases, sign foundations and hand holes / junction cans.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-6   
Electrical General Requirements
c.
Existing L-867 bases for taxiway that are to remain for reinstallation of new fixtures shall 
be provided with new hardware. Existing mounting bolt hardware will likely require penetrating 
oil application for removal. Contractor shall be prepared for task of removing existing hardware 
and broken bolts for installation of new hardware and fixtures on bases that are designated to 
remain.
(1) Coordinate with Airport / Operations for NOTAMs and Lockout / Tag-out of all circuits 
affected by construction.
(2) Remove indicated conduits, ducts and conductors from site and dispose of according to local 
regulations.
(3) Material and equipment not designated for re-installation, including signs, light fixtures and 
isolation transformers, shall be safely stored to protect from damage during construction then 
offered for salvage to the appropriate Airport personnel at the end of completion. Non-re-
usable material, including conduit, concrete hand holes / pull boxes, foundations, base cans 
and conductors, shall become the property of the Contractor and shall be removed from the 
site and disposed of according to Local Ordinance
d. Existing signage that is required to remain operational shall remain in place on existing 
foundation until installation of new sign is ready to be performed. Removal of existing mounting 
anchors for replacement with new shall also be included in demolition efforts.  
100-3.3
Conductors.    Installation of underground 5 kV series circuits and parallel circuit conductors 
are specified in Item L-108 of these specifications.
100-3.4
Grounding.  All metal support structures, and metal enclosures shall be grounded in 
accordance with the requirements of the latest edition of Specifications FAA-C-1217, FAA-C-1391, and FAA-
STD-019, as indicated in Item L-108 and as detailed on the drawings.
100-3.5
Ground rods.  Grounding rods shall be 3/4-inch diameter by 10 feet long copper-jacketed 
steel.  Grounding connections to ground rods where buried or encased shall be by the exothermic weld 
process, Cadweld or equal.  Extruded, drawn or stamped-type ground clamps will not be acceptable.  The 
resistance to ground shall not exceed 25 ohms.
100-3.6
Ground conductors.  Equipment grounding conductors shall be insulated copper, except 
where shown on the project drawings to be bare, and sized as shown on the project drawings; and all 
grounds will be shown in accordance with Article 250 of the National Electrical Code, with FAA-STD-019 
and Item L-108.  Attachment of wire to supports, boxes, etc., shall be accomplished using approved ground 
lug attached with a separate stainless-steel screw, lock washer and nut.  Screws used for support of the 
electrical enclosure shall not be used for connection of the ground wire.  Pipe straps shall not be used for 
ground purposes.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-7   
Electrical General Requirements
COLOR CODING OF GROUND CONDUCTORS
TYPE OF GROUND CONDUCTOR
COLOR OF INSULATION 
Grounding Electrode Conductor
Bare (solid)- No Insulation 
Counterpoise Conductor
Bare (solid) 
No Insulation
External Sign and Transformer 
Housing Ground Conductor
Bare 
No Insulation
Equipment Grounding Conductor
Green (safety)
The multi-ground system supplements but does not replace the equipment-grounding conductor required 
by the National Electrical Code. 
Each of these separate ground conductors is insulated in order to keep it distinct and not allow contact with 
any other conductor.
Electrical continuity of cable armor or shield shall be maintained.  Grounding of the cable armor or shield 
shall be required at all terminations and shall be accomplished by connecting a #6 AWG solid bare copper 
wire to the cable armor or shield by means of a compression-type ground clamp installed within the 
terminating enclosure.  Armor or shield ground wire shall be connected to the ground electrode conductor 
using split bolt connector, Burndy or equal.  Grounding of direct earth burial (DEB) armored power and 
shielding control cable shall be at each end in accordance with FAA-C-1391.
100-3.7
Identification.  Conductors shall be identified as per FAA-C-1217, Section 5.2.5.2.2. Cable 
tagging and circuit identification markers shall be identified as per FAA-C-1391, Sections 5.12.1 and 5.12.2.  
Transformers, panelboards, constant current regulators, splice cabinets, enclosures and other vault 
equipment shall be identified by nameplate of nonferrous metal or rigid plastic, engraved with 3/8-inch 
high lettering with information as per FAA-C-1217, Section 5.11.
100-3.8
Contractor testing and submittals.  Equipment and materials list and shop drawings 
shall be submitted as per FAA-C-1391, Section 3.2.  Testing shall be required and performed as per FAA-C-
1217, Section 4.8, and FAA-C-1391, Section 3.3.5. The Contractor shall pretest all cable on the reel prior to 
installation and provide a copy of the test results to the Owner. The Contractor shall be responsible for 
repairs or replacement of any cable found defective after installation.
The Contractor shall test existing affected circuits prior to start of construction and the installed airfield 
lighting and miscellaneous power cables at the completion of this project. The results of the testing shall be 
provided to the Owner for review and acceptance. The Contractor shall be responsible for repairs or 
replacement of any cable found defective after installation.  
Installation tests in addition to all tests contained in other L-Series Items shall be provided as follows:

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-8   
Electrical General Requirements
Item
Test Required
Manufac-
turer's Rep. 
Present?
5 kV Rated Airfield Lighting and 
Power Cables (On the Reel, Not 
Including 
Equipment 
for 
Contractor 
Quality 
Control. 
Maybe deleted per-coordination 
with Engineer).
Megger check at 500 to 1000 Volts prior to 
installation.  Values of insulation resistance for each 
reel shall be noted and given to the Construction 
Manager/ Owner for acceptance.  It is expected that 
the readings will be greater than 1000 meg-ohms 
(1 gig-ohm).
No
5 kV Rated Airfield Lighting and 
Power 
Cables 
(All 
Circuits 
Installed in This Project)
Megger check at 500 to 1000 volts at the completion 
of installation.  Test every circuit for conductor-to-
ground 
and 
conductor-to-conductor 
(between 
circuits) insulation resistance.  Test results shall be 
tabulated 
and 
given 
to 
the 
Construction 
Manager/Owner for acceptance.  It is required that 
the readings be greater than 100 meg-ohms.
No
5 kV Rated Airfield Lighting and 
Power 
Cables 
(All 
Circuits 
Installed in This Project)
Megger check at 500 to 1000 volts at the completion 
of installation.  Test every circuit for conductor-to-
ground 
and 
conductor-to-conductor 
(between 
circuits) insulation resistance.  Test results shall be 
tabulated 
and 
given 
to 
the 
Construction 
Manager/Owner for acceptance.
No
5 kV and 600 Volt and Multi-pair 
Cables
If a power cable puller is used, continuous-tape pull 
tension readings for each section of cable shall be 
provided to the Construction Manager or Owner for 
review.
No
100-3.9
Notification of testing.  The Contractor shall notify the project RE and the Airport, a 
minimum of 48 hours in advance of system, or partial system, testing including, but not limited to, installed 
cable insulation resistance (megger) testing, and operational testing of any modified lighting circuit.
METHOD OF MEASUREMENT
100-4.1 Remove and salvage elevated taxiway edge light and isolation transformer, 
remove base can. The quantity to be measured shall be for the removal of existing incandescent, quartz 
elevated taxiway edge lights, fixture mounting base plates and isolation transformers for storing and 
protecting safely during construction until reinstallation or return to Airport. This shall also include 
complete removal and disposal off site of existing concrete encased base cans, fixtures or transformers that 
Airport does not require returned in accordance with the Plans and Specifications and as accepted. 
100-4.2
Remove and salvage taxiway edge light and isolation transformer, existing 
base can to remain.  The quantity to be measured shall be for the removal and safe storage of existing 
runway edge lights to protect from damage within the area of construction. It shall also include protection 
of designated existing edge lighting fixture bases, in place, per the Plans and Specifications and as accepted.
100-4.3
Remove existing conductor, conduit to remain. This item shall consist of removal 
and disposal off site of existing airfield and apron lighting cable from within existing underground conduits

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-9   
Electrical General Requirements
in accordance with the Plans and Specifications and as accepted. Cable removal is quantified as an effort to 
remove any number of conductors from within each conduit in a single run or each duct bank conduit. No 
separate measurement will be made for multiple conductors located in each conduit. No separate 
measurement will be made for slack.
100-4.4 Excavate and remove existing conduit and conductor. This item shall consist of 
complete removal and disposal off site of airfield lighting cable and complete removal of existing 
underground conduits in accordance with the Plans and Specifications and as accepted. No separate 
measurement will be made for multiple conduits in an existing duct bank. No separate measurement will 
be made for removal of existing airfield cable within conduits designated for removal. This shall also include 
backfill, compaction and restoration of disturbed area as required. 
100-4.5
Remove existing lighted airfield guidance sign and isolation transformer, 
demo sign base. The quantity to be measured shall be for the removal of existing airfield guidance sign 
and isolation transformer from concrete foundation, excavation for complete removal and disposal from 
site of concrete sign foundation including backfill, compaction and restoration of disturbed area as 
required. It shall also include the safe storage of existing signs to protect until they are returned to Airport 
or disposed of, as required.
100-4.6
Remove existing lighted airfield guidance sign and isolation transformer, 
sign base to remain. The quantity to be measured shall be for the removal of existing airfield guidance 
sign and isolation transformer from concrete foundation, as required. It shall also include the safe storage 
of existing signs to protect until they are returned to Airport or disposed of, as required.
BASIS OF PAYMENT
100-5.1
Electrical services.  Payment will be made at the contract price for the electrical services 
completed and accepted. This price shall be full compensation for furnishing all materials and for all labor, 
equipment, tools, and incidentals necessary to complete these items.   The unit price of each of these items 
Payment will be made under:
No. 20, Spec No. L-100-5.1
Remove and Salvage Existing Taxiway Edge Light and Isolation 
Transformer Demolish Base Can 
per Each
No. 21, Spec No. L-100-5.2
Remove and Salvage Existing Taxiway Edge Light and Isolation 
Transformer and Return to Owner - Base Can to Remain 
per 
Each
No. 22, Spec No. L-100-5.3
Remove Existing Conductors Back to Next Adjacent Light fixture 
or Hand Hole, Conduit to Remain
per Linear Foot
No. 23, Spec No. L-100-5.4
Excavate and Remove Existing Conduit and Conductors
per 
Linear Foot
No. 24, Spec No. L-100-5.5
Remove and Salvage Existing Airfield Guidance Sign and Return 
to Owner - Remove Concrete Sign Base
per Each

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-100-10   
Electrical General Requirements
No. 25, Spec No. L-100-5.6
Remove and Salvage Existing Airfield Guidance Sign and Isolation 
Transformer and Return to Owner, Sign Base to Remain
per 
Each
END OF ITEM L-100

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-1   
Underground Power Cable for Airports
Item L-108 Underground Power Cable for Airports
DESCRIPTION
108-1.1 This item shall consist of furnishing and installing power cables that are direct buried and 
furnishing and/or installing power cables within conduit or duct banks per these specifications at the 
locations shown on the plans. It includes excavation and backfill of trench for direct-buried cables only. 
Also included are the installation of counterpoise wires, ground wires, ground rods and connections, cable 
splicing, cable marking, cable testing, and all incidentals necessary to place the cable in operating condition 
as a completed unit to the satisfaction of the RPR. This item shall not include the installation of duct banks 
or conduit, trenching and backfilling for duct banks or conduit, or furnishing or installation of cable for 
FAA owned/operated facilities.
EQUIPMENT AND MATERIALS
108-2.1 General.  
a.
Airport lighting equipment and materials covered by advisory circulars (AC) shall 
be approved under the Airport Lighting Equipment Certification Program per AC 150/5345-53, 
current version.
b.
All other equipment and materials covered by other referenced specifications shall 
applicable 
specification, when requested by the RPR.
c.
to provide materials per these specifications. Materials supplied and/or installed that do not 
comply with these specifications shall be removed (when directed by the RPR) and replaced with 
d.
All materials and equipment used to construct this item shall be submitted to the 
RPR for approval prior to ordering the equipment. Submittals consisting of marked catalog sheets 
or shop drawings shall be provided. Submittal data shall be presented in a clear, precise and 
thorough manner. Original catalog sheets are preferred. Photocopies are acceptable provided they 
are as good a quality as the original. Clearly and boldly mark each copy to identify products or 
models applicable to this project. Indicate all optional equipment and delete any non-pertinent 
data. Submittals for components of electrical equipment and systems shall identify the equipment 
to which they apply on each submittal sheet. Markings shall be made bold and clear with arrows or 
circles (highlighting is not acceptable). The Contractor is solely responsible for delays in the project 
that may accrue directly or indirectly from late submissions or resubmissions of submittals.
e.
The data submitted shall be sufficient, in the opinion of the RPR, to determine 
submitted in pdf format. The RPR reserves the right to reject any and all equipment, materials, or 
procedures that do not meet the system design and the standards and codes, specified in this 
document.
f.
All equipment and materials furnished and installed under this section shall be 
guaranteed against defects in materials and workmanship for at least twelve (12) months from the 
date of final acceptance by the Owner. The defective materials and/or equipment shall be repaired 
maintain a minimum insulation resistance in accordance with paragraph 108-3.10e with isolation 
transformers connected in new circuits and new segments of existing circuits through the end of

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-2   
Underground Power Cable for Airports
the contract warranty period when tested in accordance with AC 150/5340-26, Maintenance 
Airport Visual Aid Facilities, paragraph 5.1.3.1, Insulation Resistance Test. 
108-2.2 Cable. Underground cable for airfield lighting facilities (runway and taxiway lights and signs) 
shall conform to the requirements of AC 150/5345-7, Specification for L-824 Underground Electrical Cable 
for Airport Lighting Circuits latest edition.  Conductors for use on 6.6 ampere primary airfield lighting series 
circuits shall be single conductor, seven strand, #8 American wire gauge (AWG), L-824 Type C, 5,000 volts, 
non-shielded, with cross-linked polyethylene insulation.  Conductors for use on 20 ampere primary airfield 
lighting series circuits shall be single conductor, seven strand, #6 AWG, L-824 Type C, 5,000 volts, non-
shielded, with cross-linked polyethylene insulation.  L-824 conductors for use on the L-830 secondary of 
other conductors shall comply with FAA and National Electric Code (NEC) requirements. Conductor sizes 
noted above shall not apply to leads furnished by manufacturers on airfield lighting transformers and 
fixtures.
Wire for electrical circuits up to 600 volts shall comply with Specification L-824 and/or Commercial Item 
Description A-A-59544A and shall be type THWN-2, 75°C for installation in conduit and RHW-2, 75°C for 
direct burial installations. Conductors for parallel (voltage) circuits shall be type and size and installed in 
accordance with NFPA-70, National Electrical Code.
Unless noted otherwise, all 600-volt and less non-airfield lighting conductor sizes are based on a 75°C, 
THWN-2, 600-volt insulation, copper conductors, not more than three single insulated conductors, in 
raceway, in free air.  The conduit/duct sizes are based on the use of THWN-2, 600-volt insulated 
conductors.  The Contractor shall make the necessary increase in conduit/duct sizes for other types of wire 
insulation.  In no case shall the conduit/duct size be reduced.  The minimum power circuit wire size shall 
be #12 AWG.
Conductor sizes may have been adjusted due to voltage drop or other engineering considerations.  
Equipment provided by the Contractor shall be capable of accepting the quantity and sizes of conductors 
shown in the Contract Documents.  All conductors, pigtails, cable step-down adapters, cable step-up 
adapters, terminal blocks and splicing materials necessary to complete the cable termination/splice shall 
be considered incidental to the respective pay items provided.
Cable type, size, number of conductors, strand and service voltage shall be as specified in the Contract 
Document.
108-2.3 Bare copper wire (counterpoise, bare copper wire ground and ground rods).
Wire for counterpoise or ground installations for airfield lighting systems shall be No. 6 AWG bare solid 
copper wire for counterpoise and/or No. 6 AWG insulated stranded for grounding bond wire per ASTM B3 
and ASTM B8, and shall be bare copper wire.  For voltage powered circuits, the equipment grounding 
conductor shall comply with NEC Article 250.
Ground rods shall be copper-clad steel. The ground rods shall be of the length and diameter specified on 
the plans, but in no case be less than 10 feet long and 3/4 inch in diameter.
108-2.4 Cable connections. In-line connections or splices of underground primary cables shall be of 
the type called for on the plans, and shall be one of the types listed below. No separate payment will be made 
for cable connections.
a.
The cast splice. A cast splice, employing a plastic mold and using epoxy resin 
-B, or an approved 
equivalent, used for potting the splice is acceptable.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-3   
Underground Power Cable for Airports
b.
The field-attached plug-in splice. Field attached plug-in splices shall be installed 
as shown on the plans.  The Contractor shall determine the outside diameter of the cable to be 
spliced and furnish appropriately sized connector kits and/or adapters.  Tape or heat shrink tubing 
Connector Kits manufactured by Amerace, "Super Kit", Integro "Complete Kit", or approved equal 
is acceptable.
c.
The factory-molded plug-in splice. Specification for L-823 Connectors, Factory-
Molded to Individual Conductors, is acceptable.
d. The taped or heat-shrink splice. Taped splices employing field-applied rubber, or synthetic 
rubber tape covered with plastic tape is acceptable. The rubber tape should meet the requirements of ASTM 
D4388 and the plastic tape should comply with Military Specification MIL-I-24391 or Commercial Item 
Description A-A-55809. Heat shrinkable tubing shall be heavy-wall, self-sealing tubing rated for the voltage 
of the wire being spliced and suitable for direct-buried installations. The tubing shall be factory coated with 
a thermoplastic adhesive-sealant that will adhere to the insulation of the wire being spliced forming a 
moisture- and dirt-proof seal. Additionally, heat shrinkable tubing for multi-conductor cables, shielded 
cables, and armored cables shall be factory kits that are designed for the application. Heat shrinkable tubing 
and tubing kits shall be manufactured by Tyco Electronics/ Raychem Corporation, Energy Division, or 
approved equivalent.
In all the above cases, connections of cable conductors shall be made using crimp connectors using a 
crimping tool designed to make a complete crimp before the tool can be removed. All L-823/L-824 splices 
recommendations and listings.
All connections of counterpoise, grounding conductors and ground rods shall be made by the exothermic 
process or approved equivalent, except that a light base ground clamp connector shall be used for 
attachment to the light base. All exothermic connections
recommendations and listings.
108-2.5 Splicer qualifications. Every airfield lighting cable splicer shall be qualified in making 
airport cable splices and terminations on cables rated at or above 5,000 volts AC. The Contractor shall 
submit to the RPR proof of the qualifications of each proposed cable splicer for the airport cable type and 
voltage level to be worked on. Cable splicing/terminating personnel shall have a minimum of three (3) years 
continuous experience in terminating/splicing medium voltage cable.
108-2.6 Concrete. Concrete shall be proportioned, placed, and cured per GTP 30.03, Concrete for 
Structures.
108-2.7 Flowable backfill. Flowable material used to backfill trenches for power cable trenches shall 
conform to the requirements of Item P-153, Controlled Low Strength Material.
108-2.8 Cable identification tags. Cable identification tags shall be made from a non-corrosive 
material with the circuit identification stamped or etched onto the tag. The tags shall be of the type as 
detailed on the plans.
108-2.9 Tape. Electrical tapes shall be ScotchTM Electrical Tapes ScotchTM 88 (1-1/2-inch wide) and 
ScotchTM 130C® linerless rubber splicing tape (2-inch wide), as manufactured by the Minnesota Mining and 
Manufacturing Company (3MTM), or an approved equivalent.
108-2.10 Electrical coating. Electrical coating shall be Scotchkote
as manufactured by 3MTM, or 
an approved equivalent.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-4   
Underground Power Cable for Airports
108-2.11 Existing circuits. Whenever the scope of work requires connection to an existing circuit, 
performed per this item and prior to any activity that will affect the respective circuit. The Contractor shall 
record the results on forms acceptable to the RPR. When the work affecting the circuit is complete, the 
record the results on forms acceptable to the RPR. The second reading shall be equal to or greater than the 
first reading or the Contractor shall make the necessary repairs to the existing circuit to bring the second 
reading above the first reading. All repair costs including a complete replacement of the L-823 connectors, 
L-830 transformers and L-824 cable, if necessary, shall be borne by the Contractor. All test results shall be 
submitted in the Operation and Maintenance (O&M) Manual
108-2.12 Detectable warning tape. Plastic, detectable, American Public Works Association 
(APWA) Red (electrical power lines, cables, conduit and lighting cable) with continuous legend tape shall 
be polyethylene film with a metalized foil core and shall be 3-6 inches wide. Detectable tape is incidental to 
the respective bid item. Detectable warning tape for communication cables shall be orange.  Detectable 
warning tape color code shall comply with the APWA Uniform Color Code.
CONSTRUCTION METHODS
108-3.1 General. The Contractor shall install the specified cable at the approximate locations indicated 
on the plans. Unless otherwise shown on the plans, all cable required to cross under pavements expected to 
carry aircraft loads shall be installed in concrete encased duct banks. Cable shall be run without splices, 
from fixture to fixture.
Cable connections between lights will be permitted only at the light locations for connecting the 
underground cable to the primary leads of the individual isolation transformers. The Contractor shall be 
responsible for providing cable in continuous lengths for home runs or other long cable runs without 
connections unless otherwise authorized in writing by the RPR or shown on the plans.
In addition to connectors being installed at individual isolation transformers, L-823 cable connectors for 
maintenance and test points shall be installed at locations shown on the plans. Cable circuit identification 
markers shall be installed on both sides of the L-823 connectors installed and on both sides of slack loops 
where a future connector would be installed.
Provide not less than 3 feet of cable slack on each side of all connections, isolation transformers, light units, 
and at points where cable is connected to field equipment. Where provisions must be made for testing or 
for future above grade connections, provide enough slack to allow the cable to be extended at least one foot 
vertically above the top of the access structure. This requirement also applies where primary cable passes 
through empty light bases, junction boxes, and access structures to allow for future connections, or as 
designated by the RPR.
Primary airfield lighting cables installed shall have cable circuit identification markers attached on both 
sides of each L-823 connector and on each airport lighting cable entering or leaving cable access points, 
such as manholes, hand holes, pull boxes, junction boxes, etc. Markers shall be of sufficient length for 
imprinting the cable circuit identification legend on one line, using letters not less than 1/4 inch in size. The 
cable circuit identification shall match the circuits noted on the construction plans.
108-3.2 Installation in duct banks or conduits. This item includes the installation of the cable 
in duct banks or conduit per the following paragraphs. The maximum number and voltage ratings of cables 
installed in each single duct or conduit, and the current-carrying capacity of each cable shall be per the 
latest version of the National Electric Code, or the code of the local agency or authority having jurisdiction.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-5   
Underground Power Cable for Airports
The Contractor shall make no connections or splices of any kind in cables installed in conduits or duct 
banks.
Unless otherwise designated in the plans, where ducts are in tiers, use the lowest ducts to receive the cable 
first, with spare ducts left in the upper levels. Check duct routes prior to construction to obtain assurance 
that the shortest routes are selected and that any potential interference is avoided.
Duct banks or conduits shall be installed as a separate item per Item L-110, Airport Underground Electrical 
Duct Banks and Conduit. The Contractor shall run a mandrel through duct banks or conduit prior to 
installation of cable to ensure that the duct bank or conduit is open, continuous and clear of debris. The 
mandrel size shall be compatible with the conduit size. The Contractor shall swab out all conduits/ducts 
and clean light bases, manholes, etc., interiors immediately prior to pulling cable. Once cleaned and 
swabbed, the light bases and all accessible points of entry to the duct/conduit system shall be kept closed 
except when installing cables. Cleaning of ducts, light bases, manholes, etc., is incidental to the pay item of 
the item being cleaned. All raceway systems left open, after initial cleaning, for any reason shall be re-
project as clear and open. The Contractor shall notify the RPR of any blockage in the existing ducts. 
The cable shall be installed in a manner that prevents harmful stretching of the conductor, damage to the 
insulation, or damage to the outer protective covering. The ends of all cables shall be sealed with moisture-
seal tape providing moisture-tight mechanical protection with minimum bulk, or alternately, heat 
shrinkable tubing before pulling into the conduit and it shall be left sealed until connections are made. 
Where more than one cable is to be installed in a conduit, all cable shall be pulled in the conduit at the same 
time. The pulling of a cable through duct banks or conduits may be accomplished by hand winch or power 
winch with the use of cable grips or pulling eyes. Maximum pulling tensions shall not exceed the cable 
A non-hardening cable-pulling lubricant recommended for the type of 
cable being installed shall be used where required.
The Contractor shall submit the recommended pulling tension values to the RPR prior to any cable 
installation. If required by the RPR, pulling tension values for cable pulls shall be monitored by a 
dynamometer in the presence of the RPR. Cable pull tensions shall be recorded by the Contractor and 
reviewed by the RPR. Cables exceeding the maximum allowable pulling tension values shall be removed 
and replaced by the Contractor at the Con
weather, particular attention shall be paid to the man
heated storage of the cable and maintenance of an acceptable cable temperature during installation when 
Cable shall not be dragged across base can or manhole edges, pavement or earth. When cable must be coiled, 
lay cable out on a canvas tarp or use other appropriate means to prevent abrasion to the cable jacket.
108-3.3 Installation of direct-buried cable in trenches. [NOT USED] Unless otherwise 
specified, the Contractor shall not use a cable plow for installing the cable. Cable shall be unreeled uniformly 
in place alongside or in the trench and shall be carefully placed along the bottom of the trench. The cable 
shall not be unreeled and pulled into the trench from one end. Slack cable sufficient to provide strain relief 
shall be placed in the trench in a series of S curves. Sharp bends or kinks in the cable shall not be permitted.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-6   
Underground Power Cable for Airports
Where cables must cross over each other, a minimum of 3 inches vertical displacement shall be provided 
with the topmost cable depth at or below the minimum required depth below finished grade.
a. Trenching. Where turf is well established and the sod can be removed, it shall be carefully stripped 
and properly stored. Trenches for cables may be excavated manually or with mechanical trenching 
equipment. Walls of trenches shall be essentially vertical so that a minimum of surface is disturbed. Graders 
shall not be used to excavate the trench with their blades. The bottom surface of trenches shall be essentially 
smooth and free from coarse aggregate. Unless otherwise specified, cable trenches shall be excavated to a 
minimum depth of 18 inches (0.5 m) below finished grade per NEC Table 300.5, except as follows:
When off the airport or crossing under a roadway or driveway, the minimum depth shall be 36 
inches unless otherwise specified.
Minimum cable depth when crossing under a railroad track, shall be 42 inches unless otherwise 
specified.
The Contractor shall excavate all cable trenches to a width not less than 6 inches. Unless otherwise 
specified on the plans, all cables in the same location and running in the same general direction shall be 
installed in the same trench.
When rock is encountered, the rock shall be removed to a depth of at least 3 inches below the required 
cable depth and it shall be replaced with bedding material of earth or sand containing no mineral aggregate 
particles that would be retained on a 1/4-inch sieve. Flowable backfill material may alternatively be used. 
Duct bank or conduit markers temporarily removed for trench excavations shall be replaced as 
required.
Where existing active cables cross proposed installations, the Contractor shall ensure that these cables are 
adequately protected. Where crossings are unavoidable, no splices will be allowed in the existing cables, 
except as specified on the plans. Installation of new cable where such crossings must occur shall proceed as 
follows:
(1) Existing cables shall be located manually. Unearthed cables shall be inspected to assure 
absolutely no damage has occurred.
(2) Trenching, etc., in cable areas shall then proceed, with approval of the RPR, with care taken to 
minimize possible damage or disruption of existing cable, including careful backfilling in area of cable.
In the event that any previously identified cable is damaged during the course of construction, the 
Contractor shall be responsible for the complete repair or replacement.
b. Backfilling. After the cable has been installed, the trench shall be backfilled. The first layer of 
backfill in the trench shall encompass all cables; be 3 inches deep, loose measurement; and shall be either 
earth or sand containing no mineral aggregate particles that would be retained on a 1/4-inch sieve. This 
layer shall not be compacted. The second layer shall be 5 inches deep, loose measurement, and shall contain 
no particles that would be retained on a one-inch sieve. The remaining third and subsequent layers of 
backfill shall not exceed 8 inches of loose measurement and be excavated or imported material and shall 
not contain stone or aggregate larger than 4 inches maximum diameter.
The second and subsequent layers shall be thoroughly tamped and compacted to at least the density of 
the adjacent material. If the cable is to be installed in locations or areas where other compaction 
requirements are specified (under pavements, embankments, etc.) the backfill compaction shall be to a 
minimum of 100 percent of ASTM D1557 or backfilled with controlled low strength material (CLSM) in 
accordance with P-153 as indicated on plans.
Trenches shall not contain pools of water during backfilling operations. The trench shall be completely 
backfilled and tamped level with the adjacent surface, except that when turf is to be established over the 
trench, the backfilling shall be stopped at an appropriate depth consistent with the type of turfing operation

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-7   
Underground Power Cable for Airports
to be accommodated. A proper allowance for settlement shall also be provided. Any excess excavated 
material shall be removed and disposed of per the plans and specifications.
Underground electrical warning (caution) tape shall be installed in the trench above all direct-buried 
cable. Contractor shall submit a sample of the proposed warning tape for acceptance by the RPR. If not 
shown on the plans, the warning tape shall be located 6 inches above the direct-buried cable or the 
counterpoise wire if present. A 3-6-inch-wide polyethylene film detectable tape, with a metalized foil core, 
shall be installed above all direct buried cable or counterpoise. The tape shall be of the color and have a 
continuous legend as indicated on the plans. The tape shall be installed 8 inches minimum below finished 
grade.
c. Restoration. Following restoration of all trenching near airport movement surfaces, the 
Contractor shall visually inspect the area for foreign object debris (FOD) and remove any that is found.  
Where soil and sod has been removed, it shall be replaced as soon as possible after the backfilling is 
completed. All areas disturbed by work shall be restored to its original condition. The restoration shall 
include the sodding, top soiling, fertilizing, liming, seeding, sprigging, or mulching as shown on the plans. 
The Contractor shall be held responsible for maintaining all disturbed surfaces and replacements until final 
acceptance. When trenching is through paved areas, restoration shall be equal to existing conditions. If the 
cable is to be installed in locations or areas where other compaction requirements are specified (under 
pavements, embankments, etc.) the backfill compaction shall be to a minimum of 100 percent of ASTM 
D1557 or backfilled with controlled low strength material (CLSM) in accordance with P-153 as indicated in 
plans. Restoration shall be considered incidental to the pay item of which it is a component part.
108-3.4 Cable markers for direct-buried cable. The location of direct buried circuits shall be 
marked by a concrete slab marker, 2 feet square and 4-6-inch-thick, extending approximately one inch 
above the surface. Each cable run from a line of lights and signs to the equipment vault shall be marked at 
approximately every 200 feet along the cable run, with an additional marker at each change of direction of 
cable run. All other direct-buried cable shall be marked in the same manner. Cable markers shall be 
i
on each cable marking slab. The letters shall be approximately 4 inches high and 3 inches wide, with width 
of stroke 1/2 inch and 1/4 inch deep. Stencils shall be used for cable marker lettering; no hand lettering 
shall be permitted.
At the location of each underground cable connection/splice, except at lighting units, or isolation 
transformers, a concrete marker slab shall be installed to mark the location of the connection/splice. The 
h slab. The Contractor also shall impress additional 
circuit identification symbols on each slab as directed by the RPR. All cable markers and splice markers 
shall be painted international orange. Paint shall be specifically manufactured for uncured exterior 
concrete. After placement, all cable or splice markers shall be given one coat of high-visibility aviation 
orange paint as approved by the RPR. Furnishing and installation of cable markers is incidental to the 
respective cable pay item.
108-3.5 Splicing. Connections of the type shown on the plans shall be made by experienced personnel 
regularly engaged in this type of work and shall be made as follows:
a. Cast splices. These shall be made by using crimp connectors for jointing conductors. Molds shall 
satisfaction of the RPR.
b. Field-attached plug-in splices.
instructions. These splices shall be made by plugging directly into mating connectors. The joint where the 
connectors come together shall be finished by one of the following methods: (1) wrapped with at least one 
layer of rubber or synthetic rubber tape and one layer of plastic tape, one-half lapped, extending at least 1-
1/2 inches on each side of the joint (2) Covered with heat shrinkable tubing with integral sealant extending

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-8   
Underground Power Cable for Airports
at least 1-1/2 inches on each side of the joint or (3) On connector kits equipped with water seal flap; roll-
over water seal flap to sealing position on mating connector.
c. Factory-molded plug-in splices. These shall be made by plugging directly into mating 
connectors. The joint where the connectors come together shall be finished by one of the following methods: 
(1) Wrapped with at least one layer of rubber or synthetic rubber tape and one layer of plastic tape, one-half 
lapped, extending at least 1-1/2 inches on each side of the joint. (2)  Covered with heat shrinkable tubing 
with integral sealant extending at least 1-1/2 inches on each side of the joint. or (3) On connector kits so 
equipped with water seal flap; roll-over water seal flap to sealing position on mating connector.
d. Taped or heat-shrink splices. A taped splice shall be made in the following manner:
Bring the cables to their final position and cut so that the conductors will butt. Remove insulation and jacket 
allowing for bare conductor of proper length to fit compression sleeve connector with 1/4 inch of bare 
conductor on each side of the connector. Prior to splicing, the two ends of the cable insulation shall be 
penciled using a tool designed specifically for this purpose and for cable size and type. Do not use emery 
paper on splicing operation since it contains metallic particles. The copper conductors shall be thoroughly 
cleaned. Join the conductors by inserting them equidistant into the compression connection sleeve. Crimp 
conductors firmly in place with crimping tool that requires a complete crimp before tool can be removed. 
Test the crimped connection by pulling on the cable. Scrape the insulation to assure that the entire surface 
over which the tape will be applied (plus 3 inches on each end) is clean. After scraping, wipe the entire area 
with a clean lint-free cloth. Do not use solvents.
Apply high-voltage rubber tape one-half lapped over bare conductor. This tape should be tensioned as 
recommended by the manufacturer. Voids in the connector area may be eliminated by highly elongating 
the tape, stretching it just short of its breaking point. The manufacturer's recommendation for stretching 
tape during splicing shall be followed. Always attempt to exactly half-lap to produce a uniform buildup. 
Continue buildup to 1-1/2 times cable diameter over the body of the splice with ends tapered a distance of 
approximately one inch over the original jacket. Cover rubber tape with two layers of vinyl pressure-
sensitive tape one-half lapped. Do not use glyptol or lacquer over vinyl tape as they react as solvents to the 
tape. No further cable covering, or splice boxes are required.
not be permitted unless recommended by the manufacturer. Cable surfaces within the limits of the heat-
shrink application shall be clean and free of contaminates prior to application.
e. Assembly. Surfaces of equipment or conductors being terminated or connected shall be prepared 
connected shall be thoroughly cleaned to remove all dirt, grease, oxides, nonconductive films, or other 
foreign material.  Paints and other nonconductive coatings shall be removed to expose base metal.  Clean 
all surfaces at least 1/4 inch beyond all sides of the larger bonded area on all mating surfaces.  Use a joint 
compound suitable for the materials used in the connection.  Repair painted/coated surface to original 
condition after completing the connection. 
108-3.6 Bare counterpoise wire installation for lightning protection and grounding.
If shown on the plans or included in the job specifications, bare solid #6 AWG copper counterpoise wire 
shall be installed for lightning protection of the underground cables. The RPR shall select one of two 
methods of lightning protection for the airfield lighting circuit based upon sound engineering practice and 
lightning strike density.
a. Equipotential.
may be used by the RPR for areas that have high rates of lightning strikes.  The 
counterpoise size is determined by the RPR.  The equipotential method is applicable to all airfield lighting 
systems, i.e. runway, taxiway, apron 
touchdown zone, centerline, edge, threshold, and approach lighting 
systems.  The equipotential method is also successfully applied to provide lightning protection for power,

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-9   
Underground Power Cable for Airports
signal, and communication systems. The light bases, counterpoise, etc. 
all components - are bonded 
together and bonded to the vault power system ground loop/electrode. 
Counterpoise wire shall be installed in the same trench for the entire length of buried cable, conduits 
and duct banks that are installed to contain airfield cables.  The counterpoise is centered over the 
cable/conduit/duct to be protected.
The counterpoise conductor shall be installed no less than 8 inches minimum or 12 inches maximum 
above the raceway or cable to be protected, except as permitted below:
(1) The minimum counterpoise conductor height above the raceway or cable to be protected shall 
be permitted to be adjusted subject to coordination with the airfield lighting and pavement designs.
(2) The counterpoise conductor height above the protected raceway(s) or cable(s) shall be 
calculated to ensure that the raceway or cable is within a 45-degree area of protection, (45 degrees on each 
side of vertical creating a 90-degree angle).
The counterpoise conductor shall be bonded to each metallic light base, mounting stake, and metallic 
airfield lighting component.
All metallic airfield lighting components in the field circuit on the output side of the constant current 
regulator (CCR) or other power source shall be bonded to the airfield lighting counterpoise system.
All components rise and fall at the same potential, with no potential difference, no damaging arcing 
and no damaging current flow.
See AC 150/5340-30, Design and Installation Details for Airport Visual Aids and NFPA 780, Standard 
for the Installation of Lightning Protection Systems, Chapter 11, for a detailed description of the 
Equipotential Method of lightning protection.
Reference FAA STD-019E, Lightning and Surge Protection, Grounding Bonding and Shielding 
Requirements for Facilities and Electronic Equipment, Part 4.1.1.7.
b. Isolation
used in areas where lightning strikes are not common.  Counterpoise size is selected 
by the RPR.  The isolation method is an alternate method for use only with edge lights installed in turf and 
stabilized soils and raceways installed parallel to and adjacent to the edge of the pavement.  NFPA 780 uses 
The counterpoise conductor shall be installed 8 inches (203 mm) minimum below grade. The 
counterpoise is not connected to the light base or mounting stake.  An additional grounding electrode is 
required at each light base or mounting stake.  The grounding electrode is bonded to the light base or 
mounting stake with a 6 AWG solid copper conductor.
See AC 150/5340-30, Design and Installation Details for Airport Visual Aids and NFPA 780, Standard 
for the Installation of Lightning Protection Systems, Chapter 11, for a detailed description of the Isolation 
Method of lightning protection.
c. Common installation requirements. When a metallic light base is used, the grounding 
electrode shall be bonded to the metallic light base or mounting stake with a No. 6 AWG bare, annealed or 
soft drawn, solid copper conductor.
When a nonmetallic light base is used, the grounding electrode shall be bonded to the metallic light 
fixture or metallic base plate with a No. 6 AWG bare, annealed or soft drawn, solid copper conductor.
Grounding electrodes may be rods, ground dissipation plates, radials, or other electrodes listed in the 
NFPA 70 (NEC) or NFPA 780.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-10   
Underground Power Cable for Airports
Where raceway is installed by the directional bore, jack and bore, or other drilling method, the 
counterpoise conductor shall be permitted to be installed concurrently with the directional bore, jack and 
bore, or other drilling method raceway, external to the raceway or sleeve.
The counterpoise wire shall also be exothermically welded to ground rods installed as shown on the 
plans but not more than 500 feet apart around the entire circuit.  The counterpoise system shall be 
continuous and terminate at the transformer vault or at the power source.  It shall be securely attached to 
the vault or equipment external ground ring or other made electrode-grounding system.  The connections 
shall be made as shown on the plans and in the specifications.
Where an existing airfield lighting system is being extended or modified, the new counterpoise 
conductors shall be interconnected to existing counterpoise conductors at each intersection of the new and 
existing airfield lighting counterpoise systems.
d. Parallel voltage systems.  Provide grounding and bonding in accordance with NFPA 70, 
National Electrical Code.
108-3.7 Counterpoise installation above multiple conduits and duct banks.
Counterpoise wires shall be installed above multiple conduits/duct banks for airfield lighting cables, with 
the intent being to provide a complete area of protection over the airfield lighting cables. When multiple 
conduits and/or duct banks for airfield cable are installed in the same trench, the number and location of 
counterpoise wires above the conduits shall be adequate to provide a complete area of protection measured 
45 degrees each side of vertical.
Where duct banks pass under pavement to be constructed in the project, the counterpoise shall be placed 
above the duct bank. Reference details on the construction plans.
108-3.8 Counterpoise installation at existing duct banks. When airfield lighting cables are 
indicated on the plans to be routed through existing duct banks, the new counterpoise wiring shall be 
terminated at ground rods at each end of the existing duct bank where the cables being protected enter and 
exit the duct bank. The new counterpoise conductor shall be bonded to the existing counterpoise system.
108-3.9 Exothermic bonding. Bonding of counterpoise wire shall be by the exothermic welding 
process or equivalent method accepted by the RPR. Only personnel experienced in and regularly engaged 
in this type of work shall make these connections.
Contractor shall demonstrate to the satisfaction of the RPR, the welding kits, materials and procedures to 
be used for welded connections prior to any installations in the field. The installations shall comply with 
e following:
a. All slag shall be removed from welds.
b. Using an exothermic weld to bond the counterpoise to a lug on a galvanized light base is not 
directions for proper methods of bonding copper wire to the light base.  See AC 150/5340-30 for galvanized 
light base exception.
c. If called for in the plans, all buried copper and weld material at weld connections shall be thoroughly 
coated with 6 mm of 3MTM ScotchkoteTM, or approved equivalent, or coated with coal tar Bitumastic® 
material to prevent surface exposure to corrosive soil or moisture.
108-3.10 Testing. The Contractor shall furnish all necessary equipment and appliances for testing the 
airport electrical systems and underground cable circuits before and after installation. The Contractor shall 
perform all tests in the presence of the RPR. The Contractor shall demonstrate the electrical characteristics 
to the satisfaction of the RPR. All costs for testing are incidental to the respective item being tested. For 
phased projects, the tests must be completed by phase. The Contractor must maintain the test results 
throughout the entire project as well as during the warranty period that meet the following:

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-11   
Underground Power Cable for Airports
a.
Earth resistance testing methods shall be submitted to the RPR for approval. Earth 
resistance testing results shall be recorded on an approved form and testing shall be performed 
in the presence of the RPR. All such testing shall be at the sole expense of the Contractor.
b.
Should the counterpoise or ground grid conductors be damaged or suspected of 
being damaged by construction activities the Contractor shall test the conductors for continuity 
with a low resistance ohmmeter. The conductors shall be isolated such that no parallel path 
exists and tested for continuity. The RPR shall approve of the test method selected. All such 
testing shall be at the sole expense of the Contractor.
After installation, the Contractor shall test and demonstrate to the satisfaction of the RPR the following:
c.
That all affected lighting power and control circuits (existing and new) are 
continuous and free from short circuits.
d.
That all affected circuits (existing and new) are free from unspecified grounds.
e.
That the insulation resistance to ground of all new non-grounded high voltage 
series circuits or cable segments is not less than 100 megohms. Verify continuity of all series 
airfield lighting circuits prior to energization.
f.
That the insulation resistance to ground of all new non-grounded conductors of 
new multiple circuits or circuit segments is not less than 100 megohms.
g.
That all affected circuits (existing and new) are properly connected per applicable 
wiring diagrams.
h.
That all affected circuits (existing and new) are operable. Tests shall be conducted 
that include operating each control not less than 10 times and the continuous operation of each 
lighting and power circuit for not less than 1/2 hour.
i.
That the impedance to ground of each ground rod does not exceed 25 ohms prior 
to establishing connections to other ground electrodes. The fall-of-potential ground impedance 
test shall be used, as described by American National Standards Institute/Institute of Electrical 
and Electronic Engineers (ANSI/IEEE) Standard 81, to verify this requirement. As an alternate, 
clamp-on style ground impedance test meters may be used to satisfy the impedance testing 
requirement.  Test equipment and its calibration sheets shall be submitted for review and 
approval by the RPR prior to performing the testing.
Two copies of tabulated results of all cable tests performed shall be supplied by the Contractor to the RPR. 
Where connecting new cable to existing cable, insulation resistance tests shall be performed on the new 
cable prior to connection to the existing circuit.
replacement.
METHOD OF MEASUREMENT
108-4.1 Cable installed in duct bank or conduit shall be measured by the number of linear feet installed 
with primary connector kits, grounding conductor and grounding connectors ready for operation, and 
accepted by Owner / Engineer. Separate measurement shall be made for each single cable (1/C), cable pair 
(2/C) or multiple conductor feeder set, installed in duct bank or conduit with associated ground wire and 
include additional 
quantities required for slack. No separate measurement will be made to multiply the number of individual 
conductors installed in a single conduit, in one installation effort.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-12   
Underground Power Cable for Airports
108-4.2
Counterpoise wire and connections are considered incidental to the installation of duct bank 
or conduit, per item L-110. No separate payment will be made.
108-4.3
Ground rods shall be considered incidental to the installation of counterpoise, light base, 
transformer housing, sign or other grounding. No separate payment will be made.  
BASIS OF PAYMENT
108-5.1
Payment will be made at the contract unit price for cable and equipment ground installed in 
duct bank or conduit, in place by the Contractor and accepted by the Engineer. This price shall be full 
compensation for furnishing all materials and for all preparation and installation of these materials, and 
for all labor, equipment, tools, and incidentals, including ground rods and ground connectors and trench 
marking tape, necessary to complete this item. 
Payment will be made under:
No. 26, Spec No. L-108-5.1
L-824, Type C, 1/C #8 AWG, 5kV Cable
per Linear 
Foot
No. 27, Spec No. L-108-5.2
L-824, Type C, 2/C #8 AWG, 5kV Cable 
per Linear 
Foot
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are 
referred to within the text by the basic designation only.
Advisory Circulars (AC)
AC 150/5340-26
Maintenance of Airport Visual Aid Facilities
AC 150/5340-30
Design and Installation Details for Airport Visual Aids
AC 150/5345-7
Specification for L-824 Underground Electrical Cable for Airport Lighting Circuits
AC 150/5345-26
Specification for L-823 Plug and Receptacle, Cable Connectors
AC 150/5345-53
Airport Lighting Equipment Certification Program
Commercial Item Description
A-A-59544A
Cable and Wire, Electrical (Power, Fixed Installation)
A-A-55809
Insulation Tape, Electrical, Pressure-Sensitive Adhesive, Plastic
ASTM International (ASTM)
ASTM B3
Standard Specification for Soft or Annealed Copper Wire
ASTM B8
Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, 
Medium-Hard, or Soft
ASTM B33
Standard Specification for Tin-Coated Soft or Annealed Copper Wire for Electrical 
Purposes

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-13   
Underground Power Cable for Airports
ASTM D4388
Standard Specification for Nonmetallic Semi-Conducting and Electrically 
Insulating Rubber Tapes
Mil Spec
MIL-PRF-23586F
Performance Specification: Sealing Compound (with Accelerator), Silicone 
Rubber, Electrical
MIL-I-24391
Insulation Tape, Electrical, Plastic, Pressure Sensitive
National Fire Protection Association (NFPA)
NFPA-70
National Electrical Code (NEC)
NFPA-780
Standard for the Installation of Lightning Protection Systems
American National Standards Institute (ANSI)/Institute of Electrical and Electronics Engineers (IEEE)
ANSI/IEEE STD 81
IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth 
Surface Potentials of a Ground System
Federal Aviation Administration Standard
FAA STD-019E 
Lightning and Surge Protection, Grounding Bonding and Shielding Requirements 
for Facilities and Electronic Equipment
END OF ITEM L-108

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-108-14   
Underground Power Cable for Airports
PAGE INTENTIONALLY LEFT BLANK

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-1
Airport Underground Electrical Duct 
Banks and Conduit  
ITEM L-110 AIRPORT UNDERGROUND ELECTRICAL DUCT BANKS AND 
CONDUITS
DESCRIPTION
110-1.1 This item shall consist of underground electrical conduits and duct banks (single or multiple 
conduits encased in concrete or buried in sand) installed per this specification at the locations and per the 
dimensions, designs, and details shown on the plans. This item shall include furnishing and installing of all 
underground electrical duct banks and individual and multiple underground conduits. It shall also include 
all turfing trenching, backfilling, removal, and restoration of any paved or turfed areas; concrete 
encasement, mandrelling, pulling lines, duct markers, plugging of conduits, and the testing of the 
installation as a completed system ready for installation of cables per the plans and specifications. This item 
shall also include furnishing and installing conduits, counterpoise conductor, ground rods and connections 
including all incidentals for providing positive drainage of the system. Verification of existing ducts is 
incidental to the pay items provided in this specification.
EQUIPMENT AND MATERIALS
110-2.1 General.
a. All equipment and materials covered by referenced specifications shall be subject to acceptance 
requested by the Engineer.
b.
materials per these specifications and acceptable to the Engineer. Materials supplied and/or 
installed that do not comply with these specifications shall be removed, when directed by the 
Engineer and replaced with materials that comply with these specifications, at
c.
All materials and equipment used to construct this item shall be submitted to the Engineer for 
approval prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop 
drawings shall be provided. Submittal data shall be presented in a clear, precise, and thorough 
manner. Original catalog sheets are preferred. Photocopies are acceptable provided they are as good 
a quality as the original. Clearly and boldly mark each copy to identify products or models 
applicable to this project. Indicate all optional equipment and delete non-pertinent data. 
Submittals for components of electrical equipment and systems shall identify the equipment for 
which they apply on each submittal sheet. Markings shall be made bold and clear with arrows or 
circles (highlighting is not acceptable). The Contractor is solely responsible for delays in project 
that accrue directly or indirectly from late submissions or resubmissions of submittals.
d. The data submitted shall be sufficient, in the opinion of the Engineer, to determine compliance with 
tabbed by specification section. The Engineer reserves the right to reject any and all equipment, 
materials or procedures that do not meet the system design and the standards and codes specified 
in this document.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-2
Airport Underground Electrical Duct 
Banks and Conduit  
e. All equipment and materials furnished and installed under this section shall be guaranteed against 
defects in materials and workmanship for a period of at least twelve (12) months from final 
acceptance by the Owner. The defective materials and/or equipment shall be repaired or replaced, 
110-2.2 Steel Conduit. Rigid galvanized steel (RGS) conduit and fittings shall be hot dipped 
galvanized inside and out and conform to the requirements of Underwriters Laboratories Standards 6, 
514B, and 1242. All RGS conduits or RGS elbows installed below grade, in concrete, permanently wet 
locations or other similar environments shall be painted with a 10-mil thick coat of asphaltum sealer or 
shall have a factory bonded polyvinyl chloride (PVC) cover.  Any exposed galvanizing or steel shall be coated 
with 10 mil of asphaltum sealer.  When using PVC coated RGS conduit, care shall be exercised not to damage 
the factory PVC coating.  Damaged PVC coating shall be repaired per the manufacturer's written 
instructions.
110-2.3 Plastic Conduit. Plastic conduit and fittings-shall conform to the following requirements:
UL 514B covers W-C-1094-Conduit fittings all types, classes 1 thru 3 and 6 thru 10.
UL 514C covers W-C-1094- all types, Class 5 junction box and cover in plastic (PVC). 
UL 651 covers W-C-1094-Rigid PVC Conduit, types I and II, Class 4.
UL 651A covers W-C-1094-Rigid PVC Conduit and high-density polyethylene (HDPE) Conduit type 
III and Class 4.
Underwriters Laboratories Standards UL-651 and Article 352 of the current National Electrical Code shall 
be one of the following, as shown on the plans:
a.
Type I Schedule 40 PVC suitable for underground use either direct-buried or encased in 
concrete.
b.
Type II Schedule 40 PVC suitable for either above ground or underground use.
c.
Type III 
Schedule 80 PVC suitable for either above ground or underground use either direct-
buried or encased in concrete.
d.
Type III HDPE pipe, minimum standard dimensional ratio (SDR) 11, suitable for placement 
with directional boring under pavement.
The type of solvent cement shall be as recommended by the conduit/fitting manufacturer.
110-2.4 Split Conduit. Split conduit shall be pre-manufactured for the intended purpose and shall 
be made of steel or plastic.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-3
Airport Underground Electrical Duct 
Banks and Conduit  
110-2.5 Conduit Spacers. Conduit spacers shall be prefabricated interlocking units manufactured 
for the intended purpose. They shall be of double wall construction made of high grade, high density 
polyethylene complete with interlocking cap and base pads, they shall be designed to accept No. 4 
reinforcing bars installed vertically.
110-2.6 Concrete. Concrete shall conform to Item P-610, Structural Portland Cement Concrete, using 
1-inch maximum size coarse aggregate with a minimum 28-day compressive strength of 4000 psi. Where 
reinforced duct banks are specified, reinforcing steel shall conform to ASTM A615 Grade 60. Concrete and 
reinforcing steel are incidental to the respective pay item of which they are a component part.
110-2.7 Flowable Backfill. Flowable material used to back fill conduit and duct bank trenches shall 
conform to the requirements of Item P-153, Controlled Low Strength Material.  Fill shall be designed to 
achieve a 28-day compressive strength of 200 psi (1.4 MPa) under pavement.
110-2.8 Detectable Warning Tape.  Plastic, detectable, American Wood Preservers Association 
(AWPA) Red (electrical power lines, cables, conduit, and lighting cable) with continuous legend magnetic 
tape shall be polyethylene film with a metallized foil core and shall be 3-6 inches wide.  Detectable tape is 
incidental to the respective bid item.
110-2.9
Retro-Fit Existing Pavement. Where conduit is installed under existing asphalt 
shoulder pavement, Contractor shall saw cut and remove existing section prior to excavation, conduit and 
counterpoise installation and slurry backfill. Contractor shall repair/replace shoulder pavement in kind. 
-405, P-201, and P-152 
requirements. All saw cut and pavement repair / replacement shall be considered incidental to the 
associated item being installed (i.e. there is no separate measurement of payment).
CONSTRUCTION METHODS
110-3.1 General. The Contractor shall install underground duct banks and conduits at the 
approximate locations indicated on the plans. The Engineer shall indicate specific locations as the work 
progresses, if required to differ from the plans. Duct banks and conduits shall be of the size, material, and 
type indicated on the plans or specifications. Where no size is indicated on the plans or in the specifications, 
conduits shall be not less than 2 inches inside diameter or comply with the National Electrical Code based 
on cable to be installed, whichever is larger. All duct bank and conduit lines shall be laid so as to grade 
toward access points and duct or conduit ends for drainage. Unless shown otherwise on the plans, grades 
shall be at least 3 inches per 100 feet. On runs where it is not practicable to maintain the grade all one way, 
the duct bank and conduit lines shall be graded from the center in both directions toward access points or 
conduit ends, with a drain into the storm drainage system. Pockets or traps where moisture may accumulate 
shall be avoided. No duct bank or underground conduit shall be less than 18 inches below finished grade. 
Where under pavement, the top of the duct bank shall not be less than 18 inches below the subgrade.
The Contractor shall mandrel each individual conduit whether the conduit is direct-buried or part of a duct 
bank. An iron-shod mandrel, not more than 1/4 inch smaller than the bore of the conduit shall be pulled or 
pushed through each conduit. The mandrel shall have a leather or rubber gasket slightly larger than the 
conduit hole.
The Contractor shall swab out all conduits/ducts and clean base can, manhole, pull boxes, etc., interiors 
IMMEDIATELY prior to pulling cable. Once cleaned and swabbed the light bases, manholes, pull boxes,

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-4
Airport Underground Electrical Duct 
Banks and Conduit  
etc., and all accessible points of entry to the duct/conduit system shall be kept closed except when installing 
cables. Cleaning of ducts, base cans, manholes, etc., is incidental to the pay item of the item being cleaned. 
All raceway systems left open, after initial cleaning, for any reason shall be re-
expense. All accessible points shall be kept closed when not installing cable. The Contractor shall verify 
existing ducts proposed for use in this project as clear and open. The Contractor shall notify the Engineer 
of any blockage in the existing ducts.
For pulling the permanent wiring, each individual conduit, whether the conduit is direct-buried or part of 
a duct bank, shall be provided with a 200-pound test polypropylene pull rope. The ends shall be secured, 
and sufficient length shall be left in access points to prevent it from slipping back into the conduit. Where 
spare conduits are installed, as indicated on the plans, the open ends shall be plugged with removable 
tapered plugs, designed for this purpose.
All conduits shall be securely fastened in place during construction and shall be plugged to prevent 
contaminants from entering the conduits. Any conduit section having a defective joint shall not be installed. 
Ducts shall be supported and spaced apart using approved spacers at intervals not to exceed 5 feet.
Unless otherwise shown on the plans, concrete encased duct banks shall be used when crossing under 
pavements expected to carry aircraft loads, such as runways, taxiways, taxi-lanes, ramps, and aprons. When 
under paved shoulders and other paved areas, conduit and duct banks shall be encased using flow-able fill 
for protection. 
All conduits within concrete encasement of the duct banks shall terminate with female ends for ease in 
current and future use. Install factory plugs in all unused ends. Do not cover the ends or plugs with concrete.
Where turf is well established and the sod can be removed, it shall be carefully stripped and properly stored.
Trenches for conduits and duct banks may be excavated manually or with mechanical trenching equipment 
unless in pavement, in which case they shall be excavated with mechanical trenching equipment. Walls of 
trenches shall be essentially vertical so that a minimum of shoulder surface is disturbed. Blades of graders 
shall not be used to excavate the trench.
When rock is encountered, the rock shall be removed to a depth of at least 3 inches below the required 
conduit or duct bank depth and it shall be replaced with bedding material of earth or sand containing no 
mineral aggregate particles that would be retained on a 1/4 inch sieve. Flow-able backfill may alternatively 
be used The Contractor shall ascertain the type of soil or rock to be excavated before bidding. All such rock 
removal shall be performed and paid for under Item P-152.
Underground electrical warning (Caution) tape shall be installed in the trench above all underground duct 
banks and conduits in unpaved areas. Contractor shall submit a sample of the proposed warning tape for 
approval by the Engineer. If not shown on the plans, the warning tape shall be located 6 inches above the 
duct/conduit or the counterpoise wire if present.
of conduit. Plastic conduit shall be prepared by application of a plastic cleaner and brushing a plastic solvent 
on the outside of the conduit ends and on the inside of the couplings. The conduit fitting shall then be 
slipped together with a quick one-quarter turn twist to set the joint tightly. Where more than one conduit 
is placed in a single trench, or in duct banks, joints in the conduit shall be staggered a minimum of 2 feet.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-5
Airport Underground Electrical Duct 
Banks and Conduit  
Changes in direction of runs exceeding 10 degrees, either vertical or horizontal, shall be accomplished using 
manufactured sweep bends.
Whether or not specifically indicated on the drawings, where the soil encountered at established duct bank 
grade is an unsuitable material, as determined by the Engineer, the unsuitable material shall be removed 
per Item P-152 and replaced with suitable material. Alternatively, additional duct bank supports that are 
adequate and stable shall be installed, as approved by the Engineer.
All excavation shall be unclassified and shall be considered incidental to the respective L-110 pay item of 
which it is a component part. Dewatering necessary for duct installation, erosion, and turbidity control, per 
Federal, state, and local requirements is incidental to its respective pay item as a part of Item L-110. The 
cost of all excavation regardless of type of material encountered shall be included in the unit price bid for 
the L-110 Item.
Unless otherwise specified, excavated materials that are deemed by the Engineer to be unsuitable for use in 
backfill or embankments shall be removed and disposed of offsite.
Any excess excavation shall be filled with suitable material approved by the Engineer and compacted per 
Item P-152.
Where existing active cables cross proposed installations, the Contractor shall ensure that these cables are 
adequately protected. Where crossings are unavoidable, no splices will be allowed in the existing cables, 
except as specified on the plans. Installation of new cable where such crossings must occur shall proceed as 
follows:
a.
Existing cables shall be located manually. Unearthed cables shall be inspected to assure absolutely 
no damage has occurred
b.
Trenching, etc., in cable areas shall then proceed with approval of the Engineer, with care taken to 
minimize possible damage or disruption of existing cable, including careful backfilling in area of 
cable.
In the event that any previously identified cable is damaged during the course of construction, the 
Contractor shall be responsible for the complete repair.
110-3.2 Duct Banks. Unless otherwise shown in the plans, duct banks shall be installed so that the top 
of the concrete envelope is not less than 18 inches below the bottom of the base or stabilized base course 
layers where installed under runways, taxiways, aprons, or other paved areas, and not less than 18 inches 
below finished grade where installed in unpaved areas.
Unless otherwise shown on the plans, duct banks under paved areas shall extend at least 3 feet beyond the 
edges of the pavement or 3 feet beyond any under drains that may be installed alongside the paved area. 
Trenches for duct banks shall be opened the complete length before concrete is placed so that if any 
obstructions are encountered, provisions can be made to avoid them. Unless otherwise shown on the plans, 
all duct banks shall be placed on a layer of concrete not less than 3 inches thick prior to its initial set. The 
Contractor shall space the conduits not less than 3 inches apart (measured from outside wall to outside 
wall). All such multiple conduits shall be placed using conduit spacers applicable to the type of conduit. As

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-6
Airport Underground Electrical Duct 
Banks and Conduit  
the conduit laying progresses, concrete shall be placed around and on top of the conduits not less than 3 
inches thick unless otherwise shown on the plans. All conduits shall terminate with female ends for ease of 
access in current and future use. Install factory plugs in all unused ends. Do not cover the ends or plugs 
with concrete. 
Conduits forming the duct bank shall be installed using conduit spacers. No. 4 reinforcing bars shall be 
driven vertically into the soil a minimum of 6 inches to anchor the assembly into the earth prior to placing 
the concrete encasement. For this purpose, the spacers shall be fastened down with locking collars attached 
to the vertical bars. Spacers shall be installed at 5-foot intervals. Spacers shall be in the proper sizes and 
configurations to fit the conduits. Locking collars and spacers shall be submitted to the Engineer for review 
prior to use.
When specified, the Contractor shall reinforce the bottom side and top of encasements with steel reinforcing 
mesh or fabric or other approved metal reinforcement. When directed, the Contractor shall supply 
additional supports where the ground is soft and boggy, where ducts cross under roadways, or where shown 
on the plans. Under such conditions, the complete duct structure shall be supported on reinforced concrete 
footings, piers, or piles located at approximately 5-foot intervals.
All pavement surfaces that are to have ducts installed therein shall be neatly saw cut to form a vertical face. 
All excavation shall be included in the contract with price for the duct.
Install a plastic, detectable, color as noted, 3 to 6 inches wide tape, 8 inches minimum below grade above 
all underground conduit or duct lines not installed under pavement.  Utilize the 3-inch wide tape only for 
single conduit runs. Utilize the 6-inch wide tape for multiple conduits and duct banks. For duct banks equal 
to or greater than 24 inches in width, utilize more than one tape for sufficient coverage and identification 
of the duct bank as required.
When existing cables are to be placed in split duct, encased in concrete, the cable shall be carefully located 
and exposed by hand tools. Prior to being placed in duct, the Engineer shall be notified so that he may 
inspect the cable and determine that it is in good condition. Where required, split duct shall be installed as 
shown on the drawings or as required by the Engineer.
110-3.3 Conduits Without Concrete Encasement. Trenches for single-conduit lines shall be 
not less than 6 inches nor more than 12 inches wide. The trench for 2 or more conduits installed at the same 
level shall be proportionately wider. Trench bottoms for conduits without concrete encasement shall be 
made to conform accurately to grade so as to provide uniform support for the conduit along its entire length.
Unless otherwise shown on the plans, a layer of fine earth material, at least 4 inches thick (loose 
measurement) shall be placed in the bottom of the trench as bedding for the conduit. The bedding material 
shall consist of soft dirt, sand, or other fine fill, and it shall contain no particles that would be retained on a 
1/4-inch sieve. The bedding material shall be tamped until firm. Flow-able backfill may alternatively be 
used.
Unless otherwise shown on plans, conduits shall be installed so that the tops of all conduits within the 
all be installed so that the tops of the conduits are at least 24 
inches below the finished grade per National Electric Code (NEC), Table 300.5.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-7
Airport Underground Electrical Duct 
Banks and Conduit  
When two or more individual conduits intended to carry conductors of equivalent voltage insulation rating 
are installed in the same trench without concrete encasement, they shall be spaced not less than 3 inches 
apart (measured from outside wall to outside wall) in a horizontal direction and not less than 6 inches apart 
in a vertical direction. Where two or more individual conduits intended to carry conductors of differing 
voltage insulation rating are installed in the same trench without concrete encasement, they shall be placed 
not less than 3 inches apart (measured from outside wall to outside wall) in a horizontal direction and lot 
less than 6 inches apart in a vertical direction.
Trenches shall be opened the complete length between normal termination points before conduit is 
installed so that if any unforeseen obstructions are encountered, proper provisions can be made to avoid 
them.
Conduits shall be installed using conduit spacers. No. 4 reinforcing bars shall be driven vertically into the 
soil a minimum of 6 inches to anchor the assembly into the earth while backfilling. For this purpose, the 
spacers shall be fastened down with locking collars attached to the vertical bars. Spacers shall be installed 
at 5-foot intervals. Spacers shall be in the proper sizes and configurations to fit the conduits. Locking collars 
and spacers shall be submitted to the Engineer for review prior to use.
110-3.4 Markers. The location of each end and of each change of direction of conduits and duct banks 
shall be marked by a concrete slab marker 2 feet square and 4 - 6 inches thick extending approximately one 
inch above the surface. The markers shall also be located directly above the ends of all conduits or duct 
banks, except where they terminate in a junction/access structure or building. Each cable or duct run from 
a line of lights and signs to the equipment vault must be marked at approximately every 200 feet along the 
cable or duct run, with an additional marker at each change of direction of cable or duct run. 
shall be done in a manner, approved by the Engineer, for a neat, professional appearance. All letters and 
words must be neatly stenciled. After placement, all markers shall be given one coat of high-visibility orange 
paint, as approved by the Engineer. The Contractor shall also impress on the slab the number and size of 
conduits beneath the marker along with all other necessary information as determined by the Engineer. 
The letters shall be 4 inches high and 3 inches wide with width of stroke 1/2 inch and 1/4-inch-deep or as 
large as the available space permits. Furnishing and installation of duct markers is incidental to the 
respective duct pay item.
110-3.5 Backfilling for Conduits. For conduits, 8 inches of sand, soft earth, or other fine fill (loose 
measurement) shall be placed around the conduits ducts and carefully tamped around and over them with 
hand tampers. The remaining trench shall then be backfilled and compacted per Item P-
diameter.
Flow-able backfill may alternatively be used.
Trenches shall not contain pools of water during back filling operations.
The trench shall be completely backfilled and tamped level with the adjacent surface; except that, where 
sod is to be placed over the trench, the backfilling shall be stopped at a depth equal to the thickness of the 
sod to be used, with proper allowance for settlement.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-8
Airport Underground Electrical Duct 
Banks and Conduit  
Any excess excavated material shall be removed and disposed of per instructions issued by the Engineer.
110-3.6 Backfilling for Duct Banks. After the concrete has cured, the remaining trench shall be 
backfilled and compacted per Item P-
backfill shall be select material not larger than 4 inches in diameter. In addition to the requirements of P-
152, where duct banks are installed under pavement, one moisture/density test per lift shall be made for 
Flow-able backfill may alternatively be used.
Trenches shall not contain pools of water during backfilling operations.
The trench shall be completely backfilled and tamped level with the adjacent surface; except that, where 
sod is to be placed over the trench, the backfilling shall be stopped at a depth equal to the thickness of the 
sod to be used, with proper allowance for settlement.
Any excess excavated material shall be removed and disposed of per instructions issued by the Engineer.
110-3.7 Restoration. All areas disturbed by the work shall be restored to its original condition. The 
Contractor shall be held responsible for maintaining all disturbed surfaces and replacements until final 
acceptance. All restoration shall be considered incidental to the respective L-110 pay item. Following 
restoration of all trenching near airport movement surfaces, the Contractor shall thoroughly visually inspect 
the area for foreign object debris (FOD) and remove any such FOD that is found.  This FOD inspection and 
removal shall be considered incidental to the pay item of which it is a component part.
METHOD OF MEASUREMENT
110-4.1 Underground conduits and duct banks shall be measured by the linear feet of conduits and duct 
banks installed, including encasement, counterpoise conductor, ground rods and connections, locator tape, 
trenching and backfill with designated material, and for drain lines, the termination at the drainage 
structure, all measured in place, completed, and accepted. Separate measurement shall be made for the 
various types and sizes.
110-4.2 Retrofit conduits in existing asphalt shoulder pavement shall include saw cutting, slurry backfill 
and replacement / patch of asphalt pavement in kind. 
BASIS OF PAYMENT
110-5.1 Payment will be made at the contract unit price per linear foot for each type and size of conduit 
and duct bank completed and accepted, including trench and backfill with the designated material, and, for 
drain lines, the termination at the drainage structure. This price shall be full compensation for furnishing 
all materials and for all preparation, assembly, and installation of these materials, and for all labor, 
equipment, tools, and incidentals necessary to complete this item per the provisions and intent of the plans 
and specifications.
Payment will be made under:
No. 28, Spec No. L-110-5.1
Single-Way 1-2" Conduit Direct Buried
per Linear Foot

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-9
Airport Underground Electrical Duct 
Banks and Conduit  
No. 29, Spec No. L-110-5.2
Multiple-Way 2-2" Conduit Concrete Encased
per Linear Foot
No. 30, Spec No. L-110-5.3
Multiple-Way 4-2" Conduit Concrete Encased
per Linear Foot
MATERIAL REQUIREMENTS
Advisory Circular 
AC 150/5340-30
Design and Installation Details for Airport Visual Aids
AC 150/5345-53
Airport Lighting Equipment Certification Program
ASTM International (ASTM)
ASTM A615
Standard Specification for Deformed and Plain Carbon-Steel Bars for 
Concrete Reinforcement
ASTM D1556
Standard Test Method for Density and Unit Weight of Soil in Place by the 
Sand-Cone Method
ASTM D1557
Standard Test Methods for Laboratory Compaction Characteristics of 
Soil Using Modified Effort (56,000 ft-lbf/ft3(2,700 kN-m/m3))
ASTM D2167
Standard Test Method for Density and Unit Weight of Soil in Place by the 
Rubber Balloon Method
ASTM D2922
Standard Test Methods for Density of Soil and Soil-Aggregate in Place by 
Nuclear Methods (Shallow Depth)
NFPA-70
National Electrical Code (NEC)
Underwriters Laboratories Standard 6
Electrical Rigid Metal Conduit - Steel 
Underwriters Laboratories Standard 514B          Conduit, Tubing, and Cable Fittings 
Underwriters Laboratories Standard 514C
Nonmetallic Outlet Boxes, Flush-Device Boxes, and 
Covers
Underwriters Laboratories Standard 1242
Electrical Intermediate Metal Conduit Steel
Underwriters Laboratories Standard 651                Schedule 40, 80, Type EB and A Rigid PVC Conduit and 
Fittings
Underwriters Laboratories Standard 651A             Type EB and A Rigid PVC Conduit and HDPE Conduit
END OF ITEM L-110

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-110-10
Airport Underground Electrical Duct 
Banks and Conduit  
PAGE INTENTIONALLY LEFT BLANK

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-1   
Electrical Manholes and Junction 
Structures
ITEM L-115 ELECTRICAL MANHOLES AND JUNCTION STRUCTURES
DESCRIPTION
115-1.1
This item shall consist of electrical manholes and junction structures (hand holes, pull boxes, 
junction cans, etc.) installed per this specification, at the indicated locations and conforming to the lines, 
grades and dimensions shown on the plans or as required by the Engineer. This item shall include the 
installation of each electrical manhole and/or junction structures with all associated excavation, backfilling, 
sheeting and bracing, concrete, reinforcing steel, ladders, appurtenances, testing, dewatering and 
restoration of surfaces to the satisfaction of the Engineer.
EQUIPMENT AND MATERIALS
115-2.1 General.
All equipment and materials covered by referenced specifications shall be subject to acceptance through 
Engineer.
these specifications. Materials supplied and/or installed that do not comply with these specifications shall 
be removed (when directed by the Engineer) and replaced with materials that comply with these 
All materials and equipment used to construct this item shall be submitted to the Engineer for approval 
prior to ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be 
provided. Submittal data shall be presented in a clear, precise, and thorough manner. Original catalog 
sheets are preferred. Photocopies are acceptable provided they are as good a quality as the original. Clearly 
and boldly mark each copy to identify products or models applicable to this project. Indicate all optional 
equipment and delete any non-pertinent data. Submittals for components of electrical equipment and 
systems shall identify the equipment to which they apply on each submittal sheet. Markings shall be made 
bold and clear with arrows or circles (highlighting is not acceptable). The Contractor is solely responsible 
for delays in the project that may accrue directly or indirectly from late submissions or resubmissions of 
submittals.
The data submitted shall be sufficient, in the opinion of the Engineer, to determine compliance with the 
plans and specifications. 
specification section. The Engineer reserves the right to reject any and all equipment, materials or 
procedures that do not meet the system design and the standards and codes, specified in this document.
All equipment and materials furnished and installed under this section shall be guaranteed against defects 
in materials and workmanship for a period of at least twelve (12) months from the date of final acceptance 
discretion, with no additional cost to the Owner.
115-2.2 Concrete structures. Cast-in-place concrete structures are not used.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-2   
Electrical Manholes and Junction 
Structures
Provide precast concrete structures where shown on the plans. Precast concrete structures shall be an 
approved standard design of the manufacturer. Precast units shall have mortar or bitumastic sealer placed 
between all joints to make them watertight. The structure shall be designed to withstand 100,000 lbs.
aircraft loads, unless otherwise shown on the plans. Openings or knockouts shall be provided in the 
structure as detailed on the plans.
Threaded inserts and pulling eyes shall be cast in as shown.
If the Contractor chooses to propose a different structural design, signed and sealed shop drawings, design 
calculations, and other information requested by the Engineer shall be submitted by the Contractor to allow 
for a full evaluation by the Engineer. The Engineer shall review per the process defined in the General 
Provisions.
115-2.3 Junction Boxes. Junction boxes shall be L-867 Class 1 (non-load bearing) or L-868 Class 1 
(load bearing) airport light bases that are encased in concrete. The light bases shall have a galvanized steel 
blank cover, gasket, and stainless steel or coated steel hardware per FAA Engineering Brief (EB) #83. Covers 
shall be 3/8-inch thickness for L-867 and 3/4-inch thickness for L-868.
115-2.4 Mortar. The mortar shall be composed of one part of Portland cement and two parts of mortar 
sand, by volume. The Portland cement shall be per the requirements in ASTM C150, Type I. The sand shall 
be per the requirements in ASTM C144. Hydrated lime may be added to the mixture of sand and cement in 
an amount not to exceed 15% of the weight of cement used. The hydrated lime shall meet the requirements 
of ASTM C6. Water shall be potable, reasonably clean and free of oil, salt, acid, alkali, sugar, vegetable, or 
other substances injurious to the finished product.
115-2.5 Concrete. All concrete used in structures shall conform to the requirements of Item P-610, 
Structural Portland Cement Concrete.
115-2.6 Frames and Covers. The frames shall conform to one of the following requirements:
a.
ASTM A48
Gray iron castings
b.
ASTM A47
Malleable iron castings
c.
ASTM A27
Steel castings
d.
ASTM A283, Grade D
Structural steel for grates and frames
e.
ASTM A536
Ductile iron castings
f.
ASTM A897
Austempered ductile iron castings
All castings specified shall withstand a maximum tire pressure of 125 psi and maximum load of 100,000
lbs.
All castings or structural steel units shall conform to the dimensions shown on the plans and shall be 
designed to support the loadings specified.
Each frame and cover unit shall be provided with fastening members to prevent it from being dislodged by 
traffic, but which will allow easy removal for access to the structure.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-3   
Electrical Manholes and Junction 
Structures
All castings shall be thoroughly cleaned. After fabrication, structural steel units shall be galvanized to meet 
the requirements of ASTM A123.
ELECTRIC
cover shall be as shown on the plans or approved equivalent. No cable notches are required.
DANGER -- PERMIT-REQUIRED CONFINED SPACE, DO 
NOT ENTER
1910.146 (c)(2).
115-2.7 Ladders. Ladders, if specified, shall be galvanized steel or as shown on the plans.
115-2.8 Reinforcing Steel. All reinforcing steel shall be deformed bars of new billet steel meeting the 
requirements of ASTM A615, Grade 60.
115-2.9 Bedding/Special Backfill. Bedding or special backfill shall be as shown on the plans.
115-2.10 Flowable Backfill. Flowable material used to backfill shall conform to the requirements of 
Item P-153, Controlled Low Strength Material.
115-2.11 Cable Racks. Cable Racks shall be of non-conductive plastic. Cable racks shall be located as 
shown on the plans.
115-2.12 Plastic Conduit. Plastic conduit shall comply with Item L-110, Airport Underground 
Electrical Duct Banks and Conduits.
115-2.13 Conduit Terminators. Conduit terminators shall be pre-manufactured for the specific 
purpose and sized as required or as shown on the plans.
115-2.14 Pulling-In Irons. Pulling-in irons shall be manufactured with 7/8-inch diameter hot-
dipped galvanized steel or stress-relieved carbon steel roping designed for concrete applications (7 strand, 
1/2 inch diameter with an ultimate strength of 270,000 psi (1862 MPa)). Where stress-relieved carbon steel 
roping is used, a rustproof sleeve shall be installed at the hooking point and all exposed surfaces shall be 
encapsulated with a polyester coating to prevent corrosion.
115-2.15 Ground Rods. Ground rods shall be one piece, copper clad. The ground rods shall be of the 
length and diameter specified on the plans, but in no case shall they be less than 10 feet long nor less than 
¾ inch in diameter.
CONSTRUCTION METHODS
115-3.1  Unclassified excavation.
within the work area prior to excavation. Damage to utility lines, through lack of care in excavating, shall 
be repaired or replaced to the satisfaction of the Engineer without additional expense to the Owner.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-4   
Electrical Manholes and Junction 
Structures
The Contractor shall perform excavation for structures and structure footings to the lines and grades or 
elevations shown on the plans or as staked by the Engineer. The excavation shall be of sufficient size to 
permit the placing of the full width and length of the structure or structure footings shown.
All excavation shall be unclassified and shall be considered incidental to the respective L-115 pay item of 
which it is a component part. Dewatering necessary for L-115 structure installation, erosion and turbidity 
control, per Federal, state, and local requirements is incidental to its respective pay item as a part of Item 
L-115. The cost of all excavation regardless of type of material encountered, shall be included in the unit 
price bid for the L-115 Item.
Boulders, logs and all other objectionable material encountered in excavation shall be removed. All rock 
and other hard foundation material shall be cleaned of all loose material and cut to a firm surface either 
level, stepped or serrated, as directed by the Engineer. All seams, crevices, disintegrated rock and thin strata 
shall be removed. When concrete is to rest on a surface other than rock, special care shall be taken not to 
disturb the bottom of the excavation. Excavation to final grade shall not be made until just before the 
concrete or reinforcing is to be placed.
The Contractor shall provide all bracing, sheeting and shoring necessary to implement and protect the 
excavation and the structure as required for safety or conformance to governing laws. The cost of bracing, 
sheeting, and shoring shall be included in the unit price bid for the structure.
Unless otherwise provided, bracing, sheeting and shoring involved in the construction of this item shall be 
removed by the Contractor after the completion of the structure. Removal shall be effected in a manner that 
will not disturb, or mar finished masonry. The cost of removal shall be included in the unit price bid for the 
structure.
After each excavation is completed, the Contractor shall notify the Engineer. Structures shall be placed after 
the Engineer has approved the depth of the excavation and the suitability of the foundation material.
approved by the Engineer as a suitable base to receive the structure. The base material shall be compacted 
and graded level and at proper elevation to receive the structure in proper relation to the conduit grade or 
ground cover requirements, as indicated on the plans.
115-3.2 Concrete Structures. Concrete structures shall be built on prepared foundations 
conforming to the dimensions and form indicated on the plans. The concrete and construction methods 
shall conform to the requirements specified in Item P-610. Any reinforcement required shall be placed as 
indicated on the plans and shall be approved by the Engineer before the concrete is placed.
115-3.3 Precast Unit Installations. Precast units shall be installed plumb and true. Joints shall be 
made watertight by use of sealant at each tongue-and-groove joint and at roof of manhole. Excess sealant 
shall be removed and severe surface projections on exterior of neck shall be removed.
115-3.4 Placement and Treatment of Castings, Frames and Fittings. All castings, frames 
and fittings shall be placed in the positions indicated on the Plans or as directed by the Engineer and shall 
be set true to line and to correct elevation. If frames or fittings are to be set in concrete or cement mortar, 
all anchors or bolts shall be in place and position before the concrete or mortar is placed. The unit shall not 
be disturbed until the mortar or concrete has set.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-5   
Electrical Manholes and Junction 
Structures
Field connections shall be made with bolts, unless indicated otherwise. Welding will not be permitted unless 
shown otherwise on the approved shop drawings and written permission is granted by the casting 
manufacturer. Erection equipment shall be suitable and safe for the workman. Errors in shop fabrication 
or deformation resulting from handling and transportation that prevent the proper assembly and fitting of 
parts shall be reported immediately to the Engineer and approval of the method of correction shall be 
Anchor bolts and anchors shall be properly located and built into connection work. Bolts and anchors shall 
be preset by the use of templates or such other methods as may be required to locate the anchors and anchor 
bolts accurately.
Pulling-in irons shall be located opposite all conduit entrances into structures to provide a strong, 
convenient attachment for pulling-in blocks when installing cables. Pulling-in irons shall be set directly into 
the concrete walls of the structure.
115-3.5 Installation of Ladders. Not Used.
115-3.6 Removal of Sheeting and Bracing. In general, all sheeting and bracing used to support 
the sides of trenches or other open excavations shall be withdrawn as the trenches or other open excavations 
are being refilled. That portion of the sheeting extending below the top of a structure shall be withdrawn, 
unless otherwise directed, before more than 6 inches of material is placed above the top of the structure 
and before any bracing is removed. Voids left by the sheeting shall be carefully refilled with selected material 
and rammed tight with tools especially adapted for the purpose or otherwise as may be approved.
The Engineer may order the Contractor to delay the removal of sheeting and bracing if, in his judgment, the 
installed work has not attained the necessary strength to permit placing of backfill.
115-3.7 Backfilling. After a structure has been completed, the area around it shall be backfilled in 
horizontal layers not to exceed 6 inches in thickness measured after compaction to the density requirements 
in Item P-152. Each layer shall be deposited all around the structure to approximately the same elevation. 
The top of the fill shall meet the elevation shown on the plans or as directed by the Engineer.
Backfill shall not be placed against any structure until permission is given by the Engineer. In the case of 
concrete, such permission shall not be given until tests made by the laboratory under supervision of the 
Engineer establish that the concrete has attained sufficient strength to provide a factor of safety against 
damage or strain in withstanding any pressure created by the backfill or the methods used in placing it.
Where required, the Engineer may direct the Contractor to add, at his own expense, sufficient water during 
compaction to assure a complete consolidation of the backfill. The Contractor shall be responsible for all 
damage or injury done to conduits, duct banks, structures, property, or persons due to improper placing or 
compacting of backfill.
115-3.8 Connection of Duct Banks. To relieve stress of joint between concrete-encased duct banks 
and structure walls, reinforcement rods shall be placed in the structure wall and shall be formed and tied 
into duct bank reinforcement at the time the duct bank is installed.
115-3.9 Grounding. A ground rod shall be installed in the floor of all concrete structures so that the 
top of rod extends 6 inches above the floor. The ground rod shall be installed within one foot of a corner of 
the concrete structure. Ground rods shall be installed prior to casting the bottom slab. Where the soil

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-6   
Electrical Manholes and Junction 
Structures
condition does not permit driving the ground rod into the earth without damage to the ground rod, the 
Contractor shall drill a 4-inch diameter hole into the earth to receive the ground rod. The hole around the 
ground rod shall be filled throughout its length, below slab, with Portland cement grout. Ground rods shall 
be installed in precast bottom slab of structures by drilling a hole through bottom slab and installing the 
ground rod. Bottom slab penetration shall be sealed watertight with Portland cement grout around the 
ground rod.
A grounding bus of 4/0 bare stranded copper shall be exothermically bonded to the ground rod and loop 
the concrete structure walls. The ground bus shall be a minimum of one foot above the floor of the structure 
and separate from other cables. No. 2 American wire gauge (AWG) bare copper pigtails shall bond the 
grounding bus to all cable trays and other metal hardware within the concrete structure. Connections to the 
grounding bus shall be exothermic. If an exothermic weld is not possible, connections to the grounding bus 
shall be made by using connectors approved for direct burial in soil or concrete per UL 467.  Hardware 
connections may be mechanical, using a lug designed for that purpose.
115-3.10 Cleanup and Repair. After erection of all galvanized items, damaged areas shall be 
repaired by applying a liquid cold-galvanizing compound per MIL-P-21035. Surfaces shall be prepared, and 
Prior to acceptance, the entire structure shall be cleaned of all dirt and debris.
115-3.11 Restoration. After the backfill is completed, the Contractor shall dispose of all surplus 
material, dirt, and rubbish from the site. The Contractor shall restore all disturbed areas equivalent to or 
better than their original condition. All sodding, grading and restoration shall be considered incidental to 
the respective L-115 pay item.
The Contractor shall grade around structures as required to provide positive drainage away from the 
structure.
Areas with special surface treatment, such as roads, sidewalks, or other paved areas shall have the backfill 
compacted to match surrounding areas, and surfaces shall be repaired using materials comparable to 
original materials.
Following restoration of all trenching near airport movement surfaces, the Contractor shall thoroughly 
visually inspect the area for foreign object debris (FOD) and remove any such FOD that is found.  This FOD 
inspection and removal shall be considered incidental to the pay item of which it is a component part.
After all work is completed, the Contractor shall remove all tools and other equipment, leaving the entire 
site free, clear and in good condition.
115-3.12 Inspection. Prior to final approval, the electrical structures shall be thoroughly inspected 
for conformance with the plans and this specification. Any indication of defects in materials or 
workmanship shall be further investigated and corrected. The earth resistance to ground of each ground 
rod shall not exceed 25 ohms. Each ground rod shall be tested using the fall-of-potential ground impedance 
test per American National Standards Institute / Institute of Electrical and Electronic Engineers 
(ANSI/IEEE) Standard 81. This test shall be performed prior to establishing connections to other ground 
electrodes.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-7   
Electrical Manholes and Junction 
Structures
115-3.13 Manhole Elevation Adjustments. The Contractor shall adjust the tops of existing 
manholes in areas designated in the Contract Documents to the new elevations shown. The Contractor shall 
be responsible for determining the exact height adjustment required to raise the top of each manhole to the 
new elevations. The existing top elevation of each manhole to be adjusted shall be determined in the field 
and subtracted/added from the proposed top elevation.
The Contractor shall remove/extend the existing top section or ring and cover on the manhole structure or 
manhole access. The Contractor shall then install precast concrete sections or grade rings of the required 
dimensions to adjust the manhole top to the new proposed elevation or shall cut the existing manhole walls 
to shorten the existing structure, as required by final grades. Finally, the Contractor shall reinstall the 
manhole top section or ring and cover on top and check the new top elevation.
The Contractor shall construct a concrete slab around the top of adjusted structures located in graded areas 
that are not to be paved. The concrete slab shall conform to the dimensions shown on the plans.
115-3.14 Duct Extension to Existing Ducts. Where existing concrete encased ducts are to be 
extended, the duct extension shall be concrete encased plastic conduit. The fittings to connect the ducts 
together shall be standard manufactured connectors designed and approved for the purpose. The duct 
extensions shall be installed according to the concrete encased duct detail and as shown on the plans.
METHOD OF MEASUREMENT 
115-4.1 Electrical manholes and junction structures shall be measured by each unit completed in place 
and accepted. The following additional items are specifically included in each unit:
All Required Excavation, Dewatering
Sheeting and Bracing
All Required Backfilling with On-Site Materials
Restoration of All Surfaces and Finished Grading, Sodding
All Required Connections
Dewatering If Required
Temporary Cables and Connections
Ground Rod Testing
BASIS OF PAYMENT 
115-5.1 The accepted quantity of electrical manholes and junction structures will be paid for at the 
Contract unit price per each, complete and in place. This price shall be full compensation for furnishing all 
materials and for all preparation, excavation, backfilling and placing of the materials, furnishing and 
installation of appurtenances and connections to duct banks and other structures as may be required to 
complete the item as shown on the plans and for all labor, equipment, tools and incidentals necessary to 
complete the structure.
115-5.2 Payment shall be made at the contract unit price for L-867 junction cans. This price shall be full 
compensation for furnishing all materials and for all preparation, assembly, and installation of these

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-115-8   
Electrical Manholes and Junction 
Structures
materials, and for all labor, equipment, tools, and incidentals necessary, including but not limited to, 
concrete, rebar, dewatering, excavating, backfill, topsoil, sodding and pavement restoration, where 
required, to complete this item as shown in the plans and to the satisfaction of the Engineer.
Payment will be made under:
No. 31, Spec No. L-115-5.1
New 2'x3'x3' Hand Hole with Aircraft-Rated Lid with Spring Assisted 
Opening - per Each
No. 32, Spec No. L-115-5.2
Install New Steel Blank Cover on Existing L-867 Base Can with New Bolts
- per Each
MATERIAL REQUIREMENTS
ANSI/IEEE STD 81
IEEE Guide for Measuring Earth Resistivity, Ground Impedance, and Earth 
Surface Potentials of a Ground System
Advisory Circular 
(AC) 150/5345-7
Specifications for L-824 Underground Electrical Cable for Airport Lighting 
Circuits  
AC 150/5345-26
Specification for L-823 Plug and Receptacle, Cable Connectors
AC 150/5345-42 
Specification for Airport Light Bases, Transformer Housings, Junction Boxes, 
and Accessories
AC 150/5340-30
Design and Installation Details for Airport Visual Aids
AC 150/5345-53 
Airport Lighting Equipment Certification Program
Commercial Item Description 
A-A 59544
Cable and Wire, Electrical (Power, Fixed Installation)
ASTM A27
Standard Specification for Steel Castings, Carbon, for General Application
ASTM A47
Standard Specification for Ferritic Malleable Iron Castings
ASTM A48
Standard Specification for Gray Iron Castings
ASTM A123
Standard Specification for Zinc (Hot Dip Galvanized) Coatings on Iron and Steel Products
ASTM A283
Standard Specification for Low and Intermediate Tensile Strength  Carbon Steel Plates
ASTM A536
Standard Specification for Ductile Iron Castings
ASTM A615 Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete
Reinforcement
ASTM A897
Standard Specification for Austempered Ductile Iron Castings 
ASTM C144
Standard Specification for Aggregate for Masonry Mortar
ASTM C150
Standard Specification for Portland Cement
ASTM C206
Standard Specification for Finishing Hydrated Lime
FAA EB #83
In Pavement Light Fixture Bolts
MIL-P-21035
Paint High Zinc Dust Content, Galvanizing Repair
NFPA-70
National Electrical Code (NEC)
END OF ITEM L-115

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-1   
Installation of Airport Lighting 
Systems
Item L-125 Installation of Airport Lighting Systems
DESCRIPTION
125-1.1 This item shall consist of airport lighting systems furnished and installed in accordance with this 
specification, the referenced specifications, and the applicable advisory circulars (ACs). The systems shall 
be installed at the locations and in accordance with the dimensions, design, and details shown in the plans. 
This item shall include the furnishing of all equipment, materials, services, and incidentals necessary to 
place the systems in operation as completed units to the satisfaction of the RPR.
EQUIPMENT AND MATERIALS
125-2.1 GENERAL. 
Airport lighting equipment and materials covered by Federal Aviation Administration (FAA) specifications 
shall be certified under the Airport Lighting Equipment Certification Program in accordance with AC 
150/5345-53, current version.  FAA certified airfield lighting shall be compatible with each other to perform 
in compliance with FAA criteria and the intended operation.   If the Contractor provides equipment that 
does not performs as intended because of incompatibility with the system, the Contractor assumes all costs 
to correct the system for to operate properly.
a. Manufacturer's certifications shall not relieve the Contractor of their responsibility to 
provide materials in accordance with these specifications and acceptable to the RPR. Materials 
supplied and/or installed that do not comply with these specifications shall be removed, when 
directed by the RPR and replaced with materials, which do comply with these specifications, at the 
sole cost of the Contractor.
b. All materials and equipment used shall be submitted to the RPR for approval prior to 
ordering the equipment. Submittals consisting of marked catalog sheets or shop drawings shall be 
provided. Clearly mark each copy to identify pertinent products or models applicable to this project. 
Indicate all optional equipment and delete non-pertinent data. Submittals for components of 
electrical equipment and systems shall identify the equipment for which they apply on each 
submittal sheet. Markings shall be clearly made with arrows or circles (highlighting is not 
acceptable). The Contractor shall be responsible for delays in the project accruing directly or 
indirectly from late submissions or resubmissions of submittals.
c.
The data submitted shall be sufficient, in the opinion of the RPR, to determine compliance 
with the plans and specifications. The Contractor's submittals shall be submitted in electronic PDF 
format, tabbed by specification section. The RPR reserves the right to reject any or all equipment, 
standards and codes, specified herein.
d. All equipment and materials furnished and installed under this section shall be guaranteed 
against defects in materials and workmanship for a period of at least twelve (12) months from final

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-2   
Installation of Airport Lighting 
Systems
acceptance by the Owner. The defective materials and/or equipment shall be repaired or replaced, 
at the Owner's discretion, with no additional cost to the Owner.
e. All LED light fixtures, with the exception of obstruction lighting (AC 150/5345-43) must 
be warranted by the manufacturer for a minimum of 4 years after date of installation inclusive of 
ual manufacturer.
EQUIPMENT AND MATERIALS
125-2.2 Conduit/Duct. Conduit shall conform to Specification Item L-110 Airport Underground 
Electrical Duct Banks and Conduits.
125-2.3 Cable and Counterpoise. Cable and Counterpoise shall conform to Item L-108 
Underground Power Cable for Airports.
125-2.4 Tape. Rubber and plastic electrical tapes shall be Scotch Electrical Tape Numbers 23 and 88 
respectively, as manufactured by 3M Company or an approved equal.
125-2.5 Cable Connections. Cable Connections shall conform to Item L-108 Installation of 
Underground Cable for Airports.
125-2.6 Retroreflective Markers. Retroreflective markers shall be type L-853 and shall conform to 
the requirements of AC 150/5345-39.
125-2.7 Runway and Taxiway Lights.  Runway and taxiway lights shall conform to the 
requirements of AC 150/5345-46. Lamps shall be of size and type indicated, or as required by fixture 
manufacturer for each lighting fixture required under this contract. Filters shall be of colors conforming to 
the specification for the light concerned or to the standard referenced.
LIGHTS
Type
Class
Mode
Style
Option
Base
Filter
Transformer
Notes
L-861T
2 
Base 
Mounted
1 
6.6A
N/A
4 
(Mounting 
Hardware)
L-
Threaded 
Frangible 
Coupling
Blue 
(Globes)
Glass
30/45W
MITL 
Taxiway 
Edge
30W 
Quartz 
Halogen 
Height
125-2.8 Runway and Taxiway Signs. Runway and Taxiway Guidance Signs should conform to the 
requirements of AC 150/5345-44.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-3   
Installation of Airport Lighting 
Systems
SIGNS
Type
Size
Style
Class
Mode
Notes
L-858Y
L-858L
1
2
2
2
LED
Modular Refer to 
Plans
125-2.9 Runway End Identifier Light (REIL). Not Required
125-2.10 Precision Approach Path Indicator (PAPI). Not Required
125-2.11 Circuit Selector Cabinet. Not Required
125-2.12 Light Base and Transformer Housings. Light Base and Transformer Housings should 
conform to the requirements of AC 150/5345-42. Light bases shall be Type L-867, Class 1A, Size B shall be 
provided as indicated or as required to accommodate the fixture or device installed thereon. Base plates, 
cover plates, and adapter plates, extensions and spacers shall be provided to accommodate various sizes of 
fixtures, and elevation adjustments in accordance with the Plans.
125-2.13 Isolation Transformers. Isolation Transformers shall be Type L-830, size as required for 
each installation. Transformer shall conform to AC 150/5345-47.
INSTALLATION
125-3.1 Installation.  The Contractor shall furnish, install, connect, and test all equipment, 
accessories, conduit, cables, wires, buses, grounds, and support items necessary to ensure a complete and 
operable airport lighting system as specified here and shown in the plans. 
The equipment installation and mounting shall comply with the requirements of the National Electrical 
Code and state and local code agencies having jurisdiction.
The Contractor shall install the specified equipment in accordance with the applicable advisory circulars 
and the details shown on the plans. 
125-3.2 Testing.  All lights shall be fully tested by continuous operation for not less than 24 hours as a 
completed system prior to acceptance. The test shall include operating the constant current regulator in 
each step not less than 10 times at the beginning and end of the 24-hour test. The fixtures shall illuminate 
properly during each portion of the test.
125-3.3 Shipping and Storage. Equipment shall be shipped in suitable packing material to prevent 
damage during shipping.  Store and maintain equipment and materials in areas protected from weather 
and physical damage. Any equipment and materials, in the opinion of the RPR, damaged during 
construction or storage shall be replaced by the Contractor at no additional cost to the owner. Painted or 
recommendations.

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-4   
Installation of Airport Lighting 
Systems
125-3.4 Elevated and In-pavement Lights. Water, debris, and other foreign substances shall be 
removed prior to installing fixture base and light.
A jig or holding device shall be used when installing each light fixture to ensure positioning to the proper 
elevation, alignment, level control, and azimuth control. Light fixtures shall be oriented with the light beams 
parallel to the runway or taxiway centerline and facing in the required direction. The outermost edge of 
fixture shall be level with the surrounding pavement. Surplus sealant or flexible embedding material shall 
be removed. The holding device shall remain in place until sealant has reached its initial set.
METHOD OF MEASUREMENT
125-4.1 Taxiway lights and isolation transformers will be measured by the number of each type installed 
as completed units in place, ready for operation, and accepted by the RPR. 
Isolation Transformers for guidance signs will be measured by the number of each type and size installed 
as completed units, in place, ready for operation, and accepted by the RPR.
BASIS OF PAYMENT
125-5.1 Payment will be made at the Contract unit price for each complete runway or taxiway light, 
guidance sign or reflective marker installed by the Contractor and accepted by the RPR. This payment will 
be full compensation for furnishing all materials and for all preparation, assembly, and installation of these 
materials, and for all labor, equipment, tools, and incidentals necessary to complete this item.
Payment will be made under:
No. 33, Spec No. L-125-5.1
New L-861T Quartz Taxiway Edge Light and Isolation Transformer on 
New L-867 Base Can
Per Each
No. 34, Spec No. L-125-5.2
New L-858 (L) LED Size 2, Style 3, Class 2, 2-Module Airfield 
Guidance Sign on New Concrete Base
Per Each
No. 35, Spec No. L-125-5.3
New L-858 (L) LED Size 2, Style 3, Class 2, 3-Module Airfield 
Guidance Sign on New Concrete Base
Per Each
No. 36, Spec No. L-125-5.4
New L-858(L) LED Size 2, Style 3, Class 2, 3-Module Airfield 
Guidance Sign on Existing Concrete Sign Base - Per Each
No. 37, Spec No. L-125-5.5
New L-858 Size 2, Unlighted Taxiway Ending Marker Sign on New 
Concrete Sign Base - Per Each
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are 
referred to within the text by the basic designation only.
Advisory Circulars (AC)
AC 150/5340-18
Standards for Airport Sign Systems

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-5   
Installation of Airport Lighting 
Systems
AC 150/5340-26
Maintenance of Airport Visual Aid Facilities
AC 150/5340-30
Design and Installation Details for Airport Visual Aids
AC 150/5345-5
Circuit Selector Switch
AC 150/5345-7
Specification for L-824 Underground Electrical Cable for Airport Lighting 
Circuits
AC 150/5345-26
Specification for L-823 Plug and Receptacle, Cable Connectors
AC 150/5345-28
Precision Approach Path Indicator (PAPI) Systems
AC 150/5345-39
Specification for L-853, Runway and Taxiway Retroreflective Markers
AC 150/5345-42
Specification for Airport Light Bases, Transformer Housings, Junction 
Boxes, and Accessories
AC 150/5345-44
Specification for Runway and Taxiway Signs
AC 150/5345-46
Specification for Runway and Taxiway Light Fixtures
AC 150/5345-47
Specification for Series to Series Isolation Transformers for Airport 
Lighting Systems
AC 150/5345-51
Specification for Discharge-Type Flashing Light Equipment
AC 150/5345-53
Airport Lighting Equipment Certification Program
Engineering Brief (EB)
EB No. 67
Light Sources Other than Incandescent and Xenon for Airport and 
Obstruction Lighting Fixtures
END OF ITEM L-125

CHD Taxiway B Improvements Phase 1
COC Project No. AI2302.401
ADOT Project No. E3S4C
CR Engineers
September 2024
L-125-6   
Installation of Airport Lighting 
Systems
PAGE INTENTIONALLY LEFT BLANK

09/27/2024

EXHIBIT D
Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
D-1 
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev. 10/23/23 
GIS / GPS DATA DELIVERY REQUIREMENTS 
N/A

EXHIBIT E
Project Name: TAXIWAY B IMPROVEMENTS PHASE 1 
E-1
City Project No.: AI2302.401; ADOT No.: E3S4C  
Rev. 10/23/23 
FEDERAL PROVISIONS 
N/A