Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page 1 
Project No.:PR2504.402 
Rev. 3/19/2024 
CITY OF CHANDLER 
JOB ORDER PROJECT AGREEMENT 
VETERANS MEMORIAL PHASE 3 RECOGNITION PANELS 
Project No. PR2504.402 
Council Date: July 17, 2025
This JOB ORDER PROJECT AGREEMENT (”Job Order”) is made this _____ day of _________ 2025 
(“Effective Date”), by and between the City of Chandler, an Arizona municipal corporation, (“City”) 
and Hunter Contracting Co., an Arizona limited liability company, (“JOC Contractor”) and is 
entered into pursuant to Job Order Master Agreement No. JOC2419.401 (“JOC Master Agreement”). 
City and JOC Contractor may be referred to individually as “Party” or collectively as “Parties”). 
City and JOC Contractor, in consideration of the mutual covenants herein set forth, agree as 
follows:   
RECITALS 
A. On or about February 13, 2024, the Parties entered into the JOC Master Agreement, which terms
and conditions are made a part of and incorporated into this Job Order Project Agreement by this
reference.
B. City proposes to engage JOC Contractor for construction services as more fully described in
Article 1 and Exhibit "A", which is attached to and made a part of this Job Order by this reference.
C. JOC Contractor is ready, willing, and able to provide the services described in Exhibit “A” for
the compensation and fees set forth and as described in Exhibit ”B”, which is attached to and
made a part of this Agreement by this reference.
ARTICLE 1.  DESCRIPTION OF WORK 
The Parties enter into this Job Order Project Agreement for the Veterans Memorial Phase 3 
Recognition Panels, Project Number PR2504.402  The scope of work consists of custom 
manufacturing and installing of new Veteran name panels and associated cabinets in between the 
existing donor columns at Veterans Oasis Park Memorial, all as more particularly set forth in 
Exhibit “A” attached hereto and incorporated herein by reference. 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page 2 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
The JOC Contractor will not accept any change of scope, or change in Agreement provisions, unless 
issued in writing, as a Agreement amendment or change order and signed by the authorized 
signatories for each party. 
 
Performance and Payment Bonds, as set forth in Exhibit “C” and Exhibit “D” respectively attached 
hereto and incorporated herein by reference, will be due prior to execution of each Job Order 
Project Agreement in the full amount of each Job Order. 
 
At project completion, JOC Contractor must complete Contractor's Affidavit Regarding Settlement 
of Claims and Certificate of Completion, as set forth in Exhibit “E” and Exhibit “F” respectively 
attached hereto and incorporated herein by reference. 
 
ARTICLE 2.  PROJECT PRICE 
 
City will pay JOC Contractor for completion of the Work in accordance with the JOC Master 
Agreement a fee not to exceed the Guaranteed Maximum Price of $266,880.08 Dollars determined 
and payable as set forth in JOC Master Agreement and Exhibit “B” attached hereto and made a 
part hereof by reference.  
 
ARTICLE 3.  AGREEMENT TIME & SCHEDULE 
 
JOC Contractor agrees to complete all Construction within 180 calendar days from the Notice to 
Proceed (NTP) Date.  
 
ARTICLE 4.  JOB ORDER CONTACTS 
 
The following parties serve in the capacity below for this Job Order Project. 
 
CITY: 
 
Construction Project Manager:  Adam Kleiser 
 
Phone: 480-782-3325 
 
Email: Adam.Kleiser@chandleraz.gov 
 
JOC CONTRACTOR: 
Hunter Contracting Co. 
 
701 North Cooper Road 
 
JOC Contractor Representative:  Michael Gonzales 
 
Phone: 602-541-0671 
 
Email: michaelg@huntercontracting.com  
 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page 3 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
 
ARTICLE 5. FORCED LABOR OF ETHNIC UYGHURS PROHIBITED   
 
By entering into this Agreement, Contractor certifies and agrees Contractor does not currently use 
and will not use for the term of this Agreement: (i) the forced labor of ethnic Uyghurs in the 
People's Republic of China; or (ii) any goods or services produced by the forced labor of ethnic 
Uyghurs in the People's Republic of China; or (iii) any contractors, subcontractors or suppliers that 
use the forced labor or any goods or services produced by the forced labor of ethnic Uyghurs in 
the People's Republic of China 
 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page 4 
Project No.:PR2504.402 
Rev. 3/19/2024 
IN WITNESS WHEREOF, the Parties have executed this Job Order as of the Effective Date. 
“CITY”  
CITY OF CHANDLER 
Mayor 
RECOMMENDED BY: 
Daniel Haskins, P.E. 
CIP City Engineer   
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
 City Clerk 
 Seal 
“JOC CONTRACTOR” 
HUNTER CONTRACTING CO. 
Signature 
 Date 
Print Name 
Title 
Signer Email Address 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123
President
chucke@huntercontracting.com
June 23, 2025
Chuck English
June 23, 2025

Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page A-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
EXHIBIT A 
SCOPE OF WORK 
 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

701 N. Cooper Rd, Gilbert, AZ 85233
6930 N. Camino Martin, Tucson, AZ 85741
3580 W. Ina Rd, Ste170, Tucson, AZ 85741
www.huntercontracting.com
Project Manager:
Agreement Title: JOC – Field of Honor Ph3 - Name Recognition Plaques
Agreement No.: PR2504.402
Contractor: Hunter Contracting Co.
Address: 701 N. Cooper Road
City/State/Zip: Gilbert/AZ/85233
JOC Rep. Name: Michael Gonzales
Email: michaelg@huntercontracting.com 
Phone: 602.541.0671
Documents:
Description of Services:
Special Terms/Notes:
* Permit costs
* Quality Control testing
* Survey
Excluded Items:
*A portion of the site will be closed for approximately 1-month during installation.                             
* This price represents installation of 10 panels in 2 sections                                                                    
* Included in the schedule of values is an allowance for the purchase and installation of 
420 name plaques to fill all 10 panels - pricing may adjust based on how many are ordered. 
This price is per individual plate painted and shipped separately. There would be a 
discounted rate if they are order in more than 1 per order.                                                     * 
The work associated with this proposal is performed and paid for on a cost, or time and materials 
basis, the costs may be reimbursed to Hunter Contracting and chargeable against the Contract 
Price which includes all fees, costs, insurance, bond premiums, allowances, construction 
contingency, and taxes of any type necessary to fully, properly and timely perform and construct 
the Work. This not to exceed price is shown on Exhibit B.
EXHIBIT "A"
JOB ORDER COST PROPOSAL
Field of Honor Ph3 - Name Recognition Plaques
SCOPE OF WORK
This project includes the procurement, manufacture, and installation of blank panels and 
associated frames. Individual name plaque allowance is included in the contingency.
Plans - Field of Honor - Veteran's Memorial Phase 3 / by Kimley Horn /  4-17-2025
Specs - None
Geotech - None
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT B 
FEE SCHEDULE 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page B-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
 
 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

701 N. Cooper Rd, Gilbert, AZ 85233
6930 N. Camino Martin, Tucson, AZ 85741
3580 W. Ina Rd, Ste170, Tucson, AZ 85741
www.huntercontracting.com
Negotiated Prices
JOC – Field of Honor Ph3 - Name Recognition Plaques
175,841.74
$                
-
$                              
27,137.20
$                  
-
$                              
-
$                              
SUBTOTAL (NEGOTIATED PRICES):
202,978.94
$               
10.50%
21,312.79
$                  
TOTAL (NEGOTIATED PRICES + OVERHEAD & PROFIT):
224,291.73
$               
Sales Tax Percentage (Current Tax Rate)
5.07%
11,371.59
$                  
General Liability Insurance Percentage (Actual Cost per Job Order)
2,668.80
$                    
Builder's Risk Insurance Percentage (Actual Cost per Job Order)
132.91
$                       
Payment Bond (Actual Cost per Job Order)
1,727.05
$                    
Performance Bond (Actual Cost per Job Order)
-
$                              
SUBTOTAL (INSURANCE, BONDS, & TAXES):
15,900.34
$                  
COMBINED TOTAL (TOTAL + INSURANCE, BONDS, & TAXES):
240,192.07
$               
Owner Contingency
26,688.01
$                  
TOTAL JOB ORDER:
266,880.08
$       
4.1.7
Actual Cost of the Project (Delivery Order) Value
$1 to 
$49,999
$50,000 to 
$99,999
$100,000 to 
$199,999
$200,000 to 
$499,999
$500,000 to 
$999,999
$1,000,000 +
Coefficient
13.00%
11.50%
10.50%
10.50%
9.50%
8.00%
General Conditions
Preconstruction Labor (if applicable)
Construction Labor (if applicable)
Overhead and Profit (Coefficient per Job Order Master Agreement)
Insurance, Bonds, & Taxes
ENTER TAX % HERE:
Price of Subconsultant(s)
EXHIBIT "B"
JOB ORDER COST PROPOSAL
SUMMARY SHEET
Price of Subcontractor(s)
Per the Job Order Master Agreement - This Fee Table includes all fees, costs, insurance and bond premiums, allowances, construction contingency, and taxes of 
any type necessary to fully, properly and timely perform and construct the Work.  Also per the Job Order Master Agreement - For any portion of the Work which, 
either through this Contract, Change Order or otherwise, is performed and paid for on a cost, or time and materials basis, the costs may be reimbursed to JOC 
Contractor and chargeable against the Contract Price will be determined as set forth in MAG 109.5.
Not to Exceed
The coefficients shown in the table below will be used to determine the total amount payable to JOC Contractor for each specific Job Order. Overhead and 
profit will include all other expenses or costs not included in the actual cost of the project as determined in Articles 4.1.3.   
Field of Honor Ph3 - Name Recognition Plaques
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

Date:
6/12/25
Bid ItemDescription
 Bid Qty 
UM
Unit Cost
Total Cost
Project Cost
1
Base Bid: Cabinets (2ea) & Panels (10 ea)
1
                
LS
121,779.00
$         
121,779.00
$              
Early Procurement Contract Deduct as each will be seperate contract
(1)
              
LS
68,434.46
$           
(68,434.46)
$               
2
Veteran Name Plaques
420
           
AL
291.66
$                 
122,497.20
$              
SUBTOTAL - COST
2
General Requirements and Supervision
2
               
MO
18,091.47
$           
27,137.20
$                
2.1
Temp Facilities (Fence, J-john, Clean Up, etc)
1
                
LS
$6,733.00
$6,733.00
5.2
Project Engineer
60
             
HR
$77.23
$4,633.80
5.3
Project Superintendent
120
           
HR
$105.92
$12,710.40
5.4
Truck, Pick Up
180
           
HR
$17.00
$3,060.00
SUBTOTAL - GENERAL CONDITIONS
GRAND TOTAL - COST
 $             202,978.94 
$                                                175,841.74 
$                                                  27,137.20 
EXHIBIT "B.2"
JOB ORDER COST PROPOSAL
Field of Honor Ph3 - Name Recognition Plaques
SCHEDULE OF VALUES
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT C 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page C-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
 
 
PERFORMANCE BOND 
 
 
ARIZONA STATUTORY PERFORMANCE BOND 
PURSUANT TO TITLES 28, 34, AND 41, ARIZONA REVISED STATUTES 
(Penalty of this bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:___________________________________________________ 
 
(hereinafter "Principal"), and __________________________________________________________ (hereinafter "Surety"), a 
corporation organized and existing under the laws of the State of ______________ with its principal office in the City of 
_____________________________, holding a certificate of authority to transact surety business in Arizona issued by the 
Director of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
__________________________(hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, Principal and Surety bind themselves, and their heirs, administrators, 
executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated  
 
the ____________ day of _______________________, 20___ for construction of Veterans Memorial Phase 3 Recognition 
Panels, PR2504.402 which Agreement is hereby referred to and made a part hereof as fully and to the same extent as 
if copies at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal faithfully performs and 
fulfills all the undertakings, covenants, terms, conditions and agreements of the Agreement during the original term of 
the Agreement and any extension of the Agreement, with or without notice of the Surety, and during the life of any 
guaranty required under the Agreement, and also performs and fulfills all the undertakings, covenants, terms, 
conditions, and agreements of all duly authorized modifications of the Agreement that may hereafter be made, notice 
of which modifications to the Surety being hereby waived, the above obligation is void.  Otherwise it remains in full force 
and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2, 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions of Title 34, 
Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length in this Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
             AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT D 
 
 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page D-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
PAYMENT BOND 
 
 
ARIZONA STATUTORY PAYMENT BOND 
PURSUANT TO TITLES 28, 34, AND 41, OF THE ARIZONA REVISED STATUTES 
(Penalty of this Bond must be 100% of the Agreement amount) 
 
KNOW ALL MEN BY THESE PRESENTS THAT:________________________________________________  
 
(hereinafter "Principal"), as Principal, and _________________________________________(hereinafter "Surety"), a corporation 
organized and existing under the laws of the State of __________________   with its principal office in the City of 
__________________, holding a certificate of authority to transact surety business in Arizona issued by the Director of the 
Department of Insurance pursuant to Title 20, Chapter 2, Article 1, as Surety, are held and firmly bound unto 
________________________  (hereinafter "Obligee") in the amount of ________________________________________________ 
(Dollars) ($___________), for the payment whereof, the Principal and Surety bind themselves, and their heirs, 
administrators, executors, successors and assigns, jointly and severally, firmly by these presents. 
 
WHEREAS, the Principal has entered into a certain written Agreement with the Obligee, dated the _________ day of 
_______________________, 20___ for construction of Veterans Memorial Phase 3 Recognition Panels, PR2504.402 which 
Amendment is hereby referred to and made a part hereof as fully and to the same extent as if copied at length herein. 
 
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the Principal promptly pays all moneys 
due to all persons supplying labor or materials to the Principal or the Principal's subcontractors in the prosecution of 
the work provided for in said Agreement, this obligation is void. Otherwise it remains in full force and effect. 
 
PROVIDED, HOWEVER that this bond is executed pursuant to the provisions of Title 34, Chapter 2, Article 2 
Arizona Revised Statutes, and all liabilities on this bond will be determined in accordance with the provisions, conditions 
and limitations of Title 34, Chapter 2, Article 2, Arizona Revised Statutes, to the same extent as if it were copied at length 
in this Agreement. 
 
The prevailing party in a suit on this bond may recover as part of the judgment reasonable attorney fees that 
may be fixed by a judge of the court. 
 
Witness our hands this ________________ day of ____________________, 20__. 
____________________________________ 
PRINCIPAL         
 
SEAL 
___________________________________ 
                 AGENT OF RECORD 
By _________________________________ 
____________________________________ 
SURETY  
 
SEAL 
___________________________________ 
                  AGENT ADDRESS 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT E 
 
 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page E-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
CONTRACTOR'S AFFIDAVIT REGARDING SETTLEMENT OF CLAIMS 
 
________________________, Arizona 
 
Date ____________________________ 
Project: 
VETERANS MEMORIAL PHASE 3 RECOGNITION PANELS   
Project No.: PR2504.402 
 
To the City of Chandler, Arizona 
Gentlemen: 
This is to certify that all lawful claims for materials, rental of equipment and labor used in 
connection with the construction of the above project, whether by subcontractor or claimant in 
person, have been duly discharged. 
 
The undersigned, for the consideration of $________________________, as set out in the final pay 
estimate, as full and complete payment under the terms of the Agreement, hereby waives and 
relinquishes any and all further claims or right of lien under, in connection with, or as a result of 
the above described project.  The undersigned further agrees to indemnify and save harmless 
the City of Chandler against any and all liens, claims or liens, suits, actions, damages, charges 
and expenses whatsoever, which said City may suffer arising out of the failure of the 
undersigned to pay for all labor performances and materials furnished for the performance of 
said installation. 
 
Signed and dated at ________________, this _________ day of _______________ 20_____. 
 
 
__________________________________ 
                       CONTRACTOR 
 
By _______________________________ 
STATE OF ARIZONA  
) 
) SS 
COUNTY OF MARICOPA 
) 
 
The foregoing instrument was subscribed and sworn to before me this __________ day of 
__________________ 20 _________. 
___________________________________ 
 
 
 
 
 
Notary Public 
___________________________________ 
 
 
 
 
 
My Commission Expires
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT F 
 
 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page F-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
CERTIFICATE OF COMPLETION 
Project: 
VETERANS MEMORIAL PHASE 3 RECOGNITION PANELS   
Project No.: PR2504.402 
(TO BE COMPLETED BY CONTRACTOR) 
 
I HEREBY CERTIFY THAT ALL GOODS AND/OR SERVICES REQUIRED BY CITY OF CHANDLER PROJECT NO. 
PR2504.402 HAVE BEEN DELIVERED IN ACCORDANCE WITH THE AGREEMENT DOCUMENTS AND BID 
SPECIFICATIONS AND ALL ACTIVITIES REQUIRED BY THE CONTRACTOR UNDER THE AGREEMENT HAVE BEEN 
COMPLETED AS OF ____________________________. 
 
 
(Date) 
 
FIRM NAME: 
________________________________ 
 
PRINCIPAL: 
________________________________ 
         (Name) 
 
________________________________ 
      (Signature) 
 
________________________________ DATE: ___________________ 
          (Title) 
 
CERTIFIED BY ENGINEER/CONSULTANT (IF APPLICABLE): 
 
_________________________________ 
 
DATE: ____________________ 
      (Signature) 
 
_________________________________ 
 
        (Firm Name) 
  
PROJECT ACCEPTED BY USER DEPARTMENT 
 
_________________________________ 
 
DATE: ____________________ 
         (Signature) 
 
_________________________________ 
 
          (Dept. /Div.) 
 
_______________ Date of Final Walk-Through 
 
_______________ Date As-Built Received 
 
_______________ City As-Built Number 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT G 
 
 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page G-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
SUBCONTRACTOR DOCUMENTS WITH JOC CONTRACTOR 
 
Any subcontractor assumptions, clarifications, exclusions, terms & conditions, 
signature blocks, etc. included are strictly between the JOC Contractor and their 
subcontractors, and do not apply to the Agreement between the JOC Contractor and 
the City. 
 
N/A 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123

EXHIBIT H 
 
 
 
Project Name: Veterans Memorial Phase 3 Recognition Panels 
Page H-1 
Project No.:PR2504.402 
Rev. 3/19/2024 
 
BUILDERS RISK INSURANCE 
 
 
 
Docusign Envelope ID: 37E619E5-C1F4-4012-B2E1-D00857A94123