Chandler Blvd: Price Rd to Dobson Rd Improvements
Project No. ST2604
Transportation Commission
September 17, 2025
1

Project Limits
2
Project Purpose
•
Repave Chandler Boulevard
o Pavement Quality Index
o Price Road to Dobson Road
o Address American with Disabilities 
Act (ADA)
o Sidewalks, curb ramps and 
driveways
Project Activities
•
Road Safety Assessment (RSA)
o
Evaluate Previous ADA 
Assessment
•
Design and Construction

Project Funding and Timeline
3
Frye Road from Paseo Trail to San Marcos Park (2.5 miles)
•
Maricopa Association of Governments (MAG) Prop 479
o
Arterial Rehabilitation & Reconstruction Program (ARRP/Federal Funding)

FFY2026 – $182K (plus local matching - $78K) = $260,000 for Design

FFY2027 - $4,246,060 (plus local matching - $1,819,740) = $6,325,800 for Construction
•
Design
o
Anticipated Start - January 2026
•
Construction
o Anticipated Start – 2027
o End - 2028

Road Safety Assessment (RSA)
4
• Perform an RSA
• Based on Funding – Implement RSA Recommendations
Price Rd/ 
Loop 101
Chandler Blvd
Dobson Rd

Planned Public Outreach
5
•
Develop Project Info Website
•
Outreach to Nearby & Adjacent residents/Businesses
•
Website setup to accept comments
•
Potential return to Commission after Public Outreach

Questions and Comments