Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev. 2/28/2025 
 
 Page 1 
 
 
AMENDMENT NO. 1 TO  
PRE-CONSTRUCTION SERVICES AGREEMENT 
 
WATER SYSTEM UPGRADES PROGRAM 
PROJECT NO. WA2100.251 
 
Council Date: October 16, 2025 
 
THIS AMENDMENT NO. 1 (“Amendment No. 1”) to the professional services agreement 
dated November 26, 2024, (the “Agreement”) is made by and between the City of Chandler, 
an Arizona municipal corporation, (“City”) and Archer Western Construction, LLC, an Illinois 
company, (“Consultant”), on this ______ day of ___________________, 2025, (“Effective Date” by 
Clerk).  (City and Consultant may individually be referred to as “Party” and collectively 
referred to as “Parties”). 
 
RECITALS 
 
A. 
The Parties entered into the Agreement for pre-construction services (“Services”) for 
the Water System Upgrades Program project. 
 
B. 
The Parties have determined that it is necessary and desirable for the Consultant to 
perform services for the City under the terms and conditions set forth in this Amendment 
No. 1 and the Agreement. 
 
AGREEMENT 
 
NOW, THEREFORE, in consideration of the premises and mutual promises contained in the 
Agreement and this Amendment No. 1, the Parties agree to amend and modify the 
Agreement as follows. 
 
SECTION I – CONSULTANT’S SERVICES 
 
The Consultant’s Services are modified as described in the Exhibit "A" attached to and 
made part of this amendment by reference.  
 
SECTION II – PERIOD OF SERVICE 
 
The Period of Service is increased by 207 calendar days for a revised total of 626 calendar 
days. 
 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev. 2/28/2025 
 
 Page 2 
SECTION III – PAYMENT OF COMPENSATION AND FEES 
 
The Fees are increased by $356,673 and will be payable in accordance with Exhibit "B" 
attached to and made part of this amendment by reference, for a revised total not to exceed 
$1,270,638. 
 
SECTION IV – CONFLICT AMONG DOCUMENTS 
 
The Agreement, this Amendment No. 1, and any previous amendments constitute the 
complete agreement between the Parties concerning the subject matter of the Agreement 
and replace any prior oral or written communications between the Parties.  If a conflict or 
ambiguity arises between the Agreement and this Amendment No. 1, the instrument in the 
following order prevails and controls: (1) this Amendment No. 1; (2) any previous 
amendments from most recent to oldest; and (3) the Agreement. 
 
 
 
 
 
SIGNATURE PAGE TO FOLLOW 
 
 
 
 
 
 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Name: Water System Upgrades Program – Amendment No. 1 
Project No.: WA2100.251
Rev. 2/28/2025 
 Page 3 
IN WITNESS WHEREOF, the Parties hereto have caused this Amendment No. 1 to be duly 
executed.  Each Party warrants and represents that its respective signatories whose 
signatures appear below have been and are on the date of signature duly authorized to 
execute this Amendment No. 1. 
“CITY”  
CITY OF CHANDLER 
Mayor 
RECOMMENDED BY: 
Daniel Haskins, P.E. 
CIP City Engineer   
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
City Clerk 
Seal 
“CONSULTANT” 
ARCHER WESTERN CONSTRUCTION, LLC 
Signature
Date 
Print Name 
Title 
Signer Email Address 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354
Kyle Ledbetter
September 17, 2025
Program Manager
kledbetter@walshgroup.com
September 18, 2025

Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev. 2/28/2025 
 
 Page 4 
 
AMENDMENT NO. 1 (cont.) 
PROJECT:  WA2100.251 
PROJECT NO.: Water System Upgrades Program
 
These changes result in the following adjustments of Agreement amount and/or time: 
 
Amendment authorized by Owner name: Gina Ishida-Raybourn Date: 9/3/2025 
Consultant Contact Name: Kyle Ledbetter                         email:  kledbetter@walshgroup.com 
Original Agreement amount: 
$913,965 
Previous Amendment(s) total: 
N/A 
Last Agreement amount approved by Council: 
$913,965 
This Amendment: 
$356,673 
This Amendment + previous Amendment(s) not approved by 
Council total: 
$356,673 
Revised Agreement total: 
$1,270,638 
Council Approval Required (yes indicates approval required) 
Yes 
No 
Amendment(s) total over $100,000: 
☒ 
☐ 
Amendment(s) total causes Agreement to exceed $100,000:  
☒ 
☐ 
Agreement Time 
Notice to Proceed (NTP) date for Original Agreement: 
11/26/2024 
Agreement time prior to this Amendment                            
(including previous  amendments): 
419 
Calendar Days 
Net change resulting from this Amendment: 
207 
Calendar Days 
Revised Agreement time (including this Amendment): 
626 
Calendar Days 
Council Approval (if applicable) 
Council Approval Date:    10/16/2025 
 
cc:  Project Manager, Consultant, Owner, File 
 
 
 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev 2/28/2025 
 
Page A-1 
EXHIBIT A 
SCOPE OF WORK 
 
 
 
 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

July 31, 2025 
 
Gina Ishida-Raybourn, PE 
Utilities Engineering Manager 
Public Works & Utilities | Utilities Administration 
City of Chandler 
 
Re:  
CM@Risk Preconstruction Services Proposal – Amendment #1 
Project WA2100.251 Pecos Surface Water Treatment Plant Improvements 
 
Archer Western Construction, LLC (Archer Western) appreciates the continued opportunity to 
collaborate with the City of Chandler (City) Public Works & Utilities Department and its selected design 
team (Hazen) during the design phase of the Pecos Surface Water Treatment Plant (WTP) Improvement 
project. In this proposal to amendment the existing preconstruction services contract, we have prepared 
a detailed scope of work (Attachment 1) and schedule of values (Attachment 2) for your final review and 
approval.  
 
Based on the current schedule established with City and Hazen staff, we are assuming an additional 6-
month preconstruction services duration commencing in January 2026. We have used Exhibit A 
CM@Risk Pre-Construction Services Scope of Work document and Archer Western’s past experience to 
develop the requirements and corresponding schedule of values.  
 
Archer Western will continue to invoice monthly with back-up information provided as described in the 
scope of work. Allowances will only be used upon written approval from the City.  
 
We are looking forward to continue providing exceptional preconstruction services to ensure the City 
and Hazen are provided with the greatest value for the Pecos WTP and ongoing operations. 
 
In your review, please let us know if you have any questions/comments or if you need additional 
information to complete the review.  
 
Respectfully, 
 
 
Nathan Antonneau, P.E. 
 
 
 
 
 
Kyle Ledbetter 
Preconstruction Manager 
 
 
 
 
 
Project Director 
 
Attachment 1: Preconstruction Services Scope of Work 
Attachment 2: Preconstruction Services Schedule of Values 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

TABLE OF CONTENTS 
 
OVERVIEW ..................................................................................................................................................... 1 
ASSUMPTIONS .............................................................................................................................................. 1 
PROPOSED PRECONSTRUCTION MANAGEMENT TEAM ............................................................................... 1 
PRECONSTRUCTION SERVICES SCOPE OF WORK .......................................................................................... 2 
17.2 – GENERAL ........................................................................................................................................ 2 
17.3 - DETAILED PROJECT SCHEDULE ........................................................................................................ 3 
17.4 – DESIGN DOCUMENT REVIEWS ....................................................................................................... 3 
17.5 – BASELINE COSTS MODEL, DETAIL COST ESTIMATE, SCHEDULE OF VALUES .................................. 5 
17.6 – SUBCONTRACTOR AND MAJOR SUPPLIER SELECTIONS ................................................................. 6 
17.7 – GMP PROPOSAL ............................................................................................................................. 6 
17.8 – PAYMENT PROCEDURE FOR PRE-CONSTRUCTION SERVICES......................................................... 7 
ALLOWANCE ITEMS ................................................................................................................................... 7 
 
ATTACHMENTS 
1. PRECONSTRUCTION SERVICES SCOPE OF WORK 
2. SCHEDULE OF VALUES
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

ATTACHMENT 1 
 
PRECONSTRUCTION SERVICES 
SCOPE OF WORK 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 1 
OVERVIEW 
The scope of work (SOW) description follows Section 17 of the General Conditions and corresponds with 
the schedule of values (SOV).  
ASSUMPTIONS 
Archer Western is assuming the following for the development of the Schedule of Values: 
• 
The initial preconstruction phase is anticipated to be November 2024 through December 2025. 
• 
The amended preconstruction services phase is anticipated to be January 2026 through June 
2026. 
• 
The SOV includes preconstruction activities that include design from 60% through 100% (final 
design) as requested by the City.  
• 
Pricing has been put together based the initial phase for preconstruction services. 
• 
Ozone will not be part of the project and Chlorine dioxide may be used as a pre-oxidant. 
• 
Autodesk Construction Cloud (ACC) will be used for collaboration with team members. It is 
assumed that the Hazen Revit files will be made available to the CM@Risk at least on a weekly 
basis (preferably more frequently). 
• 
Submittals will be electronically transmitted.  
• 
Meeting attendance will have both virtual and in person option. 
PROPOSED PRECONSTRUCTION MANAGEMENT TEAM 
The following personnel are assigned to the preconstruction services team. 
• 
Project Director: Kyle Ledbetter 
• 
Preconstruction Manager: Nathan Antonneau 
• 
Constructability Manager: Doug Post 
• 
Superintendent: Jimmy Foster 
• 
Felix Electric Preconstruction Manager: Jason Lipsky 
• 
Felix Electric Technical Advisor: Brad Fransen 
• 
Chief Estimator: Ali Minerva 
• 
AWC Estimators: Tony Jannero, Jonas Vikander, Jacob Roberson, David Songer 
• 
Felix Electric Estimator: Zach Watts 
• 
BIM Modeling: Brent Bieske 
• 
Preconstruction Admin: Kristine Aldrin 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 2 
PRECONSTRUCTION SERVICES SCOPE OF WORK 
17.2 – GENERAL 
17.2.3. Meetings & Workshops 
17.2.3.A Project Kick-off / Chartering Meeting 
Not applicable. 
17.2.3.B Project Progress Meetings 
Description: Archer Western and Felix Electric staff will attend Project Progress meetings for the 
duration of the preconstruction phase to coordinate design tasks with the City and Hazen. Archer 
Western and Felix Electric Staff will attend and participate, as may be appropriate, in meetings related 
to the following: 
Assumptions:  Monthly meetings with an expected duration of 1-hour and will be attended virtually via 
Teams.  
17.2.3.B Miscellaneous Project Meetings 
Description: Archer Western and Felix Electric staff will hold internal coordination and review meetings 
throughout the course of design and preconstruction phase. 
17.2.3.C Designer/CM@Risk Coordination Meeting 
Description: Archer Wester and Felix Electric staff will attend project meetings with Designer to review 
design progress, evaluate constructability, discuss schedule updates, and workshop alternate scenarios 
to achieve the desired project budget and schedule goals. 
Assumptions: Bi-weekly meetings with an expected duration of 1-hour and will be attended virtually via 
teams.  
17.2.3.D Owner/CM@Risk Coordination Check-In 
Description: Archer Western will attend bi-weekly check-in with Owner and Program Manager/Designer 
to flush out any outstanding or upcoming financial and non-financial tasks.  
Assumptions: Bi-weekly meetings with an expected during of 30 minutes and will be attended virtually 
via teams. 
17.2.3.E GMP Review/Negotiation Meetings 
Description: Archer Western and Felix Electric staff will participate in meetings with City and Hazen to 
review the GMP after submission. 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 3 
Assumptions: It is assumed there will be one (1) resolution meeting for GMP-3. 
17.3 - DETAILED PROJECT SCHEDULE 
17.3.2.A Develop Preliminary Construction Schedule & Phasing Plans 
Not applicable. 
17.3.2.B Develop Baseline Construction Schedule 
Description: Archer Western and Felix Electric will develop a preconstruction deliverable schedule, 
preliminary construction schedule and phasing plan for the overall project in association with the 
baseline cost model and proposed construction activities and the remainder of the construction phase.  
Assumptions: A P6 schedule will be provided for items included in each GMP. The full baseline 
construction schedule will be included in the amendment for delivery of the project’s baseline schedule 
at the final GMP.  
Deliverable: A pdf copy and .xer file of the schedule will be provided at each GMP. The baseline 
construction schedule will be finalized after the construction contract award. 
17.3.5 Long Lead Analysis and Recommendations 
Not applicable. 
17.3.6 Equipment Plan 
Not applicable. 
17.4 – DESIGN DOCUMENT REVIEWS 
17.4.4 Constructability/Biddability Analysis 
Description: In review of the drawings, specifications, and other relevant design information, Archer 
Western will identify opportunities to improve the constructability of the work elements. Archer 
Western will also engage subcontractors, suppliers, and process equipment manufacturers to assess the 
biddability of work packages. Information gathered will be presented in a meeting and/or workshop 
setting.   
Assumptions:  Bluebeam Revu and/or ACC will be used for constructability reviews.  
Deliverable:  In advance of the meetings/workshops, Archer Western will prepare the 
constructability/biddability agenda information and submit to the City. Any subsequent documentation 
developed from the meeting/workshop action items will be submitted to Pecos SWTP. 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 4 
17.4.4.2 Document Complementary Review and Cross Checks 
Description: Archer Western will perform reviews and provide written comments regarding the bid-
ability of the Project. Archer Western will check cross-references and complementary Drawings and 
sections within the specifications per GC section 17.4.4.2.  
Assumptions: Bluebeam Revu and/or ACC will be used for comments and RFIs 
17.4.6 Value Analysis & Alternate Approach Evaluation & Meetings/Workshops 
Description: Throughout the course of design, Archer Western will identify opportunities to enhance 
value to the City through alternate strategies. Alternate strategies may be construction means and 
methods, alternative materials or equipment that perform the same function, or scope evaluation with 
respect to project priorities. Archer Western will also consider operating costs and maintainability 
features of the work elements in the evaluation.  
Deliverable:  Archer Western will submit a Value Analysis & Alternate Strategies Summary at 90% and 
host a meeting/workshop to review submitted information. 
17.4.7 Utility/Site Investigations 
Not applicable. 
17.4.8 Site Utilization Plan 
Not applicable. 
17.4.9 Utility Design Review and Comment 
Not applicable. 
17.4.10 Maintenance of Plant Operations (MOPOs) 
Description: Archer Western and Felix Electric will continue to evaluate scope and design for tasks that 
have the potential to affect plant operations; lead development of planning to minimize or eliminate 
disruption to Owner's facilities. This may require a plant visit to discuss options with WTP plant staff to 
understand operational constraints. 
Deliverable: Archer Western will submit a revised MOPO plan.  
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 5 
17.5 – BASELINE COSTS MODEL, DETAIL COST ESTIMATE, SCHEDULE OF VALUES 
17.5.2 Cost Model Reports (Baseline-30-60-90) 
17.5.2.A Baseline Cost Model 
Not applicable. 
17.5.2.B Cost Model (30% Design) 
Not applicable. 
17.5.2.C Cost Model (60% Design) 
Not applicable. 
17.5.2.D Cost Model (90% Design) 
Description: Upon receipt of acceptable 90% drawings and specifications, Archer Western will review all 
available information regarding the design and scope of the Project using Archer Western’s experience 
in performing similar work, knowledge of similar projects and current and projected construction costs 
and, based upon that review, must update the Cost Model for review by the Project Team and approval 
by City. 
Deliverable:  90% cost model report, both hard copy and electronic copy. 
17.5.2.E Continuous Cost Model/Estimate Updates (Design Evolution Log) 
Description: Archer Western will track, estimate/price, and address the Project Team’s overall project 
cost issues that arise outside of the Baseline Cost Model and the latest approved Detailed Cost Estimate 
such as: City generated changes, Project Team proposed changes, alternate system analysis, 
constructability items and value engineering analysis. 
Deliverable: Archer Wester will create and update a design evolution log at 90% cost model comparing 
to 60% cost model. 
17.5.4 Schedule of Values 
Description: For each GMP, Archer Western will prepare and submit a Schedule of Values for review by 
the Project Team and approval by City. The Schedule of Values will be developed and submitted 
following the approved GMP but prior to the commencement of construction activities. 
Assumptions:  SOV will be based on AIA Document G703.  
Deliverable:  Schedule of Values for each GMP proposal. 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 6 
17.6 – SUBCONTRACTOR AND MAJOR SUPPLIER SELECTIONS  
17.6.1. Subcontractors 
17.6.1.A Procurement Prequalifications & Subcontractor Prequalifications 
Description: Archer Western will evaluate potential suppliers and subcontractors with respect to safety, 
financial capacity, ability to meet/exceed schedule, and quality to obtain adequate pool of acceptable 
bidders. 
Assumption: Included in early preconstruction scope is prequalification of long lead vendors and 
manufacturers. Additional time is added for GMP3 subcontractors, vendors and manufacturer’s scopes. 
Deliverable: Archer Western will submit a Prequalification List. 
17.6.1.B Subcontractor Selection Plan  
Not applicable. 
17.6.2 Subcontractor Bid Evaluation/Reports 
Description: Archer Western will prepare and submit a detailed list of recommended subcontractors and 
summary report of the entire selection process. 
Deliverable: Archer Western will submit bid comparison sheets with each GMP. 
17.6.7 Pre-bid Conference  
Not applicable. 
17.7 – GMP PROPOSAL  
17.7.5.A Early Equipment/Early GMP Preparations 
Not applicable. 
17.7.5.B GMP Preparation and Submission  
Description: Archer Western and Felix Electric will prepare and submit the GMP Proposal in accordance 
with City’s request for GMP Proposal requirements based on the most current completed Drawings and 
Specifications at that time, which unless otherwise directed by City in writing, will be at 100% 
Construction Drawings.   
Deliverable: Archer Western will submit GMP3which will include the scope of work, cost model, CPM 
schedule, assumptions / clarifications, risk register, subcontractor / material quotations, and other 
supporting information. 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

CM@Risk Preconstruction Services Scope of Work 
Pecos Surface Water Treatment Plant Improvements 
Project WA2100.251 
 
 
Page | 7 
17.8 – PAYMENT PROCEDURE FOR PRE-CONSTRUCTION SERVICES  
17.8.1 Monthly Progress Reports/Request for Payment  
Description: Archer Western will prepare and submit a monthly request for payment accompanied by a 
progress report, detailed invoices and receipts, if applicable. 
Deliverable: Archer Western will submit monthly invoices with appropriate back-up information. 
ALLOWANCE ITEMS 
A.1 Topographic Survey 
Not applicable. 
A.2 Site Utility Investigations (Potholing) 
Not applicable. 
A.3 Order Long Lead Items 
Description: An allowance to be used to order materials for long lead items, including streetlights, 
heads, and traffic poles (as directed by City).  Archer does not anticipate any long lead procurement 
outside of GMP long lead items. An allowance is being carried in the event the City wants to purchase an 
item quickly. 
Deliverable: As necessary, Archer Western will submit a written request to the City with the cost 
estimate and applicable back-up information for approval.  
A.4 Owner's Allowance (Contingency) 
Description: This allowance is for out-of-scope requests by the City. In the schedule of values, it is an 
assumed value as 10% of the scope of work value.  
Deliverable: As necessary, Archer Western will submit a written request to the City with the cost 
estimate and applicable back-up information for approval. 
A.5 Subcontractor Consulting Allowance 
Not applicable. 
A.6 Cash Flow Projections 
Not applicable. 
 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev. 2/28/2025 
 
Page B-1 
EXHIBIT B 
FEE SCHEDULE 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

ATTACHMENT 2 
 
PRECONSTRUCTION SERVICES 
SCHEDULE OF VALUES 
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Director
Precon Manager
Constructability 
Manager
Superintendent
Felix Electric 
Precon Mgr
Felix Technical 
Advisor
Precon Eng
Chief Estimator
AWC Estimators
Felix Electric 
Estimator
BIM Modeling
Precon Admin
RATES
200.00
$              
175.00
$              
175.00
$              
150.00
$              
175.00
$              
175.00
$              
150.00
$              
175.00
$              
150.00
$              
150.00
$              
125.00
$              
100.00
$              
17.2 General
40
64
30
30
34
81
16
25
36
15
12
30
366
$59,775 
17.2.3 Meetings & Workshops (prep, attendance, minutes)
   17.2.3.A. Project Kick-off / Chartering Meeting
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.2.3.B. Project Progress Meetings (monthly - 1 hr/ea)
6
12
6
6
6
6
0
3
0
3
0
6
54
8,925
$                
   17.2.3.B. Miscellaneous Project Meetings (AW only)
12
12
12
12
12
12
12
12
36
6
12
12
162
25,500
$              
17.2.3.C. Designer /AW Coordination Meetings (bi-weekly - 1 hr/ea)
12
24
12
12
12
12
0
6
0
6
0
12
108
17,850
$              
17.2.3.D. Owner /AW Coordination Meetings (bi-weekly - 30 min/ea)
6
12
0
0
0
0
0
0
0
0
0
0
18
3,300
$                
17.2.3.E. GMP Review/Negotionation Meetings
4
4
0
0
4
4
4
4
0
0
0
0
24
4,200
$                
17.3 Detailed Project Schedule
20
8
20
80
16
0
0
0
0
0
0
0
144
$23,700 
17.3.2.A. Preliminary Construction Schedule and Phasing Plan
17.3.2.A.30. Schedule Integration (30% Design)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.3.2.A.60. Schedule Integration (60% Design)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.3.2.B Baseline Construction Schedule
17.3.2.B.1. Schedule Integration (GMP1)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.3.2.B.2. Schedule Integration (GMP2)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.3.2.B.3. Schedule Integration (GMP3)
20
8
20
80
16
0
0
0
0
0
0
0
144
23,700
$              
17.3.5 Long Lead Analysis and Recommendations
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.3.6 Equipment Plan
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.4 Design Document Reviews
28
48
72
56
40
44
0
32
96
24
24
0
460
$75,600 
17.4.4 Constructability/Biddability Analysis
4
8
24
24
8
8
0
0
0
8
24
0
108
17,000
$              
17.4.4.2 Document Complementary Review and Cross Checks
16
16
16
16
16
16
0
16
48
16
0
0
176
29,200
$              
17.4.6 Value Analysis & Alternate Approach Evaluation & Meetings/Workshops (Prep)
4
16
16
0
8
8
0
16
48
0
0
0
116
19,200
$              
17.4.7 Utility/Site Investigations
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.4.8 Site Utilization Plan
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.4.9 Utility Design Review and Comment
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.4.10 Maintenance of Plant Operations
4
8
16
16
8
8
0
0
0
0
0
0
60
10,200
$              
17.5 Baseline Cost Model, Detailed Cost Estimates & Schedule of Values
28
32
24
8
8
0
16
124
320
80
0
4
644
$102,500 
17.5.2 Cost Model Reports (Baseline-30-60-90)
-
$                    
17.5.2.A. Cost Model Reports (Baseline)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.5.2.B. Cost Model Reports (30% Design)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.5.2.C. Cost Model Reports (60% Design)
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.5.2.D. Cost Model Reports (90% Design) 
16
24
24
8
8
0
8
100
320
80
0
4
592
93,300
$              
17.5.2.E. Continuous Cost Model/Estimate Updates (Design Evolution Log)
4
8
0
0
0
0
8
16
0
0
0
0
36
6,200
$                
17.5.4 Schedule of Values
8
0
0
0
0
0
0
8
0
0
0
0
16
3,000
$                
17.6 Subcontractor and Major Supplier Selections
0
16
0
0
8
8
4
24
48
16
0
12
136
$21,200 
17.6.1. Subcontractors
   17.6.1.A Procurement Prequalifications and Subcontractor Prequalifications
0
16
0
0
0
0
4
8
24
8
0
4
64
10,000
$              
   17.6.1.B Subcontractor Selection Plan
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.6.2 Subcontractor Bid Evaluation/Reports
0
0
0
0
8
8
0
16
24
8
0
8
72
11,200
$              
17.6.7 Pre-bid Conference
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
17.7  GMP Proposals
4
16
0
0
4
0
0
16
0
0
0
8
48
$7,900 
GMP Proposal 1 - Filter 9-12 Rehab
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
GMP Proposal 2 - Long Lead Procurement
0
0
0
0
0
0
0
0
0
0
0
0
0
-
$                    
GMP Proposal 3 - Remaining Construction 
4
16
0
0
4
0
0
16
0
0
0
8
48
7,900
$                
17.8 Payment Procedure for Pre-Construction Services
0
24
0
0
12
0
0
0
0
0
0
0
36
$6,300 
Prepare Application for Payment (10 months)
0
24
0
0
12
0
0
0
0
0
0
0
36
6,300
$                
Total Hours & Costs
120
208
146
174
122
133
36
221
500
135
36
54
1,834
296,975
Allowance Expenses
A.1 Topographic Survey
-
$                    
A.2 Site Utility Investigations (Potholing)
-
$                    
A.3 Order Long Lead Items
30,000
$              
A.4 Owner's Allowance (10% of base cost)
29,698
$              
A.5 Subcontractor Consulting Allowance
-
$                    
A.6 Cash Flow Projections
-
$                    
Allowance Expense Totals
59,698
PRECONSTRUCTION SERVICES TOTAL
356,673
CITY OF CHANDLER
PRECONSTRUCTION SERVICES SCHEDULE OF VALUES - AMENDMENT #1
PROJECT WA2204.101 PECOS SWTP FACILITY UPGRADE CMAR SERVICES
DESCRIPTION
LABOR HOURS
Total Hours
Total Cost
Docusign Envelope ID: DDA10ABA-BE0E-4E61-9B8C-810834D6D354

Project Name: Water System Upgrades Program – Amendment No. 1 
 
 
 
 
 
Project No.: WA2100.251 
Rev. 2/28/2025 
 
Page C-1 
EXHIBIT C 
SUBCONSULTANT DOCUMENTS WITH CONSULTANT 
 
Any subconsultant assumptions, clarifications, exclusions, terms & conditions, 
signature blocks, etc. included are strictly between the Consultant and their 
subconsultants, and do not apply to the Agreement between the Consultant and the 
City. 
 
N/A 