Paseo Crossing Improvements

City of Chandler — Regular Meeting (2026-02-18)

View PDF Meeting page

Extracted text (via pymupdf) 1654 characters
City of Chandler Project No.
TP2502.201
Paseo Trail
Crossing
Improvements

•
Along the east side of the Consolidated Canal from
Queen Creek Road and McQueen Road
Project Location
2
Project History
•
2022 MAG Design Assistance Study evaluating
alternatives for crossing improvements along the
Ashley Trail and Paseo Trail
•
2024 City funded the final design of the two Paseo
segments – Chandler Blvd/Cooper Road and
Queen Creek Road/McQueen Road
•
The current project under design focuses on the
Queen Creek Road/McQueen Road segment

3
•
Fills a missing link in the overall
improved Paseo Trail system
promoting safer, continuous
pedestrian and bicycle travel
•
Provides connectivity to trail
systems in Gilbert and Mesa
Need for the Project

4
•
Min. 10-ft wide concrete shared use pathway
•
Paseo Trail branded path lighting
•
Signalized crossing improvements at Queen Creek
Road and McQueen Road
•
Other improvements including wayfinding,
landscape, irrigation, and site amenities
Project Improvements

•
South to west crossing alignment
at the Chandler Airport
Commerce Park
•
Existing traffic signal upgrades
•
Wayfinding and pavement
marking improvements
•
Concrete pathway and curb ramp
improvements
McQueen Road Crossing

Queen Creek Road Crossing
•
South to east crossing alignment
at Airport Blvd
•
Existing traffic signal upgrades
•
Wayfinding and pavement
marking improvements
•
Concrete pathway and curb ramp
improvements
•
Rest node amenity space

7
•
30% submittal 08/29/2025
•
60% submittal 12/16/2025
•
95% target date 03/31/2026
•
R/W / TCE Acquisition
•
Final submittal Summer/Fall 2026
•
Begin construction early 2027
Project Schedule