Construction Report

City of Chandler — Regular Meeting (2026-02-11)

View PDF Meeting page

Extracted text (via pymupdf) 1337 characters
Capital Projects – Design Phase: 
 
West Airport Facilities Upgrade: City funded at $3.9 million.  Revised scope includes operations 
garage, parking lot and aircraft observation area.  Finalizing plan comments. Evaluating utility 
relocation options and new phasing plan. 
 
Airport Fuel Tank Relocation: City funded at $610,000.  Cost negotiation with vendors.  Budget 
transfer under evaluation.  Evaluating alternative methods. 
 
Runway End Identifier Light (REIL) Installation Runway 4L-22R (North Runway): FAA funding 
for $110,000.  Revising drawings for circuit change for 24/7 REILs. FAA confirmed environmental 
clearance. 
 
Capital Projects - Construction Phase: 
 
Hangar Area Pavement Rehabilitation:  Substantially complete.  Water leak under pavement near 
east side of C hangars. 
 
Taxiway B Improvements- Phase 1: ADOT grant for $2,035,000.  Construction start scheduled for 
January 5, 2026. Substantial completion scheduled for 3rd week of February.  Work underway. 
 
Former K&K Site Remediation: City funding for soil remediation near end of Cooper Road north 
of Queen Creek.  5.8 acre restricted use area remaining.  Substantially complete for initial phase.  
Additional excavation needed and starting on January 20th. 
 
Meeting Date:  
February 11, 2026 
Chandler Municipal Airport 
Construction Report