April 2026 Project Status Update List

City of Chandler — Regular Meeting (2026-04-29)

View PDF Meeting page

Extracted text (via pymupdf) 5356 characters
ROADWAY AND TRAFFIC PROJECTS
Designer
Contractor
Status
Comments
PROJECT  
COST  
ESTIMATE 
($MILLIONS)
ST1804 Chandler Heights Road Improv. [Gilbert Road to Val Vista Drive for two  
through lanes each direction]
Kimley-Horn
Sunland Asphalt
Project is in closeout
Federal Funds
$9.80
ST2001 Lindsay Road Improv. [Ocotillo Road to Hunt Highway for two 
through lanes in each direction]
Kimley-Horn
Acehn-Gardner
Bids were opened on November 3, 2025. Construction is tentiate to start late 
February or early March 2026.
Federal Funds
$27.20
ST2007 Hamilton Street Improv. [Appleby Road to Carob Drive]
Nfra Consultants
Redpoint
Project is in closeout
Federal Funds
$5.20
ST2103 Intersection Improv. at Ray Road and Dobson Road
Kimley Horn
tbd
Design is currently at 95%. Project needs ROW, and anticipated  
to go out to bid Fall 2026.
Grant funds & local funds
$11.85
ST2301  Armstrong Way and Hamilton Street Improvement (Improves the south  
half of Armstrong Way and the west half of Hamilton Street)
EPS Group, Inc.
tbd
Design underway.  Construction tentatively scheduled Spring  
2026.
Local Funds
$2.00
ST2303 Cooper Road - Insight Loop Extension (Connects Cooper Road to Insight  
Way & Emmett Dr intersection)
Aztec
tbd
Design is currently at 90%.  Project needs ROW, and anticipates  
going out to bid Summer 2026.
Local Funds
$9.30
ST2309 Alma School Road Germann Rd to Queen Creek Rd (widening Alma School  
Road from Germann Road to Queen Creek Road)
Olsson Associates
tbd
Design is currently at 90%.  Construction tentatively scheduled  
for bid early 2026.
Local Funds
$11.30
ST2310 Alley Rehab PM10 Dust Emissions Reduction Phase 3 (FMA Areas 6, 24, 26,  
27)
Premier / Olsson
tbd
Design is at 100%. City to obligate soon and go out to bid.  
Federally Funded
$3.50
ST2403 McQueen Road Improvements - Warner Road to Pecos Road Study  
(Study to widen McQueen Road in three phases from Warner Road to Pecos Road)
Kimley-Horn and  
Associates
NA
Design Study is closed out.  Design of Phase 1 to start Fiscal Year 27-28.
Study is Locally Funded, Project will be Federally Funded and  
Design starts in FY 27-28
$84.00
ST2503 Kyrene Road Improvements - (Loop 202 to Chandler Blvd) (Widening  
Kyrene Road from the Loop 202 Santan to Chandler Blvd including the intersection)
Kimley-Horn and  
Associates
tbd
Project is currently in design.
Federal Funds (RARF ALCP)
$45.00
ST2504 Arizona Avenue and Warner Road Intersection Improvement
tbd
tbd
Preparing for Design phase
Local Funds
$1.50
ST2603 Warner Road (Price Rd to Arizona Avenue) Study (Study to widen Warner  
Road in three phases from Price Road to Arizona Avenue)
tbd
NA
Design study only
Local Funds
$14.00
ST2604 Chandler Boulevard Roadway Improvements (Price Road to Dobson  
Road) - Mill and Overlay
tbd
tbd
Preparing for Design phase
Federal Funded
$6.30
ST2404 Willis Rd Improvement (Vine St to 1600 ft east)
Strand
tbd
Design is at 95%.  Project needs ROW, anticipated to go out to  
bid Summer 2026.
Local Funds
$3.00
PR2106 Ryan Rd Improvements (RR xing to McQueen Rd) - Tumbleweed Park  
Diamond Field Complex
Huitt-Zollars
Hunter
Design is approaching 60%.  GMP3 will include roadway  
construction anticipated for Summer 2026.
Local Funds
$6.00
ST2405 Turf to Xeriscape Program Phase I (Various Locations)
J2 Engineering
ELT
Construction is underway.
WIFA Grant and Local Funds
$4.60
PEDESTRIAN, BICYCLE, AND TRANSIT PROJECTS
Designer
Contractor
Status
Comments
PROJECT  
COST  
ESTIMATE
ST2106 Frye Road Protected Bike Lanes [Paseo Trail to San Marcos 
Elementary School]
TY Lin
Granite Construction Co
Construction underway.  Completion anticipated in Fall 2026.
$13.5 Million grant awarded for construction and $650,000 for  
design.
$14.00
TP2202  Kyrene Branch and Highline Canal Shared Use Paths
Kimley-Horn
tbd
Design and Right-of-Way complete.  Construction in mid-late 2026.
Federal grants have been awarded to fund study, design and  
construction.
$4.50
Ashley and Paseo Trails Connection
Y2K Engineering
tbd
Study and design completed by Y2K.  Construction in mid 2026.
Study was federally funded.  Construction and design are  
locally funded.
$1.00
Paseo Trail Riggs Road Crossing
Kimley Horn
tbd
Study to develop preliminary design for a Paseo Trail crossing of  
Riggs Road and construction of the path between Riggs Road  
and Hunt Highway.  
Awarded $60,000 federal grant for study.
$0.06
Jacaranda Protected Bike Lanes
Burgess & Niple
tbd
Design underway.  Public outreach underway.
Locally funded project will add low-cost, quick-build protected bike lanes to 
approximately 4 miles of bike lanes on Jacaranda Parkway.
$0.40 
Roadway Safety Action Plan
tbd
tbd
Comprehensive study to analyze safety for all road users and  
develop recommentations.
Awarded $560,000 Safe Streets for All grant to complete study  
(with 20% local match).  Design contract award anticipated May 2026, with the 
12- to 18-month study beginning shortly after.
$0.70
Chandler Flex
NA
Via
Waymo partnership began Septenber 2025.  Passengers may be able to take a trip 
on Waymo when Chandler Flex is at full capacity and cannot provide a requested 
trip.
Awarded $2 Million grant for project startup and two years of  
operations.  Awarded $1 Million congressionally-directed  
spending grant to continue operations.
$1.4 Annually
Transportation Project Status - April 2026