Project Name: Water System Upgrades Program – Change Order No. 1 
 
Project No.: WA2100.402 
Rev. 12/03/2025 
 
Page  1 
 
 
This Change Order No. 1 (“Change Order No. 1”) to the construction services agreement is made by and 
between the City of Chandler (“City”), and Archer Western Construction, LLC, an Illinois company (“CM@Risk”), 
on this ________ day of ___________________, 2026 (“Effective Date” by Clerk).   
Change Order not valid until signed by both the City and the CM@Risk.  CM@Risk’s signature indicates 
Agreement herewith, including any adjustments in the Agreement Price or Agreement Time.   
Project Name: 
Water System Upgrades Program 
Project No.: 
WA2100.402 
User Dept: 
Public Works & Utilities 
NTP Date:  11/12/2025 
 
TO: 
Archer Western Construction, LLC 
 
4710 East Elwood Street, Suite 6, Phoenix, AZ 85040 
 
(CM@Risk) 
 
(Mailing Address) 
 
Daniel P Walsh 
 
dpwalsh@walshgroup.com 
 
(Company Representative) 
 
(Email Address) 
CM@Risk must make the following changes to this Agreement: 
 (Detail scope change (Exh. A) / cost breakdown (Exh. B), if needed) 
• 
Exhibit A and Exhibit B provide the detailed scope and cost for the balance of design work.   
• 
Cyber Technology Liability Insurance applies to the work in this change order, see Exhibit C.  
• 
Milestone 1 – Substantial Completion of Dewatering Facility – January 28, 2028 
• 
Milestone 2 -Project Substantial Completion – August 17, 2028 
Amendment authorized by Owner Name: 
Daniel P Walsh 
Date: 
5/11/2026 
Original Agreement amount: 
$12,909,632.07 
Previous Change Order total: 
$0 
Last Agreement amount approved by Council: 
$12,909,632.07 
This Change Order: 
$127,842,397.94 
This Change Order + previous Change Order(s) not approved by Council total: 
$127,842,397.94 
Revised Agreement total: 
$140,752,030.01 
Council Approval Required (yes indicates approval required) 
YES 
NO 
Change Order(s) total over $100,000: 
☒ 
☐ 
Change Order(s) total causes Agreement to exceed $100,000:  
☒ 
☐ 
Agreement Time 
Agreement time prior to this Change Order (including previous change order(s): 
 
658 
 
Calendar Days 
Net change resulting from this Change Order: 
 
436 
 
Calendar Days 
Revised Agreement time (including this Change Order): 
 
1,094 
 
Calendar Days 
Council Approval (if applicable) 
Council Approval Date:  6/25/2026 
 
PROJECT NO.:  
WA2100.402 
CHANGE ORDER NO.: 
1 
DATE:  
5/20/2026 
 
 
Docusign Envelope ID: 748D8D37-CDBF-8BC0-803D-6A0A28177691

Project Name: Water System Upgrades Program – Change Order No. 1 
Project No.: WA2100.402 
Rev. 12/03/2025 
Page  2 
THE ABOVE IS AGREED TO BY: 
“CITY”  
CITY OF CHANDLER 
“CM@RISK” 
ARCHER WESTERN CONSTRUCTION, LLC 
Mayor 
Signature 
 Date 
RECOMMENDED BY: 
Print Name 
Daniel Haskins, P.E. 
Title 
Signer Email Address 
APPROVED AS TO FORM: 
City Attorney 
ATTEST: 
City Clerk 
Seal 
Docusign Envelope ID: 748D8D37-CDBF-8BC0-803D-6A0A28177691
President
June 1, 2026
Daniel P Walsh
dpwalsh@walshgroup.com
June 1, 2026

Project Name: Water System Upgrades Program - Change Order No. 1  
Project No.:  WA2100.402  
Rev 12/03/2025 
Page A&B-1 
EXHIBIT A 
SCOPE OF WORK 
&
EXHIBIT B
FEE SCHEDULE

EXHIBIT A 
SCOPE OF WORK 
       (Additional Backup Available upon Request)

SECTION B
PROJECT DESCRIPTION

1. 
PROJECT DESCRIPTION 
The Pecos Surface Water Treatment Plant (PSWTP) Improvement Project will provide both pre-
construction and construction services to implement a series of upgrades to the facility’s liquid and solid 
treatment processes. These improvements are designed to enhance water quality, operational 
efficiency, and long-term reliability throughout the City of Chandler’s (City) water system.  
Hazen and Sawyer (Hazen) have used the City naming conventions to standardize the work breakdown 
structure as summarized below: 
1.1 Work Breakdown Structure 
A Work Breakdown Structure (WBS) was developed for this estimate to organize the cost data based on 
distinct attributes that can be filtered and sorted for the purpose of generating specific subtotals.  The 
WBS values for this estimate consist of work area and work package which are largely derived from CSI 
division codes. 
 
Facility ID 
Facility Name 
Work Packages 
01
Site Work
02-Demolition
03-Concrete 
04-Masonry 
05-Misc Metals 
09-Paint & Coatings 
26-EI&C 
31-Erosion Control 
31-Earthwork 
32-Paving, Curb & Gutters 
33-Fiber Optic 
33-Utilities 
40-Process Pipe & Valves 
10
Seal Weir Structure
03-Concrete
05-Misc Metals 
06-FRP Materials 
09-Paint & Coatings 
22-Plumbing & HVAC 
26-EI&C 
31-Earthwork 
40-Process Pipe & Valves 
43/46-Process Equipment 
30
Existing Raw Water Pump 
Station 1 
09-Paint & Coatings
40-Process Pipe & Valves 
35
Existing Raw Water Pump 
Station 2 
09-Paint & Coatings
40-Process Pipe & Valves 
42
GAC Pump Station
03-Concrete
05-Misc Metals 
09-Paint & Coatings

Facility ID 
Facility Name 
Work Packages 
40-Process Pipe & Valves
43/46-Process Equipment 
43
Post-Filter GAC Contactors
03-Concrete
05-Misc Metals 
06-FRP Materials 
08-Doors & Windows 
09-Paint & Coatings 
13-Special Construction 
22-Plumbing & HVAC 
26-EI&C 
31-Earthwork 
40-Process Pipe & Valves 
43/46-Process Equipment 
43E
Post Filter GAC Electrical 
Building 
03-Concrete
04-Masonry 
05-Misc Metals 
07-Roofing 
08-Doors & Windows 
09-Paint & Coatings 
13-Special Construction 
21-Fire Suppression 
22-Plumbing & HVAC 
26-EI&C 
31-Earthwork 
45
Filtered Water Reservoirs
03-Concrete
09-Paint & Coatings 
31-Earthwork 
40-Process Pipe & Valves 
50
Finished Water Pump Station
09-Paint & Coatings
40-Process Pipe & Valves 
65
Equalization Basins
03-Concrete
09-Paint & Coatings 
26-EI&C 
40-Process Pipe & Valves 
43/46-Process Equipment 
75
Dewatering Facility
03-Concrete
04-Masonry 
05-Misc Metals 
06-FRP Materials 
07-Roofing 
08-Doors & Windows 
09-Paint & Coatings 
13-Special Construction 
21-Fire Suppression 
22-Plumbing & HVAC 
26-EI&C

Facility ID 
Facility Name 
Work Packages 
31-Earthwork
40-Process Pipe & Valves 
43/46-Process Equipment 
86
Chlorine Dioxide Facility
03-Concrete
04-Masonry 
05-Misc Metals 
06-FRP Materials 
07-Roofing 
08-Doors & Windows 
09-Paint & Coatings 
13-Special Construction 
21-Fire Suppression 
22-Plumbing & HVAC 
26-EI&C 
31-Earthwork 
40-Process Pipe & Valves 
43/46-Process Equipment 
87
Post Treatment Chemical 
Facility 
09-Paint & Coatings
26-EI&C 
40-Process Pipe & Valves 
43/46-Process Equipment 
90
Disinfection Building
09-Paint & Coatings
40-Process Pipe & Valves 
95
Admin Building (Lab)
09-Paint & Coatings
40-Process Pipe & Valves 
99
Construction Manager General 
Conditions 
26-EI&C 
97-Site Wide Equipment 
99-GC/GR 
 
Archer Western is delivering the project components in three phases. Each phase is described below: 
1.2 Work completed in GMP-1 (COC Contract WA2100.401): 
Work completed under a separate contract, the GMP-1 included the following: 
• 
Replacement of GAC (granular activated carbon) media in existing filters 
• 
Concrete repair and rehabilitation of existing filters 
1.3 Work under contract in GMP-2 (COC Contract WA2100.402): 
• 
Electrical gear long lead procurement 
• 
Site demolition 
• 
Erosion control 
• 
Excavation and shoring for the Post-filter GAC contactors and GAC pump station 
• 
Utilities around the Post-filter GAC contactors and GAC pump station

•
Allowances for structural concrete activities at the GAC pump station
1.4 Work proposed for GMP-3 (Remaining Project Scope): 
•
Site demolition
•
Installation of long lead procured equipment
•
Additional concrete repairs and rehabilitation of existing filters
•
Construction of new post-filter GAC, pump station, and seal weir structure
•
New electrical room at the post-filter GAC
•
Modifications to the existing filtered water reservoirs 1 and 2
•
Replace the 16-in BWR at the finished water pump station
•
Replacement and reconfiguration of EQ submersible pumps in tanks 1 and 2
•
Construction of new dewatering equipment and associated building
•
Construction of a new chlorine dioxide generation facility
•
Addition of new sodium hypochlorite metering systems and new tie-in points
•
Add chemical addition to the existing raw water pump stations 1 and 2
•
Add new tie-in points at the existing disinfection building softening system
•
Add new sample sink and sample lines at the Admin Bldg laboratory
•
Miscellaneous electrical and yard piping improvements
•
Relocation/Demolition of existing dewatering equipment
1.5 Project Delivery and Schedule: 
The program will be delivered through multiple design and construction packages over the period of Q3 
2024 through Q4 2028. Pre-construction services began in Q3 2024, with construction started in Q1 
2025 and continue through Q4 2028. 
The detailed construction baseline schedule is included in Section E. 
Guaranteed Maximum Price (GMP) Packages: 
1.
Filters 9 to 12 construction (completed)
2.
Long Lead Procurement and Early Construction Work (under contract)
3.
Remaining Construction (this GMP)
2.
SCOPE OF WORK
This GMP covers the work related to the balance of construction and commissioning. The work under 
this project will address the following:

The scope of work includes the following: 
FACILITY 
AREA 
DESCRIPTION 
 01 
 SITE WORK 
DEMO 
 02.01.100A  
 GMP 2 CHANGE ORDER- DEDUCT TO GO TO SUB  
 02.01.100B 
 DEMO 8' CMU WALL & HEADWALL  
 02.01.111 
 DEMO 4' CONCRETE RETAINING WALL  
 02.01.113A  
 ADDITIONAL DEMO OF CONCRETE SLAB  
 02.01.114A  
 DEMO EX. ASPHALT PAVEMENT (ASSUMED 3" THICK)  
 02.01.115A  
 REMOVE EX. CURB & GUTTER  
 02.01.116 
 REMOVE & SALVAGE DG (ASSUMED 3" THICK)  
 02.01.117 
 REMOVE EX. CONCRETE SIDEWALK (ASSUMED 4" THICK)  
 02.01.124 
 RELOCATE STORAGE CONTAINERS  
 02.01.131 
 REMOVE EX. PLANT DRAIN PIPE-04" PVC  
 02.01.132 
 CAP EX. DEWATERING FILTRATE-08" 
 02.01.134 
 CAP EX. FILTERED WATER LINE-08" 
 02.01.135 
 REMOVE & SALVAGE RIP RAP (ASSUMED 1.5' THICK)  
 02.01.121 
 REMOVE & SALVAGE RIVER ROCK (ASSUMED 1' THICK)  
 02.01.130 
 REMOVE EX. STORM DRAIN-06" HDPE  
 02.01.137 
 REMOVE EX. LIGHT, POLE, & BASE (ASSUMED 3' DIA X 5' DEEP)  
 02.01.150 
 ***REMOVE ADDITIONAL EX. ASPHALT PAVEMENT (ASSUMED 3" THICK)*** 
CONCRETE 
 03.01.300 
 CMU FTG 1260LF (C-12, 13, 16, 18, 19)  
 03.01.305 
 LIGHT POLES  
 03.001.025 
 HEADWALL ON C-13/C-16  
 03.01.330 
 HEADWALL REPLACEMENT ON C-30 
 03.01.998 
 T&M CRACK INJECTIONS AT FILTERS  
MASONRY 
 01.04.805 
 MASONRY SUBCONTRACT 
 32.11.114A  
 TEMP FENCING 
MISC METALS 
 01.50.800A  
 INSTALL BOLLARDS PLUS CONCRETE  
 01.500.800 
 MISC METALS SUBCONTRACT 
PAINT & COATINGS 
 09.01.800 
 PAINTING SUBCONTRACT - BOLLARDS & MASONRY WALL  
SPECIAL CONSTRUCTION 
 13.01.700 
 SIGNS  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
 01.26.800 
 SITE ELECTRICAL WORK 
 01.26.805 
 SITE ELECTRICAL DUCTBANK 
EROSION CONTROL 
 31.01.100A  
 INSTALL SILT FENCE

FACILITY 
AREA 
DESCRIPTION 
 31.01.101A  
 MONTHLY MAINTENANCE OF SILT FENCE 
 31.01.102 
 REMOVE SILT FENCE  
 31.01.103A  
 INLET PROTECTION  
 31.01.104A  
 MONTHLY MAINTENANCE OF INLET PROTECTION  
 31.01.105 
 REMOVE INLET PROTECTION  
 31.01.107 
 REMOVE CONSTRUCTION EXITS  
 31.01.108A  
 STREET SWEEPING  
EARTHWORK 
 19020B 
 GMP 3-ADDITIONAL STAFF 
 31.01.300 
 RETENTION BASIN EXCAVATION  
 31.10.100A  
 ROADWAY/SITE EXCAVATION  
PAVING, CURB & GUTTER 
 32.01.100 
 8' TALL CMU WALL PREP (SEE DETAIL ON S75-12) 
 32.01.101 
 7.5' TALL RETAINING WALL PREP (SEE DETAIL ON S75-11) 
 32.01.102 
 07" THICK CONCRETE PAVING ON 04" THICK ABC 
 32.01.103 
 09" THICK CONCRETE PAVING ON 04" THICK ABC 
 32.01.106 
 2'-0" RIBBON CURB PER MAG 220-1, TYPE B  
 32.01.107 
 04" THICK CONCRETE SIDEWALK ON 06" THICK ABC  
 32.01.108 
 CONCRETE VALLEY GUTTER PER MAG 240 
 32.01.109 
 RAISE & COLLAR EX. CLEANOUT PER DETAIL 6/CD-02  
 32.01.110 
 RAISE & COLLAR EX. MANHOLE  
 32.01.112 
 ASPHALT ROADWAY/DRIVEWAY REPLACEMENT-03" THICK  
 32.01.113 
 D50=04" RIP RAP, 06" THICK W/ FABRIC 
 32.01.114 
 PLACE 03" OF DG ONSITE  
 32.01.115 
 D50=06" RIP RAP, 12" THICK W/ FABRIC 
 32.01.116 
 D50=12" RIP RAP, 24" THICK W/ FABRIC 
 32.01.117 
 D50=04" RIP RAP, 08" THICK W/ FABRIC 
 32.01.118 
 CHAIN LINK SECURITY FENCING-08' TALL  
 32.01.119 
 LIGHT POLE BASE FOUNDATIONS-02' DIAMETER-PER E26-0601  
 32.01.125 
 ***ASPHALT CONTINGENCY AT GAC*** 
 32.01.126 
 ***ADDITIONAL ASPHALT ROADWAY REPLACEMENT-03" THICK*** 
FIBER OPTICS 
 33.01.100 
 DIG AND BACKFILL NEW FIBER OPTIC  
 33.01.101 
 MOPO #11  
UTILITIES 
 19020B 
 GMP 3-ADDITIONAL STAFF 
 33.01.300 
 3" SOFTENED WATER-AVG. DEPTH-8.00'  
 33.01.301 
 BEDDING ENCASED DUCTBANK-7 (PARTIAL) & 8  
 33.01.303 
 BEDDED/ENCASED CHEMICAL DUCT BANK-9-AVG. DEPTH-8.13' (2 CASE/4 CHEM LINES)  
 33.01.304 
 BEDDED/ENCASED CHEMICAL DUCT BANK-7-AVG. DEPTH-6.28' (2 CASE/2 CHEM LINES)  
 33.01.305 
 BEDDED/ENCASED CHEMICAL DUCT BANK-6-AVG. DEPTH-7.17' (2 CASE/2 CHEM LINES)  
 33.01.306 
 BEDDED/ENCASED CHEMICAL DUCT BANK-5-AVG. DEPTH-6.76' (2 CASE/2 CHEM LINES)

FACILITY 
AREA 
DESCRIPTION 
 33.01.307 
 BEDDED/ENCASED CHEMICAL DUCT BANK-4-AVG. DEPTH-6.60' (7 CASE/7 CHEM LINES)  
 33.01.308 
 BEDDED/ENCASED CHEMICAL DUCT BANK-3-AVG. DEPTH-4.00' (2 CASE/2 CHEM LINES)  
 33.01.309 
 BEDDED/ENCASED CHEMICAL DUCT BANK-1-AVG. DEPTH-6.37' (8 CASE/8 CHEM LINES)  
 33.01.310 
 BEDDED/ENCASED CHEMICAL DUCT BANK-2-AVG. DEPTH-7.04' (6 CASE/6 CHEM LINES)  
 33.01.311 
 BEDDED/ENCASED CHEMICAL DUCT BANK-2A-AVG. DEPTH-6.87' (4 CASE/4 CHEM LINES)  
 33.01.312 
 BEDDED/ENCASED CHEMICAL DUCT BANK-2B-AVG. DEPTH-5.47' (2 CASE/2 CHEM LINES)  
 33.01.312B 
 BEDDED/ENCASED CHEMICAL DUCT BANK-10-AVG. DEPTH-6.46' (4 CASE/4 CHEM LINES)  
 33.01.312C 
 BEDDED/ENCASED CHEMICAL DUCT BANK-11-AVG. DEPTH-3.64' (4 CASE/4 CHEM LINES)  
 33.01.312D 
 BEDDED/ENCASED CHEMICAL DUCT BANK-12-AVG. DEPTH-5.87' (6 CASE/10 CHEM LINES)  
 33.01.312E 
 BEDDED/ENCASED CHEMICAL DUCT BANK-13-AVG. DEPTH-6.43' (5 CASE/9 CHEM LINES)  
 33.01.313 
 INSTALL CHEMICAL VAULT-5'X5'-AVG. DEPTH-7.50'  
 33.01.314 
 INSTALL CHEMICAL VAULT-4'X4'-AVG. DEPTH-6.03'  
 33.01.315 
 INSTALL CHEMICAL VAULT-3'X3'-AVG. DEPTH-7.83'  
 33.01.315A  
 INSTALL TRANSITION VAULT-4'X4'-AVG. DEPTH-8.29'  
 33.01.318 
 6" PERFORATED HDPE STORM-AVG. DEPTH-2.00'  
 33.01.319 
 24" RCP STORM-AVG. DEPTH-4.04' 
 33.01.319A  
 12" HDPE STORM-AVG. DEPTH-2.85'  
 33.01.327 
 REROUTE EX. 4" PVC PUMP DISCHARGE LINE-ASSUMED AVG. DEPTH-3.43'  
 33.01.328 
 REROUTE EX. 8" FILTERED WATER LINE-ASSUMED AVG. DEPTH-7.00' 
 33.01.329 
 6" CL 350 DIP FIRE LINE-AVG. DEPTH-6.42'  
 33.01.330 
 2" PEX/6" CL 350 DIP POTABLE WATER-AVG. DEPTH-5.89'  
 33.01.331 
 4" PVC SEWER-AVG. DEPTH-5.18' 
 33.01.333 
 1" SCH. 80 PVC SAMPLE PIPE-ASSUMED AVG. DEPTH-3.00'  
 33.01.340 
 36" WSP BACKWASH WASTE (BWW)-AVG. DEPTH-9.74'  
 33.01.342 
 42" WSP FILTERED WATER (FW)-GAC WETWELL TO SEAL WEIR-AVG. DEPTH-14.23'  
 33.01.343 
 60" WSP FILTERED WATER (FW)-EFFLUENT CONNECTION TO SEAL WEIR-AVG. DEPTH-16.30'  
 33.01.345 
 48" WSP GAC EFFLUENT (GE) TO 48"X60" REDUCER-AVG. DEPTH-16.60'  
 33.01.346 
 6' SAMPLING MANHOLE-48" GE-DEPTH-18.61'  
 33.01.346A  
 6' SAMPLING MANHOLE-60" FW-DEPTH-24.26'  
 33.01.348 
 60" WSP FINISH WATER (FW) 48"X60" REDUCER TO 60X60 TEE (STA 9+01)-AVG. DEPTH-22.11'  
 33.01.349 
 60"/54"/36"/30" WSP FINISH WATER (FW) 60X60 TEE (STA 9+01) TO TANKS-AVG. DEPTH-23.75'  
 33.01.355 
 CONNECT TO EX. CAOCL LINE-1.5"-AVG. DEPTH-7.38'  
 33.01.358 
 18" CL350 DIP FILTER TO WASTE (FTW) REROUTE-AVG. DEPTH-10.62' 
 33.01.360 
 16" WSP BACKWASH RECIRCULATION (BWR) REROUTE-AVG. DEPTH-10.06'  
 33.01.370 
DEDUCT FOR EXPORT/IMPORT REPLACED BY  NATIVE FILL IN NON PIPE ZONE AREAS 
 33.43.300A  
 GMP 2-CHANGE ORDER- DEDUCT TO GO TO DEFINED SCOPE  
 33.43.305A  
 GMP 2-CHANGE ORDER- DEDUCT TO GO TO DEFINED SCOPE  
 10 
 WEIR STRUCTURE 
CONCRETE 
 19020 
 SELF-PERFORM STAFF  
 03.010.000 
 SEAL WATER STRUCT. - SOG 
 03.010.005 
 SEAL WATER - PERIMETER WALLS

FACILITY 
AREA 
DESCRIPTION 
 03.010.010 
 SW - WEIR WALL  
 03.010.020 
 SW - ELEV. DECK & BEAMS  
 03.010.022 
 PUMP FND SOG 
 03.010.023 
 PUMP PADS  
 03.010.025 
 BLIND FLANGE MATERIAL/LEAK TEST SEAL WEIR  
 03.010.099 
 REBAR - SEAL WEIR STRUCT.  
 03.010.105 
 SEAL WATER - PERIMETER WALL PIPE (SET)  
 03.10.999 
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK  
MISC METALS 
 05.10.700 
 MISC METALS SUBCONTRACT 
FRP MATERIALS 
 06.10.700 
 FRP WEIR PLATES  
PAINT & COATINGS 
 09.10.700 
 PAINTING SUBCONTRACT 
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
 10.26.800 
 WEIR STRUCTURE EI&C  
EARTHWORK 
 31.10.100 
 EXCAVATION  
 31.10.200 
 BACKFILL WEIR STRUCTURE  
PROCESS PIPE & VALVES 
 40.10.200 
 1" CPVC CHEMICAL HFSA ( HYDROFLUOSILICIC ACID)  
 40.10.201 
 2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE)  
 40.10.202 
 1" CS SCH 40 WELD CHEMICAL NAOH ( SODIUM HYDROXIDE)  
 40.10.300 
 SAMPLE PIPING AT SEAL WEIR & SAMPLING MANHOLE  
 40.10.400 
 FW 60" / 42" CARBON STEEL & DYNAMIC MOVEMENT JOINTS  
 40.10.500 
 BWR 16" CARBON STEEL & DYNAMIC MOVEMENT JOINT  
 40.10.501 
 30" VENT  
PROCESS EQUIPMENT 
 46.10.200 
 SEAL WATER SAMPLE SUMP PUMPS  
 46.10.205 
 SEAL WATER SLIDE GATES  
 46.10.210 
 CHLORINE INJECTION ASSEMBLIES  
 46.10.999 
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK  
 30 
 EXISTING RAW WATER PUMP STATION 1 
PAINT & COATINGS 
 09.30.700 
 PAINTING SUBCONTRACT 
PROCESS PIPE & VALVES 
 40.30.430 
 ABANDON EXISTING NAOCI 
 40.30.440 
1-1/2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE)
 40.30.450 
 3" CPVC CHEMICAL CIO2 (CHLORINE DIOXIDE)  
PROCESS EQUIPMENT 
 46.30.210 
 CHLORINE INJECTION ASSEMBLIES  
 35 
 EXISTING RAW WATER PUMP STATION 2

FACILITY 
AREA 
DESCRIPTION 
PAINT & COATINGS 
 09.35.700 
 PAINTING SUBCONTRACT 
PROCESS PIPE & VALVES 
 40.35.430 
 ABANDON EXISTING NAOCI 
 40.35.440 
1-1/2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE)
 40.35.450 
 3" CPVC CHEMICAL CIO2 (CHLORINE DIOXIDE)  
PROCESS EQUIPMENT 
 46.35.210 
 CHLORINE INJECTION ASSEMBLIES  
 42 
 GAC PUMP STATION 
CONCRETE 
 19020 
 SELF-PERFORM STAFF  
 03.042.000 
 PUMP STATION SOG 
 03.042.004 
 PS - LAUNDERER DECK  
 03.042.005 
 PUMP STATION PERIMETER WALLS  
 03.042.006 
 PS - COLUMNS  
 03.042.007 
 PS - PUMP BAFFLE WALL  
 03.042.008 
 PS - BEAMS IN DECK 
 03.042.009 
 PS - DECK LAUNDER WALL  
 03.042.010 
 PS - SUPPORTED PUMP DECK  
 03.042.011 
 FEED PUMP CANS EQUIP PADS TOP DECK  
 03.042.012 
 PS - 2 STAIR LANDINGS & GRADE BEAM FND 
 03.042.013 
 BLIND FLANGE MATERIAL/LEAK TEST PUMP STATION  
 03.042.099 
 REBAR - GAC PUMP STATION  
 03.42.999 
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK  
MISC METALS 
 05.42.700 
 MISC METALS SUBCONTRACT 
PAINT & COATINGS 
 09.42.700 
 PAINTING SUBCONTRACT 
PROCESS PIPE & VALVES 
 40.42.400 
 FW 24"/36" CARBON STEEL AND VALVES  
 40.42.410 
 BWS 24"/36" CARBON STEEL AND VALVES  
 40.42.420 
 OF 42" CARBON STEEL AND FLAP GATE 
 40.42.430 
 FW 42"/30" CARBON STEEL AND VALVES IN WET WELL  
 40.42.440 
 BWS/FW 36" PIPING BETWEEN STRUCTURES 
 40.42.445 
 DRAIN 2" / 4" CPVC AIR RELEASE VENT DRAIN PIPING 
PROCESS EQUIPMENT 
 19020 
 SELF-PERFORM STAFF  
 46.42.500 
 GAC PS FLAP GATE 
 46.42.505 
 GAC FEED PUMPS 
 46.42.510 
 GAC BACKWASH PUMPS 
 46.42.999 
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK  
 43 
 POST FILTER GAC CONTACTORS

FACILITY 
AREA 
DESCRIPTION 
CONCRETE 
 19020 
 SELF-PERFORM STAFF  
 03.043.015 
 CONTACTOR & CHANNEL SOG - N/S 
 03.043.020 
 GAG PIPE GALLERY SOG  
 03.043.023 
 CONTACTOR LAUNDER DIVIDER WALLS  
 03.043.030 
 NORTH/SOUTH PIPE GALLERY WALLS - 2'WIDE  
 03.043.040 
 NORTH/SOUTH BAFFLE WALL  
 03.043.045 
 NORTH/SOUTH/EAST CHANNEL INNER WALL  
 03.043.050 
 NORTH/SOUTH EXTERIOR WALLS  
 03.043.051 
 WEST END WALLS  
 03.043.052 
 WEST DOCK WALL  
 03.043.053 
 EAST EXTERIOR WALL  
 03.043.054 
 NORTHEAST CORNER WEIR WALL  
 03.043.055 
 CHANNEL DECKS NORTH/SOUTH/EAST 
 03.043.057 
 ELEV. DECKS OVER CHANNELS  
 03.043.060 
 GALLERY ELEVATED BEAMS & DECK 
 03.043.061 
 ELEVATED DECK ROOF CURBING  
 03.043.064 
 DOOR STOOP, STAIR FTR & LANDING, 2 EQUIP PADS  
 03.043.066 
 GAC OVERHEAD DOOR APPROACH SOG 
 03.043.067 
 GAC WEST PONY WALL AT ROLL-UP DOOR AREA  
 03.043.068 
 ROLL-UP DOOR SUPPORTED DECK AT DOCK ENTRY  
 03.043.075 
 BLIND FLANGE MATERIAL/LEAK TEST GAC 
 03.043.080 
 GAC WEIR - SOG 
 03.043.082 
 GAC WEIR - WALLS & WEIR WALL  
 03.043.084 
 GAC WEIR - ELEV. DECK  
 03.043.085 
 BLIND FLANGE MATERIAL/LEAK TEST WEIR STRUCTURE  
 03.043.099 
 REBAR - POST FILTER GAC FACILITY  
 03.43.399 
 SAFETY & ACCESS CONTROLS (SCAFFOLDING, STAIRS, HANDRAIL, LADDERS) 
 03.43.999 
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK  
MISC METALS 
 05.43.700 
 MISC METALS SUBCONTRACT 
FRP MATERIALS 
 06.43.705 
 FRP LADDER 25' W/ SAFETY CLIMB SYSTEM 
 06.43.710 
 FRP WEIR PLATES  
DOORS & WINDOWS 
 08.43.700 
 SINGLE HM DOOR  
 08.43.705 
 OH COILING DOOR  
PAINT & COATINGS 
 09.43.700 
 PAINTING SUBCONTRACT 
 09.43.702 
 CRYSTALLINE WATERPROOFING 
 09.43.705 
 GAC CHANNEL COATINGS  
PLUMBING & HVAC

FACILITY 
AREA 
DESCRIPTION 
  
 22.43.800  
 GAC PLUMBING  
  
 22.43.801  
 DRAIN PIPE ENCASEMENT  
  
 23.43.800  
 LOUVERS AND VENTS  
  
  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
  
 26.43.800  
 POST FILTER GAC CONTACTORS EI&C  
  
  
EARTHWORK 
  
 19020A  
 GMP 3-DEDUCT TO SALARY STAFF TO GO TO SUB  
  
 31.43.300A  
 GMP 3-DEDUCT TO SELF-PERFORM WORK TO GO TO SUB  
  
 31.43.300B  
 GMP 2 CHANGE ORDER-ADDER FOR SHORING SUB TO GO FROM TIE BACK TO BEAM & LAG  
  
 31.43.300C  
 GMP 2 CHANGE ORDER-ADDER TO TRUCK MATERIAL OFF SITE  
  
 31.43.301A  
 GMP 2 CHANGE ORDER-DEDUCT TO GO TO SUB  
  
 31.43.305  
 BACKFILL FOR GAC  
  
  
PROCESS PIPE & VALVES 
  
 40.43.400  
 FW 24" WALL PIPE & VALVES  
  
 40.43.410  
 BWS 24"/36" CARBON STEEL AND VALVES  
  
 40.43.420  
 BWW 36" WALL PIPE & VALVES  
  
 40.43.430  
 CTW 16" FAB SPOOL  
  
 40.43.440  
 GE 14"/36" CARBON STEEL AND VALVES  
  
 40.43.560  
 FILTER BED SAMPLE PIPING & SAMPLE PUMP STATION  
  
 40.43.580  
 4" GS GAC SLURRY 316 SS  
  
 40.43.590  
 36" BWW ENCASED PIPE AT GAC  
  
 40.43.595  
 48" GE ENCASED PIPE AT EFF WEIR STRUCTURE  
  
 40.43.596  
 SUMP PUMP DISCHARGE 1-1/2" CPVC  
  
 40.43.597  
 2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE) AT EFF WEIR  
  
 40.43.598  
 1" CS SCH 40 WELD CHEMICAL NAOH ( SODIUM HYDROXIDE) AT EFF WEIR  
  
 40.43.599  
 FW 42" CARBON STEEL FROM GAC TO EFF WEIR DYNAMIC MOVEMENT JOINT  
  
 40.43.600  
 20" WEIR VENT  
  
  
MONORAIL 
  
 41.43.700  
 CRANE  
  
  
PROCESS EQUIPMENT 
  
 19020  
 SELF-PERFORM STAFF  
  
 46.43.500  
 CONTACTOR UNDERDRAIN SYSTEM  
  
 46.43.515  
 GAC EFFLUENT WATER SAMPLE PUMP  
  
 46.43.520  
 GAC MEDIA  
  
 46.43.525  
 DAVIT CRANE  
  
 46.43.530  
 ALUM. COVERS  
  
 46.43.535  
 GAC DRAIN SUBMERSIBLE SUMP PUMPS  
  
 46.43.540  
 GAC SLIDE GATES  
  
 46.43.999  
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK  
 43E  
  
 POST FILTER GAC ELECTRICAL BLDG  
  
  
CONCRETE 
  
 03.43E.000  
 GAC ELECTRICAL SOG

FACILITY 
AREA 
DESCRIPTION 
  
 03.43E.011  
 GAC ELECTRICAL HVAC EXTERIOR SOGS  
  
 03.43E.012  
 GAC ELECTRICAL EQUIP PADS - INT.  
  
 03.43E.099  
 REBAR - GAC ELECTRICAL BLDG  
  
 03.43E.999  
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK  
  
  
MASONRY 
  
 04.43E.700  
 MASONRY SUBCONTRACT  
  
  
MISC METALS 
  
 05.43E.700  
 MISC METALS SUBCONTRACT   
  
 05.43E.710  
 METAL FLASHING 10" H DRIP EDGE UNDER MASONRY  
  
  
ROOFING 
  
 07.43E.700  
 EXTERIOR EIFS SYSTEM   
  
 07.43E.705  
 ROOFING DOWNSPOUTS, GUTTERS. ETC  
  
 07.43E.710  
 ROOFING COMPONENTS  
  
  
DOORS & WINDOWS 
  
 08.43E.700  
 SINGLE HM DOOR  
  
 08.43E.705  
 DOUBLE HM DOOR  
  
  
PAINT & COATINGS 
  
 09.43E.700  
 PAINTING SUBCONTRACT  
  
  
FIRE SUPPRESSION 
  
 21.43E.800  
 FIRE SUPPRESSION SYSTEM  
  
  
PLUMBING & HVAC 
  
 22.43E.800  
 POST FILTER GAC ELEC BLDG PLUMBING  
  
 23.43E.800  
 POST FILTER GAC ELEC BLDG HVAC  
  
  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
  
 26.43E.800  
 POST FILTER GAC ELECTRICAL BUILDING  
  
  
EARTHWORK 
  
 31.43E.305  
 BACKFILL FOR GAC ELEC  
 45  
  
 FILTERED WATER RESERVOIRS  
  
  
CONCRETE 
  
 03.045.000  
 2 PIPE SUPPORTS IN TANK  
  
 03.45.999  
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK  
  
  
PAINT & COATINGS 
  
 09.45.700  
 PAINTING SUBCONTRACT  
  
  
EARTHWORK 
  
 19020  
 SELF-PERFORM STAFF  
  
 33.43.360  
 EXCAVATE & BACKFILL SHORING PIT AT FILTERED WATER RESERVOIR NO. 1  
  
 33.43.361  
 EXCAVATE & BACKFILL SHORING PIT AT FILTERED WATER RESERVOIR NO. 2  
  
  
PROCESS PIPE & VALVES 
  
 40.45.405  
 1" SAM CPVC SAMPLE PIPE FROM MANHOLE TO SAMPLE PUMPS  
  
 40.45.410  
 36" FW CARBON STEEL INSIDE RESERVOIR NO 2  
  
 40.45.420  
 30" FW CARBON STEEL INSIDE RESERVOIR NO 1  
  
 40.45.460  
 60" / 36" CARBON STEEL ABANDON IN PLACE

FACILITY 
AREA 
DESCRIPTION 
  
  
PROCESS EQUIPMENT 
  
 19020  
 SELF-PERFORM STAFF  
  
 46.45.205  
 FILTERED WATER SAMPLE PUMPS  
  
 46.45.999  
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK  
 50  
  
 FINISHED WATER PUMP STATION  
  
  
PAINT & COATINGS 
  
 09.50.700  
 PAINTING SUBCONTRACT  
  
  
PROCESS PIPE & VALVES 
  
 40.50.400  
 BWR 16" CARBON STEEL  
 65  
  
 EQUALIZATION BASINS  
  
  
CONCRETE 
  
 03.065.000  
 2 PUMP SLABS OUTSIDE EQ. BASINS  
  
 03.065.099  
 REBAR - PUMP SOGS  
  
 03.065.999  
 DEMO & REPLACE GROUT ON BOTTOM OF TANK  
  
  
MISC METALS 
  
 05.65.700  
 MISC METALS SUBCONTRACT   
  
  
PAINT & COATINGS 
  
 09.65.700  
 PAINTING SUBCONTRACT  
  
  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
  
 65.26.800  
 EQ BASIN EI&C  
  
 65.26.801  
 GMP 2 CHANGE ORDER-VFD CHANGE TO STAND ALONE ON EQ PUMPS  
  
  
PROCESS PIPE & VALVES 
  
 40.65.400  
 PRW 8" DIP BASIN 1  
  
 40.65.420  
 PRW 8" DIP BURIED VAULT TO BASIN 1  
  
 40.65.425  
 PRW 8" DIP VALVES ABOVE GROUND BASIN 1  
  
 40.65.440  
 PRW 8" DIP BASIN 2  
  
 40.65.450  
 PRW 12" / 8" DIP BURIED BASIN 2  
  
 40.65.455  
 PRW 8" VALVES ABOVE GROUND BASIN 2  
  
  
PROCESS EQUIPMENT 
  
 19020  
 SELF-PERFORM STAFF  
  
 40.65.500  
  DEMOLITION OF EXISTING EQ BASIN 1 EQUIPMENT   
  
 40.65.505  
  DEMOLITION OF EXISTING EQ BASIN 2 EQUIPMENT   
  
 46.65.515  
  EQB-1 BASIN PUMP   
  
 46.65.525  
  EQB-2 BASIN PUMP   
  
 46.65.999  
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK  
 75  
  
 DEWATERING FACILITY  
  
  
SPECIAL CONSTRUCTION 
  
 13.75.500  
 GENERAL CONTRACTOR-DEWATERING FACILITY  
  
  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
  
 26.75.800  
 DEWATERING BUILDING EI&C  
 86  
  
 CHLORINE DIOXIDE  
  
  
SPECIAL CONSTRUCTION

FACILITY 
AREA 
DESCRIPTION 
 13.86.500 
 GENERAL CONTRACTOR-CHLORINE DIOXIDE BLDG  
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
 26.86.800 
 ELECTRICAL SUBCONTRACT  
EARTHWORK 
 19020 
 SELF-PERFORM STAFF  
 31.86.300 
 EXCAVATION FOR CHEMICAL BLDG 
 31.86.305 
 BACKFILL FOR CHEMICAL BLDG  
 87 
 POST TREATMENT CHEMICAL FACILITY 
PAINT & COATINGS 
 09.87.700 
 PAINTING SUBCONTRACT 
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
 87.26.800 
 POST TREATMENT EI&C 
PROCESS PIPE & VALVES 
 40.87.410 
 SH PUMP TIE IN 2" / 1" CPVC  
 40.87.415 
 SH STORAGE TANK TIE IN 2" / 1" CPVC  
 40.87.420 
 SODIUM HYDROXIDE PUMP TIE IN 1" WELDED CS  
 40.87.425 
 SODIUM HYDROXIDE STORAGE TANK AREA 3/4" WELDED CS  
PROCESS EQUIPMENT 
 46.87.205 
 SODIUM HYPOCHLORITE METERING PUMP 
 46.87.210 
 SODIUM HYDROXIDE METERING PUMP 
 46.87.520 
 CHLORINE INJECTION ASSEMBLIES  
 90 
 DISINFECTION BUILDING 
PAINT & COATINGS 
 09.90.700 
 PAINTING SUBCONTRACT 
PROCESS PIPE & VALVES 
 40.90.400 
 3" SOFT WATER TIE IN CPVC  
 95 
 ADMIN BUILDING 
PAINT & COATINGS 
 09.95.700 
 PAINTING SUBCONTRACT 
PROCESS PIPE & VALVES 
 40.95.500 
 SAMPLE PIPING AT ADMIN BUILDING 
 99 
 CONSTRUCTION MANAGER GENERAL CONDITIONS 
ELECTRICAL, INSTRUMENTATION, & CONTROLS 
 19999 
 TEMPORARY ELECTRICAL  
CONSTRUCTION MANAGER GENERAL CONDITIONS 
 19010A  
 GMP 3-ADDITION CM STAFF 
CONSTRUCTION MANAGER GENERAL REQUIREMENTS 
 19050 
 GENERAL REQUIREMENTS  
 19030A  
 GMP 3-ADDITION TO SITE WIDE EQUIPMENT

3.
ORGANIZATIONAL CHART
The following individuals and their reporting system will be used during the construction phase of the 
project: 
Felix Construction Employee – Assigned 
AWC Employee – Assigned 
AWC Employee – General Oversight (Overhead) 
4.
ROLES & RESPONSIBILITIES
Several supervision staff are included in the project. Descriptions of their roles and responsibilities are 
provided below.

1.6 Project Director 
1.6.1 Purpose:  
Responsible for the overall direction, completion, financial outcome, technical success and quality of a 
very large, complex construction project or multiple projects simultaneously. The Project Director also 
establishes and manages strategic client relationships. Identifies opportunities to expand company 
relationships and business opportunities.  
1.6.2 Major Responsibilities: 
•
Plans, organizes, coordinates and controls projects in accordance with established policies,
procedures, systems and requirements approved by the Company. Creates and manages processes
for tracking projects and associated deliverables, collects and analyzes data, and works closely with
field personnel, designers, engineers, vendors and subcontractors to manage various programmatic
and project processes.
•
Leads interdisciplinary teams, such as preconstruction, to deliver projects that reside within a major
business group or function. Determines staffing needs, personnel development, performance
management and training for the project team. Provides leadership, guidance and direction to the
project team members. Ensures projects are completed, tracked and reported on in accordance with
all compliance regulations and goals. Completes and/or approves Performance Reviews for
subordinates.
•
Maintains exceptional relationships with owners, subcontractors, design partners and unions.
Responsible for day-to-day contact as well as contact of a multifaceted nature.
•
Assists with bid package development, pre-qualification activities and budget preparation. May draft
budget/estimate documents and provide oversight for the estimating process.
•
Leads efforts to analyze risk and define schedule-related issues, including analysis of long lead
materials or equipment which may impact project cost or scheduled delivery.
•
Analyzes and presents project delivery approaches, develops alternative approaches and facilitates
implementation, ensuring compliance with corporate, federal and state regulations.
•
Serves as the primary contact for senior department managers relative to critical business issues.
Helps allocate regional assets and resources to projects within business group. Maintains
vehicle/equipment database in online management tool in conjunction with EOG/Project Engineer.
Assists with obtaining vehicle registrations and vehicle repairs. Tracks and monitors vehicle
assignments to ensure vehicle availability and mitigate risk.
•
Participates in the design and execution of project safety planning activities to ensure that projects
are completed within established safety goals.

1.7 Project Manager 
1.7.1 Purpose:  
Responsible for the overall direction, completion, financial outcome, technical success and quality of a 
construction project or a portion of a large complex project. The Project Manager also establishes and 
maintains positive relationships with owners, subcontractors, design partners and unions. The Project 
Manager will provide training and guidance to this level and will have responsibility for process 
improvement. 
1.7.2 Major Responsibilities: 
•
Plans, organizes, coordinates and controls project(s) in accordance with established policies,
procedures, systems and requirements approved by the Company. Reviews and approves
preliminary project and equipment schedules, financial projections, cost-to-complete and project
status reports for the duration of the project.
•
Directs and supervises work of project administration staff and engineers, as well as works in
partnership with project superintendents to establish operational priorities. Establishes the site
organizational plan and responsibility matrix. Ensures that construction site rules and procedures
are implemented and that best practices and customer focus is achieved in an efficient and effective
manner. Provides leadership, guidance, direction and positive attitude to the project team
members.
•
Maintains exceptional relationships with owners, subcontractors, design partners and unions.
Responsible for day-to-day contact and communications with customers, as well as subcontractor
partners. Ensures creation and maintenance of subcontractor partner contracts
•
Responsible for forecasting, tracking/reporting project costs/revenue and adherence to project
estimates. Provides leadership for multiple aspects of controls including costs/revenue, planning,
scheduling and architecture/engineering.
•
Develops strategy for staffing, personnel development, performance management and training.
Ensures delivery of project training programs and compliance to all corporate, federal and state
regulations. Coordinates with company EEO Compliance Officer to ensure that projects are
completed, tracked and reported on in accordance with mandated policies and project EEO goals.
Conducts or approves Performance Reviews of subordinate staff.
•
Responsible for problem resolution involving labor disputes, staffing, materials, equipment and
contracts/subcontracts administration.
•
Provides feedback to BGL, PGM and/or ROM on a regular basis. Notifies management of significant
project events such as project successes, issues, injuries, client relations, potential losses/claims, etc.
•
Coordinates with Safety & Quality Manager to ensure that projects are completed in accordance
with established department goals.

1.8 Assistant Project Manager 
1.8.1 Purpose:  
Responsible for assisting the Project Manager with the overall direction, completion and financial 
outcome of a construction project. 
1.8.2 Major Responsibilities: 
•
Prepare, review and negotiate project contracts, subcontractor agreements, subcontractor services
agreements, purchase orders, quality acceptance agreements, etc.
•
Responsible for procurement of materials. From contract execution, through submittal phase,
release for fabrication, and tracking of deliveries to ensure schedule of the project is maintained.
•
Review owner contracts. Draft and articulate argument/positions on owner contracts. Negotiate
owner change orders and claims for extra work. Develop change management and
allowance/contingency controls. Review and prepare time and material allowance/contingency
usage for execution. Aid in preparation of revenue forecasts.
•
Records equipment and material deliveries to ensure accuracy and to ensure that project remains
on schedule.
•
Coordinate the purchase/renewal of insurance policies on the project. Pursue or aid in pursuing
insurance claims on the projects.
•
Establish and administer document control procedures.
•
Work with Operations team on a daily basis on risk management, and contractual and commercial
issues.
•
Plans, organizes, coordinates and controls project(s) in accordance with established policies,
procedures, systems and requirements approved by the Company.
•
Supervises work of project administration, superintendents, and engineers to ensure that work is
accomplished in an efficient, effective, profitable and safe manner and meets all quality standards.
•
Reviews cost-coding of timesheets and invoices, reviews daily production reports and supervises
forecasted final cost/revenue reporting to ensure that profitability goals are met.
•
Reviews submittal of change orders and analyzes impact on project schedules. Participates in work
planning of self-performed activities.
•
Gathers and records subcontractor log and weather conditions and makes recommendations
accordingly. May coordinate and schedule subcontractors.
•
May coordinate with owners and engineers for project scheduling and issue resolution.
•
Assists with the development and review of detailed MOPO plans.
•
Manages allowance and contingency tracking and gathering supporting documentation.
•
Attend weekly owner progress meetings and support the Project Manager as required.

1.10 Project Superintendent 
1.10.1 Purpose:  
In conjunction with Project Management, responsible for the direct supervision of field forces, and the 
efficient scheduling of the physical completion of all project work. 
1.10.2 Major Responsibilities: 
•
The superintendent will be the day-to-day contact on the project for any site activities taking place
under the contract.
•
Coordinates subcontracts, drawings, and specifications to ensure conformity. Examines drawings
and specifications for various work tasks and ensures current information is passed down to front
line supervision and trades personnel. Carries out inspections as needed.
•
Responsible for daily planning, creation and maintenance of project schedules, including
subcontractor specialty schedules and short interval schedules. Involved in creating work plans for
each specific work activity.
•
Supervises and organizes workers; ensures workers are available and fully qualified to perform
assigned duties. Reports on labor and materials. Schedules crews according to available work
packages for the project and all required equipment and materials necessary to complete tasks.
Monitors timely delivery of necessary materials to assure continued productivity.
•
Responsible for controlling costs, adhering to budgets and managing equipment-related expenses.
Ensures staff is aware of production rates for assigned items of work.
•
Conducts regular safety meetings; maintains a safe work environment with the goal of keeping
accidents and injuries to a minimum and complying with company and regulatory safety procedures.
Complies with EPA requirements for hazardous materials.
•
Coordinates subcontractors through a regular and disciplined series of meetings, questioning and
verifying their plans and efforts, changing or augmenting as needed.
•
Assists project management team ensuring compliance with the legal and regulatory requirements
of the city, state and federal government applicable to the project. Alerts management to any
potential concerns.
•
Participates in the development and implementation of appropriate portions of the jobsite quality,
safety and production plans; ensures maintenance of all records in accordance with project
standards.
•
Coordinates with internal staff to build professional and productive relationships with owners,
architects, engineers and subcontractors.

EXHIBIT B 
FEE SCHEDULE

EXHIBIT D
CM@RISK GMP SUMMARY

EXHIBIT D
CMAR GMP SUMMARY
Project Name: Pecos Surface Water Treatment Plant Improvements
Date: 5/8/2026
Project Location: 1475 E Pecos Rd
City of Chandler Project No WA2100.251
GMP 3
A. Cost of Work
A.1 Cost of Work (self-perform, no mark-ups)
$61,738,317.85
A.2. Cost of Work - Subcontracts
$38,792,629.73
TOTAL COST OF WORK:
$100,530,947.58
B. General Conditions
$6,981,384.71
SUBTOTAL 1 (Cost of Work) (A+B)
$107,512,332.29
C. CMAR's Fee (8.0%)
$8,600,986.58
SUBTOTAL 2 (A+B+C):
$116,113,318.87
D. Bonds and Insurance
D.1. Bonds (Payment and Performance)
$823,642.47
D.2. Insurance
$1,764,225.09
TOTAL BONDS & INSURANCE:
$2,587,867.56
SUBTOTAL 3 (SUBTOTAL 2 + BONDS & INS):
$118,701,186.44
E. Sales Tax
E.1. Sales Tax (5.07%)
$6,018,150.15
E.2. Tax Credits
-$1,476,938.65
TOTAL SALES TAX:
$4,541,211.50
TOTAL BASELINE ESTIMATE WITHOUT ALLOWANCES/CONTINGENCIES:
$123,242,397.94
F. Approved Allowances
TOTAL ALLOWANCES:
$0.00
G. Contingencies
G. 1. Construction Contingency
$3,000,000.00
G. 2. Owner Contingency
$1,000,000.00
G. 3. Escalation Contingency
$600,000.00
TOTAL CONTINGENCIES:
$4,600,000.00
TOTAL GMP 3 PROPOSAL:
$127,842,397.94
Establishment of Values:
a. Cost of Work (A) and Allowances (F) to be submitted with GMP Proposal.
b. General Conditions Cost (B) to be established in Baseline Cost Model.
c. CMAR Fee as set forth in Section 3.7.3. of this Agreement.

EXHIBIT D: ALLOWANCE DESCRIPTIONS 
There is no work planned as an allowance in this GMP. 
EXHIBIT D: CONTINGENCY DESCRIPTIONS 
G.1. Design Evolution Contingency 
Design Evolution Contingency is intended to cover anticipated design evolution between the current 
design and 100% design including but not limited to: 
• 
Incorporate 90% review comments; 
• 
Added complexity to current design; 
• 
Minor scope changes; 
• 
Modifications to current design; and 
• 
Additional detailing. 
G.2. Owner Contingency 
Owner contingency is to be determined by the City and will be used as directed by General Conditions 
15.4.2. 
G.3. Construction Contingency 
Construction Contingency is intended to cover minor modifications and unforeseen issues with the final 
design that arise during construction and are described in paragraph 15.4.1 of the City of Chandler 
General Conditions which included unexpected costs due to: 
• 
scope gaps between trade subcontractors; 
• 
agreement default by trade subcontractors; 
• 
unforeseen field conditions, but only as defined in Section 9.5 (Differing Site Conditions); 
• 
work completed to meet the intent of the design, but which was not indicated on the plans; 
• 
costs overruns not covered by allowances; 
• 
costs of corrective work not provided for elsewhere; and 
• 
implementation of any Recovery Plan. 
Per the City request, the Construction Contingency will also cover cost increases due to tariffs. As such, a 
dedicated line item in the Risk Register is included for tariff cost impacts. 
Construction Contingency specifically excludes, but may not be limited to:  
• 
Design Evolution Contingency 
• 
Owners’ contingency (as defined by 15.4.2 of the General Conditions) 
• 
Significant changes in scope. 
• 
Exclusions included herein.

• 
Major unexpected work stoppages (strikes, etc.) 
• 
Disasters (hurricanes, tornados, etc.) 
• 
Excessive, unexpected inflation or currency fluctuations. 
• 
Changes in law and regulation that increase costs are implemented after GMP (excluding tariffs). 
GENERAL NOTES 
The GMP Worksheet includes bonds, insurance, and taxes for the full value of the project. Any 
allowance and contingency usage will only have fee added beyond the cost of work shown.

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
 01 
 SITE WORK 
                        1 
 LS 
                        69,655  $                      6,691,205.69  $                      8,469,673.66  $                      4,812,971.33  $                      2,282,583.51  $                    22,256,434.19 
DEMO
                        1 
 LS 
                               550  $                             45,187.57  $                                3,530.48  $                             50,998.14  $                             36,135.01  $                          135,851.20 
02.01.100A
 GMP 2 CHANGE ORDER- DEDUCT TO GO TO SUB 
1
                       
LS
(129)
                            
(7,852.64)
$                              
11,645.72
$                             
(6,128.00)
$ 
(2,334.92)
$ 
02.01.100B
 DEMO 8' CMU WALL & HEADWALL 
370
                  
LF
24,327.99
$                             
24,327.99
$ 
02.01.111
 DEMO 4' CONCRETE RETAINING WALL 
5
                       
LF
6
                                   
469.02
$                                    
28.15
$                                       
310.00
$                                    
570.66
$ 
1,377.83
$ 
02.01.113A
 ADDITIONAL DEMO OF CONCRETE SLAB 
101
                  
SF
2
                                   
189.48
$                                    
50.72
$                                       
3,178.00
$                                
115.37
$ 
3,533.57
$ 
02.01.114A
 DEMO EX. ASPHALT PAVEMENT (ASSUMED 3" THICK) 
21,004
           
SF
252
                              
19,702.55
$                             
1,848.60
$                                
8,584.08
$                                
11,961.41
$ 
42,096.64
$ 
02.01.115A
 REMOVE EX. CURB & GUTTER 
862
                  
LF
103
                              
8,085.89
$                                
546.51
$                                    
1,206.80
$ 
9,839.20
$ 
02.01.116
 REMOVE & SALVAGE DG (ASSUMED 3" THICK) 
231
                  
SF
26
                                
2,007.40
$                                
2,444.33
$ 
4,451.73
$ 
02.01.117
 REMOVE EX. CONCRETE SIDEWALK (ASSUMED 4" THICK) 
80
                    
SF
6
                                   
469.02
$                                    
13.82
$                                       
116.00
$                                    
570.66
$ 
1,169.50
$ 
02.01.124
 RELOCATE STORAGE CONTAINERS 
5
                       
EA
36
                                
2,814.11
$                                
1,825.50
$ 
4,639.61
$ 
02.01.131
 REMOVE EX. PLANT DRAIN PIPE-04" PVC 
99
                    
LF
24
                                
1,857.32
$                                
0.48
$                                         
2,263.62
$ 
4,121.42
$ 
02.01.132
 CAP EX. DEWATERING FILTRATE-08" 
3
                       
EA
36
                                
2,814.11
$                                
637.35
$                                    
3,423.96
$ 
6,875.42
$ 
02.01.134
 CAP EX. FILTERED WATER LINE-08" 
2
                       
EA
32
                                
2,443.39
$                                
383.92
$                                    
3,043.52
$ 
5,870.83
$ 
02.01.135
 REMOVE & SALVAGE RIP RAP (ASSUMED 1.5' THICK) 
2,604
              
SF
58
                                
4,523.53
$                                
2,170.05
$                                
5,506.88
$ 
12,200.46
$ 
02.01.121
REMOVE & SALVAGE RIVER ROCK (ASSUMED 1' THICK)
1,200
              
SF
18
                                
1,388.92
$                                
666.30
$                                    
1,692.96
$ 
3,748.18
$ 
02.01.130
REMOVE EX. STORM DRAIN-06" HDPE
322
                  
LF
77
                                
6,040.96
$                                
4.32
$                                         
7,352.01
$ 
13,397.29
$ 
02.01.137
 REMOVE EX. LIGHT, POLE, & BASE (ASSUMED 3' DIA X 5' DEEP) 
1
                       
EA
3
                                   
234.51
$                                    
16.61
$                                       
285.33
$ 
536.45
$ 
CONCRETE
                        1 
 LS 
                               311  $                             22,902.94  $                             21,448.04  $                          202,840.90  $                                               -    $                          247,191.88 
03.01.300
 CMU FTG 1260LF (C-12, 13, 16, 18, 19) 
195
                  
CY
250
                              
18,321.12
$                             
8,544.06
$                                
137,640.00
$                           
164,505.18
$ 
03.01.305
 LIGHTPOLES 
12
                    
EA
22,084.26
$                             
22,084.26
$ 
03.001.025
HEADWALL ON C-13/C-16
7
                       
CY
28
                                
2,116.68
$                                
6,451.99
$                                
12,456.84
$                             
21,025.51
$ 
03.01.330
 HEADWALL REPLACEMENT ON C-30 
16
                    
CY
33
                                
2,465.14
$                                
6,451.99
$                                
30,659.80
$                             
39,576.93
$ 
MASONRY
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                          278,067.22  $                                               -    $                          278,067.22 
01.04.805
 MASONRY SUBCONTRACT 
9,983
              
SF
243,316.04
$                           
243,316.04
$ 
32.11.114A
 TEMP FENCING 
430
                  
LF
34,751.18
$                             
34,751.18
$ 
MISC METALS
                        1 
 LS 
                                   -    $                                               -    $                             10,000.00  $                             24,682.73  $                                               -    $                             34,682.73 
01.50.800A
 INSTALL BOLLARDS PLUS CONCRETE 
40
                    
EA
10,000.00
$                             
10,000.00
$ 
01.500.800
 MISC METALS SUBCONTRACT  
40
                    
EA
24,682.73
$                             
24,682.73
$ 
PAINT & COATINGS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                             84,020.60  $                                               -    $                             84,020.60 
09.01.800
 PAINTING SUBCONTRACT - BOLLARDS & MASONRY WALL 
1
                       
LS
84,020.60
$                             
84,020.60
$ 
SPECIAL CONSTRUCTION
                        1 
 LS 
                                 23  $                                1,609.22  $                                9,200.00  $                                               -    $                                               -    $                             10,809.22 
13.01.700
 SIGNS 
46
                    
EA
23
                                
1,609.22
$                                
9,200.00
$                                
10,809.22
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
                        1 
 LS 
                           1,455  $                          106,359.23  $                             17,268.42  $                      2,500,367.93  $                          103,249.18  $                      2,727,244.76 
01.26.800
 SITE ELECTRICAL WORK  
1
                       
LS
2,500,367.93
$                       
2,500,367.93
$ 
01.26.805
 SITE ELECTRICAL DUCTBANK 
3,595
              
LF
1,455
                          
106,359.23
$                           
17,268.42
$                             
103,249.18
$ 
226,876.83
$ 
EROSION CONTROL
                        1 
 LS 
                               886  $                             68,479.87  $                             17,313.49  $                             46,800.00  $                          189,832.32  $                          322,425.68 
31.01.100A
 INSTALL SILT FENCE 
7,035
              
LF
182
                              
13,858.88
$                             
14,542.50
$                             
30,598.21
$ 
58,999.59
$ 
31.01.101A
 MONTHLY MAINTENANCE OF SILT FENCE 
26
                    
MO
390
                              
30,240.37
$                             
1,530.00
$                                
97,212.03
$ 
128,982.40
$ 
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
31.01.102
 REMOVE SILT FENCE 
7,035
              
LF
211
                              
16,332.03
$                             
10.99
$                                       
33,451.21
$ 
49,794.23
$ 
31.01.104A
 MONTHLY MAINTENANCE OF INLET PROTECTION 
26
                    
MO
34
                                
2,620.83
$                                
529.20
$                                    
7,512.00
$ 
10,662.03
$ 
31.01.105
 REMOVE INLET PROTECTION 
10
                    
EA
25
                                
1,938.49
$                                
4.80
$                                         
2,322.00
$ 
4,265.29
$ 
31.01.107
 REMOVE CONSTRUCTION EXITS 
2
                       
EA
45
                                
3,489.27
$                                
696.00
$                                    
18,736.87
$ 
22,922.14
$ 
31.01.108A
 STREET SWEEPING 
26
                    
MO
46,800.00
$                             
46,800.00
$ 
EARTHWORK
                        1 
 LS 
                           3,560  $                          395,504.68  $                             47,102.42  $                                               -    $                          151,910.57  $                          594,517.67 
19020B
 GMP 3-ADDITIONAL STAFF 
1
                       
LS
1,447
                          
216,227.87
$                           
(18,584.36)
$                            
197,643.51
$ 
31.01.300
RETENTION BASIN EXCAVATION
2,536
              
CY
1,304
                          
110,622.66
$                           
51,814.78
$                             
59,720.80
$ 
222,158.24
$ 
31.10.100A
 ROADWAY/SITE EXCAVATION 
2,890
              
CY
809
                              
68,654.15
$                             
13,872.00
$                             
92,189.77
$ 
174,715.92
$ 
PAVING, CURB & GUTTER
                        1 
 LS 
                           5,100  $                          444,082.76  $                          313,279.39  $                          653,020.91  $                          103,205.03  $                      1,513,588.09 
32.01.100
8' TALL CMU WALL PREP (SEE DETAIL ON S75-12)
1,070
              
LF
706
                              
54,852.49
$                             
34,327.27
$                             
14,285.50
$ 
103,465.26
$ 
32.01.101
7.5' TALL RETAINING WALL PREP (SEE DETAIL ON S75-11)
5
                       
LF
12
                                
1,077.93
$                                
156.52
$                                    
246.88
$ 
1,481.33
$ 
32.01.102
07" THICK CONCRETE PAVING ON 04" THICK ABC
756
                  
SF
18
                                
1,607.26
$                                
533.38
$                                    
12,604.39
$                             
366.28
$ 
15,111.31
$ 
32.01.103
09" THICK CONCRETE PAVING ON 04" THICK ABC
2,238
              
SF
54
                                
4,757.99
$                                
1,645.14
$                                
36,878.67
$                             
1,086.72
$ 
44,368.52
$ 
32.01.106
2'-0" RIBBON CURB PER MAG 220-1, TYPE B
3,238
              
LF
194
                              
17,209.97
$                             
12,841.20
$                             
134,643.21
$                           
3,932.05
$ 
168,626.43
$ 
32.01.107
04" THICK CONCRETE SIDEWALK ON 06" THICK ABC
218
                  
SF
6
                                   
531.50
$                                    
209.71
$                                    
4,829.50
$                                
121.41
$ 
5,692.12
$ 
32.01.108
CONCRETE VALLEY GUTTER PER MAG 240
3,592
              
SF
86
                                
7,636.59
$                                
4,726.00
$                                
49,733.35
$                             
1,744.43
$ 
63,840.37
$ 
32.01.109
RAISE & COLLAR EX. CLEANOUT PER DETAIL 6/CD-02
3
                       
EA
3,000.00
$                                
3,000.00
$ 
32.01.110
RAISE & COLLAR EX. MANHOLE
3
                       
EA
5,250.00
$                                
5,250.00
$ 
32.01.112
ASPHALT ROADWAY/DRIVEWAY REPLACEMENT-03" THICK
53,554
           
SF
643
                              
56,925.78
$                             
58,926.35
$                             
258,481.17
$                           
13,004.33
$ 
387,337.63
$ 
32.01.113
D50=04" RIP RAP, 06" THICK W/ FABRIC
7,472
              
SF
747
                              
66,189.47
$                             
14,333.41
$                             
15,121.13
$ 
95,644.01
$ 
32.01.114
PLACE 03" OF DG ONSITE
163,218
        
SF
1,584
                          
140,290.14
$                           
152,915.03
$                           
32,049.44
$ 
325,254.61
$ 
32.01.115
D50=06" RIP RAP, 12" THICK W/ FABRIC
6,234
              
SF
623
                              
55,222.85
$                             
23,010.51
$                             
12,615.78
$ 
90,849.14
$ 
32.01.116
D50=12" RIP RAP, 24" THICK W/ FABRIC
1,145
              
SF
229
                              
20,285.58
$                             
8,286.50
$                                
4,634.28
$ 
33,206.36
$ 
32.01.117
D50=04" RIP RAP, 08" THICK W/ FABRIC
535
                  
SF
54
                                
4,739.21
$                                
1,347.06
$                                
1,082.67
$ 
7,168.94
$ 
32.01.118
CHAIN LINK SECURITY FENCING-08' TALL
1,445
              
LF
137,600.62
$                           
137,600.62
$ 
32.01.119
LIGHT POLE BASE FOUNDATIONS-02' DIAMETER-PER E26-0601
12
                    
EA
144
                              
12,756.00
$                             
21.31
$                                       
2,914.13
$ 
15,691.44
$ 
32.01.125
ASPHALT AT GAC
1
                       
LS
10,000.00
$                             
10,000.00
$ 
FIBER OPTICS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                          310,015.00  $                                               -    $                          310,015.00 
33.01.100
 DIG AND BACKFILL NEW FIBER OPTIC 
1
                       
LS
60,015.00
$                             
60,015.00
$ 
33.01.101
 MOPO #11 
1
                       
LS
250,000.00
$                           
250,000.00
$ 
UTILITIES
                        1 
 LS 
                        57,770  $                      5,607,079.42  $                      8,030,531.42  $                          662,157.90  $                      1,698,251.40  $                    15,998,020.14 
19020B
 GMP 3-ADDITIONAL STAFF 
1
                       
LS
14,118
                       
2,126,398.95
$                       
(55,796.00)
$                            
2,070,602.95
$ 
33.01.300
 3" SOFTENED WATER-AVG. DEPTH-8.00' 
351
                  
LF
476
                              
36,270.36
$                             
25,333.24
$                             
1,404.00
$                                
18,506.74
$ 
81,514.34
$ 
33.01.301
BEDDING ENCASED DUCTBANK-7 (PARTIAL) & 8
50
                    
LF
364,054.59
$                           
364,054.59
$ 
33.01.303
 BEDDED/ENCASED CHEMICAL DUCT BANK-9-AVG. DEPTH-8.13' (2 CASE/4 CHEM 
LINES) 
501
                  
LF
1,279
                          
100,533.88
$                           
122,823.64
$                           
26,196.90
$                             
49,762.40
$ 
299,316.82
$ 
33.01.304
BEDDED/ENCASED CHEMICAL DUCT BANK-7-AVG. DEPTH-6.28' (2 CASE/2 CHEM LINES)
256
                  
LF
514
                              
39,788.15
$                             
36,935.58
$                             
20,589.00
$                             
19,977.32
$ 
117,290.05
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
33.01.305
 BEDDED/ENCASED CHEMICAL DUCT BANK-6-AVG. DEPTH-7.17' (2 CASE/2 CHEM 
LINES) 
82
  
LF
132
  
10,412.36
$  
  
6,560.70
$  
  
5,119.80
$ 
22,092.86
$ 
33.01.306
 BEDDED/ENCASED CHEMICAL DUCT BANK-5-AVG. DEPTH-6.76' (2 CASE/2 CHEM 
LINES) 
11
  
LF
18
  
1,413.57
$  
  
1,657.11
$  
  
696.39
$ 
3,767.07
$ 
33.01.307
 BEDDED/ENCASED CHEMICAL DUCT BANK-4-AVG. DEPTH-6.60' (7 CASE/7 CHEM 
LINES) 
15
  
LF
39
  
3,040.93
$  
  
5,161.04
$  
  
1,497.81
$ 
9,699.78
$ 
33.01.308
 BEDDED/ENCASED CHEMICAL DUCT BANK-3-AVG. DEPTH-4.00' (2 CASE/2 CHEM 
LINES) 
145
   
LF
387
  
29,878.41
$  
  
26,088.37
$  
  
19,152.30
$  
  
15,067.61
$ 
90,186.69
$ 
33.01.309
 BEDDED/ENCASED CHEMICAL DUCT BANK-1-AVG. DEPTH-6.37' (8 CASE/8 CHEM 
LINES) 
251
   
LF
727
  
57,006.96
$  
  
56,730.91
$  
  
7,179.60
$  
  
28,279.49
$ 
149,196.96
$ 
33.01.310
 BEDDED/ENCASED CHEMICAL DUCT BANK-2-AVG. DEPTH-7.04' (6 CASE/6 CHEM 
LINES) 
296
   
LF
949
  
73,863.28
$  
  
65,775.72
$  
  
27,681.90
$  
  
36,924.01
$ 
204,244.91
$ 
33.01.311
 BEDDED/ENCASED CHEMICAL DUCT BANK-2A-AVG. DEPTH-6.87' (4 CASE/4 CHEM 
LINES) 
57
  
LF
178
  
13,781.55
$  
  
14,243.91
$  
  
7,035.00
$  
  
6,921.06
$ 
41,981.52
$ 
33.01.312
 BEDDED/ENCASED CHEMICAL DUCT BANK-2B-AVG. DEPTH-5.47' (2 CASE/2 CHEM 
LINES) 
42
  
LF
104
  
8,020.95
$  
  
8,752.26
$  
  
5,510.10
$  
  
4,057.71
$ 
26,341.02
$ 
33.01.312B
 BEDDED/ENCASED CHEMICAL DUCT BANK-10-AVG. DEPTH-6.46' (4 CASE/4 CHEM 
LINES) 
183
   
LF
501
  
38,746.07
$  
  
41,051.15
$  
  
21,938.60
$  
  
19,498.80
$ 
121,234.62
$ 
33.01.312C
 BEDDED/ENCASED CHEMICAL DUCT BANK-11-AVG. DEPTH-3.64' (4 CASE/4 CHEM 
LINES) 
110
   
LF
193
  
15,227.46
$  
  
11,961.08
$  
  
7,504.63
$ 
34,693.17
$ 
33.01.312D
 BEDDED/ENCASED CHEMICAL DUCT BANK-12-AVG. DEPTH-5.87' (6 CASE/10 CHEM 
LINES) 
224
   
LF
787
  
61,194.99
$  
  
97,496.02
$  
  
19,895.80
$  
  
30,602.07
$ 
209,188.88
$ 
33.01.312E
 BEDDED/ENCASED CHEMICAL DUCT BANK-13-AVG. DEPTH-6.43' (5 CASE/9 CHEM 
LINES) 
559
   
LF
1,491
  
117,108.58
$  
   
201,097.48
$  
   
34,758.00
$  
  
57,998.43
$ 
410,962.49
$ 
33.01.313
 INSTALL CHEMICAL VAULT-5'X5'-AVG. DEPTH-7.50' 
14
  
EA
630
  
49,804.15
$  
  
140,607.33
$  
   
24,509.67
$ 
214,921.15
$ 
33.01.314
 INSTALL CHEMICAL VAULT-4'X4'-AVG. DEPTH-6.03' 
1  
EA
45
  
3,557.44
$  
  
6,245.71
$  
  
1,750.69
$ 
11,553.84
$ 
33.01.315
 INSTALL CHEMICAL VAULT-3'X3'-AVG. DEPTH-7.83' 
7  
EA
360
  
28,459.51
$  
  
35,852.10
$  
  
14,005.52
$ 
78,317.13
$ 
33.01.315A
 INSTALL TRANSITION VAULT-4'X4'-AVG. DEPTH-8.29' 
3  
EA
158
  
12,451.04
$  
  
18,780.52
$  
  
6,127.42
$ 
37,358.98
$ 
33.01.318
 6" PERFORATED HDPE STORM-AVG. DEPTH-2.00' 
256
   
LF
213
  
16,864.90
$  
  
7,050.99
$  
  
8,298.27
$ 
32,214.16
$ 
33.01.319
 24" RCP STORM-AVG. DEPTH-4.04' 
48
  
LF
195
  
14,876.61
$  
  
12,192.93
$  
  
3,397.00
$  
  
7,601.89
$ 
38,068.43
$ 
33.01.319A
12" HDPE STORM-AVG. DEPTH-2.85'
196
   
LF
259
  
20,242.35
$  
  
12,005.61
$  
  
1,470.00
$  
  
10,087.87
$ 
43,805.83
$ 
33.01.327
 REROUTE EX. 4" PVC PUMP DISCHARGE LINE-ASSUMED AVG. DEPTH-3.43' 
167
   
LF
255
  
19,445.30
$  
  
13,960.91
$  
  
9,908.91
$ 
43,315.12
$ 
33.01.328
 REROUTE EX. 8" FILTERED WATER LINE-ASSUMED AVG. DEPTH-7.00' 
138
   
LF
356
  
27,154.26
$  
  
16,601.20
$  
  
576.00
$  
  
13,834.34
$ 
58,165.80
$ 
33.01.329
 6" CL 350 DIP FIRE LINE-AVG. DEPTH-6.42' 
584
   
LF
1,372
  
104,482.14
$  
   
179,238.62
$  
   
4,425.00
$  
  
53,368.82
$ 
341,514.58
$ 
33.01.330
 2" PEX/6" CL 350 DIP POTABLE WATER-AVG. DEPTH-5.89' 
639
   
LF
1,069
  
81,203.23
$  
  
89,702.23
$  
  
4,853.03
$  
  
41,569.17
$ 
217,327.66
$ 
33.01.331
 4" PVC SEWER-AVG. DEPTH-5.18' 
420
   
LF
1,110
  
84,755.04
$  
  
33,070.08
$  
  
5,970.00
$  
  
43,183.70
$ 
166,978.82
$ 
33.01.333
 1" SCH. 80 PVC SAMPLE PIPE-ASSUMED AVG. DEPTH-3.00' 
2,166
   
LF
1,793
  
136,403.45
$  
   
51,426.24
$  
  
29,481.88
$  
  
69,770.85
$ 
287,082.42
$ 
33.01.340
 36" WSP BACKWASH WASTE (BWW)-AVG. DEPTH-9.74' 
1,057
   
LF
4,926
  
396,798.91
$  
   
2,555,587.17
$  
   
263,707.20
$  
   
191,626.68
$ 
3,407,719.96
$ 
33.01.342
 42" WSP FILTERED WATER (FW)-GAC WETWELL TO SEAL WEIR-AVG. DEPTH-14.23' 
464
   
LF
3,198
  
257,363.98
$  
   
331,618.56
$  
   
80,663.81
$  
  
124,404.06
$ 
794,050.41
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
33.01.343
 60" WSP FILTERED WATER (FW)-EFFLUENT CONNECTION TO SEAL WEIR-AVG. DEPTH-
16.30' 
135
   
LF
4,413
  
358,986.11
$  
   
1,064,167.73
$  
   
94,386.89
$  
  
171,676.59
$ 
1,689,217.32
$ 
33.01.345
 48" WSP GAC EFFLUENT (GE) TO 48"X60" REDUCER-AVG. DEPTH-16.60' 
420
   
LF
1,835
  
147,891.72
$  
   
421,540.16
$  
   
69,576.28
$  
  
71,373.70
$ 
710,381.86
$ 
33.01.346
 6' SAMPLING MANHOLE-48" GE-DEPTH-18.61' 
1  
EA
216
  
17,720.13
$  
  
29,483.59
$  
  
1,750.00
$  
  
8,403.31
$ 
57,357.03
$ 
33.01.346A
 6' SAMPLING MANHOLE-60" FW-DEPTH-24.26' 
1  
EA
162
  
13,430.50
$  
  
33,655.95
$  
  
1,750.00
$  
  
6,302.49
$ 
55,138.94
$ 
33.01.348
60" WSP FINISH WATER (FW) 48"X60" REDUCER TO 60X60 TEE (STA 9+01)-AVG. DEPTH-
22.11' 
481
   
LF
4,880
  
394,801.86
$  
   
942,157.31
$  
   
112,066.74
$  
   
189,844.87
$ 
1,638,870.78
$ 
33.01.349
 60"/54"/36"/30" WSP FINISH WATER (FW) 60X60 TEE (STA 9+01) TO TANKS-AVG. 
DEPTH-23.75' 
305
   
LF
5,958
  
485,448.05
$  
   
1,385,868.58
$  
   
58,126.37
$  
  
231,795.30
$ 
2,161,238.30
$ 
33.01.355
 CONNECT TO EX. CAOCL LINE-1.5"-AVG. DEPTH-7.38' 
2  
EA
113
  
8,893.60
$  
  
1,959.20
$  
  
4,376.73
$ 
15,229.53
$ 
33.01.358
 18" CL350 DIP FILTER TO WASTE (FTW) REROUTE-AVG. DEPTH-10.62' 
43
  
LF
417
  
34,405.88
$  
  
36,258.87
$  
  
6,540.00
$  
  
16,223.06
$ 
93,427.81
$ 
33.01.360
 16" WSP BACKWASH RECIRCULATION (BWR) REROUTE-AVG. DEPTH-10.06' 
237
   
LF
1,948
  
158,952.81
$  
   
170,655.31
$  
   
29,425.38
$  
  
75,793.22
$ 
434,826.72
$ 
33.01.370
DEDUCT FOR EXPORT/IMPORT REPLACED BY  NATIVE FILL IN NON PIPE ZONE AREAS
1  
LS
-   
(225,027.69)
$  
  
(36,403.47)
$  
  
(261,431.16)
$ 
33.43.300A
 GMP 2-CHANGE ORDER- DEDUCT TO GO TO DEFINED SCOPE 
1  
LS
(100,000.00)
$  
  
(100,000.00)
$ 
33.43.305A
 GMP 2-CHANGE ORDER- DEDUCT TO GO TO DEFINED SCOPE 
1  
LS
(525,000.00)
$  
  
(525,000.00)
$ 
 10 
 WEIR STRUCTURE 
  1 
 LS 
  11,001  $  
  1,091,689.42  $  
  1,146,957.40  $  
  375,940.55  $  
  189,923.00  $  
  2,804,510.37 
CONCRETE
  1 
 LS 
  7,118  $  
  758,219.09  $  
  169,217.42  $  
  88,838.91  $  
  72,759.00  $  
  1,089,034.42 
19020
 SELF-PERFORM STAFF 
1  
LS
2,851
  
418,264.55
$  
   
418,264.55
$ 
03.010.000
 SEAL WATER STRUCT. - SOG 
53
  
CY
262
  
19,728.84
$  
  
15,963.41
$  
  
2,346.68
$  
  
38,038.93
$ 
03.010.005
 SEAL WATER - PERIMETER WALLS 
143
   
CY
2,570
  
197,644.05
$  
   
70,558.87
$  
  
6,065.56
$  
  
274,268.48
$ 
03.010.010
 SW - WEIR WALL 
24
  
CY
383
  
29,463.30
$  
  
11,302.29
$  
  
1,044.80
$  
  
41,810.39
$ 
03.010.020
 SW - ELEV. DECK & BEAMS 
24
  
CY
430
  
33,057.96
$  
  
16,219.21
$  
  
1,013.20
$  
  
50,290.37
$ 
03.010.022
 PUMP FND SOG 
2  
CY
54
  
4,054.37
$  
  
2,317.39
$  
  
6,371.76
$ 
03.010.023
 PUMP PADS 
1  
CY
24
  
1,829.93
$  
  
1,310.05
$  
  
3,139.98
$ 
03.010.025
 BLIND FLANGE MATERIAL/LEAK TEST SEAL WEIR 
54,620
  
GAL
151
  
11,070.04
$  
  
26,546.20
$  
  
37,616.24
$ 
03.010.099
 REBAR - SEAL WEIR STRUCT. 
78,520
  
LBS
78,368.67
$  
  
78,368.67
$ 
03.010.105
 SEAL WATER - PERIMETER WALL PIPE (SET) 
1  
LS
42
  
3,151.23
$  
  
25,000.00
$  
  
28,151.23
$ 
03.10.999
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK 
1  
LS
352
  
39,954.82
$  
  
72,759.00
$ 
112,713.82
$ 
MISC METALS
  1 
 LS 
- 
$
 -  $
- 
$
  56,874.73  $  
 - 
$
  56,874.73 
05.10.700
 MISC METALS SUBCONTRACT  
1  
LS
56,874.73
$  
  
56,874.73
$ 
FRP MATERIALS
  1 
 LS 
  32  $  
  2,408.14  $  
  3,375.00  $  
 -
 $
 -  $
  5,783.14 
06.10.700
 FRP WEIR PLATES 
27
  
LF
32
  
2,408.14
$  
  
3,375.00
$  
  
5,783.14
$ 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  25,000.00  $  
- 
$
  25,000.00 
09.10.700
 PAINTING SUBCONTRACT 
1  
LS
25,000.00
$  
  
25,000.00
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  167,885.26  $  
 - 
$
  167,885.26 
10.26.800
 WEIR STRUCTURE EI&C 
1  
LS
167,885.26
$  
   
167,885.26
$ 
EARTHWORK
  1 
 LS 
  1,976  $  
  179,442.12  $  
  221,022.28  $  
  539.50  $  
  65,740.00  $  
  466,743.90 
31.10.100
 EXCAVATION 
4,921
   
CY
1,230
  
111,697.35
$  
   
23,620.80
$  
  
40,931.00
$ 
176,249.15
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
31.10.200
 BACKFILL WEIR STRUCTURE 
4,442
              
CY
746
                              
67,744.77
$                             
197,401.48
$                           
539.50
$                                    
24,809.00
$ 
290,494.75
$ 
PROCESS PIPE & VALVES
                        1 
 LS 
                           1,444  $                          117,203.95  $                          584,735.24  $                             33,802.15  $                                               -    $                          735,741.34 
40.10.200
 1" CPVC CHEMICAL HFSA ( HYDROFLUOSILICIC ACID) 
110
                  
LF
95
                                
7,479.33
$                                
5,144.42
$                                
45.62
$                                       
12,669.37
$ 
40.10.201
 2" CPVC CHEMIACL NAOCI (SODIUM HYPOCHLORITE) 
36
                    
LF
83
                                
6,633.89
$                                
8,059.18
$                                
14,693.07
$ 
40.10.202
 1" CS SCH 40 WELD CHEMIACL NAOH ( SODIUM HYDROXIDE) 
42
                    
LF
73
                                
5,882.82
$                                
2,925.47
$                                
7,000.00
$                                
15,808.29
$ 
40.10.300
 SAMPLE PIPING AT SEAL WEIR & SAMPLING MANHOLE 
140
                  
LF
167
                              
13,265.27
$                             
13,095.77
$                             
22.60
$                                       
26,383.64
$ 
40.10.400
 FW 60" / 42" CARBON STEEL & DYNAMIC MOVEMENT JOINTS 
24
                    
LF
912
                              
74,776.75
$                             
495,596.28
$                           
21,874.67
$                             
592,247.70
$ 
40.10.500
 BWR 16" CARBON STEEL & DYNAMIC MOVEMENT JOINT 
32
                    
LF
115
                              
9,165.89
$                                
44,914.12
$                             
4,859.26
$                                
58,939.27
$ 
40.10.501
 30" VENT 
1
                       
LS
15,000.00
$                             
15,000.00
$ 
PROCESS EQUIPMENT
                        1 
 LS 
                               431  $                             34,416.12  $                          168,607.46  $                                3,000.00  $                             51,424.00  $                          257,447.58 
46.10.200
 SEAL WATER SAMPLE SUMP PUMPS 
3
                       
EA
63
                                
4,965.66
$                                
13,806.00
$                             
2,000.00
$                                
20,771.66
$ 
46.10.205
 SEAL WATER SLIDE GATES 
3
                       
EA
332
                              
26,589.38
$                             
102,028.00
$                           
128,617.38
$ 
46.10.210
 CHLORINE INJECTION ASSEMBLIES 
2
                       
EA
36
                                
2,861.08
$                                
52,773.46
$                             
1,000.00
$                                
56,634.54
$ 
46.10.999
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK 
1
                       
LS
51,424.00
$ 
51,424.00
$ 
 30 
 EXISTING RAW WATER PUMP STATION 1 
                        1 
 LS 
                               156  $                             12,478.18  $                             35,685.73  $                                4,075.88  $                                               -    $                             52,239.79 
PAINT & COATINGS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                                1,270.60  $                                               -    $                                1,270.60 
09.30.700
 PAINTING SUBCONTRACT 
1
                       
LS
1,270.60
$                                
1,270.60
$ 
PROCESS PIPE & VALVES
                        1 
 LS 
                               138  $                             11,047.64  $                                9,299.00  $                                2,305.28  $                                               -    $                             22,651.92 
40.30.430
 ABANDON EXISTING NAOCI  
1
                       
LS
16
                                
1,289.23
$                                
100.00
$                                    
75.00
$                                       
1,464.23
$ 
40.30.440
 1-1/2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE) 
20
                    
LF
50
                                
4,001.55
$                                
3,250.05
$                                
7,251.60
$ 
40.30.450
 3" CPVC CHEMICAL CIO2 (CHLORTINE DIOXIDE) 
15
                    
LF
72
                                
5,756.86
$                                
5,948.95
$                                
2,230.28
$                                
13,936.09
$ 
PROCESS EQUIPMENT
                        1 
 LS 
                                 18  $                                1,430.54  $                             26,386.73  $                                    500.00  $                                               -    $                             28,317.27 
46.30.210
 CHLORINE INJECTION ASSEMBLIES 
1
                       
EA
18
                                
1,430.54
$                                
26,386.73
$                             
500.00
$                                    
28,317.27
$ 
 35 
 EXISTING RAW WATER PUMP STATION 2 
                        1 
 LS 
                               183  $                             14,674.79  $                             37,775.40  $                                4,075.88  $                                               -    $                             56,526.07 
PAINT & COATINGS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                                1,270.60  $                                               -    $                                1,270.60 
09.35.700
 PAINTING SUBCONTRACT 
1
                       
LS
1,270.60
$                                
1,270.60
$ 
PROCESS PIPE & VALVES
                        1 
 LS 
                               165  $                             13,244.25  $                             11,388.67  $                                2,305.28  $                                               -    $                             26,938.20 
40.35.430
 ABANDON EXISTING NAOCI  
1
                       
LS
16
                                
1,289.23
$                                
100.00
$                                    
75.00
$                                       
1,464.23
$ 
40.35.440
 1-1/2" CPVC CHEMICAL NAOCI (SODIUM HYPOCHLORITE) 
50
                    
LF
66
                                
5,318.24
$                                
5,604.10
$                                
10,922.34
$ 
40.35.450
 3" CPVC CHEMICAL CIO2 (CHLORTINE DIOXIDE) 
23
                    
LF
83
                                
6,636.78
$                                
5,684.57
$                                
2,230.28
$                                
14,551.63
$ 
PROCESS EQUIPMENT
                        1 
 LS 
                                 18  $                                1,430.54  $                             26,386.73  $                                    500.00  $                                               -    $                             28,317.27 
46.35.210
 CHLORINE INJECTION ASSEMBLIES 
1
                       
EA
18
                                
1,430.54
$                                
26,386.73
$                             
500.00
$                                    
28,317.27
$ 
 42 
 GAC PUMP STATION 
                        1 
 LS 
                        36,392  $                      3,709,672.48  $                      5,180,265.00  $                          810,553.12  $                      1,539,991.00  $                    11,240,481.60 
CONCRETE
                        1 
 LS 
                        27,616  $                      2,714,956.18  $                          671,690.51  $                          575,133.79  $                      1,357,200.00  $                      5,318,980.48 
19020
 SELF-PERFORM STAFF 
1
                       
LS
7,176
                          
1,028,063.40
$                       
1,028,063.40
$ 
03.042.000
 PUMP STATION SOG 
463
                  
CY
2,555
                          
192,709.99
$                           
131,963.44
$                           
20,376.00
$                             
345,049.43
$ 
03.042.004
 PS - LAUNDERER DECK 
4
                       
CY
69
                                
5,338.25
$                                
2,438.31
$                                
150.76
$                                    
7,927.32
$ 
03.042.005
 PUMP STATION PERIMETER WALLS 
738
                  
CY
9,995
                          
767,265.92
$                           
307,391.78
$                           
31,297.16
$                             
1,105,954.86
$ 
03.042.006
 PS - COLUMNS 
12
                    
CY
310
                              
23,744.58
$                             
8,542.94
$                                
501.64
$                                    
32,789.16
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
03.042.007
 PS - PUMP BAFFLE WALL 
22
                    
CY
742
                              
57,099.59
$                             
12,653.51
$                             
932.80
$                                    
70,685.90
$ 
03.042.008
 PS - BEAMS IN DECK 
49
                    
CY
950
                              
73,454.80
$                             
20,048.55
$                             
2,014.20
$                                
95,517.55
$ 
03.042.009
 PS - DECK LAUNDER WALL 
3
                       
CY
83
                                
6,361.04
$                                
4,645.31
$                                
136.80
$                                    
11,143.15
$ 
03.042.010
 PS - SUPPORTED PUMP DECK 
400
                  
CY
2,007
                          
152,425.88
$                           
158,208.87
$                           
16,800.00
$                             
327,434.75
$ 
03.042.011
 FEED PUMP CANS EQUIP PADS TOP DECK 
4
                       
CY
158
                              
12,094.59
$                             
6,812.81
$                                
148.80
$                                    
19,056.20
$ 
03.042.012
 PS - 2 STAIR LANDINGS & GRADE BEAM FND 
5
                       
CY
83
                                
6,293.81
$                                
1,822.64
$                                
198.80
$                                    
8,315.25
$ 
03.042.013
 BLIND FLANGE MATERIAL/LEAK TEST PUMP STATION 
790,588
        
GAL
144
                              
10,533.58
$                             
17,162.35
$                             
27,695.93
$ 
03.042.099
 REBAR - GAC PUMP STATION 
469,584
        
LBS
502,576.83
$                           
502,576.83
$ 
03.42.999
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK 
1
                       
LS
3,344
                          
379,570.75
$                           
1,357,200.00
$ 
1,736,770.75
$ 
MISC METALS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                          176,898.73  $                                               -    $                          176,898.73 
05.42.700
 MISC METALS SUBCONTRACT  
1
                       
LS
176,898.73
$                           
176,898.73
$ 
PAINT & COATINGS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                             30,020.60  $                                               -    $                             30,020.60 
09.42.700
 PAINTING SUBCONTRACT 
1
                       
LS
30,020.60
$                             
30,020.60
$ 
PROCESS PIPE & VALVES
                        1 
 LS 
                           1,575  $                          126,596.10  $                      1,163,158.49  $                                4,500.00  $                                               -    $                      1,294,254.59 
40.42.400
 FW 24"/36" CARBON STEEL AND VALVES 
107
                  
LF
497
                              
39,929.39
$                             
533,371.39
$                           
2,250.00
$                                
575,550.78
$ 
40.42.410
 BWS 24"/36" CARBON STEEL AND VALVES 
124
                  
LF
509
                              
40,919.15
$                             
419,836.30
$                           
2,250.00
$                                
463,005.45
$ 
40.42.420
 OF 42" CARBON STEEL AND FLAP GATE 
11
                    
LF
119
                              
9,591.47
$                                
10,071.34
$                             
19,662.81
$ 
40.42.430
 FW 42"/30" CARBON STEEL AND VALVES IN WET WELL 
26
                    
LF
189
                              
15,196.00
$                             
165,111.34
$                           
180,307.34
$ 
40.42.440
 BWS/FW 36" PIPING BETWEEN STRUCTURES 
2
                       
EA
64
                                
5,113.02
$                                
10,450.00
$                             
15,563.02
$ 
40.42.445
 DRAIN 2" / 4" CPVC AIR RELEASE VENT DRAIN PIPING 
320
                  
LF
198
                              
15,847.07
$                             
24,318.12
$                             
40,165.19
$ 
PROCESS EQUIPMENT
                        1 
 LS 
                           7,201  $                          868,120.20  $                      3,345,416.00  $                             24,000.00  $                          182,791.00  $                      4,420,327.20 
19020
 SELF-PERFORM STAFF 
1
                       
LS
5,223
                          
692,206.26
$                           
36,000.00
$                             
728,206.26
$ 
46.42.500
 GAC PS FLAP GATE 
1
                       
EA
71
                                
5,715.52
$                                
15,358.00
$                             
21,073.52
$ 
46.42.505
 GAC FEED PUMPS 
4
                       
EA
788
                              
63,009.26
$                             
1,882,319.00
$                       
13,000.00
$                             
1,958,328.26
$ 
46.42.510
 GAC BACKWASH PUMPS 
3
                       
EA
591
                              
47,256.94
$                             
1,411,739.00
$                       
11,000.00
$                             
1,469,995.94
$ 
46.42.999
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK 
1
                       
LS
528
                              
59,932.22
$                             
182,791.00
$ 
242,723.22
$ 
 43 
 POST FILTER GAC CONTACTORS 
                        1 
 LS 
                     116,142  $                    11,005,342.27  $                    11,091,323.31  $                      6,416,817.79  $                      3,224,899.46  $                    31,738,382.83 
CONCRETE
                        1 
 LS 
                        83,316  $                      7,644,344.25  $                      2,797,123.92  $                      1,608,430.10  $                      2,320,500.00  $                    14,370,398.27 
19020
 SELF-PERFORM STAFF 
1
                       
LS
16,293
                       
2,390,213.10
$                       
2,390,213.10
$ 
03.043.015
 CONTACTOR & CHANNEL SOG - N/S 
1,011
              
CY
5,017
                          
376,998.35
$                           
295,842.57
$                           
43,238.40
$                             
716,079.32
$ 
03.043.020
 GAG PIPE GALLERY SOG 
589
                  
CY
2,974
                          
222,231.54
$                           
171,893.64
$                           
25,916.40
$                             
420,041.58
$ 
03.043.023
 CONTACTOR LAUNDER DIVIDER WALLS 
390
                  
CY
6,128
                          
471,921.68
$                           
192,636.65
$                           
16,541.92
$                             
681,100.25
$ 
03.043.030
 NORTH/SOUTH PIPE GALLARY WALLS - 2'WIDE 
649
                  
CY
8,270
                          
635,977.24
$                           
287,466.97
$                           
27,519.12
$                             
950,963.33
$ 
03.043.040
 NORTH/SOUTH BAFFLE WALL 
293
                  
CY
5,009
                          
385,582.81
$                           
145,877.50
$                           
12,424.00
$                             
543,884.31
$ 
03.043.045
 NORTH/SOUTH/EAST CHANNEL INNER WALL 
348
                  
CY
6,565
                          
505,421.37
$                           
169,274.58
$                           
14,760.00
$                             
689,455.95
$ 
03.043.050
 NORTH/SOUTH EXTERIOR WALLS 
498
                  
CY
7,136
                          
547,884.36
$                           
214,932.43
$                           
21,118.32
$                             
783,935.11
$ 
03.043.051
 WEST END WALLS 
102
                  
CY
1,515
                          
116,365.05
$                           
43,482.45
$                             
4,313.80
$                                
164,161.30
$ 
03.043.052
 WEST DOCK WALL 
57
                    
CY
889
                              
68,304.05
$                             
23,627.07
$                             
2,422.84
$                                
94,353.96
$ 
03.043.053
 EAST EXTERIOR WALL 
155
                  
CY
2,314
                          
177,739.64
$                           
66,773.64
$                             
6,567.28
$                                
251,080.56
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
03.043.054
 NORTHEAST CORNER WEIR WALL 
5
                       
CY
104
                              
7,970.54
$                                
2,570.44
$                                
198.76
$                                    
10,739.74
$ 
03.043.055
 CHANNEL DECKS NORTH/SOUTH/EAST 
121
                  
CY
1,749
                          
132,282.85
$                           
306,269.01
$                           
5,132.00
$                                
443,683.86
$ 
03.043.057
 ELEV. DECKS OVER CHANNELS 
134
                  
CY
3,648
                          
278,227.13
$                           
95,894.90
$                             
5,690.28
$                                
379,812.31
$ 
03.043.060
 GALLARY ELEVATED BEAMS & DECK 
271
                  
CY
5,677
                          
436,485.86
$                           
173,398.07
$                           
11,558.80
$                             
621,442.73
$ 
03.043.061
 ELEVATED DECK ROOF CURBING 
3
                       
CY
251
                              
19,236.36
$                             
3,895.94
$                                
23,132.30
$ 
03.043.064
 DOOR STOOP, STAIR FTR & LANDING, 2 EQUIP PADS 
5
                       
CY
92
                                
7,040.61
$                                
1,932.41
$                                
180.28
$                                    
9,153.30
$ 
03.043.066
 GAC OVERHEAD DOOR APPROACH SOG 
4
                       
CY
43
                                
3,261.00
$                                
1,412.83
$                                
169.48
$                                    
4,843.31
$ 
03.043.067
 GAC WEST PONY WALL AT ROLL-UP DOOR AREA 
6
                       
CY
142
                              
10,856.53
$                             
5,875.50
$                                
257.36
$                                    
16,989.39
$ 
03.043.068
 ROLL-UP DOOR SUPPORTED DECK AT DOCK ENTRY 
6
                       
CY
89
                                
6,753.49
$                                
7,800.36
$                                
250.00
$                                    
14,803.85
$ 
03.043.075
 BLIND FLANGE MATERIAL/LEAK TEST GAC 
1,401,191
    
GAL
236
                              
17,730.17
$                             
59,511.91
$                             
77,242.08
$ 
03.043.080
 GAC WEIR - SOG 
32
                    
CY
179
                              
13,439.27
$                             
10,282.12
$                             
1,425.92
$                                
25,147.31
$ 
03.043.082
 GAC WEIR - WALLS & WEIR WALL 
96
                    
CY
2,228
                          
171,128.20
$                           
48,544.87
$                             
4,060.72
$                                
223,733.79
$ 
03.043.084
 GAC WEIR - ELEV. DECK 
10
                    
CY
179
                              
13,627.99
$                             
7,341.10
$                                
438.12
$                                    
21,407.21
$ 
03.043.085
 BLIND FLANGE MATERIAL/LEAK TEST WEIR STRUCTURE 
21,739
           
GAL
80
                                
5,903.88
$                                
10,586.96
$                             
16,490.84
$ 
03.043.099
 REBAR - POST FILTER GAC FACILITY 
1,507,793
    
LBS
1,404,246.30
$                       
1,404,246.30
$ 
03.43.399
 SAFETY & ACCESS CONTROLS (SCAFFOLDING, STAIRS, HANDRAIL, LADDERS) 
18
                    
MOS
3,168
                          
242,190.43
$                           
450,000.00
$                           
692,190.43
$ 
03.43.999
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK 
1
                       
LS
3,344
                          
379,570.75
$                           
2,320,500.00
$ 
2,700,070.75
$ 
MISC METALS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                          755,977.73  $                                               -    $                          755,977.73 
05.43.700
 MISC METALS SUBCONTRACT  
1
                       
LS
755,977.73
$                           
755,977.73
$ 
FRP MATERIALS
                        1 
 LS 
                                 30  $                                2,293.47  $                                3,175.00  $                                7,500.00  $                                               -    $                             12,968.47 
06.43.705
 FRP LADDER 25' W/ SAFETY CLIMB SYSTEM 
1
                       
EA
0
                                   
25.48
$                                       
7,500.00
$                                
7,525.48
$ 
06.43.710
 FRP WEIR PLATES 
25
                    
LF
30
                                
2,267.99
$                                
3,175.00
$                                
5,442.99
$ 
DOORS & WINDOWS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                             46,804.43  $                                               -    $                             46,804.43 
08.43.700
 SINGLE HM DOOR 
2
                       
EA
20,000.00
$                             
20,000.00
$ 
08.43.705
 OH COILING DOOR 
1
                       
EA
26,804.43
$                             
26,804.43
$ 
PAINT & COATINGS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                          270,959.60  $                                               -    $                          270,959.60 
09.43.700
 PAINTING SUBCONTRACT 
1
                       
LS
142,020.60
$                           
142,020.60
$ 
09.43.702
 XYPEX/WATERPROOFING 
1
                       
LS
128,939.00
$                           
128,939.00
$ 
09.43.705
 GAC CHANNEL COATINGS 
1
                       
LS
-
$ 
PLUMBING & HVAC
                        1 
 LS 
                               411  $                             30,825.23  $                             38,219.78  $                          374,902.04  $                                               -    $                          443,947.05 
22.43.800
 GAC PLUMBING 
1
                       
LS
237,000.00
$                           
237,000.00
$ 
22.43.801
 DRAIN PIPE ENCASEMENT 
1
                       
LS
411
                              
30,825.23
$                             
38,219.78
$                             
4,986.68
$                                
74,031.69
$ 
23.43.800
 LOUVERS AND VENTS 
1
                       
LS
132,915.36
$                           
132,915.36
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
                        1 
 LS 
                                   -    $                                               -    $                                               -    $                      1,819,161.34  $                                               -    $                      1,819,161.34 
26.43.800
 POST FILTER GAC CONTACTORS EI&C 
1
                       
LS
1,819,161.34
$                       
1,819,161.34
$ 
EARTHWORK
                        1 
 LS 
                         (1,673)  $                         (116,943.36)  $                          304,837.10  $                          337,549.91  $                                6,365.46  $                          531,809.11 
19020A
 GMP 3-DEDUCT TO SALARY STAFF TO GO TO SUB 
1
                       
LS
(771)
                            
(92,688.11)
$                            
(55,796.00)
$                            
(148,484.11)
$ 
31.43.300A
 GMP 3-DEDUCT TO SELF-PERFORM WORK TO GO TO SUB 
1
                       
LS
(2,104)
                        
(137,266.12)
$                         
40,275.00
$                             
(162,733.00)
$ 
(259,724.12)
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
31.43.300B
 GMP 2 CHANGE ORDER-ADDER FOR SHORING SUB TO GO FROM TIE BACK TO BEAM 
& LAG 
1  
LS
130,318.51
$  
   
130,318.51
$ 
31.43.300C
 GMP 2 CHANGE ORDER-ADDER TO TRUCK MATERIAL OFF SITE 
1  
LS
179,456.40
$  
   
179,456.40
$ 
31.43.301A
 GMP 2 CHANGE ORDER-DEDUCT TO GO TO SUB 
1  
LS
(150)
 
(9,785.85)
$
  
(12,500.00)
$  
  
(6,160.00)
$ 
(28,445.85)
$ 
31.43.305
 BACKFILL FOR GAC 
8,115
   
CY
1,353
  
122,796.72
$  
   
360,633.10
$  
   
175,258.46
$ 
658,688.28
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  7,816  $  
  628,921.59  $  
  4,665,338.51  $  
  54,488.64  $  
- 
$
  5,348,748.74 
40.43.400
 FW 24" WALL PIPE & VALVES 
10
  
EA
303
  
24,415.33
$  
  
514,938.29
$  
   
539,353.62
$ 
40.43.410
 BWS 24"/36" CARBON STEEL AND VALVES 
383
   
LF
1,686
  
135,814.38
$  
   
947,981.38
$  
   
4,500.00
$  
  
1,088,295.76
$ 
40.43.420
 BWW 36" WALL PIPE & VALVES 
10
  
EA
606
  
48,803.56
$  
  
1,154,114.30
$  
   
1,202,917.86
$ 
40.43.430
 CTW 16" FAB SPOOL 
10
  
LF
122
  
9,822.13
$  
  
2,399.14
$  
  
12,221.27
$ 
40.43.440
 GE 14"/36" CARBON STEEL AND VALVES 
332
   
LF
2,521
  
202,353.30
$  
   
1,058,301.75
$  
   
4,500.00
$  
  
1,265,155.05
$ 
40.43.560
 FILTER BED SAMPLE PIPING & SAMPLE PUMP STATION 
1  
LS
175
  
13,972.75
$  
  
11,254.00
$  
  
75.48
$  
   
25,302.23
$ 
40.43.580
 4" GS GAC SLURRY 316 SS 
160
   
LF
266
  
21,452.27
$  
  
86,983.48
$  
  
108,435.75
$ 
40.43.590
 36" BWW ENCASED PIPE AT GAC 
40
  
LF
440
  
34,629.58
$  
  
244,713.95
$  
   
1,869.64
$  
  
281,213.17
$ 
40.43.595
 48" GE ENCASED PIPE AT EFF WEIR STRUCTURE 
28
  
LF
725
  
58,680.70
$  
  
293,320.16
$  
   
17,315.10
$  
  
369,315.96
$ 
40.43.596
 SUMP PUMP DISCHARGE 1-1/2" CPVC 
80
  
LF
53
  
4,241.19
$  
  
5,763.93
$  
  
10,005.12
$ 
40.43.597
 2" CPVC CHEMIACL NAOCI (SODIUM HYPOCHLORITE) AT EFF WEIR 
40
  
LF
42
  
3,351.63
$  
  
6,179.86
$  
  
9,531.49
$ 
40.43.598
 1" CS SCH 40 WELD CHEMIACL NAOH ( SODIUM HYDROXIDE) AT EFF WEIR 
35
  
LF
43
  
3,438.66
$  
  
7,666.73
$  
  
7,000.00
$  
  
18,105.39
$ 
40.43.599
 FW 42" CARBON STEEL FROM GAC TO EFF WEIR DYNAMIC MOVEMENT JOINT 
40
  
LF
834
  
67,946.11
$  
  
319,721.54
$  
   
19,228.42
$  
  
406,896.07
$ 
40.43.600
 20" WEIR VENT 
1  
LS
12,000.00
$  
  
12,000.00
$ 
MONORAIL
  1 
 LS 
- 
$
 - 
$
 -  $
  209,597.00  $  
 - 
$
  209,597.00 
41.43.700
 CRANE 
1  
EA
209,597.00
$  
   
209,597.00
$ 
PROCESS EQUIPMENT
  1 
 LS 
  26,243  $  
  2,815,901.09  $  
  3,282,629.00  $  
  931,447.00  $  
  898,034.00  $  
  7,928,011.09 
19020
 SELF-PERFORM STAFF 
1  
LS
13,649
  
1,817,980.43
$  
   
68,660.00
$  
  
25,000.00
$  
  
1,911,640.43
$ 
46.43.500
 CONTACTOR UNDERDRAIN SYSTEM 
10
  
EA
9,122
  
651,760.16
$  
   
3,016,719.00
$  
   
20,000.00
$  
  
3,688,479.16
$ 
46.43.515
 GAC EFFLUENT WATER SAMPLE PUMP 
2  
EA
46
  
3,593.07
$  
  
9,184.00
$  
  
2,000.00
$  
  
14,777.07
$ 
46.43.520
 GAC MEDIA 
1,580,000
  
LB
240
  
16,956.96
$  
  
40,000.00
$  
  
56,956.96
$ 
46.43.525
 DAVIT CRANE 
5  
EA
130
  
10,177.17
$  
  
41,600.00
$  
  
51,777.17
$ 
46.43.530
 ALUM. COVERS 
7,500
   
SF
416
  
33,520.03
$  
  
15,000.00
$  
  
842,447.00
$  
   
890,967.03
$ 
46.43.535
 GAC DRAIN SUBMERISBLE SUMP PUMPS 
2  
EA
94
  
7,460.77
$  
  
10,109.00
$  
  
2,000.00
$  
  
19,569.77
$ 
46.43.540
 GAC SLIDE GATES 
4  
EA
434
  
34,723.61
$  
  
121,357.00
$  
   
156,080.61
$ 
46.43.999
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK 
1  
LS
2,112
  
239,728.89
$  
   
898,034.00
$ 
1,137,762.89
$ 
 43E 
 POST FILTER GAC ELECTRICAL BLDG 
  1 
 LS 
  712  $  
  57,316.93  $  
  37,134.11  $  
  1,569,137.27  $  
  5,000.00  $  
  1,668,588.31 
CONCRETE
  1 
 LS 
  623  $  
  47,337.15  $  
  19,800.76  $  
  10,908.15  $  
- 
$
  78,046.06 
03.43E.000
 GAC ELECTRICAL SOG 
34
  
CY
446
  
33,886.34
$  
  
11,516.92
$  
  
1,492.84
$  
  
46,896.10
$ 
03.43E.011
 GAC ELECTRICAL HVAC EXTERIOR SOGS 
2  
CY
90
  
6,848.27
$  
  
1,036.33
$  
  
7,884.60
$ 
03.43E.012
 GAC ELECTRICAL EQUIP PADS - INT. 
1  
CY
88
  
6,602.54
$  
  
7,247.51
$  
  
13,850.05
$ 
03.43E.099
 REBAR - GAC ELECTRICAL BLDG 
10,876
  
LBS
9,415.31
$  
  
9,415.31
$ 
03.43E.999
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK 
1  
LS
-
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
MASONRY
  1 
 LS 
- 
$
 - 
$
 -  $
  65,100.00  $  
 -  $
  65,100.00 
04.43E.700
 MASONRY SUBCONTRACT 
1,725
   
SF
65,100.00
$  
  
65,100.00
$ 
MISC METALS
  1 
 LS 
- 
$
 -  $
- 
$
  3,600.00  $  
 -
$
  3,600.00 
05.43E.700
 MISC METALS SUBCONTRACT  
1  
LS
-
$ 
05.43E.710
 METAL FLASHING 10" H DRIP EDGE UNDER MASONRY 
120
   
LF
3,600.00
$  
  
3,600.00
$ 
ROOFING
  1 
 LS 
  66  $  
  8,222.57  $  
  12,415.00  $  
  33,750.00  $  
 - 
$
  54,387.57 
07.43E.700
 EXTERIOR EIFS SYSTEM  
1  
LS
31,050.00
$  
  
31,050.00
$ 
07.43E.705
 ROOFING DOWNSPOUTS, GUTTERS. ETC 
1  
LS
2,700.00
$  
  
2,700.00
$ 
07.43E.710
 ROOFING COMPONENTS 
1  
LS
66
  
8,222.57
$  
  
12,415.00
$  
  
20,637.57
$ 
DOORS & WINDOWS
  1 
 LS 
- 
$
 -  $
- 
$
  28,000.00  $  
- 
$
  28,000.00 
08.43E.700
 SINGLE HM DOOR 
1  
EA
10,000.00
$  
  
10,000.00
$ 
08.43E.705
 DOUBLE HM DOOR 
1  
EA
18,000.00
$  
  
18,000.00
$ 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  20,270.60  $  
- 
$
  20,270.60 
09.43E.700
 PAINTING SUBCONTRACT 
1  
LS
20,270.60
$  
  
20,270.60
$ 
FIRE SUPPRESSION
  1 
 LS 
- 
$
 - 
$
 - 
$
 - 
$
 - 
$
  -  
21.43E.800
 FIRE SUPPRESSION SYSTEM 
1  
LS
-
$ 
PLUMBING & HVAC
  1 
 LS 
- 
$
 -  $
 -  $
  227,616.00  $  
 - 
$
  227,616.00 
22.43E.800
 POST FILTER GAC ELEC BLDG PLUMBING 
1  
LS
5,000.00
$  
  
5,000.00
$ 
23.43E.800
 POST FILTER GAC ELEC BLDG HVAC 
1  
LS
222,616.00
$  
   
222,616.00
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  1,179,892.52  $  
 -  $
  1,179,892.52 
26.43E.800
 POST FILTER GAC ELECTRICAL BUILDING 
1  
LS
1,179,892.52
$  
   
1,179,892.52
$ 
EARTHWORK
  1 
 LS 
  22  $  
  1,757.21  $  
  4,918.35  $  
- 
$
  5,000.00  $  
  11,675.56 
31.43E.305
 BACKFILL FOR GAC ELEC 
48
  
CY
22
  
1,757.21
$  
  
4,918.35
$  
  
5,000.00
$ 
11,675.56
$ 
 45 
 FILTERED WATER RESERVOIRS 
  1 
 LS 
  6,174  $  
  735,368.22  $  
  1,090,388.87  $  
  1,754,666.92  $  
  395,703.75  $  
  3,976,127.76 
CONCRETE
  1 
 LS 
  117  $  
  8,961.08  $  
  555.05  $  
  966.00  $  
  43,753.00  $  
  54,235.13 
03.045.000
 2 PIPE SUPPORTS IN TANK 
2  
CY
117
  
8,961.08
$  
  
555.05
$  
  
966.00
$  
  
10,482.13
$ 
03.45.999
 CONSTRUCTION EQUIPMENT FOR CONCRETE WORK 
1  
LS
43,753.00
$ 
43,753.00
$ 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  8,670.60  $  
 -
$
  8,670.60 
09.45.700
 PAINTING SUBCONTRACT 
1  
LS
8,670.60
$  
  
8,670.60
$ 
EARTHWORK
  1 
 LS 
  3,070  $  
  381,105.89  $  
  400,754.70  $  
  724,233.80  $  
  201,873.75  $  
  1,707,968.14 
19020
 SELF-PERFORM STAFF 
1  
LS
2,080
  
301,119.00
$  
   
301,119.00
$ 
33.43.360
 EXCAVATE & BACKFILL SHORING PIT AT FILTERED WATER RESERVIOR NO. 1 
1  
LS
540
  
43,563.29
$  
  
203,112.00
$  
   
343,433.80
$  
   
106,843.36
$ 
696,952.45
$ 
33.43.361
 EXCAVATE & BACKFILL SHORING PIT AT FILTERED WATER RESERVIOR NO. 2 
1  
LS
450
  
36,423.60
$  
  
197,642.70
$  
   
380,800.00
$  
   
95,030.39
$ 
709,896.69
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  1,189  $  
  95,310.56  $  
  675,895.12  $  
  1,018,796.52  $  
- 
$
  1,790,002.20 
40.45.405
 1" SAM CPVC SAMPLE PIPE FROM MANHOLE TO SAMPLE PUMPS 
20
  
LF
87
  
6,884.77
$  
  
3,957.65
$  
  
18.89
$  
   
10,861.31
$ 
40.45.410
 36" FW CARBON STEEL INSIDE RESERVOIR NO 2 
40
  
LF
788
  
63,522.33
$  
  
320,878.38
$  
   
30,162.71
$  
  
414,563.42
$ 
40.45.420
 30" FW CARBON STEEL INSIDE RESERVOIR NO 1 
60
  
LF
164
  
13,214.67
$  
  
315,284.41
$  
   
961,166.04
$  
   
1,289,665.12
$ 
40.45.460
 60" / 36" CARBON STEEL ABANDON IN PLACE  
240
   
LF
150
  
11,688.79
$  
  
35,774.68
$  
  
27,448.88
$  
  
74,912.35
$ 
PROCESS EQUIPMENT
  1 
 LS 
  1,798  $  
  249,990.69  $  
  13,184.00  $  
  2,000.00  $  
  150,077.00  $  
  415,251.69

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
19020
 SELF-PERFORM STAFF 
1  
LS
1,752
  
246,397.62
$  
   
4,000.00
$  
  
250,397.62
$ 
46.45.205
 FILTERED WATER SAMPLE PUMPS 
2  
EA
46
  
3,593.07
$  
  
9,184.00
$  
  
2,000.00
$  
  
14,777.07
$ 
46.45.999
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK 
1  
LS
150,077.00
$ 
150,077.00
$ 
 50 
 FINISHED WATER PUMP STATION 
  1 
 LS 
  123  $  
  9,952.44  $  
  16,517.75  $  
  17,240.60  $  
- 
$
  43,710.79 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  11,890.60  $  
- 
$
  11,890.60 
09.50.700
 PAINTING SUBCONTRACT 
1  
LS
11,890.60
$  
  
11,890.60
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  123  $  
  9,952.44  $  
  16,517.75  $  
  5,350.00  $  
- 
$
  31,820.19 
40.50.400
 BWR 16" CARBON STEEL 
12
  
LF
123
  
9,952.44
$  
  
16,517.75
$  
  
5,350.00
$  
  
31,820.19
$ 
 65 
 EQUALIZATION BASINS 
  1 
 LS 
  2,499  $  
  249,239.91  $  
  365,939.59  $  
  888,304.21  $  
  18,883.00  $  
  1,522,366.71 
CONCRETE
  1 
 LS 
  85  $  
  6,476.12  $  
  1,701.12  $  
  62,092.50  $  
 - 
$ 
  70,269.74 
03.065.000
 2 PUMP SLABS OUTSIDE EQ. BASINS 
5  
CY
85
  
6,476.12
$  
  
1,701.12
$  
  
8,177.24
$ 
03.065.099
 REBAR - PUMP SOGS 
1,395
   
LBS
2,092.50
$  
  
2,092.50
$ 
03.065.999
 DEMO & REPLACE GROUT ON BOTTOM OF TANK 
1  
LS
60,000.00
$  
  
60,000.00
$ 
MISC METALS
  1 
 LS 
- 
$
 -  $
- 
$
  86,418.73  $  
 - 
$
  86,418.73 
05.65.700
 MISC METALS SUBCONTRACT  
1  
LS
86,418.73
$  
  
86,418.73
$ 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  33,520.60  $  
- 
$
  33,520.60 
09.65.700
 PAINTING SUBCONTRACT 
1  
LS
33,520.60
$  
  
33,520.60
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  696,480.67  $  
 - 
$
  696,480.67 
65.26.800
 EQ BASIN EI&C 
1  
LS
344,063.30
$  
   
344,063.30
$ 
65.26.801
 GMP 2 CHANGE ORDER-VFD CHANGE TO STAND ALONE ON EQ PUMPS 
1  
LS
352,417.37
$  
   
352,417.37
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  1,051  $  
  82,079.42  $  
  161,428.47  $  
  3,391.71  $  
 -  $
  246,899.60 
40.65.400
 PRW 8" DIP BASIN 1 
33
  
LF
163
  
13,108.19
$  
  
20,277.65
$  
  
1,515.00
$  
  
34,900.84
$ 
40.65.420
 PRW 8" DIP BURIED VAULT TO BASIN 1 
108
   
LF
369
  
28,376.63
$  
  
35,500.34
$  
  
280.16
$  
  
64,157.13
$ 
40.65.425
 PRW 8" DIP VALVES ABOVE GROUND BASIN 1 
26
  
LF
69
  
5,510.24
$  
  
28,978.36
$  
  
34,488.60
$ 
40.65.440
 PRW 8" DIP BASIN 2 
32
  
LF
128
  
9,988.91
$  
  
18,631.62
$  
  
1,440.00
$  
  
30,060.53
$ 
40.65.450
 PRW 12" / 8" DIP BURIED BASIN 2 
71
  
LF
249
  
19,133.98
$  
  
27,080.33
$  
  
156.55
$  
  
46,370.86
$ 
40.65.455
 PRW 8" VALVES ABOVE GROUND BASIN 2 
40
  
LF
74
  
5,961.47
$  
  
30,960.17
$  
  
36,921.64
$ 
PROCESS EQUIPMENT
  1 
 LS 
  1,363  $  
  160,684.37  $  
  202,810.00  $  
  6,400.00  $  
  18,883.00  $  
  388,777.37 
19020
 SELF-PERFORM STAFF 
1  
LS
894
  
120,467.09
$  
   
4,000.00
$  
  
124,467.09
$ 
40.65.500
  DEMOLITION OF EXISTING EQ BASIN 1 EQUIPMENT  
1  
LS
60
  
4,715.55
$  
  
1,200.00
$  
  
5,915.55
$ 
40.65.505
  DEMOLITION OF EXISTING EQ BASIN 2 EQUIPMENT  
1  
LS
60
  
4,715.55
$  
  
1,200.00
$  
  
5,915.55
$ 
46.65.515
  EQB-1 BASIN PUMP  
2  
EA
132
  
10,506.18
$  
  
99,805.00
$  
  
2,000.00
$  
  
112,311.18
$ 
46.65.525
  EQB-2 BASIN PUMP  
2  
EA
129
  
10,291.30
$  
  
99,005.00
$  
  
2,000.00
$  
  
111,296.30
$ 
46.65.999
 CONSTRUCTION EQUIPMENT FOR PROCESS MECHANICAL WORK 
1  
LS
88
  
9,988.70
$  
  
18,883.00
$ 
28,871.70
$ 
 75 
 DEWATERING FACILITY 
  1 
 LS 
- 
$
 - 
$
 -  $
  14,455,078.46  $  
 - 
$
  14,455,078.46 
SPECIAL CONSTRUCTION
  1 
 LS 
- 
$
 -  $
- 
$
  13,340,287.83  $  
- 
$
  13,340,287.83 
13.75.500
 GENERAL CONTRACTOR-DEWATERING FACILITY 
1  
LS
13,340,287.83
$  
  
13,340,287.83
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  1,114,790.63  $  
 -  $
  1,114,790.63 
26.75.800
 DEWATERING BUILDING EI&C 
1  
LS
1,114,790.63
$  
   
1,114,790.63
$

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
 86 
 CHLORINE DIOXIDE 
  1 
 LS 
  1,270  $  
  130,116.00  $  
  49,504.84  $  
  6,806,031.83  $  
  65,739.37  $  
  7,051,392.04 
SPECIAL CONSTRUCTION
  1 
 LS 
- 
$
 -  $
-  $
  5,988,628.38  $  
 - 
$
  5,988,628.38 
13.86.500
GENERAL CONTRACTOR-CHLORINE DIOXIDE BLDG
1  
LS
5,988,628.38
$  
   
5,988,628.38
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  815,263.45  $  
 - 
$
  815,263.45 
26.86.800
ELECTRICAL SUBCONTRACT
1  
LS
815,263.45
$  
   
815,263.45
$ 
EARTHWORK
  1 
 LS 
  1,270  $  
  130,116.00  $  
  49,504.84  $  
  2,140.00  $  
  65,739.37  $  
  247,500.21 
19020
SELF-PERFORM STAFF
1  
LS
390
  
55,209.71
$  
  
55,209.71
$ 
31.86.300
EXCAVATION FOR CHEMICAL BLDG
813
   
CY
379
  
32,189.05
$  
  
3,902.40
$  
  
28,355.52
$ 
64,446.97
$ 
31.86.305
BACKFILL FOR CHEMCIAL BLDG
1,026
   
CY
500
  
42,717.24
$  
  
45,602.44
$  
  
2,140.00
$  
  
37,383.85
$ 
127,843.53
$ 
 87 
 POST TREATMENT CHEMICAL FACILITY 
  1 
 LS 
  1,115  $  
  89,352.45  $  
  210,586.07  $  
  346,063.98  $  
- 
$
  646,002.50 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  4,520.60  $  
 -
$
  4,520.60 
09.87.700
 PAINTING SUBCONTRACT 
1  
LS
4,520.60
$  
  
4,520.60
$ 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  255,953.38  $  
 - 
$
  255,953.38 
87.26.800
 POST TREATMENT EI&C 
1  
LS
255,953.38
$  
   
255,953.38
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  1,001  $  
  80,478.62  $  
  33,342.07  $  
  79,590.00  $  
 - 
$
  193,410.69 
40.87.410
 SH PUMP TIE IN 2" / 1" CPVC 
80
  
LF
336
  
27,039.04
$  
  
7,762.34
$  
  
34,801.38
$ 
40.87.415
 SH STORAGE TANK TIE IN 2" / 1" CPVC 
180
   
LF
446
  
35,873.11
$  
  
13,887.91
$  
  
3,150.00
$  
  
52,911.02
$ 
40.87.420
 SODIUM HYDROXIDE PUMP TIE IN 1" WELDED CS 
30
  
LF
121
  
9,727.77
$  
  
4,712.72
$  
  
22,840.00
$  
  
37,280.49
$ 
40.87.425
 SODIUM HYDROXIDE STORAGE TANK AREA 3/4" WELDED CS 
110
   
LF
98
  
7,838.70
$  
  
6,979.10
$  
  
53,600.00
$  
  
68,417.80
$ 
PROCESS EQUIPMENT
  1 
 LS 
  114  $  
  8,873.83  $  
  177,244.00  $  
  6,000.00  $  
 -
$
  192,117.83 
46.87.205
 SODIUM HYPOCHLORITE METERING PUMP 
1  
EA
53
  
4,154.30
$  
  
66,579.00
$  
  
2,000.00
$  
  
72,733.30
$ 
46.87.210
 SODIUM HYDROXIDE METERING PUMP 
1  
EA
53
  
4,154.30
$  
  
110,665.00
$  
   
2,000.00
$  
  
116,819.30
$ 
46.87.520
 CHLORINE INJECTION ASSEMBLIES 
1  
LS
8
  
565.23
$  
  
2,000.00
$  
  
2,565.23
$ 
 90 
 DISINFECTION BUILDING 
  1 
 LS 
  337  $  
  24,743.96  $  
  6,228.55  $  
  4,270.60  $  
- 
$
  35,243.11 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  3,070.60  $  
 -
$
  3,070.60 
09.90.700
 PAINTING SUBCONTRACT 
1  
LS
3,070.60
$  
  
3,070.60
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  337  $  
  24,743.96  $  
  6,228.55  $  
  1,200.00  $  
- 
$
  32,172.51 
40.90.400
 3" SOFT WATER TIE IN CPVC 
60
  
LF
337
  
24,743.96
$  
  
6,228.55
$  
  
1,200.00
$  
  
32,172.51
$ 
 95 
 ADMIN BUILDING 
  1 
 LS 
  151  $  
  12,099.12  $  
  16,951.39  $  
  11,532.60  $  
- 
$
  40,583.11 
PAINT & COATINGS
  1 
 LS 
- 
$
 -  $
 -
$
  5,532.60  $  
 -
$
  5,532.60 
09.95.700
 PAINTING SUBCONTRACT 
1  
LS
5,532.60
$  
  
5,532.60
$ 
PROCESS PIPE & VALVES
  1 
 LS 
  151  $  
  12,099.12  $  
  16,951.39  $  
  6,000.00  $  
- 
$
  35,050.51 
40.95.500
 SAMPLE PIPING AT ADMIN BUILDING 
200
   
LF
151
  
12,099.12
$  
  
16,951.39
$  
  
6,000.00
$  
  
35,050.51
$ 
 99 
 CONSTRUCTION MANAGER GENERAL CONDITIONS 
  1 
 LS 
  44,134  $  
  5,602,854.20  $  
  818,871.74  $  
  1,840,776.71  $  
  1,662,162.00  $  
  9,924,664.65 
ELECTRICAL, INSTRUMENTATION, & CONTROLS
  1 
 LS 
- 
$
 -  $
-  $
  515,868.71  $  
 - 
$
  515,868.71 
19999
 TEMPORARY ELECTRICAL 
1  
LS
515,868.71
$  
   
515,868.71
$ 
CONSTRUCTION MANAGER GENERAL CONDITIONS
  1 
 LS 
  35,070  $  
  4,756,712.91  $  
  (261,476.55)  $  
- 
$
-  $
  4,495,236.36 
19010A
 GMP 3-ADDITION CM STAFF 
1  
LS
35,070
  
4,756,712.91
$  
   
(261,476.55)
$  
  
4,495,236.36
$ 
CONCSTRUCTION MANAGER GENERAL REQUIREMENTS
  1 
 LS 
  9,064  $  
  846,141.29  $  
  1,080,348.29  $  
  1,324,908.00  $  
  1,662,162.00  $  
  4,913,559.58

FACILITY
AREA
DESCRIPTION
QTY
UN
MANHOURS
LABOR
MATERIAL
SUBCONTRACTOR
EQUIPMENT
TOTAL
CITY OF CHANDLER
PECOS SWTP IMPROVEMENTS WA2100.251
COST MODEL DETAIL - GMP 3
DETAILED COST SUMMARY
19050
 GENERAL REQUIREMENTS 
1  
LS
968
  
80,892.06
$  
  
1,080,348.29
$  
   
1,324,908.00
$  
   
2,486,148.35
$ 
19030A
 GMP 3-ADDITION TO SITE WIDE EQUIPMENT 
1  
LS
8,096
  
765,249.23
$  
   
1,662,162.00
$ 
2,427,411.23
$ 
SUBTOTAL COST OF WORK
1
LS
290,043.80
29,436,106.06
$ 
28,573,803.41
$ 
40,117,537.73
$ 
9,384,885.09
$ 
107,512,332.29
$