ATTACHMENT B ‐ PROPOSED WASTEWATER CAPITAL IMPROVEMENT PROGRAM
FY 2024‐2030
Project Description
2024-2025
2025-2026
2026-2027
2027-2028
2028-2029
2029-2030
TOTAL
WASTEWATER TREATMENT PLANTS
Energy, Technology, Facilities, Etc.
10,740,519
$             
2,400,000
$               
2,916,800
$               
2,000,000
$               
2,050,000
$               
2,950,000
$               
23,057,319
$             
Instrumentation and Control
5,845,000
$               
8,905,000
$               
7,625,000
$               
7,485,000
$               
10,150,000
$             
10,285,000
$             
50,295,000
$             
Operational Improvements
7,205,000
$               
4,575,000
$               
4,370,000
$               
4,020,000
$               
4,020,000
$               
4,825,000
$               
29,015,000
$             
Plant Studies
1,200,000
$               
1,050,000
$               
760,000
$                  
35,000
$                    
2,865,000
$               
2,065,000
$               
7,975,000
$               
Replacement Fund
373,487,331
$           
108,610,000
$           
157,855,000
$           
170,730,000
$           
138,905,000
$           
138,097,242
$           
1,087,684,573
$        
Subtotal - Wastewater Treatment Plants
398,477,850
$         
125,540,000
$         
173,526,800
$         
184,270,000
$         
157,990,000
$         
158,222,242
$         
1,198,026,892
$      
PIPES
Area Impact Fees
-
$                          
15,602,958
$             
8,040,000
$               
8,194,876
$               
-
$                          
-
$                          
31,837,834
$             
Emergency Repair Contract
4,140,000
$               
4,015,000
$               
4,615,000
$               
5,015,000
$               
6,415,000
$               
8,015,000
$               
32,215,000
$             
Manhole Replacement/Rehabilitation
5,315,000
$               
5,540,000
$               
5,540,000
$               
5,540,000
$               
4,540,000
$               
4,540,000
$               
31,015,000
$             
New Gravity Sewers & Force Mains
19,666,000
$             
3,432,000
$               
26,952,000
$             
502,000
$                  
502,000
$                  
500,000
$                  
51,554,000
$             
Odor Control
5,000
$                      
260,000
$                  
15,000
$                    
2,020,000
$               
-
$                          
-
$                          
2,300,000
$               
Regional Sewer Capacity Improvements
21,115,580
$             
16,985,000
$             
94,545,000
$             
30,884,530
$             
455,000
$                  
1,730,000
$               
165,715,110
$           
Relief Sewers
4,580,000
$               
13,794,000
$             
1,210,000
$               
9,370,000
$               
1,210,000
$               
1,210,000
$               
31,374,000
$             
Sewer Main Rehabilitation
60,004,481
$             
59,052,000
$             
53,883,000
$             
78,490,000
$             
64,700,000
$             
76,850,000
$             
392,979,481
$           
Subtotal - Pipes
114,826,061
$         
118,680,958
$         
194,800,000
$         
140,016,406
$         
77,822,000
$           
92,845,000
$           
738,990,425
$         
LIFT STATIONS OR PUMPS
Instrumentation and Control
1,765,000
$               
1,380,000
$               
980,000
$                  
1,470,000
$               
980,000
$                  
1,710,000
$               
8,285,000
$               
New Lift Stations  
5,585,000
$               
15,000
$                    
-
$                          
-
$                          
-
$                          
-
$                          
5,600,000
$               
Odor Control
4,115,000
$               
1,635,000
$               
1,885,000
$               
1,635,000
$               
1,635,000
$               
1,635,000
$               
12,540,000
$             
Plant & Lift Station Studies
260,000
$                  
210,000
$                  
210,000
$                  
210,000
$                  
210,000
$                  
210,000
$                  
1,310,000
$               
Replacement Fund
55,725,000
$             
18,500,000
$             
7,495,000
$               
30,195,000
$             
6,965,000
$               
6,965,000
$               
125,845,000
$           
Subtotal - Lift Stations or Pumps
67,450,000
$           
21,740,000
$           
10,570,000
$           
33,510,000
$           
9,790,000
$             
10,520,000
$           
153,580,000
$         
WATER REUSE
Water Reuse
3,612,964
$               
815,000
$                  
855,000
$                  
7,235,000
$               
43,136,877
$             
605,000
$                  
56,259,841
$             
Subtotal - Water Reuse
3,612,964
$             
815,000
$                
855,000
$                
7,235,000
$             
43,136,877
$           
605,000
$                
56,259,841
$

ATTACHMENT B ‐ PROPOSED WASTEWATER CAPITAL IMPROVEMENT PROGRAM
FY 2024‐2030
Project Description
2024-2025
2025-2026
2026-2027
2027-2028
2028-2029
2029-2030
TOTAL
ENERGY, TECHNOLOGY, FACILITIES, ETC, (OTHER)
Energy, Technology, Facilities, Etc.
19,537,462
$             
8,407,240
$               
6,443,765
$               
4,880,565
$               
4,280,565
$               
6,359,500
$               
49,909,097
$             
Instrumentation and Control
3,615,000
$               
2,515,000
$               
1,865,000
$               
4,115,000
$               
2,315,000
$               
4,815,000
$               
19,240,000
$             
Subtotal - Energy, Technology, Facilities, Etc. (Other)
23,152,462
$           
10,922,240
$           
8,308,765
$             
8,995,565
$             
6,595,565
$             
11,174,500
$           
69,149,097
$           
STAFF TIME / PERCENT FOR ARTS
Percent for Arts
1,410,875
$               
2,026,128
$               
1,927,924
$               
350,000
$                  
-
$                          
-
$                          
5,714,927
$               
Staff Time
-
$                          
3,200,000
$               
3,200,000
$               
3,200,000
$               
3,200,000
$               
3,200,000
$               
16,000,000
$             
Subtotal - Staff Time / Percent for Arts
1,410,875
$             
5,226,128
$             
5,127,924
$             
3,550,000
$             
3,200,000
$             
3,200,000
$             
21,714,927
$           
PROGRAM TOTAL
608,930,212
$         
282,924,326
$         
393,188,489
$         
377,576,971
$         
298,534,442
$         
276,566,742
$         
2,237,721,182
$