A3 TR221_D24613_TCE.PDF

Maricopa County — Formal (2023-08-09)

View PDF Item 55 Meeting page

Extracted text (via pymupdf) 2564 characters
Page 1 of 7 
 
MCDOT-FCD TCE Template 
 
Approved 11-17-21 W Peck, MCAO 
 
When Recorded Return To: 
 
Maricopa County Real Estate Depart. 
2801 W. Durango Street 
Phoenix, AZ 85009 
 
EXEMPT ARS 11-1134.A.2 
 
 
 
 
 
 
 
 
 
 
JH/SC 
TEMPORARY CONSTRUCTION EASEMENT 
 
Assessor's Parcel No.: 304-71-058 
Project No.: 
TR221 
Project Name: 
Ocotillo Road (148th Street to Greenfield Road) 
Item No.: 
D24613 (WJ) 
 
This Temporary Construction Easement is entered into by and between Michael R. Temple and 
Veronica E. Clay Temple, husband and wife, hereinafter referred to as GRANTOR, the 
owner of the real property situated in Maricopa County, Arizona, which property is set forth in 
instrument number 1991-405989 in the official records of Maricopa County (the “Burdened 
Property”), and Maricopa County, a political subdivision of the State of Arizona, its assigns and 
successors in title or interest, hereinafter collectively called GRANTEE. 
 
GRANTOR hereby grants a Temporary Construction Easement (“TCE”), together with the right 
and privilege of entering upon the area subject to the conditions set forth herein, on, over, under 
and across that portion of the Burdened Property legally described on Exhibit "A" and depicted 
in Exhibit “B” attached hereto (the “Easement Area”) for the purpose of facilitating construction 
of the project known as TR221 (“Project”). 
 
1. 
Term and Consideration.  This TCE is hereby granted for the stated purpose for a 
period of 12 months (“Term”) which shall commence upon the initiation of construction activities. 
GRANTEE estimates that the period of time stated above will be sufficient for completion of the 
work within the TCE Area. Construction is currently scheduled to start in January 2024 and is 
subject to change. GRANTEE shall provide written notification to GRANTOR of the initiation 
of construction activities no less than thirty (30) calendar days in advance of construction activities. 
The consideration for the use of the TCE Area is Three Thousand Seven-Hundred Ninety-Six 
and No/100 Dollars ($3,796.00) paid by GRANTEE to GRANTOR.  This consideration is for 
the full Term described above.  In the event GRANTEE determines that additional construction 
time within the TCE Area is needed for completion of the Project, GRANTEE shall be permitted 
to extend the term of this TCE by notifying the GRANTOR in writing and issuing a payment for 
the additional consideration in the amount of $316.33 for each additional month or part thereof for 
the required extension.

,interim
7/12/2023