To: 
City of Phoenix Planning Commission 
Date: May 1, 2025 
From: 
Racelle Escolar, AICP 
Principal Planner 
Subject: 
ITEM NO. 3 (Z-87-D-03-2) – NORTHEAST CORNER OF 64TH STREET 
AND MAYO BOULEVARD 
Rezoning Case No. Z-87-D-03-2 is a request to rezone a 51.37-acre site located at the 
northeast corner of 64th Street and Mayo Boulevard from S-1 (Approved CP/BP PCD) 
(Ranch or Farm Residence, Approved Commerce Park District, Business Park Option, 
Planned Community District), S-1 (Approved R-3A PCD) (Ranch or Farm Residence, 
Approved Multifamily Residence District, Planned Community District), and S-1 (Ranch 
or Farm Residence) to PUD PCD (Planned Unit Development, Planned Community 
District) for a Major Amendment to the Paradise Ridge PCD to allow multifamily and 
single-family attached residential. 
The Desert View Village Planning Committee (VPC) heard this request on April 1, 2025, 
and recommended approval, per the staff recommendation with modifications. After the 
VPC, the applicant worked with staff to update the Signs section of the PUD regarding 
the proposed marquee sign near the entry at the corner of Mayo Boulevard and 66th 
Street. The applicant has developed acceptable language, including a design exhibit for 
the proposed sign. 
Staff recommends approval, per the modified stipulations in bold font below: 
1.
An updated Development Narrative for the 64th & Mayo PUD reflecting the
changes approved through this request shall be submitted to the Planning and
Development Department within 30 days of City Council approval of this request.
The updated Development Narrative shall be consistent with the Development
Narrative date stamped March 13, 2025, as modified by the following stipulations:
a.
Front cover: Revise the submittal date information to add the following: City
Council adopted: [Add adoption date].
ATTACHMENT D

Z-87-D-03-2 
Planning Commission Backup Memo
May 1, 2025 
Page 2 of 6 
b. 
Page 22, Section F. Signs: Remove all language, except the first two 
sentences REPLACE THE FOLLOWING LANGUAGE AFTER THE 
FIRST PARAGRAPH AS LISTED BELOW:  
IN ADDITION TO BASE SIGNAGE, GIVEN (I) THE UNIQUE SITE 
ACCESS TO THE PROPERTY (WITH MAIN ACCESS TO ALL FOUR 
DEVELOPMENT QUADRANTS AT 66TH STREET), (II) THE 
IMPORTANCE OF CLEAR IDENTIFICATION FOR VISITORS AS WELL 
AS MODERN DELIVERY SERVICES (GOODS, FOOD DELIVER, CAR 
SHARE, ETC.), AND (III) DUE TO THE SIGNAGE CONTEXT ALONG 
THE NORTH SIDE OF MAYO BLVD, THE FOLLOWING PROJECT-
SPECIFIC MARQUEE MAIN ENTRY SIGN IS PERMITTED. THIS 
MARQUEE SIGN WILL BE DESIGNED IN A MANNER THAT DOES NOT 
EXCEED THE STANDARDS OUTLINED BELOW. 
 
MARQUEE MAIN ENTRY SIGN
• ONE (1) MARQUEE MAIN ENTRY SIGN FOR THE OVERALL PUD 
SHALL BE PERMITTED AT 66TH AND MAYO BLVD, IN GENERAL 
CONFORMANCE WITH THE LOCATION SHOWN IN ILLUSTRATION C 
BELOW. 
• THE MARQUEE SIGN SHALL BE NO TALLER THAN 18 FEET IN 
HEIGHT. 
• THE TOTAL SIGNAGE AREA SHALL BE NO GREATER THAN 100 
SQUARE FEET PER SIDE.
• THE SIGN SHALL BE GENERALLY CONSISTENT WITH THE DESIGN 
SHOWN IN EXHIBIT 8, INCLUSIVE OF MATERIALS AND COLORS AS 
LISTED THEREIN. 
 
THIS MARQUEE MAIN ENTRY SIGN IS AN IMPORTANT FEATURE OF 
THIS PUD AS TO ITS BRANDING DUE TO THERE BEING FOUR 
DEVELOPMENT UNITS, TWO OF WHICH ARE “HIDDEN” BY THE 
UNITS ALONG MAYO BLVD. TO ADDRESS THIS, AT THE MAIN 
ENTRANCE TO THE DEVELOPMENT (NORTHWEST CORNER OF 
66TH STREET AND MAYO BOULEVARD), THE MARQUEE MAIN 
ENTRY SIGN WILL SERVE AS THE PRIMARY MONUMENT SIGN FOR 
THE ENTIRETY OF THIS MASTER-PLANNED COMMUNITY. THIS SIGN 
WILL PROVIDE SUFFICIENT SPACE TO DISPLAY THE FOUR (4) 
DISTINCT MULTIFAMILY DEVELOPMENTS PLANNED FOR THE 
PROJECT, EACH WITH ITS OWN BRANDING, LOGO AND NAME. THE 
SCALE AND PLACEMENT OF THE PROPOSED SIGN WILL ENHANCE 
VISIBILITY OF THE KEY ACCESS POINT TO THE DEVELOPMENT 
FROM MAYO BOULEVARD, IMPROVING WAYFINDING AND 
FOSTERING COMMUNITY RECOGNITION, WHILE FOCUSING 
TRAFFIC TO/FROM THE SITE TO THIS SIGNALIZED INTERSECTION. 
THE 18-FOOT SIGN IS PROPORTIONATE TO THE PROJECT’S SCALE 
AND IS CONSISTENT WITH THE COHESIVE DESIGN STANDARDS OF 
THIS PUD, OFFERING A HIGH-QUALITY VISUAL IDENTITY WHILE

Z-87-D-03-2
Planning Commission Backup Memo
May 1, 2025
Page 3 of 6 
ACCOMMODATING INDIVIDUAL BRANDING FOR EACH OF THE 
FOUR DEVELOPMENT PARCELS. IT IS ALSO OF SIMILAR SIZE AND 
PLACEMENT TO OTHER SIGNS FOUND ALONG THE NORTH SIDE OF 
THE MAYO BLVD CORRIDOR, PROVIDING A VISUAL CONNECTION 
TO THE LARGER NEIGHBORHOOD OF RESIDENTIAL AND 
COMMERCIAL DEVELOPMENT FROM THE CITY LIMITS TO 64TH
STREET.  
 
RATHER THAN INSTALLING A NUMBER OF GROUND SIGNS, THE 
MARQUEE MAIN ENTRY SIGN ACHIEVES A VISUAL ENVIRONMENT 
SUPERIOR TO THAT WHICH CAN BE ACHIEVED VIA ADHERENCE 
TO THE BASE SIGN ORDINANCE STANDARDS THROUGH ITS 
CONTEMPORARY DESIGN WHICH IS COMPLEMENTARY AND 
CONSISTENT WITH THE MODERN ARCHITECTURAL STYLE AS 
PROVIDED FOR WITHIN THIS PUD. CRAFTED FROM DURABLE 
MATERIALS AND INCORPORATING COMPLEMENTARY COLORS, 
THE SIGN WILL CONVEY A SENSE OF QUALITY AND PERMANENCE. 
CONSOLIDATING INDIVIDUAL COMMUNITY SIGNS TO A SINGULAR 
SIGN AT THE PROJECT’S “FRONT DOOR” ENHANCES DESIGN 
CONSISTENCY AND SUPPORTS THE OVERALL VISION FOR THE 
COMMUNITY AS ONE COHESIVE WHOLE. STRATEGICALLY 
POSITIONED AT THE SOUTHEAST CORNER OF THE PROPERTY, 
THE SIGN’S HEIGHT, SIZE, AND LOCATION IN AN AREA OF 
ENHANCED LANDSCAPING WILL CREATE A DISTINCT "FRONT 
DOOR" TO THE COMMUNITY. THE OVERALL DESIGN, LOCATION 
AND TREATMENT OF THE SIGN WILL CONTRIBUTE TO A SENSE OF 
PLACE AND GRANDEUR, SERVING NOT ONLY AS AN ENTRY 
MARKER FOR RESIDENTS AND VISITORS, BUT ALSO AS A 
DEFINING AND ATTRACTIVE VISUAL FEATURE FOR THOSE 
TRAVELING THROUGH THE AREA. 
C. 
PAGE 22, SECTION F. SIGNS: REPLACE ILLUSTRATION C WITH THE 
IMAGE ATTACHED AS AN EXHIBIT TO THE PLANNING COMMISSION 
BACK UP MEMO DATED MAY 1, 2025.  
 
 
D. 
PAGE 54, EXHIBIT 8: REPLACE THE EXHIBIT WITH THE IMAGE 
ATTACHED AS AN EXHIBIT TO THE PLANNING COMMISSION 
BACKUP MEMO DATED MAY 1, 2025. 
 
2. 
A minimum 70 feet of right-of-way shall be dedicated and constructed for the 
north half of Mayo Boulevard, per the approved Master Street Plan.
 
3. 
A minimum 70 feet of right-of-way shall be dedicated and constructed for the east 
half of 64th Street, per the approved Master Street Plan. 
 
4. 
A minimum 40 feet of right-of-way shall be dedicated and constructed for the west 
half of 66th Street, per the approved Master Street Plan.

Z-87-D-03-2 
Planning Commission Backup Memo
May 1, 2025 
Page 4 of 6 
 
5. 
Construction, funding, and phasing of all off-site mitigation improvements shall 
comply with the approved Master Street Plan and Master Phasing Plan for 64th
Street and Mayo Boulevard.
6. 
Replace unused driveways with sidewalk, curb, and gutter. Also, replace any 
broken or out-of-grade curb, gutter, sidewalk, and curb ramps on all streets and 
upgrade all off-site improvements to be in compliance with current ADA 
guidelines
7. 
All streets within and adjacent to the development shall be constructed with 
paving, curb, gutter, sidewalk, curb ramps, streetlights, median islands, 
landscaping and other incidentals, as per plans approved by the Planning and 
Development Department. All improvements shall comply with all ADA 
accessibility standards.
 
8. 
The site is located within a Special Flood Hazard Area (SFHA), called a 
SPECIFICALLY IN Zone AO, AS SHOWN on pPanel 1315L of the Flood 
Insurance Rate Maps (FIRM), revised ON February 8, 2024 OCTOBER 16, 2013.
TO ENSURE COMPLIANCE WITH APPLICABLE REGULATIONS, The following 
requirements shall apply, as approved by the Planning and Development 
Department AND THE FLOODPLAIN MANAGEMENT SECTION OF THE 
OFFICE OF THE CITY ENGINEER, THE FOLLOWING REQUIREMENTS MUST 
BE MET:
 
a.  
The Architect/Engineer is required to show CLEARLY DELINEATE the 
floodplain boundary limits on the Grading and Drainage pPlan. THE PLAN 
MUST ALSO DEMONSTRATE and ensure that POTENTIAL impacts to 
the proposed facilities have been PROPERLY considered, following IN 
ACCORDANCE WITH the National Flood Insurance Program (NFIP) 
Regulations (44 CFR Paragraph 60.3) AND THE. This includes, but is not 
limited to, provisions OUTLINED in the latest MOST CURRENT versions of 
the Floodplain Ordinance of the Phoenix City Code. 
 
 
b. 
A copy of the PRELIMINARY Grading and Drainage Plan needs to MUST 
be submitted to the Floodplain Management sSection of the Office of the 
City Engineer for review and approval of TO ENSURE COMPLIANCE 
WITH Ffloodplain-RELATED requirements BEFORE APPLYING FOR 
GRADING & DRAINAGE AND BUILDING PERMITS. FLOODPLAIN 
MANAGEMENT MUST APPROVE THE FINAL GRADING AND 
DRAINAGE PLANS PRIOR TO THE ISSUANCE OF GRADING & 
DRAINAGE PERMITS.

Z-87-D-03-2 
Planning Commission Backup Memo
May 1, 2025 
Page 5 of 6 
c. 
FEMA approved CLOMR-F or CLOMR is required prior to issuance of a 
Grading and Drainage permit. PRIOR TO APPLYING FOR GRADING & 
DRAINAGE AND BUILDING PERMITS, AN ELEVATION CERTIFICATE 
(FEMA FORM 086-0-33), BASED ON THE CONSTRUCTION PLANS, 
MUST BE SUBMITTED TO AND APPROVED BY FLOODPLAIN 
MANAGEMENT.
 
 
D. 
PRIOR TO THE ISSUANCE OF VERTICAL CONSTRUCTION, THE 
FOLLOWING CONDITIONS MUST BE MET:
 
I. 
AN ELEVATION CERTIFICATE, BASED ON THE BUILDING 
UNDER CONSTRUCTION, MUST BE SUBMITTED TO AND 
APPROVED BY FLOODPLAIN MANAGEMENT.
 
 
 
 
II.
95% COMPACTION TEST RESULTS FOR THE BUILDING PADS 
MUST BE PROVIDED. 
 
 
 
E. 
PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY, AN 
ELEVATION CERTIFICATE BASED ON THE FINISHED 
CONSTRUCTION, DEMONSTRATING THE STRUCTURE’S 
COMPLIANCE, MUST BE SUBMITTED TO AND APPROVED BY 
FLOODPLAIN MANAGEMENT. 
 
9. 
The property owner shall record documents that disclose the existence, and 
operational characteristics of Scottsdale Municipal Airport (SDL) to future owners 
or tenants of the property. The form and content of such documents shall be 
according to the templates and instructions provided which have been reviewed 
and approved by the City Attorney. 
 
10.
If determined necessary by the Phoenix Archaeology Office, the applicant shall 
conduct Phase I data testing and submit an archaeological survey report of the 
development area for review and approval by the City Archaeologist prior to 
clearing and grubbing, landscape salvage, and/or grading approval
 
11.
If Phase I data testing is required, and if, upon review of the results from the 
Phase I data testing, the City Archaeologist, in consultation with a qualified 
archaeologist, determines such data recovery excavations are necessary, the 
applicant shall conduct Phase II archaeological data recovery excavations
 
12.
In the event archaeological materials are encountered during construction, the 
developer shall immediately cease all ground-disturbing activities within a 33-foot 
radius of the discovery, notify the City Archaeologist, and allow time for the 
Archaeology Office to properly assess the materials.

Z-87-D-03-2
Planning Commission Backup Memo
May 1, 2025
Page 6 of 6 
13.
Prior to final site plan approval, the landowner shall execute a Proposition 207 
waiver of claims form. The waiver shall be recorded with the Maricopa County 
Recorder's Office and delivered to the City to be included in the rezoning 
application file for record.
PCD Stipulations
14.
Master Plan documents shall be submitted for portions of the Planned 
Community District as development occurs, per the applicable development 
agreement.
 
15.
Right-of-way and improvements shall be determined by the final Traffic Impact 
Study and a Master Street Plan – Development Agreement between the city, 
Arizona State Land Department, and the City of Scottsdale. Additional right-of-
way and/or easements not specifically identified such as bus bays, turn lanes, 
landscape/sidewalk easements, slope and construction easements, etc., may be 
required as determined by the Master Street Plan, or when individual 
development plans are submitted to the Planning and Development Department 
for approval. 
 
16.
Detailed requirements for potable water, wastewater, and reclaimed water onsite 
and offsite infrastructure needed to service this project and infrastructure phasing 
schedules shall be determined at the time of review and approval of the PCD 
potable water, wastewater, and reclaimed water master plans. Off site 
infrastructure requirements shall be a function of the amount of major master plan 
water and sewer lines constructed by other development in the area prior to 
initiation of this project. 
Exhibits:
Design Exhibit proposed to be incorporated as Illustration C of the PUD Narrative 
(1 page) 
Design Exhibit proposed to be incorporated as Exhibit 8 of the PUD Narrative (1 page)

Illustration C

18'-0"
4' 0"
1' 6"
12' 6"
8"
4"
2' 6"
10' 6"