Adopt Resolution No. 12803 to authorize:

Person

1
Meetings
1
Jurisdictions
2023-05-02 – 2023-05-02
Activity range
Activity by Jurisdiction
Jurisdiction Meetings Items Withdrawn
City of Scottsdale 1 1
Meeting Timeline
Item 7 Gainey Village Casitas Water Line Replacement Construction Phase Services Contract – Approved on Consent. 2022-197-COS-A1 with Achen-Gardner Construction, LLC, in an amount not to exceed $4,781,689.46, for Guaranteed Maximum Price Phase Two Construction Manager at Risk Services, for a revised total contract price not to exceed $5,458,365.28, for construction phase services for the Gainey Village Casitas Water Line Replacement project. Location: Eastwood Lane and 73rd Way Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov
Adopt Resolution No. 12803 to authorize: