Project Summary

City of El Mirage — Regular Meeting (2020-12-01)

View PDF Item 11 Meeting page

Extracted text (via pymupdf) 2339 characters
1
Nick Russo
From:
Derek Castaneda
Sent:
Thursday, November 12, 2020 4:33 PM
To:
Cason Chambers; Marcus Johnson; Nick Russo
Subject:
City of El Mirage - Facility Asbestos Evaluations 
Attachments:
Dominion - Facility Wide Assessment.pdf; Terracon - Facility Wide Assessment.pdf; Western 
Technologies Inc - Facility Wide Assessment.pdf
Good Afternoon,  
 
We have received quotes(attached) from three consultant for asbestos evaluations at our city facilities. All the 
consultants are on State contracts. In order to control cost and to better compare quotes sample limits were placed on 
each facility based on the size and complexity of each facility. All contractors provided estimates on an individual facility 
basis and understand work must be completed before the end of our fiscal year. Quotes ranged from around $22k to 
$45k for all facilities. The only cost that are not included are roof repairs for core samples. These repairs could be made 
citywide by our approved contractor instead of allowing for each consultant to hire their own subcontractor. The 
evaluations were budgeted $65k for this year with some already used for an asbestos evaluation for the City Hall office 
remodel project.  
 
After meeting and reviewing proposal I am proposing we contract West Tech Inc to evaluate most our buildings but 
would also like to have Terracon and Dominion also evaluate one facility each. The idea is to have a main consultant but 
to also have experience with alternates in case we run into situation where we need to bring in another consultant to 
help out or are in a time constraint situation. The table below is a breakdown of cost from each contractor with a 
proposed move forward cost. Numbers highlighted in red represent the chosen consultant to complete each facility.  
 
 
 
 
Building will prioritized as needed and most work can be done during off hours to minimize disturbance to building 
occupants. Please provided any feedback and/or concerns you may have moving forward. The project would move 
forward once council approval is received.  
 
Thanks, 
 
Derek P Castañeda MPA 
Environmental, Water Resources, & Sustainability  
City of El Mirage ‐ Public Works Department

2
10355 N. 121st Ave, El Mirage, AZ  85335 
O: 623‐876‐4252 | F: 623‐374‐7308 Work  
M: 480‐352‐1355 |E: dcastaneda@elmirageaz.gov