PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 14 of 29 
PW21 - WRF01 
CITY OF EL MIRAGE 
PUBLIC WORKS DEPARTMENT 
 
 
 
 
 
WATER RECLAMATION FACILITY – EFFLUENT 
FILTER PROJECT 
 
Design/Build 
Scope of Project Document 
 
PW21 - WRF01

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 15 of 29 
PW21 - WRF01 
 
CONTENTS 
 
1. ABBREVIATIONS   
 
 
 
 
 
 
 
 
 
16  
 
2. INTRODUCTION  
 
 
 
 
 
 
 
 
 
 
17 
3. BACKGROUND  
 
 
 
 
 
 
 
 
 
 
17 
4. CURRENT STATUS  
 
 
 
 
 
 
 
 
 
17 
5. BUSINESS CASE  
 
 
 
 
 
 
 
 
 
 
17 
6. PROJECT OBJECTIVES  
 
 
 
 
 
 
 
 
 
17         
7. SCOPE OF SERVICES  
 
 
 
 
 
 
 
 
 
18 
Task 1 – Project Management  
 
 
 
 
 
 
 
 
18 
 
 
1.1  
Project Meetings   
 
 
 
 
 
 
 
18  
Task 2 – Verification of Existing Conditions  
 
 
 
 
 
 
18          
 
 
2.1  
Filter Placement, Structural Support and Chemical Tank Placement  
 
 
18 
Task 3 – Basis of Design Report  
 
 
 
 
 
 
 
 
19 
Task 4 – Detailed Design   
 
 
 
 
 
 
 
 
19 
Task 5 – Permitting Services  
 
 
 
 
 
 
 
 
19 
8. LOCATION OF THE WORK 
20 
9. CONTRACTORS LICENSE 
20 
10. GUARANTEE 
20 
11. INSPECTION 
20 
12. PROTECTION OF FINISHED OR PARTIALLY FINISHED WORK 
20 
13. STOCKPILE OF MATERIALS 
20 
14. SUPERVISION BY CONTRACTOR 
20 
15. STANDARD SPECIFICATIONS AND DETAILS 
21 
16. DUMPING AND DISPOSAL OF WASTE 
21 
17. CLEANUP 
21 
18. DUST PREVENTION 
21 
19. MISCELLANEOUS REMOVAL AND RELOCATIONS 
21 
20. SUBSIDIARY WORK 
21 
21. MISCELLANEOUS WORK AND ALLOWANCES 
21 
22. PROJECT COMPLETION 
21 
23. FINAL ACCEPTANCE 
21 
24. PROPOSAL SUBMITTAL SHEET 
24

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 16 of 29 
PW21 - WRF01 
25. APPENDIX A – REFERENCES 
25 
26. APPENDIX B – STATEMENT OF CONTRACTORS QUALIFICATIONS 
26 
27. AGREEMENT 
27

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 17 of 29 
PW21 - WRF01 
1. ABBREVIATIONS  
µg/L  
 
micrograms per liter  
AACE   
Association for Advancement of Cost Engineering  
AAD  
 
annual average day  
AADF   
annual average daily flow   
APP  
 
Aquifer Protection Permit  
AZPDES  
Arizona Pollutant Discharge Elimination System  
BOD  
 
biological oxygen demand  
CCR  
 
Consumer Confidence Report  
CI2  
 
chlorine  
CITY   
City of El Mirage  
CWD   
clearwater discharge  
ft  
 
feet gal gallons  
gpm  
 
gallons per minute  
gpm/sq ft  
gallons per minute per square foot  
lb/d  
 
pounds per day  
MCESD  
Maricopa County Environmental Services Department  
MG  
 
million gallons  
mg/L  
 
milligrams per liter  
mgd  
 
million gallons per day  
min  
 
minimum  
MMADF  
maximum month average day flow  
MMADL  
maximum month average day load  
MMFPF  
maximum month flow peak factor  
MML   
maximum month load  
MMLPF  
maximum month load peaking factor  
PDF  
 
peak day flow 
PHF  
 
peak hour flow  
SBR  
 
sequencing batch reactor  
scfm  
 
standard cubic feet per minute  
sq ft  
 
square feet  
TM  
 
technical memorandum  
TSS  
 
total suspended solids

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 18 of 29 
PW21 - WRF01 
2. INTRODUCTION 
The WRF is designed to meet Class A+ effluent requirements. Wastewater enters the WRF by way of a 24-inch gravity sewer 
pipeline through a coarse bar screen to remove large solids prior to entering the influent lift station. The lift station then pumps 
the influent flow to fine screens and a vortex grit basin to remove smaller solids and grit. Next, wastewater flows by gravity to 
the equalization tank before being pumped to the SBRs where it undergoes treatment in sequential phases of fill, anoxic reaction, 
aerobic reaction, settling, and idle. Secondary effluent decanted from the SBRs is sent to the surge basin. The surge basin serves 
as storage for the secondary effluent and also provides surge capacity for the SBR system during decant.  
 
3. BACKGROUND  
After several years of operation, the plant was de-rated to 2.5 mgd by the local regulatory agency. The facility originally 
operated as a Hybrid SBR treatment system that incorporated a mixed liquor recycle flow to the anoxic basins located upstream 
of the SBRs. However, due to difficulties achieving treatment objectives, the facility has been converted to operate as a 
traditional SBR system, removing the recycle flows, and utilizing the anoxic basin as an equalization basin. 
 
4. CURRENT STATUS 
The El Mirage WRF is currently operating near the total tertiary filtration capacity of 2.1 mgd MMADF. The filtration capacity 
will be exceeded in the near future due to pending industrial development. The filter limitation is an existing problem and any 
additional flows will require the additional filtration capacity through installation of new filters and diverting filter overflows to 
the headworks. The current overflow design overloads the filters, increasing run times, causing premature filter break through 
and decreasing effluent quality. 
 
5. BUSINESS CASE 
The CITY has evaluated the upgrades required to successfully treat the increased flows from the planned industrial development. 
The planned industrial development in El Mirage will include a large data center that will initially consist of one data center 
building. This building requires significant water flows for cooling operations. The cooling operations will generate an industrial 
wastewater that has constituents approximately twice the constituent level of the potable water that will supply the facility. 
Therefore, this water will require treatment prior to disposal or reuse. These two waste streams will be combined and conveyed 
to the Water Reclamation Facility located at 10355 N. 121st Ave., El Mirage, AZ 85335 
 
6. PROJECT OBJECTIVES 
The objectives for the project include the following: 
 
 
Project design to integrate one (1) Tertiary disc treatment filter capable of meeting industry-standard hydraulic 
loading. (3 – 6 gpm/sq ft for average day and PDF’s.) The existing three (3) tertiary disc treatment filters are 
functioning at 50% design limiting the amount of influent flow capacity to 2.0 mgd. After review, the filter 
manufacturer “Aqua-Aerobic” representative IES Southwest, Inc. has verified the current operational and maintenance 
practices meet the manufacturer O & M specifications. IES Southwest also recommends the current SER line be routed 
to the headworks reducing the loading on the existing and proposed additional filter. 
 
Site and Structural evaluation and modifications (Deck Support) 
 
One (1) filter control cabinet designed to operate the new filter in Local/Remote mode 
 
Each filter to include new like level indicators, pressure differential indicators, like flow metering including 
influent, effluent control valving and associated new air/electrical piping

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 19 of 29 
PW21 - WRF01 
 
Each filter to include like process controls, alarms, real time process indicators integrated into the existing 
Wonderware SCADA software 
 
Associated electrical improvements 
 
 
Filter effluent disinfection methods of application upgrade. The existing disinfection application point needs to be 
relocated. Short circuiting along with slow reaction times are being experienced. Forty-five (45) minute to sixty (60) 
minute reaction times are common, causing over and under feeding of disinfectant. The recommendation is to improve 
the mixing by injecting the chlorine into a common pipe upstream of the clear well. This can be accomplished by 
combining the four (4) filter discharge piping into a single header. The existing piping can be combined with some 
straightforward modifications. This modification would ensure that all filter discharge would become completely mixed 
with chlorine prior to entering the Clear Well. This would improve the disinfection capabilities of the facility, and better 
utilize the existing contact basin and piping to ensure sufficient disinfection at the rated plant capacity. 
 
 
Installation of a Secondary Effluent Recycle (SER) line. This SER line would return to the influent pumping station 
(Headworks) stopping recycle through the filters, reducing filter loading and overflow while reducing sediment build up 
within the surge tank. Aqua-Aerobics Director of Product Management also recommends that the existing filter 
overflow piping (SER) be reconfigured to send these solids back to the head of the plant where they can be removed in 
the secondary process. 
o 16” recycle line to influent station, 160 LF 
o Associated valve and valve controls 
 
 
Provide future influent/effluent pipe connections for EQ basin. The future EQ basin will allow for high flow 
periods, improved process treatment and effluent water quality  
o Spooled valved blind flange for future process influent piping 
 
7.  SCOPE OF SERVICES 
The Scope of Services is organized in five main tasks: 
 
Task 1 – Project Management  
 
Task 2 – Verification of Existing Conditions 
 
Task 3 – Basis of Design Report 
 
Task 4 – Detailed Design 
 
Task 5 – Permitting Services 
Task 1 – Project Management 
The project design build team will provide coordination of project work with disciplines to ensure project deliverables are 
met. The design team will complete project setup, closeout, and invoicing during the project. 
1.1 Project Meetings 
The design build team will schedule a project kick-off meeting and up to four (4) project meetings during the design phase. 
An updated project schedule and a written agenda for each meeting shall be prepared and submitted five working days prior 
to the meeting. Meeting summary notes will be prepared and submitted to the City Project Manager within five working 
days after the meeting. The meetings during the design phase will be as follows: 
 
Kick-off Meeting 
 
Draft Basis of Design Review Meeting 
 
60% Design Review Meeting 
 
90% Design Review Meeting 
 
100% Design Review Meeting

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 20 of 29 
PW21 - WRF01 
Task 2 – Verification of Existing Conditions 
Investigations required to verify existing Record Drawings and utility “record” conditions will be provided by the design 
build team. The design build team will verify record drawings and site conditions including current conditions. 
2.1 Filter Placement, Structural Support and Chemical Tank Placement 
A Structural Engineer will perform a structural evaluation including loading calculations for the cement deck area within the 
available proposed filter (2) placement space within the chemical tank/filter area or immediately adjacent to the West.  
 
Verify existing record drawings 
 
Overall site conditions 
 
Loading calculations 
 
Structural support evaluation 
 
Secondary site evaluation if appropriate 
 
Influent, effluent piping location assessment 
 
Task 3 – Basis of Design Report 
A Basis of Design Report (BODR) will be prepared by the design build team that summarizes and documents the design 
criteria and equipment selections. All data obtained from Task 2 should be included as an appendix to the BODR. 
A draft BODR will be prepared and submitted to the City for review. Comments will be reviewed with the City and 
incorporated into the final BODR. 
Deliverables: 
 
One electronic version of the draft BODR shall be provided to the City of El Mirage 
 
Two (2) hardcopies and one electronic version of the final BODR shall be provided to the City of El Mirage. 
 
Task 4 – Detailed Design 
The design build team will prepare and submit a detailed design based on the City’s project objectives, filter manufacture 
recommendation and site evaluation. The detailed design shall include detailed construction drawings, condition assessment 
results, MCC, chemical feed line, tertiary filters, associated piping, valves, electrical, SER line, future EQ basin connections, 
meter placements, and controls. 
The design build team will prepare documents for City review at each of the design review milestones indicated in Task 1. 
City review comments shall be incorporated at each milestone. The final contract documents shall be submitted in 
reproducible form and submitted to the City project manager. Distribution of contract documents will be made by the City. 
All supporting documentation related to the design calculations and computations will be sealed by a professional Engineer 
licensed in the State of Arizona. The design build team shall prepare an engineer’s estimate of probable construction cost for 
the 60%, 90%, and 100% design submittals. The final estimate will include a detailed breakdown to show the estimated 
costs for the major components of the design. Estimates shall be prepared based on the price level projected for the 
anticipated midpoint of construction.  
Deliverables: 
 
Two (2) hardcopies and one electronic version of Construction drawings at 60%, 90%, and 100% project levels of 
completions 
 
Two (2) hardcopies and one electronic version of specifications at 60%, 90%, and 100% project levels of completion 
 
Engineer’s estimate of probable construction cost at 60%, 90%, and 100% levels of completion

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 21 of 29 
PW21 - WRF01 
Task 5 – Permitting Services 
The design build team will identify, coordinate, and prepare the required permit approval documents for Maricopa County 
Environmental Services Department (MCESD) and City of El Mirage Fire, Building, & Line Safety Department (FBLSD) 
required for permitting in advance of construction. The permitting and inspection process is shall be completed through the 
(MCESD) Approval to Construct (ATC) and Approval of Construction (AOC) process. 
Once construction drawings are completed, the design build team shall prepare an ATC application package for review by 
the MCESD and FBLSD. The review coordination will require the following: 
 
 
Prepare the required application package and submit to MCESD for review Respond to MCESD review comments after 
consulting with City staff. 
 
Assist in obtaining any permits from FBLSD required in advance of construction. 
 
Deliverables: 
 
Completed ATC application 
 
Completed AOC application 
 
Completed City of El Mirage permit application 
 
8. LOCATION OF THE WORK:  
All work is located within the City of El Mirage, Maricopa County, Arizona.   
 
9. CONTRACTORS LICENSE 
Successful proposers shall be licensed contractors through the Arizona Registrar of Contractors and have the proper 
classification to perform the work specified in this contract. 
 
10. GUARANTEE:  
The Contractor shall guarantee all work and operation of materials provided for one year after completion of the work.  
 
11. INSPECTION  
A. City Inspectors will monitor the work site(s) to report as to the progress of the work, the manner in which it is being 
performed, and report whenever it appears that material furnished or work performed by the Contractor fails to fulfill 
the requirements of the specifications and contract.  The Inspectors may direct the attention of the Contractor to such 
failures or infringement. 
B. In a case of a dispute arising between the Inspector and the Contractor as to material furnished or the manner of 
performing the work, the Inspector shall have the authority to reject materials or suspend the work until the question and 
issue can be referred to and decided by the Public Works Director or designee.  Inspectors are not authorized to revoke, 
alter, enlarge, relax, or release any requirements of the specifications. Inspectors shall in no case act as foremen or 
perform other duties for the Contractor or interfere with the management of the work by the Contractor. 
C. Inspection or supervision by the Public Works Director or designee shall not be considered as direct control of the 
individual worker and/or his/her work. The direct control shall be solely the responsibility of the Contractor.

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 22 of 29 
PW21 - WRF01 
12. PROTECTION OF FINISHED OR PARTIALLY FINISHED WORK 
The Contractor shall properly guard and protect all finished or partially finished work and shall be responsible for the same 
until the entire contract is completed and accepted by the City. Partial payment on work so completed shall not release the 
Contractor from such responsibility, but he/she shall turn over the entire work in full accordance with these specifications 
before final settlement shall be made. 
 
13. STOCKPILE OF MATERIALS 
D. The contractor may, if approved by the Project Manager, place materials in the public right-of-way provided they do not 
prevent access to adjacent properties or prevent compliance with traffic regulations. 
E. Traffic shall not be required to travel over stockpiled materials, and proper dust control shall be maintained. 
 
14. SUPERVISION BY CONTRACTOR 
The Contractor shall supervise and direct the work and shall be solely responsible for the means, methods, techniques, 
sequences, and procedures of construction.  The Contractor shall employ and maintain at the work site a qualified supervisor 
or superintendent who shall have been designated in writing by the Contractor as the Contractor's representative at the site. 
The representative shall have full authority to act on behalf of the Contractor and all communications given to the 
representative shall be as binding as if given to the Contractor. The representative shall be present on the site at all times as 
required to perform adequate supervision and coordination of the work.   
 
15. STANDARD SPECIFICATIONS AND DETAILS 
Except as otherwise noted, construction of this project and all work done under this Contract shall be in accordance with 
these specifications and all applicable Uniform Standard Specifications For Public Works Construction sponsored and 
distributed by MAG, MAG Standard Details, the City of El Mirage supplements to MAG Standard Details, and City of 
Peoria supplements to MAG Standard Details, including the latest approved revisions thereto in force at the time of bid 
advertisement, which shall be referred to hereinafter as the "Standard Specifications".  In all cases where accepted standards 
(American Water Works Association (AWWA), American National Standards Institute (ANSI), MAG, etc.) are referred to 
in the "Standard Specifications", the latest revisions as of bid advertisement shall prevail.   
 
16. DUMPING AND DISPOSAL OF WASTE 
The Contractor is responsible for the cost to dispose of all waste products including excess earth material which will not be 
incorporated into the work under this contract.  The waste product referred to herein shall become the property of the 
Contractor, unless otherwise directed by the Public Works Director 
 
17. CLEAN UP 
Clean up shall include the removal of all excess materials in conjunction with the project accumulated on any driveways, 
curbs, landscaping, or any other surface. No special payment will be made for this item. 
The Contractor shall, upon completion of the work, remove all temporary construction facilities, debris, and unused 
materials provided for in the work, and put the work site of the work and public right-of-way in a neat and clean condition.  
No special payment will be made for this item.

PW21-WRF01 
SCOPE OF WORK AND 
PROJECT SPECIFICATIONS 
Public Works Department 
10000 N. El Mirage Rd. 
El Mirage, Arizona 85335 
 
Telephone: (623) 935-6405   
Fax: (623) 933-8418 
 
 
 
Page 23 of 29 
PW21 - WRF01 
18. DUST PREVENTION 
The Contractor shall take whatever steps, procedures or means required to prevent abnormal dust conditions due to 
construction operations in connection with this contract.  The dust control measures shall be maintained at all times during 
construction of the project to the satisfaction of the Public Works Director and in accordance with the requirements of the 
Maricopa County Health Department Air Pollution Control and Environmental Protection Agency (EPA) regulations.  The 
project will be small enough where a separate Dust Control Permit will not be required.  Contractor will work under the 
City’s Dust Control permit  
 
19. MISCELLANEOUS REMOVAL AND RELOCATIONS 
Miscellaneous removals and relocations shall be construed to mean the removal of all unsuitable materials whether 
designated or implied by the plans and specifications and shall include but not be limited to the removal of such items as 
pipes, concrete, asphalt, block, brick, rock, metal, etc. of every nature and description, unless such items are specifically 
designated in a separate bid item.   
 
20. PROJECT COMPLETION 
“Project Completion” is full completion of all construction associated with a contract, including, but not limited to punch list 
items, close out documentation, O & M manuals, warranties, and record drawings as certified by the Architect or Engineer 
of record.  
 
21. FINAL ACCEPTANCE 
"Final Acceptance" shall mean a written final acceptance of the work by the Public Works Director and shall make the final 
acceptance promptly after all work under the contract has been completed in accordance with the contract documents and 
after final inspection.