SHARING YOUR VISION. BUILDING SUCCESS. 
 
 
 
PCL CONSTRUCTION, INC. 
1711 West Greentree Drive,  Suite 201, Tempe, AZ 85284 
Telephone:  480-829-6333 ♦ Fax:  480-829-8252 ♦ www.pcl.com 
Equal Opportunity Employer 
 
October 9, 2020 
 
 
Scott Ketchmark 
Utilities Superintendent 
City of El Mirage 
10355 N 121st Ave 
El Mirage, AZ 85335 
 
Re: Water Reclamation Facility - Effluent Filter Project Design-Build 
 
 
 
Dear Mr. Ketchmark, 
 
PCL appreciates the opportunity to submit the following proposal for the Preconstruction Services on 
the Water Reclamation Facility Filter Upgrades. Our proposal is based on the original Request for 
Qualifications (RFQ) and incorporates the design as well as early procurement of the filter with 
assumptions/clarifications listed below.  
Preconstruction Services Price: $525,717.00 
 
 
 
Scope of Work: 
• 
Management and Coordination of the Project during the Design Phase. 
• 
Organizing, attending and Conducting of Project Design Meetings. 
• 
Development of a Basis of Design Report. 
• 
Verification of Existing Conditions including Gathering, Organizing and Reviewing Background 
Information, Geotechnical Investigation and Potholing. 
• 
Design Services including Preparation of Drawings, Technical Specifications, Cost Estimates and a 
Guaranteed Maximum Price (GMP). 
• 
Coordination and Assistance of Permit Applications, Fee’s to be paid by Owner, for MCESD ATC 
and City of El Mirage Permitting Requirements only. 
• 
Procurement of the Tertiary Filters due to lead time being Several Months. 
 
 
 
The following is our clarifications and assumptions for this project: 
1) This proposal pricing is good for 30 days. 
2) This proposal is for Design Services only, no Construction Costs Included this will be 
provided separately.

Scott Ketchmark, Utilities Superintendent 
Water Reclamation Facility – Effluent Filter Project Design-Build 
October 9, 2020  
 Page 2 of 2 
 
PCL CONSTRUCTION, INC. 
1711 West Greentree Drive,  Suite 201, Tempe, AZ 85284 
Telephone:  480-829-6333 ♦ Fax:  480-829-8252 ♦ www.pcl.com 
Equal Opportunity Employer 
 
Assumptions: 
1) Filter Equipment Manufacture to be Aqua-Aerobics, to Match Existing Filters. 
2) City will Pay Permitting Costs Directly. 
 
Exclusions: 
1) Design of Future Basins’ Connecting Piping. 
2) Construction Cost including Construction Engineering Services 
 
 
 
We look forward to working with you. 
 
Kevin Roach 
Project Manager 
 
 
cc: Adam Gordon PCL, Craig Yakubow PCL, Jesus Angulo PCL, Tim LeClair, P.E. Wood.,                          
Andrea Kagie-Hay, P.E. Wood.

Proprietary and Confidential
Date
Owner File No
BE Number
Adam Gordon
BE200899
54.502.SPE.20.105133
October 07, 2020
Estimator
Opportunity No
PW21-WRF01
General Estimate Summary & Item Analysis Sheet
Civil Infrastructure - Phoenix Special Projects
PCL Construction, Inc.
Project Start
August 20, 2020
September 9, 2020
Completion
Project
El Mirage WRF Effluent Filter Project (PDB - RFP)
Bid Closing
El Mirage, AZ, USA
City of El Mirage
Location
Owner
Designer
July 6, 2021
Time
9:04:31 AM
10:00 AM (AZ)

PCL Construction, Inc.
Subcontract
Material
Equipment
UOM
Sheet 
Name
Description
Quantity
Total Cost
Labor
Total
Unit
Total
Unit
Total
Unit
Hours
Rate
Total
Hours
Unit
Total
Services/
Tools / Supplies
Unit
Total
El Mirage AZ, USA
BE200899
PW21-WRF01
54.502.SPE.20.105133
Opportunity No
Location
Project
BE Number
Owner File No
Oct 07, 2020
Adam Gordon
General Estimate Summary
9:04:32 AM
Civil Infrastructure - Phoenix Special Projects
El Mirage WRF Effluent Filter Project (PDB - RFP)
Summary Page 1 of 1
DIRECT COSTS
153,568
LS
Phase 1 Design-Build Services
1
120,630
---
12,564
824
16,200
PRE
---
---
3,350
---
---
68
116
108.31
297,300
LS
Long Lead Material Procurement
1
297,300
---
---
---
---
MAT
---
---
---
---
---
---
---
---
DIRECT COSTS
12,564
824
16,200
417,930
---
450,868
---
---
3,350
---
---
68
---
116
GENERAL EXPENSE COSTS
FIXED GENERAL EXPENSE
1 LS
2,629
%
F6 BOND
100
---
26.29
---
---
---
GE 8
---
---
2,629
26.29
---
---
---
---
15,894
%
F7 INSURANCE
100
---
158.94
---
---
---
GE 9
---
---
15,894
158.94
---
---
---
---
18,522
FIXED GENERAL EXPENSE
1 LS
---
---
---
---
---
---
---
18,522
---
---
---
---
---
VARIABLE GENERAL EXPENSE
1 LS
---
VARIABLE GENERAL EXPENSE
1 LS
---
---
---
---
---
---
---
---
---
---
---
---
---
GENERAL EXPENSE COSTS
---
---
---
---
---
18,522
---
---
18,522
---
---
---
---
---
T.DC.
4.11%
TOTAL COST
12,564
824
16,200
417,930
---
469,390
---
---
21,872
---
---
68
---
116
56,327
Home Office Overhead and Profit
12.00% T.C.
TOTAL BID
525,717
STANDARD-LANDSCAPE-MASTER.RPT
C:\Users\cyakubow\AppData\Local\BEST\LocalFiles\3E7E2199-23C6-4571-8424-C8EA4163ABC5\
Proprietary and Confidential
U01

Detail Page 1 of 4
BE200899
BE Number
Civil Infrastructure - Phoenix Special Projects
PCL Construction, Inc.
Proprietary and Confidential
54.502.SPE.20.105133
El Mirage, AZ, USA
PW21-WRF01
Opportunity No
Location
Project
Owner File No
El Mirage WRF Effluent Filter Project (PDB - RFP)
Oct 07, 2020
9:04:33 AM
Adam Gordon
Item Analysis Sheet
PRE
1.00
LS
Phase 1 Design-Build Services
No.
Description
Labor
Equipment
Perm. Material
SubContract
Total Cost
Hours
$ / hr
Total
Total
Total
Total
Total
$ / hr
$/ItemUnit
$/ItemUnit
Unit
UOM
Quantity
Services/
Tools/Supplies
$/ItemUnit
Total
Units Per 
Hours
ManHrs
Per Unit
Project Meetings
Project Manager
8 HR
8
116.61
933
12.11
97
150.00
1,200
---
---
278.72
2,230
ST1
---
---
1.000
1.000
Superintendent
8 HR
8
126.33
1,011
12.11
97
150.00
1,200
---
---
288.44
2,308
ST3
---
---
1.000
1.000
Verification of Existing Conditions
Superintendent
8 HR
8
126.33
1,011
12.11
97
150.00
1,200
---
---
288.44
2,308
ST3
---
---
1.000
1.000
Survey
8 HR
---
---
---
---
---
---
---
---
---
150.00
1,200
1,200
150.00
---
---
Potholing/Site Investigation
Softdig Subcontractor
8 HR
---
---
---
---
---
---
---
---
---
250.00
2,000
2,000
250.00
---
---
Support Labor
8 HR
8
54.58
437
---
---
---
---
---
---
54.58
437
WK5
---
---
1.000
1.000
Misc. supplies
1 LS
---
---
---
---
---
---
---
---
---
---
150
150
---
---
---
Constructability Reviews
Project Manager
4 HR
4
116.61
466
12.11
48
150.00
600
---
---
278.72
1,115
ST1
---
---
1.000
1.000
Superintendent
8 HR
8
126.33
1,011
12.11
97
150.00
1,200
---
---
288.44
2,308
ST3
---
---
1.000
1.000
Construction Plan/Schedule Development
Project Manager
16 HR
16
116.61
1,866
12.11
194
150.00
2,400
---
---
278.72
4,460
ST1
---
---
1.000
1.000
Superintendent
8 HR
8
126.33
1,011
12.11
97
150.00
1,200
---
---
288.44
2,308
ST3
---
---
1.000
1.000
Price Modeling
Project Manager
8 HR
8
116.61
933
12.11
97
150.00
1,200
---
---
278.72
2,230
ST1
---
---
1.000
1.000
Estimator
40 HR
40
97.18
3,887
---
---
150.00
6,000
---
---
247.18
9,887
EN1
---
---
1.000
1.000
Engineering Services
Wood
1 LS
---
---
---
---
---
---
---
--- 120,630
---
120,630
---
---
---
---
116
108.31
12,564
Phase 1 Design-Build Services
1.00 LS
824
120,630
---
153,568
---
---
---
16,200
3,350
---
---
---
C:\Users\cyakubow\AppData\Local\BEST\LocalFiles\3E7E2199-23C6-4571-8424-C8EA4163ABC5\
PRE
1.00
Phase 1 Design-Build Services
STANDARD-LANDSCAPE-MASTER.RPT
U01

Detail Page 2 of 4
BE200899
BE Number
Civil Infrastructure - Phoenix Special Projects
PCL Construction, Inc.
Proprietary and Confidential
54.502.SPE.20.105133
El Mirage, AZ, USA
PW21-WRF01
Opportunity No
Location
Project
Owner File No
El Mirage WRF Effluent Filter Project (PDB - RFP)
Oct 07, 2020
9:04:33 AM
Adam Gordon
Item Analysis Sheet
MAT
1.00
LS
Long Lead Material Procurement
No.
Description
Labor
Equipment
Perm. Material
SubContract
Total Cost
Hours
$ / hr
Total
Total
Total
Total
Total
$ / hr
$/ItemUnit
$/ItemUnit
Unit
UOM
Quantity
Services/
Tools/Supplies
$/ItemUnit
Total
Units Per 
Hours
ManHrs
Per Unit
Cloth Media Filter
1 lot - AquaDisk model # ADFP-54x6E-PC Package Filter Painted Steel Tank(s)
1 lot - AquaDisk Centretube assmblies
1 lot - AquaDisk Drive Assemblies
1 lot - AquaDisk Backwash/Sludge Assembies
1 lot - AquaDisk Instrumentation
1 lot - AquaDisk Valves
1 lot - AquaDisk Controls w/Starters
1 lot - AquaDisk Engineering
1 lot - AquaDisk Supervision
1 lot - Freight
Aqua-Aerobic QUOTE
1 LS
---
---
---
---
---
---
---
--- 297,300
---
297,300
---
---
---
---
---
---
---
Long Lead Material Procurement
1.00 LS
---
297,300
---
297,300
---
---
---
---
---
---
---
---
C:\Users\cyakubow\AppData\Local\BEST\LocalFiles\3E7E2199-23C6-4571-8424-C8EA4163ABC5\
MAT
1.00
Long Lead Material Procurement
STANDARD-LANDSCAPE-MASTER.RPT
U01

Detail Page 3 of 4
BE200899
BE Number
Civil Infrastructure - Phoenix Special Projects
PCL Construction, Inc.
Proprietary and Confidential
54.502.SPE.20.105133
El Mirage, AZ, USA
PW21-WRF01
Opportunity No
Location
Project
Owner File No
El Mirage WRF Effluent Filter Project (PDB - RFP)
Oct 07, 2020
9:04:33 AM
Adam Gordon
Item Analysis Sheet
GE 8
100.00
%
F6 BOND
No.
Description
Labor
Equipment
Perm. Material
SubContract
Total Cost
Hours
$ / hr
Total
Total
Total
Total
Total
$ / hr
$/ItemUnit
$/ItemUnit
Unit
UOM
Quantity
Services/
Tools/Supplies
$/ItemUnit
Total
Units Per 
Hours
ManHrs
Per Unit
US CONTRACT BOND Class B
%
100
US CONTRACT BOND Class B
525,717 TB
---
---
---
---
---
---
---
---
---
0.005000
2,629
2,629
0.005000
---
---
100.00 %
---
---
---
---
---
---
---
---
---
26.29
2,629
US CONTRACT BOND Class B
2,629
26.29
---
---
---
---
---
F6 BOND
100.00 %
---
---
26.29
2,629
---
---
---
---
2,629
26.29
---
---
C:\Users\cyakubow\AppData\Local\BEST\LocalFiles\3E7E2199-23C6-4571-8424-C8EA4163ABC5\
GE 8
100.00
F6 BOND
STANDARD-LANDSCAPE-MASTER.RPT
U01

Detail Page 4 of 4
BE200899
BE Number
Civil Infrastructure - Phoenix Special Projects
PCL Construction, Inc.
Proprietary and Confidential
54.502.SPE.20.105133
El Mirage, AZ, USA
PW21-WRF01
Opportunity No
Location
Project
Owner File No
El Mirage WRF Effluent Filter Project (PDB - RFP)
Oct 07, 2020
9:04:33 AM
Adam Gordon
Item Analysis Sheet
GE 9
100.00
%
F7 INSURANCE
No.
Description
Labor
Equipment
Perm. Material
SubContract
Total Cost
Hours
$ / hr
Total
Total
Total
Total
Total
$ / hr
$/ItemUnit
$/ItemUnit
Unit
UOM
Quantity
Services/
Tools/Supplies
$/ItemUnit
Total
Units Per 
Hours
ManHrs
Per Unit
General Liability
%
100
Gen Liability
525,717 TB
---
---
---
---
---
---
---
---
---
0.007500
3,943
3,943
0.007500
---
---
100.00 %
---
---
---
---
---
---
---
---
---
39.43
3,943
General Liability
3,943
39.43
---
---
Builders Risk Insurance
%
100
Builders Risk
525,717 TB
---
---
---
---
---
---
---
---
---
0.004000
2,103
2,103
0.004000
---
---
100.00 %
---
---
---
---
---
---
---
---
---
21.03
2,103
Builders Risk Insurance
2,103
21.03
---
---
Subcontract Default Insurance
%
100
SDI
417,930 SC
---
---
---
---
---
---
---
---
---
0.013500
5,642
5,642
0.013500
---
---
100.00 %
---
---
---
---
---
---
---
---
---
56.42
5,642
Subcontract Default Insurance
5,642
56.42
---
---
E&O Insurance
%
100
E&O Insurance
525,717 TB
---
---
---
---
---
---
---
---
---
0.008000
4,206
4,206
0.008000
---
---
100.00 %
---
---
---
---
---
---
---
---
---
42.06
4,206
E&O Insurance
4,206
42.06
---
---
---
---
---
F7 INSURANCE
100.00 %
---
---
158.94
15,894
---
---
---
---
15,894
158.94
---
---
C:\Users\cyakubow\AppData\Local\BEST\LocalFiles\3E7E2199-23C6-4571-8424-C8EA4163ABC5\
GE 9
100.00
F7 INSURANCE
STANDARD-LANDSCAPE-MASTER.RPT
U01

G:\Infrastructure\W-WW\02-Proposals & SOQs\2020\PW20-08-01 El Mirage WRF Filters D-B\7.0 Fee Proposal\El Mirage Filter DB Design Scope Prop 
2020 10.docx  
Wood Environment & Infrastructure Solutions, Inc.
4600 East Washington Street, Suite 600
Phoenix, Arizona 85034
T: (602) 733-6000
F: (602) 733-6100
www.woodplc.com
 
 
 
October 5, 2020 
Wood Proposal No.: PW20-08-01 
 
 
PCL Construction, Inc. 
1711 W. Greentree Dr. Unit 201 
Tempe, AZ 85284 
 
RE: 
El Mirage WRF Filter Design-Build Project 
 
Lump Sum Fee Proposal for Design 
 
Dear Mr. Gordon: 
Attached is our scope of work and fee proposal for providing engineering design services for the City of El 
Mirage Design-Build project to install one new tertiary filter at the El Mirage Water Reclamation Facility. 
The project includes piping work for a pumped SER and re-routed overflow line back to the influent pump 
station, and consolidated discharge piping. 
The scope of work in this proposal includes civil, mechanical, electrical and structural design work, 
geotechnical evaluation, and permitting for county ATC and City permits. The fee for construction 
engineering services, including inspections, record drawings and AOC permitting will be provided 
separately prior to the GMP submittal to client.  Please contact Ms. Kagie-Hay at (602) 733-6149, (480) 
241-6622, or at andrea.kagie@woodplc.com with any comments or questions.  
We look forward to the opportunity to working with PCL Construction on this project. 
Respectfully submitted, 
Wood Environment & Infrastructure Solutions, Inc. 
Reviewed by: 
 
 
 
 
Andrea L Kagie-Hay, PE 
Tim LeClair, PE 
Project Manager 
Sr. Project Manager

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page i 
TABLE OF CONTENTS 
Page 
1.0 
Introduction ........................................................................................................................................................................... 1 
1.1 
Background ............................................................................................................................................................................ 1 
2.0 
Task Descriptions ................................................................................................................................................................. 1 
2.1 
Task 1 – Project Management ........................................................................................................................................ 1 
Task 1100 – Project Management and Coordination ................................................................................... 2 
Task 1200 – Project Meetings ................................................................................................................................. 2 
2.2 
Task 2 – Basis of Design Report ..................................................................................................................................... 2 
Task 2100 – Background Information ................................................................................................................. 2 
Task 2200 – Geotechnical Investigation ............................................................................................................. 2 
Task 2300 – Filter Equipment Design .................................................................................................................. 2 
Task 2400 – Basis of Design Report ..................................................................................................................... 3 
2.3 
Task 3 – Detailed Design Services ................................................................................................................................. 3 
Task 3100 – 60% Design ........................................................................................................................................... 4 
Task 3200 – 90% Design ........................................................................................................................................... 4 
Task 3300 – 100% Design ........................................................................................................................................ 4 
2.4 
Task 4 – Permitting.............................................................................................................................................................. 4 
Task 4100 – MCESD ATC .......................................................................................................................................... 4 
Task 4200 – City FBLSD ............................................................................................................................................. 5 
3.0 
Schedule .................................................................................................................................................................................. 5 
4.0 
Fee Proposal .......................................................................................................................................................................... 5

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 1 
1.0 
Introduction 
The City of El Mirage (City) needs a filter upgrade and improvements to the chlorine injection system. 
Timing is critical with flows from a new data center coming online soon. Wood Environment & 
Infrastructure Solutions (Wood) and PCL Construction, Inc. (PCL) have teamed up to provide Design-Build 
services for the installation of a new tertiary filter and associated improvements. The costs to the City will 
be presented in two parts: 
• 
GMP 1 will include Wood’s design fees to reach full design with required permitting assistance, 
PCL’s preconstruction services, and the costs required for the purchase of the tertiary filter, as this 
will be ordered as soon as possible. 
• 
GMP 2 will include the remainder of the costs associated with project, including all construction 
scope, construction engineering services, record drawings, close-out permitting, inspections, and 
materials testing. 
Wood is providing PCL with a complete design fee in this proposal and will follow up with the costs to be 
included in GMP 2 in a subsequent proposal to be presented during the design phase. This document 
provides details of the scope of services that are included in this fee and proposal. 
1.1 
Background 
The City owns and operates the El Mirage Water Reclamation Facility (WRF), a 2.5-million gallons per day 
(mgd) tertiary wastewater treatment plant. The facility operates a sequencing batch reactor (SBR) 
treatment technology and produces Class A+ effluent. The facility requires the addition of a fourth tertiary 
filter for several reasons, including the need for redundancy and the construction of a new data center in 
their service area increasing flows up to 186,000 gallons per day (gpd). The facility will also likely require 
an expansion in the coming years to keep up with the increasing demands expected from new residential 
developments that are planned within the service area. This project will expand the tertiary filtration 
capacity with the addition of a fourth filter and make operational improvements to the filter piping and 
chlorine injection. All design must take the future expansion needs into account for feasibility and cost 
effectiveness of this project and the future expansion project. 
The following sections describe the tasks required within the scope of work for this project. 
2.0 
Task Descriptions 
The scope of services and fee proposal provided in this proposal are based on the original Request for 
Qualifications (RFQ), PCL-Wood’s joint Statement of Qualifications (SOQ), a scoping discussion with the 
City and PCL via conference call on September 22, 2020 and a scoping site visit with the City and PCL on 
September 25, 2020. 
The following sections review the proposed scope of services, broken down into tasks and sub-tasks. 
2.1 
Task 1 – Project Management  
Wood will provide project management for the Project Team under Task 1 that will include project 
management, coordination, and up to five (5) design-phase meetings. The specific tasks are broken down 
as follows:

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 2 
Task 1100 – Project Management and Coordination 
Under this task, Wood will monitor and track the project budget and progress to ensure that deadlines 
are met, and the project budget is not exceeded. Wood will keep PCL and the City informed as needed 
and prepare consolidated invoices for submittal to PCL on a monthly basis. Wood will communicate with 
PCL via email and phone calls, as needed throughout the project to ensure the project needs are fully 
understood and addressed. 
Task 1200 – Project Meetings 
This task will consist of organizing, attending, and conducting up to five (5) design meetings. The project 
Team will consist of PCL, Wood, City staff and subconsultants and sub-contractors, as required. Wood will 
provide a meeting agenda prior to each meeting and meeting notes that summarize any decisions and 
actions items resulting from each meeting. 
The meeting scope includes a kick-off meeting, a 30% design concept review meeting, and up to three (3) 
design review meetings coordinated with the design submittal milestones. Design review meetings will be 
held two weeks after each design submittal to allow the City time to review the submittal. Although not 
necessary, it would be preferable to have the City provide Wood with their review comments prior to the 
meeting so they can be discussed in more detail at the meeting. Wood will utilize the design review 
comments and discussion at these meetings to continue forward with the next phase of the design. 
2.2 
Task 2 – Basis of Design Report 
The work product developed through the sub-tasks for the Basis of Design Report (BODR) task will 
provide the basis for the design of the filters and related improvements. This task includes background 
work, geotechnical investigation and the upfront filter equipment design to allow for ordering the filter as 
early as possible. The specific sub-tasks under Task 2 include the following: 
Task 2100 – Background Information 
Wood will review the background information relevant for this design. This task consists of gathering, 
organizing, and reviewing background information, including drawings and schematics for structural and 
electrical disciplines, permits, and plant data. Wood will also continue to work with plant personnel to 
ensure all constraints are accounted for in the design. 
Task 2200 – Geotechnical Investigation 
Wood will conduct a geotechnical investigation that will include drilling one boring to 20 feet and 
development of a geotechnical report to document localized site conditions for construction of the 
structural equipment pad for the tertiary filter and for the expansion of the Filter Gallery enclosure. 
Task 2300 – Filter Equipment Design 
The lead time for the tertiary filter is several months. Wood will prioritize developing the design 
requirements and specifications upfront to allow the filter to be ordered as soon as possible in the 
process. This sub-task includes working with plant personnel and the manufacturer to ensure the filter will 
meet all site requirements including hydraulic flows, and equipment preferences.

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 3 
Task 2400 – Basis of Design Report 
Wood will develop a Basis of Design Report for the filter installation. The design report is necessary to 
obtain an Approval-to-Construct (ATC) permit through Maricopa County Environmental Services 
Department (MCESD) and the required City Fire, Building, and Life Safety Department (FBLSD) permits. 
The design report will include the sizing criteria, design criteria, and other information to show 
compliance with the existing plant permits. 
2.3 
Task 3 – Detailed Design Services 
The intent of the Detailed Design Phase of the project is to prepare a complete set of Design Drawings, 
technical specifications, cost estimates and Guaranteed Maximum Price (GMP) development assistance. 
Each sub-task will build upon the previous sub-task to develop the final product for construction. 
The filter improvements project includes not only the installation of a fourth new tertiary filter, but 
additional improvements to provide improved treatment and operational flexibility. The following is a 
simplified list of the main components and scope items that will be included in the design documents: 
• 
New filter installation 
o 
Design of equipment slab on grade based on geotechnical report 
o 
Providing power to the new filter equipment 
o 
Connecting the control panel to the plant SCADA via ethernet (programming not 
included in Wood’s scope) 
• 
New filter influent piping and valves 
• 
Secondary Effluent Recycle (SER) piping is to be routed to head of the plant upstream of the 
influent pump station (IPS) 
o 
Install flow meter on the line (potentially combining SER with OF for a single meter) 
• 
New filter discharge piping 
o 
All filter discharge piping is to be consolidated into a single discharge pipe that 
incorporates a single in-pipe chlorine injection point with an inline static mixer 
• 
New filter overflow (OF) piping 
o 
All filter OF piping is to be consolidated and re-routed to the head of the plant upstream 
of the IPS 
o 
Install flow meter on the line (potentially combining SER with OF for a single meter) 
• 
Provide a variable frequency drive (VFD) on the existing second filter feed pump to provide 
flexibility and efficiency in operation 
• 
Modify the Filter Gallery wall to enclose the new filter 
Key assumptions that will guide the design include the following: 
• 
The expansion that is planned for the near future will require the construction of new basins, all of 
which will be located to the north of the Filter Gallery and to the west of the existing SBRs. 
• 
The future Surge Basin and EQ Basin each will be hydraulically connected to its respective existing 
basin. Neither will require a direct connection to or from the influent pump station. Due to the 
proposed locations, future piping for these two basins are assumed to not interfere with the filter 
installation or general area of this current project. Design of the future basins’ connecting piping 
is excluded from this current project.

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 4 
• 
An existing 18 or 21-inch sewer pipe comes from the north and feeds into the manhole located 
north of the existing flume that is upstream of the IPS. This pipe will need to be relocated prior to 
the future expansion and installation of a fifth tertiary filter. For the current project, both sewer 
pipe locations (current and future) will need to be considered while locating the SER and re-
routed OF piping. 
The specific tasks under Task 3 include the following: 
Task 3100 – 60% Design 
This design sub-task consists of developing design drawings at a 60% design level, a draft of the design 
specifications on the plans, with a fully-developed filter specification, and an outline of the main 
components of piping, valves and flow meters developed to 60%. The 60% design sub-task includes 
development of an initial Opinion of Probable Cost of Construction (OPCC) and assistance with the 
development of the GMP from an Engineer’s perspective. 
Task 3200 – 90% Design 
Wood will continue to develop the design documents up through a 90% design level, including the full 
set of specifications on plans, incorporating comments from the City and PCL at the 60% design meeting. 
The design documents will be ready for submittal for permitting pending any final comments from the 
City and PCL at the 90% design review meeting. This submittal will include an updated OPCC, and the 
sub-task will include any GMP assistance necessary. 
Task 3300 – 100% Design 
This task will capture any changes needed based on the 90% submittal review. The design documents will 
then be sealed and signed by an Arizona-registered Professional Engineer for each discipline. The design 
documents will then be submitted to MCESD and the City. Any comments received from MCESD and City 
permitting applications will be addressed and a final conformed set of design documents will be issued. 
The final design documents will include drawings, on-plan specifications, design report, and a final 
construction cost estimate. 
2.4 
Task 4 – Permitting 
Permitting assistance included in this proposal only includes the MCESD ATC application preparation and 
City of El Mirage permitting requirements. This proposal does not include any updates to the El Mirage 
WRF Aquifer Protection Permit (APP) issued through Arizona Department of Environmental Quality 
(ADEQ). This proposal also does not include any fees associated with the permits. It is assumed the City 
will pay all necessary permitting fees. 
Task 4100 – MCESD ATC 
Under this task, Wood will fill out the necessary paperwork and compile the required information needed 
to submit with the ATC permit through MCESD. Wood will address comments received from the MCESD 
and will provide any updates to the design package required to obtain the permit.

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 5 
Task 4200 – City FBLSD 
Wood will submit to the City FBLSD, as required for permits, approvals, and Engineering review. Wood will 
address comments received from the City and will provide any updates to the design package required to 
receive required permits and approvals. 
3.0 
Schedule 
Based on the scope of services detailed above, Wood anticipates the following milestone schedule for the 
design portion of the project: 
• 
Kick-off Meeting: 
NTP + 1 week 
• 
30% Design Concept Review Meeting (Filter Specification) 
NTP + 4 weeks 
• 
60% Design Submittal 
NTP + 10 weeks 
• 
60% Design Review Meeting 
NTP + 12 weeks 
• 
90% Design Submittal 
NTP + 16 weeks 
• 
90% Design Review Meeting 
NTP + 18 weeks 
• 
100% Design Documents 
NTP + 22 weeks 
4.0 
Fee Proposal 
Based on the scope and schedule outlined above, Wood estimates approximately 948 man-hours for the 
anticipated tasks, with $2,830 for Direct Expenses that includes a geotechnical drilling sub-contractor and 
required material testing for the drill, for a total lump sum contract amount of $120,630. 
A Fee Proposal table, showing the estimated hours by task, is presented in Attachment A. The fee table is 
not to be considered as the basis for billing but is provided for informational purposes. 
Hours are assigned in the Fee Proposal table for the following team members: 
 QA/QC – Quality Assurance/Quality Control Engineer 
 PM – Project Manager 
 DsnLd – Design Lead 
 EIT – Engineer-in-Training 
 SrEE – Senior Electrical and Instrumentation & Controls Engineer 
 SrSE – Senior Structural Engineer 
 GEO – Geotechnical Engineer 
 C/MCAD – Civil/Mechanical Computer-Aided Designer 
 SCAD – Structural Computer-Aided Designer 
 ADM – Administration/Clerical 
The fee and proposal presented herein excludes the following scope of work items: 
• 
Construction Engineering Services 
o 
Submittal Review / RFI Response and Conflict Resolution 
o 
Inspection Services 
o 
Materials Testing 
o 
Redlines / Record Drawings

El Mirage WRF Filter Design-Build Project 
Wood Proposal No.: PW20-08-01 
October 5, 2020 
 
Page 6 
o 
Associated Project Management, Coordination, Construction Meetings, and Direct Costs 
• 
MCESD Approval-Of-Construction Permitting Assistance 
• 
Survey 
Wood assumes survey will not be required for this project; however, all other excluded items listed above 
will be included in a subsequent fee package presented during the design phase prior to the second GMP 
submittal.

Attachment A 
Fee Table

PCL / City of El Mirage
El Mirage WRF Filter Design-Build Project - Design Scope
FEE PROPOSAL
Wood PW 20-08-01
Task No.
Description
QA/QC
PM
DsnLd
EIT
SrEE
SrSE
GEO
C/MCAD SCAD
ADM
Total
RATES
$200
$160
$185
$75
$185
$165
$185
$125
$100
$75
Hours
Total
Task 1 - Project Management
1100
Project Management and Coordination
10
1
3
14
$2,010
1200
Project Meetings (5 design phase)
12
10
15
4
4
45
$6,295
TOTAL HOURS AND COSTS
0
22
11
15
4
4
0
0
0
3
59
$8,305
Task 2 – Basis of Design Report
2100
Background Information
6
2
16
5
8
37
$4,355
2200
Geotech Investigation
1
2
4
22
2
31
$5,190
2300
Filter Equipment Design
6
2
10
18
$2,080
2400
Basis of Design Report
2
12
4
32
2
52
$5,610
TOTAL HOURS AND COSTS
2
25
8
60
0
9
22
8
0
4
138
$17,235
Task 3 – Detailed Design
3100
60% Design - Drawings/Specs, OPCC/GMP Assist.
2
32
16
80
16
45
100
60
351
$43,365
3200
90% Design - Drawings/Specs, OPCC/GMP Assist.
4
24
20
80
10
25
80
40
283
$34,315
3300
100% Design - IFC, Final OPCC (and BODR)
1
8
4
16
10
10
24
20
93
$11,920
TOTAL HOURS AND COSTS
7
64
40
176
36
80
0
204
120
0
727
$89,600
Task 4 – Permitting
4100
MCESD ATC
2
1
6
4
13
$1,455
4200
City FBLSD
2
1
6
2
11
$1,205
TOTAL HOURS AND COSTS
0
4
2
12
0
0
0
6
0
0
24
$2,660
TOTAL PROJECT HOURS AND COSTS
9
115
61
263
40
93
22
218
120
7
948
$117,800
OTHER DIRECT COSTS
1
Geotech - Drilling Sub and Testing
$2,450
2
Travel, Copies, and Printing
$380
TOTAL OTHER DIRECT COSTS
$2,830
TOTAL PROJECT COST
$120,630

Correspondence ID#: AAL-41529
October  5, 2020
Wood
Attn:  Andrea Kagie-Hay, P.E.
4600 E. Washington Street, Suite 600
Phoenix, Arizona  85034
USA
Ph# 602/733-6000
Fax# 602/733-6100
Email: andrea.kagie@woodplc.com
Project: 
EL MIRAGE WWTP AZ
RE:
AASI Proposal # 154488 dated October 5, 2020 
AASI Project ID# 105936A
Enclosed please find our proposal package for the AquaDisk® Cloth Media Filter 
equipment, freight, and supervision services for the above referenced project.  
Aqua-Aerobic Systems, Inc. is offering the proposed equipment to meet Design 
#154488, subject to approval by the Owner or the Consulting Engineer.  Please take 
a moment to review our proposal notes and drawings for Aqua-Aerobic Systems' 
equipment terminations and items not included in Aqua-Aerobic Systems' scope of 
supply which are to be provided by the Buyer or Buyer's Installation Contractor.
We appreciate the opportunity to submit our proposal for this project and look forward 
to discussing it with you in detail.  Please feel free to contact me (phone: 
815-639-4563; email: adavila@aqua-aerobic.com), or our sales representative firm
(listed below) if you have any questions regarding our proposal offering.
Senior Project Application Engineer
Sincerely,
Angelica Davila

Page 2 of 2
October  5, 2020
            Ryan Spielman / rspielman@iessouthwest.com
           Aqua-Aerobic Systems, Inc.
           Scott Kelly / SKelly@aqua-aerobic.com
CC:
IES Southwest, Inc. / ph#: 480/488-3009 / fx#: 480/488-2525

Proposal#:  154488
TO:
ATN:
PROPOSAL DATE:  October  5, 2020
CC:
Arizona  85034
PROJECT:
Wood
EL MIRAGE WWTP AZ
4600 E. Washington Street, Suite 600
Phoenix
USA
Andrea Kagie-Hay, P.E.
IES Southwest, Inc. / ph#: 480/488-3009 / fx#: 480/488-2525
Ryan Spielman
Aqua-Aerobic Systems - Regional Manager / ph#: 815/639-4467 / fx#: 815/654-2508
Scott Kelly
The following Notes apply to Aqua-Aerobic Systems' proposal:
- We are pleased to quote, for acceptance within 60 days of the proposal date, prices and terms on equipment listed
below.
- Equipment will be furnished by Aqua-Aerobic Systems, Inc. with unloading of goods, civil work, and installation by
the Buyer.
- The equipment/goods furnished by Aqua-Aerobic Systems will be as described in this proposal.
Cloth Media Filters
AquaDisk Tanks/Basins
1  AquaDisk Model # ADFP-54x6E-PC Package Filter Painted Steel Tank(s) consisting of:
- 6 disk tank(s) will be painted steel, estimated dry weight is 13,000 lbs., and estimated operating weight is 64,000 
lbs.  Tank will be painted with Tnemec N69 and Tnemec 1075.
- Adjustable influent weir assembly(ies).
- Deflection plate.
- 304 stainless steel effluent seal plate weldment(s).
- 3" threaded brass ball valve(s).
AquaDisk Centertube Assemblies 
1  Centertube Assembly(ies consisting of:
- 304 stainless steel centertube weldment(s).
- U.H.M.W. polyethylene multi-segment driven sprocket(s).
- Dual wheel carrier assembly(ies).
- Single wheel rider assembly(ies).
- Centertube end support bearing kit(s).
- Viton V-ring effluent port\centertube seal(s).
- Disk segment 304 stainless steel support rods.
- Neoprene media sealing gaskets.
- Pile cloth media and non-corrosive support frame assemblies.
1  Cloth set(s) will have the following feature:
- Cloth will be chlorine resistant.
AquaDisk Drive Assemblies
1  Drive System Assembly(ies) consisting of:
- Gearbox(es) with three phase 1/2 HP drive motor(s).
Page 1 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
- Acetal drive chain(s) with 304 stainless steel link pins.
- Chain guard weldment(s).
- Warning label(s).
- Adjustable drive bracket weldment(s).
- Stationary drive bracket weldment(s).
- Nylon drive sprocket(s).
AquaDisk Backwash/Sludge Assemblies
1  Backwash System Assembly(ies) consisting of:
- 304 stainless steel backwash nozzles.
- PVC sludge collection manifold(s).
- Nylon combination nipple(s).
- Stainless steel backwash nozzle springs.
- 1 1/2" flexible hose.
- 2" flexible hose.
- Stainless steel hose clamps.
- 304 stainless steel backwash collection manifold(s).
1  Backwash Hose Assembly(ies) consisting of:
- 3.75" O.D. hose(s).
- 0 to 15 psi pressure gauge(s).
- 0 to 30 inches mercury vacuum gauge(s).
- Vacuum transmitter(s).
1  Backwash Support Assembly(ies) consisting of:
- 304 stainless steel backwash support weldment(s).
- Stainless steel u-bolts and hardware.
1  Backwash Pump Installation(s) consisting of:
- Gorman Rupp model 12B20-B, 2HP, premium efficient, 3 phase externally mounted centrifugal pump(s).
- Bronze throttling gate valve(s).
- 2" bronze 3 way ball valve(s).
AquaDisk Instrumentation
1  Pressure Transducer Assembly(ies) consisting of:
- Level sensing pressure transducer(s).
- 304 stainless steel probe mounting bracket(s).
- Float switch(es).
AquaDisk Valves
1  Set(s) of Backwash Valve(s) consisting of:
- 2" full port, three piece, ASTM A351  Grade CF8M stainless steel body ball valve(s), grooved end connections with
single phase electric actuator(s).  Valve / actuator combination shall be manufactured by TCI / RCI (RCI, a division
of Rotork), Nibco, or equal.
1  Sludge Valve(s) consisting of:
- 2" full port, three piece, ASTM A351  Grade CF8M stainless steel body ball valve(s), grooved end connections with
single phase electric actuator(s).  Valve / actuator combination shall be manufactured by TCI / RCI (RCI, a division
of Rotork), Nibco, or equal.
AquaDisk Controls w/Starters
1  Control Panel Accessories consisting of:
- PVC conduit and fittings.
1  Control Panel(s) consisting of:
- NEMA 4X 304 stainless steel enclosure(s).
- Control panel sun shield.
- Air conditioner(s).
Page 2 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
- Circuit breaker with handle.
- 2 KVA Transformer(s).
- Fuses and fuse blocks.
- Single phase circuit breaker(s).
- Line filter(s).
- GFI convenience outlet(s).
- Control relay(s).
- Selector switch(es).
- Indicating pilot light(s).
- MicroLogix 1400 PLC(s).
- Ethernet switch(es).
- PanelView Plus 7 7" color touch screen display(s).
- Operator interface sun shield(s).
- Power supply(ies).
- Motor starter(s).
- Terminal blocks.
- UL label(s).
AquaDisk Engineering
1  Set(s) Documentation for the AquaDisk will be provided as described:
- Engineer's Approval Data (English language) in electronic format.
1  Set(s) Documentation for the AquaDisk will be provided as described:
- Operation & Maintenance Manuals (English language) in electronic format.
AquaDisk Supervision/Freight Domestic
1  Supervision Services and Freight Package(s) for the AquaDisk will be provided as follows:
- 3 Day(s) On Site for MECHANICAL SUPERVISION
- 1 Trip(s) for MECHANICAL SUPERVISION
- FREIGHT TO JOBSITE
The Following General Notes apply to Aqua-Aerobic Systems' Proposal:
- THE CONSOLIDATED APPROPRIATIONS ACT of 2014:   The goods proposed are in compliance with the
American Iron and Steel (AIS) requirements of the Consolidated Appropriations Act of 2014 as mandated in EPA's
State Revolving Fund Programs as of the date of this proposal.
- SCHEDULE: We expect submittals to be completed and in transit to you within 4-8* weeks after receipt of order
with acceptable terms and conditions and guarantee of payment.  We expect receipt of approved engineer's
submittal with release for manufacture within 4-8 weeks of our transmittal of submittal data. We expect shipment of
equipment (transit time excluded) to be approximately 14-16* weeks from our receipt of approved engineer's
submittal data and release for manufacture.  Schedules may be adjusted at time of order placement, depending
upon existing order backlog.  *Weeks quoted are actual working weeks.
- Aqua-Aerobic Systems will be closed for the Christmas Holidays beginning approximately December 24, through
approximately January 2nd.
- TARIFF PRICE ESCALATION NOTE:  The proposed goods may be affected by the recent U.S. Government
proposed tariffs on imported steel and aluminum.  Because of this, Aqua-Aerobic reserves the right to re-evaluate
the pricing quoted prior to order acceptance if; 1) a purchase order is received past the validity date stated in the
proposal or, 2) the total of the quoted lead times stated in this proposal are exceeded.  Any pricing adjustments
required due to tariff impacts will be based on published material cost indices specific to the affected materials.
- CONTROLS NON-DISCLOSURE / CONFIDENTIALITY AGREEMENT:  If applicable,  Aqua-Aerobic Systems will
provide information relating to software documentation to control the treatment system supplied using Aqua-Aerobic
Systems' proprietary and/or trade secret information subject to execution of an Aqua-Aerobic "Controls
Non-Disclosure / Confidentiality Agreement".
- INTEGRAL DOCUMENTS:  The following documents are an integral part of Aqua-Aerobic Systems' proposal:
1. Aqua-Aerobics' Design #154488 and Design Notes dated October 5th, 2020.
- Additional supervision services can be provided for an additional charge of $1200/day plus travel and living
expenses.
The Following Mechanical and/or Electrical Notes apply to Aqua-Aerobic Systems' Proposal:
Page 3 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
- Valve and line sizes are to be verified by the engineer based on actual line losses.
- Filter flow hydraulics and plant's capability to handle the intermittent backwash flow is to be confirmed by the
purchaser/purchaser's consulting engineer.
- Three phase motors will be 460 volt.
- Single phase motors will be 115 volt.
The Following Scope Exclusion Notes apply to Aqua-Aerobic Systems' Proposal:
- Materials and Services not specifically described/itemized in this proposal are not included in the quoted total
price, and are to be supplied by the installing contractor/purchaser.
- Freeze protection may be required for outdoor installation in cold weather climates.  All such protection, including
but not limited to, heat tracing and insulation of pumps and piping, as well as protection against internal tank
freezing, shall be provided and installed by the installing contractor.
SCOPE BY PURCHASER/CONTRACTOR:
*Note this is not intended as a complete listing and is provided as a courtesy.
- Unloading and storage.
- Provisions for equipment access.
- Concrete, handrail and all civil works.
- All piping, spool pieces, supports, gaskets and hardware beyond Aqua-Aerobic's equipment terminations.
- Interconnecting piping, wiring and installation.
- All flanges and/or unions in the piping to service the equipment.
- Electrical conduit, hardware, supports, attachment of cables, wiring and j-boxes (if any) between motors, electrical 
valves, instruments and the control panel.
- Installation/field wiring of the control panel(s) that ship loose.
- Influent Valve(s).
- Electrical wiring and supply power.
The Following Commercial Notes apply to Aqua-Aerobic Systems' Proposal:
- F.O.B. JOBSITE; TITLE AND RISK OF LOSS: All prices and all shipments of goods are F.O.B. Jobsite City 
Location.  It is the responsibility of the Buyer to unload shipments and utilizing the packing list and bill of lading 
provided with the shipment notate shortages/damages upon receipt of the shipments and notify Aqua-Aerobic in 
writing within 7 days of the shortages/damages to facilitate filing of a freight claim.  Delivery of the goods sold 
hereunder by the carrier shall be deemed delivery to Buyer, and upon such delivery, title to such goods and risk of 
loss or damage shall be upon Buyer.
- TAXES:  State and/or local taxes are not included in the price but will be charged unless we receive a valid sales 
exemption certificate, direct pay permit, or other documentation required specifically by the taxing entity prior to 
shipment.
- SCOPE OF SUPPLY NOTE:  Aqua-Aerobic Systems' scope of supply and pricing is as described in this proposal 
including the listed Integral Documents, terms and conditions of sale, and is based upon the Aqua Aerobic Systems' 
Design Report # 154488 dated 10-05-2020.  Please refer to the proposal notes for equipment terminations and items 
not included in the  proposal which are to be provided by the Buyer.  Engineer’s submittal data will be prepared using 
these proposed goods and services, and the submittal approved by the Consulting Engineer will become an integral 
part of the scope of supply under the contract resulting from this offer.  Any additions or deletions to the scope of 
supply will be presented as change orders.
- TRADEMARKS:  Aqua-Jet®, Aqua-Jet II®, AquaDDM®, ThermoFlo®, Endura® Series, OxyMix®, OxyStar®, Fold-
a-Float®, SAF-T Float®, Aqua MixAir®, AquaCAM-D®, AquaSBR®, Aqua MSBR®, AquaPASS®, Aqua BioMax®, 
AquaEnsure®, Aqua EnduraTube®, Aqua EnduraDisc®, Aqua CB-24®, AquaDisk®, AquaDiamond®, AquaDrum®, 
Aqua MiniDisk®, Aqua MegaDisk®, AquaPrime®, AquaStorm™, OptiComb® OptiFiber®, OptiFiber PES-13®, 
OptiFiber PA2-13®, OptiFiber PES-14®, OptiFiber PF-14®, OptiFiber UFS-9®, Trust the Tag®, AquaABF®, AquaMB 
Process®, Aqua-Aerobic® MBR,  Aqua MultiBore®, Aqua Multibore® C-Series, Aqua Multibore® P-Series, Aqua 
ElectrOzone®, Aqua ElectrOzone® M-Series, IntelliPro®, Aqua-Aerobic®, and the Aqua-Aerobic Corporate logo 
artwork are registered trademarks or pending trademarks of Aqua-Aerobic Systems, Inc.  Nereda®, AquaNereda® 
Aerobic Granular Sludge Technology, and the AquaNereda Product logo artwork are a registered trademark of Royal 
HaskoningDHV.  All other products and services mentioned are trademarks of their respective owners. 
Page 4 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
GOODS QUOTED ABOVE WILL BE SOLD SUBJECT ONLY TO THE TERMS AND CONDITIONS OF SALE SET 
FORTH HEREIN. ANY DIFFERENT OR ADDITIONAL TERMS ARE HEREBY OBJECTED TO.
Total Price:  $297,300
Page 5 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
TERMS AND CONDITIONS OF AQUA-AEROBIC SYSTEMS, INC. (A Metawater Company) 
Page 1 of 2 
This offer and all of the goods and sales of Aqua-Aerobic Systems, Inc. are subject only to the following terms and conditions.  The acceptance of any 
order resulting from this proposal is based on the express condition that the Buyer agrees to all the terms and conditions herein contained.  Any terms 
and conditions in any order, which are in addition to or inconsistent with the following, shall not be binding upon Aqua-Aerobic Systems, Inc.  This 
proposal and any contract resulting therefrom, shall be governed by and construed in accordance with the laws of the State of Illinois, without regard 
to conflicts of laws principles. 
 
PAYMENT 
Unless specifically stated otherwise, quoted terms are Net 30 Days from shipping date. Past-due charges are 1.5% per month and will apply only on 
any past-due balance.  Aqua-Aerobic Systems, Inc. does not allow retainage of any invoice amount, unless authorized in writing by an authorized 
representative of our Loves Park, Illinois office. 
 
DURATION OF QUOTATION 
This proposal of Aqua-Aerobic Systems, Inc. shall in no event be effective more than 30 days from date thereof, unless specifically stated otherwise, 
and is subject to change at any time prior to acceptance. 
 
SHIPMENT 
Shipping dates are not a guarantee of a particular day of shipment and are approximate, being based upon present production information, and are 
subject to change per the production schedules existing at time of receipt of purchase order.  Aqua-Aerobic Systems, Inc. shall not be responsible for 
any delay in shipment for causes beyond its control including, but not limited to, war, riots, strikes, labor trouble causing interruption of work, fires, 
other casualties, transportation delays, modification of order, any act of governmental authorities or acts of God. Quoted shipment dates in this 
proposal are approximate dates goods will be shipped and, unless agreed to in writing by Aqua-Aerobic Systems, Inc., Buyer may not postpone or 
delay the dates of shipment of goods from our plant or from our supplier's plants beyond the dates set forth in this proposal. 
 
TITLE AND RISK OF LOSS 
All prices and all shipments of goods are F.O.B. Aqua-Aerobic Systems, Inc.'s plant at Loves Park, Illinois unless specifically stated otherwise.  
Delivery of the goods sold hereunder to the carrier shall be deemed delivery to the Buyer, and upon such delivery, title to such goods and risk of loss 
or damage shall be upon Buyer. 
 
TAXES 
Prices quoted do not include any taxes, customs duties, or import fees. Buyer shall pay any and all use, sales, privilege or other tax or customs duties 
or import fees levied by any governmental authority with respect to the sale or transportation of any goods covered hereby.  If Aqua-Aerobic Systems, 
Inc. is required by any taxing authority to collect or to pay any such tax, duty or fee, the Buyer shall be separately billed at such time for the amounts 
Aqua-Aerobic Systems, Inc. is required to pay. 
 
INSURANCE 
Unless the goods are sold on a CIF basis, the Buyer shall provide marine insurance for all risks, including war and general coverage. 
 
SECURITY  
If at any time the financial responsibility of the Buyer becomes unsatisfactory to Aqua-Aerobic Systems, Inc., or Aqua-Aerobic Systems, Inc. 
otherwise deems itself insecure as to receipt of full payment of the purchase price from Buyer hereunder, Aqua-Aerobic Systems, Inc. reserves the 
right to require payment in advance or security or guarantee satisfactory to Aqua-Aerobic Systems, Inc. of payment in full of the purchase price. 
 
LIMITATION OF ACTION 
No action shall be brought against Aqua-Aerobic Systems, Inc. for any breach of its contract of sale more than two years after the accrual of the cause 
of action thereof, and, in no event, unless the Buyer shall first have given written notice to Aqua-Aerobic Systems, Inc., of any claim of breach of 
contract within 30 days after the discovery thereof. 
 
CANCELLATION CLAUSE 
No acceptance of this proposal, by purchase order or otherwise, may be modified except by written consent of Aqua-Aerobic Systems, Inc. nor may it 
be cancelled except by prior payment to Aqua-Aerobic Systems, Inc. the following sums as liquidated damages therefore: 1) If cancellation is prior to 
commencement of production and prior to the assumption of any obligations by Aqua-Aerobic Systems, Inc. for any materials or component parts, a 
sum equal to 15% of the total purchase price; 2) If cancellation is after the commencement of production or after the assumption of any obligations by 
Aqua-Aerobic Systems, Inc. for any materials or component parts, a sum equal to the total of the direct, out-of-pocket expenses incurred to the date of 
cancellation for labor, machine time, materials and any charges made to us by suppliers for cancellation, plus 30% of the total purchase price. All 
charges and expenses shall be as determined by Aqua-Aerobic Systems, Inc. In the event any items are used by Aqua-Aerobic Systems, Inc. to fill a 
subsequent order, then upon receipt of payment for such order, Aqua-Aerobic Systems, Inc. shall pay the Buyer a sum equal to the direct       out-of-
pocket expenses previously charged and received from Buyer. 
 
PROPRIETARY INFORMATION 
This proposal, including all descriptive data, drawings, material, information and know-how disclosed by Aqua-Aerobic Systems, Inc. to Buyer in 
relation hereto is confidential information intended solely for the confidential use of Buyer, shall remain the property of Aqua-Aerobic Systems, Inc. 
and shall not be disclosed or otherwise used to the disadvantage or detriment of Aqua-Aerobic Systems, Inc. in any manner. 
Page 6 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

PROPOSAL DATE:  October  5, 2020
Proposal#:  154488
TERMS AND CONDITIONS OF AQUA-AEROBIC SYSTEMS, INC. (A Metawater Company) 
Page 2 of 2 
QUALIFIED ACCEPTANCE AND INDEMNITY 
In the event the acceptance of this proposal by Buyer either is contingent upon or subject to the approval by any third party such as, but not limited to, 
a consulting engineer, with respect to goods, parts, materials, descriptive data, drawings, calculations, or any other matter, then upon such approval by 
any third party, Aqua-Aerobic Systems, Inc. shall have no liability to Buyer or to any third party so long as the goods sold and delivered by Aqua-
Aerobic Systems, Inc. conform to this proposal.  In the event any such third party requires modifications in the proposal prior to the approval thereof, 
Aqua-Aerobic Systems, Inc. may at its sole option and without liability to any party elect to cancel this proposal or return the purchase order to Buyer. 
In the event Aqua-Aerobic Systems, Inc. elects to modify this proposal to conform to the requirements for approval by any third party, Aqua-Aerobic 
Systems, Inc. in such event shall have no liability to Buyer or to any third party so long as the goods sold and delivered by Aqua-Aerobic Systems, 
Inc. conform to this proposal as modified. 
 
Buyer agrees to indemnify and save harmless Aqua-Aerobic Systems, Inc. from and against all costs and expenses and liability of any kind 
whatsoever arising out of or in connection with claims by third parties so long as the goods sold hereunder conform to the requirements of this 
proposal as approved by any third party. 
 
WARRANTY; LIMITATION OF LIABILITY; AND DISCLAIMER 
In return for purchase and full payment for Aqua-Aerobic Systems, Inc. goods, we warrant new goods provided by us to be free from defects in 
materials and workmanship under normal conditions and use for a period of one year from the date the goods are put into service, or eighteen months 
from date of shipment (whichever first occurs).  If the goods include an “Endura Series” motor, the complete Endura Series unit shall be warranted by 
Aqua-Aerobic to be free from defects in materials and workmanship under normal conditions and use for three years from the date the product is put 
into service or 42 months from the date of shipment (whichever occurs first).   
 
OUR OBLIGATION UNDER THIS WARRANTY IS EXPRESSLY AND EXCLUSIVELY LIMITED to replacing or repairing (at our factory 
at Loves Park, Illinois) any part or parts returned to our factory with transportation charges prepaid, and which our examination shall show to have 
been defective. Prior to return of any goods or its parts to our factory, Buyer shall notify Aqua-Aerobic Systems, Inc. of claimed defect, and       Aqua-
Aerobic Systems, Inc. shall have the privilege of examining the goods at Buyer's place of business at or where the goods have otherwise been placed 
in service. In the event this examination discloses no defect, Buyer shall have no authority to return the goods or parts to our factory for the further 
examination or repair. All goods or parts shall be returned to Buyer, F.O.B. Loves Park, Illinois. This warranty shall not apply to any goods or part 
which has been repaired or altered outside our factory, or applied, operated or installed contrary to our instruction, or subjected to misuse, chemical 
attack/degradation, negligence or accident. This warranty and any warranty and guaranty of process or performance shall no longer be applicable or 
valid if any product, including any software program, supplied by Aqua-Aerobic Systems, Inc., is modified or altered without the written approval of 
Aqua-Aerobic Systems, Inc.  Our warranty on accessories and component parts not manufactured by us is expressly limited to that of the manufacturer 
thereof. 
 
THE FOREGOING WARRANTY IS MADE IN LIEU OF ALL OTHER WARRANTIES, EXPRESS OR IMPLIED, AND OF 
ALL OTHER LIABILITIES AND OBLIGATIONS ON OUR PART, INCLUDING ANY LIABILITY FOR NEGLIGENCE, 
STRICT LIABILITY, OR OTHERWISE; AND ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS 
FOR A PARTICULAR PURPOSE IS EXPRESSLY DISCLAIMED; AND WE EXPRESSLY DENY THE RIGHT OF ANY 
OTHER PERSON TO INCUR OR ASSUME FOR US ANY OTHER LIABILITY IN CONNECTION WITH THE SALE OF 
ANY GOODS PROVIDED BY US.  THERE ARE NO WARRANTIES OR GUARANTEES OF PERFORMANCE UNLESS 
SPECIFICALLY STATED OTHERWISE. 
 
UNDER NO CIRCUMSTANCES, INCLUDING ANY CLAIM OF NEGLIGENCE, STRICT LIABILITY, OR OTHERWISE, 
SHALL AQUA-AEROBIC SYSTEMS, INC. BE LIABLE FOR ANY INCIDENTAL OR CONSEQUENTIAL DAMAGES, 
COSTS OF CONNECTING, DISCONNECTING, OR ANY LOSS OR DAMAGE RESULTING FROM A DEFECT IN THE 
GOODS.  LIMIT OF LIABILITY:  AQUA-AEROBIC SYSTEMS, INC.’S TOTAL LIABILITY UNDER THE ABOVE 
WARRANTY IS LIMITED TO THE REPAIR OR REPLACEMENT OF ANY DEFECTIVE PART.  THE REMEDIES SET 
FORTH HEREIN ARE EXCLUSIVE, AND OUR LIABILITY WITH RESPECT TO ANY CONTRACT OR SALE, OR 
ANYTHING DONE IN CONNECTION THEREWITH, WHETHER IN CONTRACT, IN TORT, UNDER ANY 
WARRANTY, OR OTHERWISE, SHALL NOT, IN ANY CASE, EXCEED THE PRICE OF THE GOODS UPON WHICH 
SUCH LIABILITY IS BASED. 
 
Final acceptance of this proposal must be given to Aqua-Aerobic Systems, Inc. at their office in Loves Park, Illinois.  Please 
acknowledge acceptance by signing the proposal and returning it to Aqua-Aerobic Systems, Inc. 
Accepted by:
Offer Respectfully Submitted,
By:
Aqua-Aerobic Systems, Inc.
Date:
Angelica Davila, Senior Project Application Engineer
Company:
Page 7 of 7
Copyright 2020, Aqua-Aerobic Systems, Inc
Printed: October  5, 2020

6306 N. Alpine Rd Loves Park, IL 61111
(815) 654-2501 www.aqua-aerobic.com 
Design#  154488
AquaDisk®
Cloth Media Filter
Process Design Report
© 2020 Aqua-Aerobic Systems, Inc
EL MIRAGE WWTP AZ
October 05, 2020
Option:  Bid Design
Designed By:  Angelica Davila

Design Notes
Filtration
- The cloth media filter recommendation and anticipated effluent quality are based upon influent water quality conditions as
shown under "Design Parameters" of this Process Design Report
- The anticipated filtered effluent quality is based on the filter influent conditions as shown under "Design Parameters" of this
Process Design Report.  In addition, the filter influent should be free of algae and other solids that are not filterable through a
nominal 10 micron pore size media.  Provisions to treat algae and condition the solids to be filterable are the responsibility of
others.
- For this application, pile filter cloth is recommended.
10/05/2020
 2:42:12PM
Aqua-Aerobic Systems, Inc
CONFIDENTIAL
EL MIRAGE WWTP AZ / Design#:  154488
Page 2 of 3

AquaDISK Tertiary Filtration - Design Summary
DESIGN INFLUENT CONDITIONS
Avg. Design Flow
Max Design Flow
= 1.50 MGD
= 5678.12 m³/day
= 3.00 MGD
= 11356.24 m³/day
Pre-Filter Treatment:
Secondary
= 1041.67 gpm
= 2083.33 gpm
DESIGN PARAMETERS
Influent
mg/l
Required
<= mg/l
Anticipated
<= mg/l
Effluent
Avg. Total Suspended Solids:
10
TSSa
5
5
TSSa
TSSa
Max. Total Suspended Solids:
TSSm
15
--
--
--
--
AquaDISK FILTER RECOMMENDATION
Qty Of Filter Units Recommended
Number Of Disks Per Unit
AquaDISK FILTER CALCULATIONS
Filter Type:
Total Number Of Disks Recommended
Total Filter Area Provided
Filter Model Recommended
= 3
= 6
= 18
= 968.4 ft²  = (89.97 m²)
= AquaDisk Package Model 54: 6 Disk Unit
Filter Media Cloth Type
= OptiFiber PES-13
Vertically Mounted Cloth Media Disks featuring automatically operated vacuum backwash . Tank shall include a rounded bottom 
and solids removal system.
Average Flow Conditions:
Average Hydraulic Loading
Maximum Flow Conditions:
Maximum Hydraulic Loading
= Avg. Design Flow (gpm) / Recommended Filter Area (ft²)
= 1041.7 / 968.4 ft²
= 1.08 gpm/ft² (2.63 m/hr) at Avg. Flow
= Max. Design Flow (gpm) / Recommended Filter Area (ft²)
= 2083.3 / 968.4 ft²
= 2.15 gpm/ft² (5.26 m/hr) at Max. Flow
Solids Loading:
Solids Loading Rate
= (lbs TSS/day at max flow and max TSS loading) / Recommended Filter Area (ft²)
= 1125.9 lbs/day / 968.4 ft²
= 1.16 lbs. TSS /day/ft² (5.67 kg. TSS/day/m²)
10/05/2020
 2:42:12PM
Aqua-Aerobic Systems, Inc
CONFIDENTIAL
EL MIRAGE WWTP AZ / Design#:  154488