Consultant CHANGE ORDER - BOS APPROVAL
Maricopa County Deparment of Transportation
Change Order Number:
Date: 10/2/2025
5
Amount:
$332,625.00
Agenda Item No.
C-64-21-028-X-05
Contract No: 2020-014
Work Order No:
TT0609
Consultant Name: WSP USA Inc.
Project Name: Tonto Hills Low Volume Roads Final Design
Intial Amount:
$634,794
Contract Notice to Proceed Date:
9/29/2020
Total Prior Change Orders:
$1,039,954.00
The change order is needed to revise designs to avoid condemnation for right of way acquisitions, to complete permit applications for the water line relocation
project, post design services for both projects, and additional coordination effort needed with the right of way acquisition process.
With this Change Order, the total amount of this contract has increased 216.2%
By reason of this change 0 days extension of time will be allowed for administrative purposes, after the time allowed for construction work.
With inclusion of this change, this contract has a revised cumulative performance period of 2585 days.
The contract completion date is: 10/28/2027
By reason of this change 0 days extension of time will be allowed for construction work. The construction work completion date is:
By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract. All other contract terms and conditions remain unchanged.
The following financial information is submitted:
Initial Contract Amount
$634,794.00
Amended Contract Amount w/ previous change orders
$1,674,748.00
Current Change Order Request
$332,625.00
Amended Contract Amount w/ current change order
$2,007,373.00
We, the undersigned Consultant, do hereby agree that upon execution of this Change Order that we will perform all work as identified above, and as may be
described in attachment(s) and will accept the above specified amount(s) as full payment thereof.
IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:
Principal (Signature)
Printed Name Joy Melita
Title
Date
MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION
Consultant (if applicable) -
Date
Project Manager - Shonnell Gibbs
Date
Branch Manager - Farzana Yasmin
Date
Division Manager - Randy Dunsey
Date
I certify that this change is within the limits authorized by the Maricopa County
Procurement Code
I certify that funds are available to accomplish this Change Order
Contract Services - Beverly Krumm
Date
CIP Cash Flow Manager - Charles Williams
Date
Deputy Transportation Director - Steven Wilcox
Date
IGA PM (if applicable) -
Date
RECOMMENDED BY:
ACCEPTED AND APPROVED:
Transportation Director/Engineer - Jesse Gutierrez
Date
Chairman, Board of Supervisors -
Date
LEGAL REVIEW
ATTEST:
Approved as to form and within the powers and authority granted under the laws
of the State of Arizona to the Maricopa County Department of Transportation.
Deputy County Attorney -
Date
Clerk of the Board -
Date
COUNTY APPROVAL
1230 W. Washington St. Ste 600
Tempe, AZ 85281
wsp.com
September 5, 2025
Shonnell Gibbs, PE
Transportation Project Management Branch Manager
Maricopa County Department of Transportation
2901 W. Durango Street Phoenix, AZ 85009
RE:
Contract No.:
2020-014
Contract Description:
TT0609 Tonto Hills Final Design
Contract Modification No. 5
Dear Ms. Gibbs:
WSP has prepared Contract Modification No. 5 for added work associated with Projects TT752 and TT609. Also
provided is a certified payroll as we are asking for rate adjustments for three classifications.
While I am on leave, Isabel Quitero (Isabel.quintero@wsp.com) will be the point of contact for the projects and
can meet to discuss the scope and fee for this CM, if needed.
Many thanks,
WSP Inc.
Zahit Katz, PE
Project Manager
Cc:
Joy Melita - WSP
Jocelyn Amador - WSP
Scope of Services – Project
Specific
Final Design
FOR THE FINAL DESIGN OF
TONTO HILLS LOW VOLUME ROADS
Consultant:
WSP USA Inc.
Project No:
Contract No.:
TT0609
2020-14
Maricopa County
Department of Transportation
2901 W. Durango Street
Phoenix, AZ 85009
SEPTEMBER 2025
Scope of Services
Project Specific
Project No.: TT0609
Contract No.: 2020-14
May 2024
Page 2 of 6
Table of Contents
SCOPE OF SERVICES – PROJECT SPECIFIC ..................................................................................................... 3
Project Overview ..................................................................................................................................................... 3
Project Location ................................................................................................................................................... 3
Project Background and Purpose .......................................................................................................................... 3
Length of Services ................................................................................................................................................... 5
100.2.1
Matrix of Responsibilities .................................................................................................................... 5
100.2.3
Communication Plan ........................................................................................................................... 5
Scope of Services ..................................................................................................................................................... 5
100.2.4
Project schedule .................................................................................................................................. 6
Scope of Services
Project Specific
Project No.: TT0609
Contract No.: 2020-14
May 2024
Page 3 of 6
SCOPE OF SERVICES – PROJECT SPECIFIC
Project Overview
Project Location
The project is located within the Tonto Hills Community within Maricopa County.
Project Background and Purpose
The residents in Tonto Hills recently provided Maricopa County Department of Transportation (MCDOT) with
signed petitions requesting that the County pave 17 roadway segments of dirt roads within the community. The
roadways require frequent maintenance to repair erosion caused by the numerous ephemeral washes that run
along and across existing roadways. The Tonto Hills Low Volume Roads project will design and reconstruct
17 roadway segments to comply with MCDOT’s PM-10 requirements and meet the local community’s
expectations. The project is located at the northeastern edge of the City of Scottsdale on the outskirts of the
Tonto National Forest within the jurisdiction of Maricopa County.
This project includes the following roadway segments:
No.
Roadway
From
To
Estimated Length
1
Old Mine Rd
Deer Trail Rd
400 ft. N/O Blue Wash Rd
0.89
2
Old Mine Rd Circle
Old Mine Rd
End Road
0.04
3
Blue Wash Rd
Old Mine Rd
La Plata Rd
0.84
4
La Plata Rd
Old Mine Rd
Blue Wash Rd
0.70
5
Quail Ln 2
La Plata Rd
220 ft. E/O La Plata Rd
0.05
6
Deer Trail Rd
Old Mine Rd
Manana Rd
0.44
7
Deer Trail Circle
Deer Trail Rd
End Road
0.05
8
Tonto Rd
La Plata Rd
Blue Wash Rd
0.51
9
Sombrero Rd
Begin Road
Old Mine Rd
0.19
10
Hohokam Rd
Old Mine Rd
Hohokam Ln
0.35
11
Hohokam Ln
Begin Road
Old Mine Rd
0.10
12
Filoree Ln
Old Mine Rd
End Road
0.10
13
Manana Rd
Old Mine Rd
Tonto Rd
0.63
14
Yucca Ln
Begin Road
Blue Wash Rd
0.10
15
Turquoise Ln
Tonto Rd
End Road
0.18
16
Quail Ln
Deer Trail Rd
End Road
0.11
17
Kachina Rd
Begin Road
Old Mine Rd
0.54
Scope of Services
Project Specific
Project No.: TT0609
Contract No.: 2020-14
May 2024
Page 4 of 6
The scoping recommendations included paving the unpaved segments within the Community in adherence to
the MCDOT Low Volume Roads Guidelines and MCDOT Roadway Design Manual for the established 25
mph design criteria. The proposed roadway typical section will be either 24-foot or 20-foot wide with curb
and gutter, similar to the 2016 improvements completed by MCDOT within the Community.
As part of this contract (2020-14), WSP is scoped to complete the final design in accordance with the Project
Development Manual (PDM) and other relevant design documents, providing 60%, 95%, 100% & Sealed
Plans, specifications, and estimate.
After the 60% submittal in April 2021 and in advance of the planned 95% submittal, the project was put on
hold. Following a public virtual meeting, the Community asked MCDOT reconsider the proposed design and
modify it to provide 20-foot roadway sections throughout the Community in lieu of the proposed 24-foot
roadway width. While the 24-foot roadway is consistent with the MCDOT Guidelines for Low Volumes Roads
and has been approved by MCDOT during scoping, MCDOT asked WSP to perform a preliminary evaluation
of the impacts of the requested design change.
In May 2022 after a second public meeting with the Community, MCDOT directed WSP to implement the
design change to include revising all the typical sections to a consistent 20-foot AC pavement with roll curb,
6-foot bench and slopes that adhere to the geotechnical recommendation for the project. This contract
modification includes added work to be done by WSP to update the design (roadway, traffic, drainage, water
line, structures) as detailed in the following sections. These changes were included with Contract Modification
No. 2.
Contract Modification No. 3 included the preparation of TCE exhibits with aerial background and an allowance
for the preparation of 15 new legal descriptions as well as the preparation of RW plans.
Contract Modification No. 4, included updating driveway details based on direction from MCRED, additional
coordination with MCRED and MCDOT, the separation of the water line design plan sheets and estimate to
be a stand-alone project and preparation of clearing and grubbing exhibits for a JOC in advance of utility
relocations.
This Contract Modification No. 5 includes work associated with the TT609 Roadway and TT752 Water Line
projects:
TT752 tasks include preparing and submitting three ATCs for the project thru the ADEQ portal, attending
meetings with ADEQ to review submittals, and fees associated with the three ATC applications. In addition,
this CM includes funds for post design services for the TT752 Water Line project.
TT609 tasks include work associated with preparing alternatives to eliminate potential R/W condemnations,
redesign as agreed to avoid R/W acquisition from several parcels and post design services for the TT609
Roadway project and continued project coordination.
In addition, this CM also includes an update to three classification rates for the PM, Designer and CADD rates
as this project will extend beyond the original anticipated duration, and based on the actual rates of staff that
will continue to support its delivery.
A summary of the project contract modifications is shown in the table below:
Original Contract | Contract Modification
Amount
Original contract
$634,794
CM 1: Legal description and water line design
$371,847
Scope of Services
Project Specific
Project No.: TT0609
Contract No.: 2020-14
May 2024
Page 5 of 6
Original Contract | Contract Modification
Amount
CM 2: Redesign and resubmittal of 60%
$336,899
CM 3: Preparation of RW exhibits and Coordination
$71,100
CM 4: Design updates, Exhibits, separation of water
line, Coordination
$260,108
CM 5: Redesign (work associated with TT0752)
(work associated with TT0609)
$50,871
$332,625
Total (with CM 5)
$2,058,244
Length of Services
Length of service for this contract modification will be completed by June 2027.
100.2.1
Matrix of Responsibilities
The Matrix of responsibilities remains unchanged.
100.2.3
Communication Plan
The Communication plan remains unchanged.
Scope of Services
This Scope of Services associated with this contract modification is as follows:
Task A: TT0752 Water Line Work
The following tasks are associated with the water line project:
WSP prepared and submitted three ATCs via ADEQs portal. Three meetings were held with ADEQ to discuss
the project scope and requirements of the ATCs.
WSP paid for the three ATC applications on behalf of MCDOT.
WSP will provide post design services for the water line project. Services will include responding to RFIs and
questions from MCDOT/Contractor. Hours have been allocated for attendance of weekly meetings for the
duration of construction.
Task B: TT0609 Design Updates and Coordination
WSP provided the following services in order to assess whether redesign can eliminate the need for
condemnation for 13 parcels that MCRED has not been able to secure land rights:
-
Prepared alternate design options for 13 parcels, with exhibits, documented in a summary matrix.
-
Met with MCDOT management to review the alternate designs.
-
Met with MCRED and MCDOT weekly to discuss RW acquisition concerns and updates.
Based on an anticipated resolution for the above, the following tasks will be completed as part of this CM:
-
Drainage redesign at 5 locations and update the drainage report
-
Roadway redesign for slopes including updates to plans and earthwork (models, plans, cross sections)
-
Roadway profile adjustment at one location
Scope of Services
Project Specific
Project No.: TT0609
Contract No.: 2020-14
May 2024
Page 6 of 6
-
Update RW plans sheets for RW changes
-
Structures new design of 2 walls, models and plans
-
Update cross sections and plans with new as-built utilities
-
Site visit with EP to review plants + review project conditions (2 visits by 2 WSP staff)
-
Continued PM support (assume 4 hrs a week for 12 months)
-
Memorandum documenting deviation from design criteria (for steeper slopes)
-
Design Exceptions (DE)s for boulders that are located within 4’ of back of the proposed curb (thus
encroaching into a 6’ clear zone) at 8 locations. Tasks will include:
o
Update the existing DE document
o
Identify design alternative that does not require a design exception
o
Provide plan view exhibits depicting the DE sought and design alternative for each location
o
Assume two rounds of comments will be provided by MCDOT
-
Design document for reduced clear zone (between 6’ and 8’).
-
Locations of DEs and reduced clear zone based on survey as follows:
Deer Trail Rd (Sta 148+65, Lt)
DE
Within 6’ clear zone
Hohokam Ln (Sta 29+30, Rt)
Document
Outside of 6' clear zone, but within 6’ bench
Sombrero (Sta 385+XX, Lt)
Document
Modify wall location - Design revision may be required
OMR (338+75, Lt)
DE
Within 6’ clear zone
OMR (335+75, Rt)
DE
Within 6’ clear zone
Turquoise Ln (53+51, Rt)
DE
Within 6’ clear zone
Turquoise Ln (54+20, Lt)
DE
Design revision may be required (Geometric revision);
boulders within proposed curb
Turquoise Ln (55+10, Lt)
Document
Outside of 6' clear zone, but within 6’ bench
Manana (421+04, Lt)
DE
Within 6’ clear zone
Kachina (204+25, Lt)
DE
Within 6’ clear zone
Kachina (204+47, Rt)
DE
Within 6’ clear zone
-
Update design for changes to existing conditions (unknown at this time)
-
Post design services during construction. Services will include attending a preconstruction meeting,
weekly meetings and responding to RFIs and questions from MCDOT/Contractor.
100.2.4
Project schedule
This contract modification includes extended this project duration to December 2027.
The project schedule will be updated as follows:
100% submittal in/or around
04/2026
Sealed submittal in/or around
06/2026
Advertisement in/or around
08/2026
Begin construction in/or around
11/2026
End construction in/or around
06/2027
Tonto Hills Low Volume Roads Final Design
WSP USA Inc.
PROJECT NO. TT0609, Contract Modification No. 5
Contract No. 2020-014
ESTIMATED DIRECT LABOR
PERSON
BILLING
CLASSIFICATION
HOURS
RATE/HOUR
TOTAL
Project Principal
-
98.56
$
-
$
Project Manager
436
109.64
$
47,803
$
Senior Project Engineer
984
67.08
$
66,007
$
Project Engineer
-
53.02
$
-
$
Engineer
-
41.99
$
-
$
Designer
556
42.48
$
23,619
$
CADD Technician
140
47.18
$
6,605
$
Project Accountant
18
42.66
$
768
$
Clerical
-
$
2,134 Hours
Estimated Labor Cost
144,802
$
Overhead 137.73%
199,436
$
FCCM
0.54%
782
$
Subtotal
345,020
$
ESTIMATED DIRECT EXPENSES
(Listed By Item At Estimated Actual Cost - NO MARKUP)
Travel
92
$
Plotting
-
$
Submittal of ATC
3,960
$
Total Estimated Expenses
4,052
$
ESTIMATED OUTSIDE SERVICES AND CONSULTANTS
Firm
Cost
-
-
$
Total Estimated Outside Services
-
$
PROFIT (Direct Labor +Overhead)
10%
34,424
TOTAL ESTIMATED FEE
383,496
$
CONTRACT TIME
600 Calendar Days
(Figures Rounded To The Nearest $1)
Consultant Firm Signature
Date
DERIVATION OF COST PROPOSAL SUMMARY
5/16/2024
Page 1 of 3
9/04/2025
Tonto Hills Low Volume Roads Final Design
WSP USA Inc.
PROJECT NO. TT0609, Contract Modification No. 5
Contract No. 2020-014
Scale
No
Shts
Hours/
Sheet
Project
Principal
Project
Manager
Senior
Project
Engineer
Project
Engineer
Engineer Designer
CADD
Technician
Project
Accountant
Total
TASK
ESTIMATED STAFF HOURS - FINAL DESIGN PHASE
TT752- Submittal of ATC / Coordination with ADEQ
40
40.0
Post design services (assume 6 hrs per week for 6 months plus CAD)
156
60
216.0
Task B - Roadway Tasks
Preparation of condemnation matrix with summary and exhibits (April to August)
80
80
160.0
Address comments / Questions from MCRED
72
72
144.0
Drainage redesign at 5 locations and update to the drainage report
16
48
64.0
Roadway redesign new models for walls, slopes, update plans, earthwork (models, plans, cross
sections)
120
48
168.0
Roadway profile adjustment at one location
24
16
40.0
Update RW plans sheets for RW changes
20
20.0
Structures new design of 2 walls, models and plans
12
40
52.0
Update cross sections and plans with new utilities
40
60
100.0
Site visit with EP to review plants + review project conditions (2 visits, 2 staff)
16
16
32.0
PM support
192
192.0
Memorandum documenting deviation from design criteria (slopes)
8
32
40.0
Design exception for boulders at 8 locations (modify existing DE document to add this new
clear zone exception); two rounds of reviews
12
128
128
268.0
Design document for locations clear zone is reduced from less than 8' but more than 6'
8
40
48.0
Update design for changes to existing conditions (Unknowns)
24
100
100
40
264.0
Post design services
148
80
40
268.0
Accountant hours for invoices
18
18.0
436
984
556
140
18
2134.0
Task A - Water Line Work
5/16/2024
Page 2 of 3
Tonto Hills Low Volume Roads Final Design
WSP USA Inc.
PROJECT NO. TT0609, Contract Modification No. 5
Contract No. 2020-014
Travel
A. Local Mileage at
0.575
$
miles round trip
160 miles
5 field meetings at
Subtotal Travel
92
$
Plotting
B. Exhibits at
100.00
$
Boards for public meetings
exhibits
C. Plots at
plots
-
$
D. Plan Submittals
Half Size Bond Copies at
Copies
Full Size Bond Copies at
Copies
Subtotal Plotting
-
$
Miscellaneous Expenses
C. Other
Carrier Services (assume 6 at $25)
Subtotal Miscellaneous Expenses
-
$
ESTIMATED OUTSIDE SERVICES & CONSULTANTS
No Subs
-
$
-
$
TOTAL ESTIMATED OUTSIDE SERVICES
-
$
TOTAL ESTIMATED EXPENSES
92
$
ESTIMATE OF DIRECT EXPENSES
5/16/2024
Page 3 of 3
A:\30900490 - MCDOT Tonto Hills Final Design 2020-014\2-0 ^CONTRACT\2-2 ^PrimeContract\222 Contract Mods (Seq)\Change Order 5 Water Submittal---Not
Submitted\Certified Payroll - Weighted Average Rate Form.docx
Maricopa County Department of Transportation
Contract Services
Certified Payroll – Weighted Average Rate
Firm Name: WSP USA Inc.
Contract Number: 2020-014
INSTRUCTIONS FOR COMPLETING WEIGHTED RATE SHEET:
List individuals who will be working on the project under the
appropriate classification with their actual hourly rate, as of the date of the initial Cost Proposal Submission. Indicate the
weighted percent involvement for each individual in each classification, the weighted average rate and the proposed hourly rate for
the classification.
Labor Classifications/Employee Name
Hourly Payroll
Rate*
Percent of
Involvement
Weighted
Average Rate
Proposed Rate for
Classification
Project Manager/ Zahit Katz
$109.64
100%
$109.64
$109.64
Designer/ Megan Davies
$42.72
50%
$21.36
$42.48
Designer/ Tianna Chemello
$42.24
50%
$21.12
$42.48
CADD Technician/ Juan Soto
$47.18
100%
$47.18
$47.18
*An individual’s hourly payroll rate must not be revised after the initial Cost Proposal submission to MCDOT.
I CERTIFY THAT THE RATES FOR THE INDIVIDUALS LISTED ABOVE ARE TRUE AND ACCURATE.
This form must be signed and dated by an Officer of the firm.
Joy Melita
Print Name
Signature
Senior Director – Local Business Leader
09/04/2025