July 26", 2024

Scott Ketchmark
Utilities Superintendent
City of El Mirage
10355 N. 121% Ave

El Mirage, AZ 85335

Subject: El Mirage 24’’ WRF Replacement Project
Team Fishel Project: 20230921

Mr. Ketchmark,
Team Fishel has issued the final invoice for the El Mirage 24’’ WRF Replacement project in the amount of $76,959.28.

This final invoice of $76,959.28 and the retention held from payment application #2 in the amount of $25,209.93
complies the final payment due to Team Fishel of $102,169.21 to close this project.

If you have any questions regarding this information, please do not hesitate to call.

Sincerely,

Michael J. Curran
Team Fishel
Project Manager
(602)571-4892

Attachment(s)

8%

ACTIVITY #

PROJECT ACTIVITY TITLE

GL ACCOUNT CARRYFORWARD

62109 SENIOR CENTER REMODEL/IMPROVEMENTS (ADDITION) Admin 111-5-1415-656 $142,500
62314 SENIOR BUS Admin 141-5-3581-650 $93,000
62335 LAND AQUISITION FOR AFFORDABLE HOUSING PROGRAM Admin 111-5-1415-660 $300,000
62211 SITE AESTHETIC ENHANCEMENTS Dev Serv 111-5-1613-658 $95,000
62009 COURT SECURITY REMODEL Court 121-5-2251-656 $497,000
62329 COURTROOM A/V SYSTEM UPGRADE Court 121-5-2251-617 $60,000
62326 PAYROLL AND TIMEKEEPING SYSTEM Finance 111-5-1532-617 $30,000
62201 REPLACEMENT APPARATUS -FIRE ENGINE - Fire 148-5-1591-650 $750,000
62201 REPLACEMENT APPARATUS -FIRE ENGINE Fire 111-5-2511-650 $100,000
61909 DYSART RD - NORTHERN AVE TO PEORIA AVE-CARRYFORWAR Streets 156-5-3581-657 $20,868,500
62046 VEHICLE REPLACEMENT PROGRAM - STREETS HURF 131-5-3581-650 $47,000
62115 NEIGHBORHOOD TRAFFIC CALMING PROGRAM (NTCP) HURF 131-5-3581-657 $119,500
62213 ROADWAY DRAINAGE IMPROVEMENTS AT 1ST AVENUE HURF 131-5-3581-658 $45,500
62304 SKID STEER LOADER AND ATTACHMENTS HURF 131-5-3581-617 $54,000
62307 DYSART RD ROADWAY WIDENING (N OF CACTUS RD) HURF. 131-5-3581-657 $325,500
62308 VARNEY RD ROADWAY IMPROVEMENTS 129TH TO EL MIRAGE HURF 131-5-3581-657 $166,500
62309 121ST AVE ROADWAY IMPROVEMENTS WWTP TO JOE R.R. RD HURF 131-5-3581-657 $136,500
62336 DRAINAGE IMPROVEMENTS 125TH AVE & DESERT COVE RD HURF 131-5-3581-658 $139,500
62321 NEOGOV HR 111-5-1521-617 $11,000
62331 COUNCIL CHAMBERS A/V ENHANCEMENTS IT 111-5-1511-656 $40,000
202111019 COUNCIL CHAMBERS A/V ENHANCEMENTS IT 147-5-1591-617 $70,000
62192 WALKING TRAIL - DRAINAGE AREA CACTUS-DYSART Non-Dept 148-5-1591-658 $915,000
62213 ROADWAY DRAINAGE IMPROVEMENTS AT 1ST AVENUE Non-Dept 131-5-3581-658 $130,000
62302 VEHICLE REPLACEMENT PROGRAM - NON-DEPARTMENTAL Non-Dept 111-5-1591-650 $71,500
202111013 TRANSIT - CFDA-21.027-CSLFRF Non-Dept 147-5-1591-650 $87,000
202111007 EMERGENCY OPERATIONS CENTER-CFDA-21.027-CSLFRF Non-Dept 147-5-1591-617 $65,000
62040 VEHICLE REPLACEMENT -POLICE Police 111-5-2111-650 $363,000
62330 POLICE VEHICLE FOR LIEUTENANT 111-5-2111-650 $65,000
62334 FIREFLY GUNSHOT SENSORS 111-5-2111-617 $197,500
62340 POLICE VEHICLE FOR SCHOOL RESOURCE OFFICER 111-5-2111-650 $65,000
62341 POLICE VEHICLE RADIOS - 6 111-5-2111-617 $42,000
62342 PORTABLE RADIO FOR SCHOOL RESOURCE OFFFICER 111-5-2111-617 $6,500
62317 PORTABLE RADIO FOR LIEUTENANT 111-5-2111-617 $6,500
62009 COURT SECURITY REMODEL 111-5-1583-656 $220,000
62036 VEHICLE REPLACEMENT PROGRAM - PARKS 111-5-1582-650 $95,500

62103

VEHICLE REPLACEMENT

111-5-1583-650_

$11-5-7115-673

$60,000

62059 DRAINAGE IMPROVEMENTS Water

62343 PUBLIC WORKS FACILITY Water 511-5-7115-656 $55,000
62343 PUBLIC WORKS FACILITY ww 541-5-7585-656 $120,000
62345 CUSTOMER SERVICE FACILITY Water $11-5-7115-656 $300,000
62065 WATER STORAGE TANK MAINTENANCE PROGRAM Water 511-5-7115-656 $140,000

TOTAL (41)

$27,594,000

APPLICATION AND CERTIFICATION FOR PAYMENT

AIA DOCUMENT

TO OWNER: City of EL Mirage
10000 N. El Mirage Rd
El Mirage, AZ 85335

FROM CONTRACTOR:
The Fishel Company
Department L-2478
Columbus, OH 43260-2478

APPLICATION NO: 6 Distribution to:

INVOICE #| 719428
ORDER #: 62316
REQ #: 23147

CONTRACTOR
FIELD

OTHER

PERIOD TO: FEBRUARY

Project Name: Waste Water Treatment Plant 24" WRF Replacement

CONTRACTOR'S APPLICATION FOR PAYMENT

Application is made for payment, as shown below, in connection with the Contract.

. ORIGINAL CONTRACT SUM
. Deduction in Contract Amount
. Contract Amount Minus Deduction

. Net change by Change Orders

. CONTRACT SUM TO DATE (Line 1 + 2)
. TOTAL COMPLETED

RwONWON R=

5. RETAINAGE

nln|lalalales

a. 0.0% % of Completed Work $0.00

b. % of Stored Material $0.00

6. TOTAL EARNED LESS RETAINAGE
(Line 4 Less Line 5 Total)

7. LESS PREVIOUS CERTIFICATES FOR
PAYMENT (Line 6 from prior Certificate)

8. CURRENT PAYMENT DUE
9. BALANCE TO FINISH
(Line 3 less Line 6)

$

$76,959.28

$

S__ 531,247.93 _

“8 531,247.93_

45,057.28

576,305.21

76,959.28

76,959.28

499,345.93

(0.00)

The undersigned Contractor certifies that to the best of the Contractor's knowledge,

information and belief the Work covered by this Application for Payment has been
completed in accordance with the Contract Documents, that all amounts have been paid by
the Contractor for Work for which previous Certificates for Payment were issued and
payments received from the Owner, and that current payment shown herein is now due.

CONTRACTOR: The Fishel Company

WMichaclh } Curran 5/15/24

@ignature Date

CERTIFICATE FOR PAYMENT

In accordance with the Contract Documents, based on on-site observations and the data
comprising the application, the Architect certifies to the Owner that to the best of the
Architect's knowledge, information and belief the Work has progressed as indicated,

the quality of the Work is in accordance with the Contract Documents, and the Contractor
is entitled to payment of the AMOUNT CERTIFIED.

AMOUNT CERTIFIED ........... $

(Attach explanation if amount certified differs from the amount applied. Initial all figures on this
Application and on the Continuation Sheet that are changed to conform with the amount certified.)
AUTHORIZATION:

By: Date:

This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the
Contractor named herein. Issuance, payment and acceptance of payment are without
prejudice to any rights of the Owner or Contractor under this Contract.

AIA DOCUMENT G702 - APPLICATION AND CERTIFICATION FOR PAYMENT - 1992 EDITION - AIA - ©1992

THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, DC 20006-5292

THE BEST The Fishel Company
CHOICE 1366 Dublin Road
SINCE 1936 sormiey

EES city OF EL MIRAGE

12001 W PEORIA AVE
EL MIRAGE, AZ 85335

GZEEEHM CITY OF EL MIRAGE - WRF 24" SEWER MAIN REPLACEMENT

10355 N 121stA\
El Mirage, ME ene PAY APP #2

Cust # Customer PO# Invoice # Invoice Date Due Date Disc Date
6640 10/31/23 11/30/23 NET 30 DAYS
Mth/Trans Line Des: ion Contract Item Unit Price Quantity Amount
10/23 6,739 1 App# 2 MOBILIZATION 20230924 001 19,094.11429 0.350 6,682.94
10/23 6,739 2. App# 2 POT HOLE / VAC EXCAVATI 20230924 002 = 1,483.28000 3.500 5,191.48
10/23 6,739 3. App# 2 BY PASS EXISTING 24" SE 20230924 003 80,249.72000 0.250 20,062.43
10/23 6,739 4 App#t 2 SAW CUT REMOVE & REPLAC 20230924 004 93.57000 257.000 24,047.49
10/23 6,739 5 App# 2 EXCAVATE, REMOVE EXIST! 20230924 005  1,501.20000 106.000 159,127.20
10/23 6,739 6 App# 2 REMOVE & HAUL OFF EXIST 20230924 006 30.72000 150.000 4,608.00
10/23 6,739 iL App# 2 REMOVE & REPLACE EXISTI 20230924 007 92.95000 25.000 2,323.75
10/23 6,739 8 App# 2 REMOVE & REPLACE EXIST! 20230924 008 —5,258.56000 0.250 1,314.64
10/23 6,739 9 App# 2 PLUG & PUMP MH. #1A TO 20230924 009 —1,966.28000 4.000 7,865.12
10/23 6,739 10. App# 2 TIE INTO EXISTING MH.# 20230924 010 16,324.38000 1.000 16,324.38
10/23 6,739 11 App# 2 REMOVE AND REPLASE EXIS 20230924 011 136.84000 25.000 3,421.00
10/23 6,739 12. App#2 REMOVE & REPLACE EXISTI 20230924 012  4,523.52000 0.250 1,130.88
Notes: Total $252,099.31

Sales Tax

Less Retainage
Total Due

Please Remit To:
Department L-2478
Columbus OH 43260-2478 Page 1 of 1

The Fishel Company
1819 S 27th Ave
Phoenix AZ 85009

GL

Date
9/30/2022

541-5-7585-670

Invoice #

591417

Begin Balance
$531,247.93

Amount
5628.72

PO Total
$525,619.21

CURRE,

Date Processed
4/25/2023

1/23/2024
1/23/2024
10/31/2023
1/31/2024

697070
704595
689573
711647

$30,024.00
$63,195.67
$226,889.38
$51,007.63

$392,575.89
$329,380.22
$102,490.84
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21
$51,483.21

1/30/2024
1/30/2024
3/5/2024
3/5/2024