COPS 2026 JUNE 2025 DOI TO REIMBURSE.PDF

Maricopa County — Formal (2025-12-31)

View PDF Item 90 Meeting page

Extracted text (via pymupdf) 4439 characters
1104550213\2\ 
Resolution Declaring Official Intent Under U.S. Treasury 
Regulations with Respect to Reimbursements from Bond 
Proceeds of Temporary Advances Made for Payments Prior to 
Issuance, and Related Matters. 
C Number:  _____________ 
WHEREAS, United States Treasury Regulations §1.150-2 (the “Reimbursement 
Regulations”) prescribe conditions under which proceeds of bonds, notes or other obligations used 
to reimburse advances made for capital and certain other expenditures paid before the issuance of 
such bonds, notes or other obligations will be deemed to be expended (or properly allocated to 
expenditures) for purposes of Sections 103 and 141-150 of the Internal Revenue Code of 1986, as 
amended (the “Code”), upon such reimbursement so that the proceeds so used will be treated as 
allocated to those original expenditures under those sections of the Code; and 
WHEREAS, certain provisions of the Reimbursement Regulations require that there be 
a declaration of official intent not later than 60 days following payment of the capital and other 
expenditures expected to be reimbursed from proceeds of bonds, notes or other obligations, and that 
the reimbursement occur within certain prescribed time periods after the capital or other expenditure 
is paid or after the property resulting from that capital or other expenditure is placed in service; and 
WHEREAS, Maricopa County, Arizona (the “County”) intends to borrow the proceeds 
of tax-exempt obligations (the “Bonds”) to finance the costs of certain capital expenditures; and 
WHEREAS, this Board wishes to declare the County’s official intent to reimburse itself 
from the proceeds of the Bonds for certain capital and other expenditures made by the County prior 
to the issuance of the Bonds as required by the Reimbursement Regulations; 
NOW, THEREFORE, be it Resolved by the Board of Supervisors of Maricopa County, 
Arizona as follows: 
Section 1. 
The County reasonably expects that certain capital and other 
expenditures (the “Original Expenditures”) made for the purposes described on Exhibit A hereto 
(the “Project”) will be reimbursed with the proceeds of the Bonds.  The maximum principal amount 
of the Bonds expected to be issued for the Project is $67,850,000.00.  The Original Expenditures 
described herein are in addition to the Original Expenditures expected to be reimbursed which were 
identified and approved by this Board on June 26, 2024 and February 12, 2025 (together with the 
Project, the “Projects”), for a total maximum principal amount of Bonds expected to be issued for 
Projects of $247,130,000.00. 
Section 2. 
The Chief Financial Officer of the County or his designee are each 
authorized to make appropriate reimbursement and timely allocations from the proceeds of the 
Bonds to reimburse the Original Expenditures, and to take any other actions as may be appropriate, 
including evidencing in writing an allocation on the books and records of the County showing the 
use of the proceeds of the Bonds to restore the money advanced for the Original Expenditures, all at 
the times and in the manner required under the Reimbursement Regulations in order for the 
reimbursement to be treated as an expenditure of such proceeds for purposes of Sections 103 and 
141 to 150 of the Code.

1104550213\2\ 
EXHIBIT A 
Bonds 
(Anticipated COP Series 2026) 
Capital Projects 
FY25 
FY26 
FY27 
FY28 
Total 
West Valley Animal Shelter1
$18,000,000
$38,000,000
$17,100,000
$73,100,000
Public Health Building1
5,000,000
$20,500,000
$12,700,000
38,200,000
Electric Vehicle Chargers1
750,000
1,000,0003
1,750,000
MCSO Headquarters Lobby Hardening1
3,000,000
3,000,000
Above Ground Fuel Tank Replacement – McDowell Mt. Park1,2
630,000
550,0003
1,180,000
MCSO Substation – District 4 Cave Creek / Anthem1
7,000,000
17,000,000
7,300,000
31,300,000
Office Space Optimization Project2
2,000,000
30,000,000
2,000,0003
34,000,000
Downtown Election Facility
11,646,517
30,353,483
42,000,000
Durango Campus Electrical Infrastructure
6,221,846
3,678,154
9,900,000
Superior Court Central Building – 8th Floor
1,200,000 
11,500,000 
12,700,000 
Total Projects
$36,380,000
$108,250,000
$68,468,363
$34,031,637
$247,130,000
________________ 
1Included in the June 26, 2024 DOI (C-18-24-141-X-00). 
2Included in the February 12, 2025 DOI (C-18-25-052-X-00). 
3Represents an increase in funding included in the February 12, 2025 DOI (C-18-25-052-X-00).