CO6 WITH TY LIN INTERNATIONAL - CONTRACT 2021-016.PDF
Extracted text (via ocr_local)
32672 characters
Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BE90CAE : ORDER - BOS APPROVAL Maricopa County Deparment of Transportation Date: 4/8/2025 Change Order Number: | Amount:[ $911,148.00] Agenda Item No. C-64-24-235-X-01 Contract No:|2021-016 Work Order No: TT0372 Consultant Name:}T Y LIN INTERNATIONAL Project Name: Northern Parkway, 99th Avenue to 87th Avenue Intial Amount: $3,201,750] Contract Notice to Proceed Date: 3/19/2021 Total Prior Change Orders: $1,354,730.00 By mutual agreement of the parties, the following contract change(s) are incorporated into the above-identified contract. All other contract terms and conditions remain unchanged. Request approval of this change order for additional design services requested by MCDOT and the Northern Parkway partners, including contingency roadway designs and analysis, additional drainage and ITS design and analysis, and ROW coordination and additional meetings. With this Change Order, the total amount of this contract has increased 70.8% By reason of this change 0 days extension of time will be allowed for construction work. The construction work completion date is: By reason of this change 0 days extension of time will be allowed for administrative purposes, after the time allowed for construction work. With inclusion of this change, this contract has a revised cumulative performance period of 2660 days. The contract completion date is: 6/30/2028 The following financial information is submitted: Initial Contract Amount $3,201 ,750.00 Amended Contract Amount w/ previous change orders $4,556,480.00 Current Change Order Request $911,148.00 Amended Contract Amount w/ current change order $5,467,628.00 We, the undersigned Consultant, do hereby agree that upon execution of this Change Order that we will perform all work as identified above, and as may be described in attachment(s) and will accept the above specified amount(s) as full payment thereof. IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order: ‘DocuSigned by: Principal (Signature) James Dorr Printed Name James Bare Be vice-president Title Date 47872025 MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION ‘DocuSigned by: (y M Leyt 4/8/2025 Consultant (if applicable) - Date Projbet-MantaefaBA@ersjamin Markert Date ; 7_UoCusiynea By: DocuSigned by: : 4/9/2025 (Candy Dassey 4/9/2025 Lareyano Yasmin. Branch tHeetagepaoraiana Yasmin Date Division anager Randy Dunsey Date I cerfity THBeeHS!ePAst¥E is within the limits authorized by the Maricopa County | certify-thaBiynetstyce available to accomplish this Change Order Proqurepent Co ahs 4/9/2025 Beit, bmn 4/10/2025 dnc vilians is) Contract Services - ‘Beverly Krumm Date CIP Cas! ERP Manader: Charles Williams Date 4/10/2025 Date IGA PM (if applicable) - Date COUNTY APPROVAL REC Ep BY: ACCEPTED AND APPROVED: Jesse autiury 4/10/2025 Transportation DirecoreEngineer - Jesse Gutierrez Date Chairman, Board of Supervisors - Date LEGAL REVIEW ATTEST: Approved as to form and within the powers and authority granted under the laws of the Qemalaned RY:the Maricopa County Department of Transportation. Mkolaus Duker 4/17/2025 Deputy COGAIV AGM? Date Clerk of the Board - Date Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES90CAE l MARICOPA COUNTY TRANSPORTATION Scope of Services — Project Specific Final Design — Change Order 6 Northern Parkway: 103"¢ Avenue to 91** Avenue Consultant: TY Lin Project No: TT0372 Contract No.: 2021-016 TRACS No.: T0233 01D/03D Federal Aid No.:_ MMA-0(281)D Maricopa County Department of Transportation 2901 W. Durango Street Phoenix, AZ 85009 MARCH 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156COBESOCAE Scope of Services l Project Specific M A R Cc fe) PA Cc oO U NTY TRANSPORTATION Table of Contents SCOPE OF SERVICES — NORTHERN PARKWAY ~—103” AVENUE TO 915" AVENUE.,......sssssssesssees 3 Project Location Length of Services Section 100 Project Management .. 100.6 Project Progress Meetings.... Section 500 Utilities and Railroad oes essssessssessssessesessecsesseneesensssescscnseneenesceensenesennasenseness 4 500.18 General Utility Coordination Section 800 Technical Memoranda and Reports ... 800.1 Traffic Analysis. 800.2 Drainage Report... 800.5 Tohono O’odham Land Avoidance Alternatives AnalySis..........csseeeeeeseseseess 5 Section 900 — Right-Of-Way.......ccsccseesecseesseseeseessesseseenessessessssseseesesecaseseaneaneasesseeseenecneeneenseneenneetenes 6 900.18 Right-of-Way Acquisition Coordination Section 1100 Plans, Specifications and Cost Estimates... 1100.4.13 95 % Intelligent Transportation Systems (ITS) Design & Plan Development....... 6 1100.7.13 Sealed Intelligent Transportation Systems (ITS) Design & Plan Development....6 Project No.: TT0372 Contract No.: 2021-016 Revised: March 2025 Page 2 of 6 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BESOCAE Scope of Services lL Project Specific MA R) Cc oO PA C oO U NTY TRANSPORTATION SCOPE OF SERVICES — NORTHERN PARKWAY ~—103" AVENUE TO 91°" AVENUE The Maricopa County Department of Transportation (MCDOT) has requested the following additional services from TYLin International (Consultant). e Prepare contingency roadway designs and traffic operational analysis to assess the performance and feasibility of implementing improvements that would avoid the need to acquire Tohono O'odham (TO) Tribal Land in the event the land rights cannot be acquired in time to meet the federal funding deadline. e Additional design analysis to remove the existing stilling basin at the reinforced concrete box culvert per ADOT's request. e Additional USA easement coordination required to complete the twenty-three (23) Bureau of Reclamation (BOR) packages as directed by Salt River Project (SRP) to date. e Additional right-of-way coordination and meetings with property owners to support acquisitions. e Additional requests to review deeds and map underlying land ownership, review Title Reports and Title Commitments to aid in USA/BOR land acquisition e Attend regular check in meetings with MCDOT Project Manager, Utility Coordinator and Maricopa County Real Estate Development (MCRED) lead agent for the project. e Additional developer coordination (Seven-Eleven, 9433 W Northern, Animal Control Center). e Additional Drainage coordination to address offsite flows between 103 Avenue and New River. e ITS relocation in advance of the TT0372 roadway project to facilitate SRP-Irrigation construction Project Location The project limits along Northern Avenue are between 103 Avenue and 91% Avenue. Length of Services The contract time for the overall TT0372 Northern Parkway contract is 1,188 days from issuance of the original NTP. This contract change order is not requesting any alteration of original contract time. Section 100 Project Management 100.6 Project Progress Meetings The original contract budget for project meetings (progress meetings, stakeholder meetings and utility coordination meetings) has been expended by the design team based on requests from the various MCDOT departments, stakeholders and utility owners over the duration of the contract to date. Since the project's kickoff meeting on April 5, 2021, Consultant has attended 125 meetings where records of attendance and discussion have been kept. This change order will establish budget for the Consultant to attend meetings for the remainder of the final design phase as necessary to facilitate approval of the project's clearances and PS&E. These meetings include, but are not limited to, recurring coordination meetings with Flood Control District, recurring check in meetings with MCDOT Project Management, Property Owner meetings to aid in land right acquisition, recurring check in meetings with SRP-Land, Irrigation Project No.: TT0372 Contract No.: 2021-016 Revised: March 2025 Page 3 of 6 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Scope of Services v Project Specific M A R C oO PA Cc oO U NTY TRANSPORTATION and Construction Groups. Hours provided in the cost proposal for this task are for all meeting types and assume the Consultant team shall have between 1 and 3 representatives in attendance at each meeting. Key meetings for status updates, resolution of project issues and to facilitate key decisions/direction for the remainder of the project are anticipated to occur with the following (anticipated number of meetings for establishing budgetary information shown in parenthesis): e Recurring MCDOT Project Management (20) e Recurring Flood Control District of Maricopa County (FCDMC) (8) e Recurring Maricopa County Real Estate Department (MCRED) (10) e Recurring SRP Land and Construction (10) e Utility Meetings (10) e Property Owners (5) e Developer Coordination; Seven-Eleven, 9433 W Northern, Animal Control Center (5) e ITS Relocation Coordination Meetings (4) Section 500 Utilities and Railroad 500.18 General Utility Coordination Consultant shall provide additional USA Easement legal description packages per direction from SRP. Twenty-six (26) packages have been created to cover the project limits as requested by SRP-Land to date. Additional services have been requested for Consultant to provide one overview exhibit, one GIS shape file of land areas and to add Schedule B title commitments on each of the 26 legal description packages once approved by SRP. Additional services have been requested for Consultant to map property deeds to confirm underlying land ownership. Additional coordination meetings and legal description revisions have been required due to SRP’s multiple iterations of legal description review and comments. Consultant has coordinated vertical design for developer's third-party utility installations. Consultant has provided calculations of vertical design at utility crossing locations. Consultant has, and shall going forward, submit survey request to MCDOT Survey to stake hubs to control electric installation. Consultant shall monitor offsite construction progress and notify MCDOT Survey to as-built survey the installation. Consultant shall coordinate with ADOT, Peoria, Glendale and MCDOT to develop contract documents to facilitate the construction relocation of the existing Number 9 ITS vault at the southwest corner of SR101L and Northern Avenue in advance of SRP-Irrigation construction. Section 800 Technical Memoranda and Reports 800.1 Traffic Analysis Consultant’s Subconsultant, Burgess & Niple, Inc. conducted and documented traffic operational analysis evaluating the performance of multiple initial phases of the fiscally constrained alternative to avoid impacting TO land. Consultant provided information to subconsultant to aid in the development of the analysis and report. The following are the four scenarios that were analyzed: e¢ Theultimate condition recommended from the TT0573 SDR. Project No.: TT0372 Contract No.: 2021-016 Revised: March 2025 Page 4 of 6 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156COBESOCAE Scope of Services l Project Specific MA RI COPA cou NTY TRANSPORTATION e The fiscally constrained alternative that achieves the maximum amount of the ultimate condition within budgetary constraints. e Two alternative initial phases evaluated for the fiscally constrained condition. Each of these alternatives was evaluated operationally through a sensitivity analysis where operational performance of the alternatives were assessed in five year increments up through the year 2050. Consultant coordinated with subconsultant and MCDOT to inform assumptions on future year conditions and obtain latest travel demand model from MAG to update traffic forecasts. Consultant developed a total of three (3) additional graphical exhibits for use in the traffic analysis memo; one graphical exhibit for the fiscally constrained alternative and one graphical exhibit for each of the two alternatives that avoid impacting the Tohono O'odham Tribal Land. The graphic developed during the Scoping Phase was utilized for the ultimate condition. 800.2 Drainage Report ADOT requested removal of the existing stilling basin located at the outlet end of the box culvert at the east side of SR101L. MCDOT requested drainage analysis be performed to determine feasibility of removing the stilling basin, which acts as an energy dissipater within the drainage channel. Consultant coordinated with MCDOT, ADOT and subconsultant, J2 Engineering to provide analysis of the hydraulic effects associated with removing the stilling basin. Results of the analysis were documented in a separate drainage report specific to the ADOT Channel crossing of Northern Avenue. Additional drainage coordination is required to confirm the drainage design concept between 103" Avenue and New River. Drainage design maintaining conveyance of existing offsite flows while minimizing the roadway inundation have been developed and presented. Once design concept is agreed upon with MCDOT, Peoria and Glendale the needed land rights will be established, and design will be completed for 95% Submittal. 800.5 Tohono O'odham Land Avoidance Alternatives Analysis Consultant developed two alternative design concepts that avoided impacts to the TO land. One roll plot was developed for each alternative and submitted to MCDOT for review by the project partners. The two alternative design concepts were then evaluated by subconsultant B&N as part of the traffic operational analysis and documented in the traffic analysis memo. Consultant developed construction cost estimates of each alternative for the project partners to utilize in decision making. Consultant coordinated potential interim utility relocations, specifically SRP-Irrigation interim relocation design avoiding the TO property. Consultant analyzed the compatibility between the ultimate project and the two alternatives that avoid impacting the TO land to determine interim construction needs or any features that would need to be removed and reconstructed with the ultimate project. Consultant developed a roadway model utilizing the ultimate Northern Parkway vertical geometry with the revised design cross section. Consultant identified interim construction needs and _ provide documentation. Project No.: TT0372 Contract No.: 2021-016 Revised: March 2025 Page 5 of 6 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Scope of Services L Project Specific MA R) Cc oO PA Cc fe) U NTY TRANSPORTATION Section 900 Right-of-Way 900.18 Right-of-Way Acquisition Coordination Consultant has been requested by MCRED to provide additional exhibits, attend meetings and provide support in the negotiations of rights-of-way with the various property owners. Consultant has been requested to review Title Reports and Title Commitments to confirm they match legal description and exhibits for the USA/BOR land acquisition. Additional effort has been requested to develop more legal descriptions than anticipated for the USA/BOR land acquisition to facilitate SRP-Irrigation relocation. There have been 26 legal description packages requested by SRP-Land to define the various underlying land ownership. In addition, there have been 22 review iterations of these legal description packages by SRP- Land to date. The team anticipates completing this phase in April 2025 and submitting packages to the BOR for approval. Additional effort has been required from Subconsultant, Wood Patel to develop legal descriptions. This additional effort is included with this contract modification. Section 1100 Plans, Specifications and Cost Estimates Subconsultant, Burgess and Niple, has prepared detailed Maintenance of Traffic (MOT) plans for the western limits of the project beyond the 103 Avenue intersection to match into the full depth limit of the TT0600 project to the west. The additional sheets prepared to account for this have included typical sections, plan sheets, profile sheets and signing and pavement marking sheets. The corridor model was also extended westerly to address the extended western terminus. The Consultant has also revised the project plans to include the various developer driven improvements between 103 Avenue and the New River impacting several of the sheet types already prepared. 1100.4.13 95 % Intelligent Transportation Systems (ITS) Design & Plan Development Subconsultant, Y2K Engineering LLC will prepare the ITS relocation design and plans to relocate the Number 9 ITS vault in advance of SRP-Irrigation construction. Consultant will work with Subconsultant to provide 95% Plans, Specifications and Cost Estimates as requested by MCDOT. Five (5) plan sheets are anticipated to be needed. Cost Estimate bid items and Special Provisions will be developed as requested and will align with any existing JOC contracts. 1100.7.13 Sealed Intelligent Transportation Systems (ITS) Design & Plan Development Consultant shall develop Sealed Plans, Specifications and Cost Estimates in accordance with Section 1100.4.13. Project No.: TT0372 Contract No.: 2021-016 Revised: March 2025 Page 6 of 6 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Northern Parkway: 103rd Ave to 91st Ave Design PROJECT NO. TT0372 DERIVATION OF COST PROPOSAL SUMMARY Engineering Firm T.Y. Lin International Contract No. 2021-016 eee a ——————————EEEEE—E——E——: (Figures Rounded To The Nearest $1) ESTIMATED DIRECT LABOR PERSON BILLING CLASSIFICATION HOURS RATE/HOUR TOTAL Principal-in-Charge 60 $ 117.40 $ 7,044 Project Manager 1,008 $ 93.54 $ 94,288 Construction Engineer - $ 84.91 $ - Senior Project Engineer 41,188 $ 60.00 $ 71,280 Project Engineer 912 $ 45.43 $ 41,432 Design Engineer 240 $ 42.39 $ 10,174 Technician - $ 32.92 $ > Clerical : $ 16.14 $ - 3,408 Hours Estimated Labor Cost $ 224,218 Overhead 157.763% $ 353,733 Subtotal $ 577,951 ESTIMATED DIRECT EXPENSES (Listed By Item At Estimated Actual Cost - NO MARKUP) Travel $ “ Plotting $ = Total Estimated Expenses $ : ESTIMATED OUTSIDE SERVICES AND CONSULTANTS Firm Cost Burgess and Niple $ 225,707.00 Aztec Engineering $ - Y2K Engineering $ 9,695.00 J2 Engineering and Design $ - Ethos Engineering $ - MakPro Services $ = Wood Patel $ 40,000.00 Total Estimated Outside Services $275,402.00 PROFIT (Direct Labor +Overhead) 10% 57,795.10 TOTAL ESTIMATED FEE $ 911,148 CONTRACT TIME 1,888 Calendar Days (Wa 3/5/2025 Consuifgnt Firm Signature Date 3/26/2013 Page 1 of 1 $40 | 080d eroziszie [osove |] | | ov | zie | ear | soot | 09 wr || | | # roe. Fal ¥ ¥ quawidojaneg ueld pue ubIseq SII Paleas = C1°Z00L} oor 4 rai 8 quoudojanad Ue|d pur UBISEC SLI %S6-Eb'y'OOLL = Ss Oz sayeujsy }soD pue suojesyioadS *SUBld - OOLL HSV LI oor ose 002 Og UoHeUIpIO0D uOHIsiNboy AeM-30-USIY - 8L°006 AeM 30 W618 - 006 ASV} loozs oz ozz 08 SISleuy S@AneUIDIIY - S°008 0082 Ov OvL OL poday abeutesq - Z'008 lo'szt og ze aL SishIeUy Owed - L008 SLYOdIY ONY VONVEOWSW IWOINHOSL - 008 ASV] looreL oz ose Ory 09¢ rd UOREUIPIOOD AyIHN [eJOUED - B1"00S GVONTIVY ONY SSILIMTILA - 00S HSV] oove Ovh ost Oz. WN SS2i60id 399/01d - 9°00L LNSWSOVNVW 1O3POud - 001 HSV sgaulbug dgaubug | s9eulbuz, sobeuey aBieyo 3904S, syus 1e}0L yeaa} uRIsuyooL ubisog qoofoig eas qoaforg furjediouua] jsinoy ON 3129S ysvL 9 YAGHO FONVHO - NUISAC TANI - SYNOH AAVLS GALVAILSA 9L0-LZ02 “ON J9B4j}U0D ZLZE0LL “ON LOArOdd euoneusazuy Urq *A"L Wul4 Bureeuibug ubiseg aay ISL6 0} aAY PicOL :AemyIed UOYYON BV00638809S/-8h26-Zv4y-8S90-16S3303} ‘cl odojanuz UBjsn20g Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Northern Parkway: 103rd Ave to 91st Ave Design Engineering Firm T.Y. Lin International PROJECT NO. TT0372 Contract No. 2021-016 ESTIMATE OF DIRECT EXPENSES ae Travel A. Local Mileage at $ 0.56 60 trips @ 28 miles round trip [= miles Subtotal Travel Plotting B. 11x17 Exhibits / Plans at $ 0.08 = Assume 320 pages for plans x6 $ S C. 8.5x11 Reports / Specs at $ 0.04 - Assume 350 pages for reports/specs x 4 $ = D. Plan Submittals @ 320 sheets 6 Half Size Bond Copies at are Copies Full Size Bond Copies at $ 2.75 -__|Copies Subtotal Plotting $ = CLOMRILOMR Permit Fees E. Courier (15 budgeted at $15/delivery) $ _- F, CLOMR/LOMR Permit Fees Subtotal Miscellaneous Expenses i sere | ESTIMATED OUTSIDE SERVICES & CONSULTANTS Burgess and Niple $225,707.00 Aztec Engineering Y2K Engineering $ 9,695.00 J2 Engineering and Design $ 2 Ethos Engineering $ & MakPro Services $ eS Wood Patel $40,000.00 TOTAL ESTIMATED OUTSIDE SERVICES $_ 275,402.00 TOTAL ESTIMATED EXPENSES $ 275,402 262013 Page 1of 1 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE BURGESS & NIPLE 1500 N. Priest Drive | Suite 102 | Tempe, AZ 85288 | 602.244.8100 Mr. James Barr, PE Re: Contract No. 2021-016 (Change Order 3) Vice President Northern Parkway: TY Lin International 103rd Avenue to 89th Avenue 1475 N Scottsdale Rd Suite 450 Fee Proposal Scottsdale, AZ 85257 March 4, 2025 PROJECT: Northern Parkway: 103rd Avenue to 89th Avenue Final Design PROJECT NO.: TT0372 Dear Mr. Barr: Burgess & Niple is pleased to submit the attached Scope of Work and Derivation of Cost / Labor Hour Estimates for the above referenced project. Please do not hesitate to contact me at 602-704-0463 if you have any questions. Respectfully, Tn Led Jason Pagnard, PE Vice President Jason.Pagnard@burgessniple.com Copy: File burgessniple.com Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE V MARICOPA COUNTY TRANSPORTATION Scope of Services — Project Specific Final Design — Change Order 3 Northern Parkway: 103rd Avenue to 89th Avenue Consultant: Burgess & Niple Project No: TT0372 Contract No.: 2021-016 (Change Order 3) Maricopa County Department of Transportation 2901 W. Durango Street Phoenix, AZ 85009 MARCH 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Scope of Services v Northern Parkway: 103rd Avenue to 89th Avenue MARICOPA COUNTY TRANSPORTATION Table of Contents SCOPE OF SERVICES — PROJECT SPECIFIC .. Project Overview... SECTION 400 PROJECT COORDINATION .....scseesseeeeeeeeeeeseccceseeeeeeeceeceeceeeeeeseeeseeassseeeccsseceseeeseeseneeeeeeeee® SECTION 800 TECHNICAL MEMORANDA AND REPORTS .... SECTION 1100 — PLANS, SPECIFICATIONS ....sssssssssssssesesescsessssssssseesnscsssusesusesenesssesenesensessasacsenenenenseneesnente 3 List of Appendices Appendix B&N -A Derivation of Cost Project No.: TT0372 Contract No.: 2021-016 (Change Order 3) Page i of i March 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Scope of Services ly Northern Parkway: 103rd Avenue to 89th Avenue MAR\ COPA COUNTY TRANSPORTATION SCOPE OF SERVICES — PROJECT SPECIFIC Project Overview The Maricopa County Department of Transportation (MCDOT) has requested services from TY Lin International (Prime) to prepare construction documents for the project. Burgess & Niple, Inc. (Consultant) is a subconsultant to Prime and will provide roadway engineering, traffic and lighting engineering and utility relocation design services. Prime has contracted with other subconsultants to complete other discipline work. The Prime and its subconsultants are herein referred to as the Design Team. MCDOT, the City of Peoria, and the City of Glendale are herein referred to as the Project Partners. The scope of work outlined addresses modifications necessitated by the MCDOT’s formal request to revise the originally approved roadway design parameters, including but not limited to traffic operational analysis, corridor access modifications for private development, corridor modeling, and cross-sectional elements. Changes will require a modification of prior design deliverables for compliance with updated project requirements and jurisdictional standards. The revised scope will encompass recalibration of horizontal and vertical alignments, collaboration with Design Team partners to reanalyze the drainage systems, and adjustments to traffic control plans to reflect the amended design intent. The associated deliverables— including plan sheets, quantity calculations, and constructability reviews—will be regenerated to integrate the revised specifications. ; The Derivation of Cost is provided in Appendix B&N - A. The scope and cost included herein document the effort remaining to prepare the construction. SECTION 400 PROJECT COORDINATION The Consultant will coordinate with the Design Team, MCDOT, Peoria, Glendale, and developers regarding developer driven improvements and resulting modifications to the design. A Maricopa County Animal Care and Control facility may be developed south of Northern Avenue between 103rd Avenue and the New River. B&N will coordinate with the Design Team and Project Partners to determine design impacts. Coordination efforts include multiple internal design team meetings, conceptual exhibit development, and multiple meetings with the Project Partners, developer, and developer's representatives. A commercial development is planned for the southwest corner of the Northern Avenue TI with Loop 101. The commercial development will be completed in advance of TT0372. The Consultant will coordinate with the Prime and commercial development to determine design modifications that are necessary to the TT0372 construction documents. The Consultant will meet and coordination with the Project Partners to update and revise the MOT concept. Project No.: TT0372 Contract No.: 2021-016 (Change Order 3) March 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Scope of Services L Northern Parkway: 103rd Avenue to 89th Avenue MARI COPA COUNTY TRANSPORTATION - SECTION 800 TECHNICAL MEMORANDA AND REPORTS MCDOT and Prime requested additional traffic analysis to determine the performance and feasibility of phased improvements to avoid near term impacts to the private property south of Northern Avenue, between SR 101L and 91st Avenue. Consultant will conduct and document traffic operational analysis evaluating the performance of multiple initial phases of the fiscally constrained alternative. The Consultant will evaluate alternatives with each reflecting a different fiscal scenario. The four scenarios are: e The ultimate condition recommended from the TT0573 SDR e The fiscally constrained alternative that achieves the maximum amount of the ultimate condition within budgetary constraints e Two alternative initial phases evaluated for the fiscally constrained condition. Each of these alternatives will be evaluated operationally through a sensitivity analysis where operational performance of the alternatives are assessed in five year increments up through the year 2050. The Consultant will coordinate with Prime, MCDOT, Peoria, and MAG to inform assumptions about the future year conditions. MAG will provide the Consultant with the latest travel demand model to update traffic forecasts. The ultimate condition and fiscally constrained alternatives will be reevaluated using these new forecasts as these forecasts make use of MAG’s new Activity Based Model, account for increased telecommuting rates, and contain the latest employment and population data. The Consultant will develop three exhibits to show the intricacies of the fiscally constrained alternative as well as the two initial phase alternatives. The Consultant will document the analysis in a traffic analysis memo which will be reviewed by MCDOT. The Consultant will address comments and incorporate them into the final traffic analysis memo. SECTION 1100 PLANS, SPECIFICATIONS The Consultant will include additional design sheets to cover the extended project limits west of 103rd Avenue. The contract was previously amended to extend the western limit to 103rd Avenue. During the development of the 95% plans, MCDOT determined that the western terminus of TT0372 should extend beyond 103rd Avenue to match the full depth limit of the TT0600 project to the west. Additional sheets include typical sections, plan sheets, profile sheets, and signing and pavement marking sheets. The Consultant will extend the corridor model to the west to address the extended western terminus. The Consultant will revise sheets to include developer driven improvements between 103rd Avenue and the New River. These improvements impact the typical section, plan sheets, profile sheets, and median staking sheets. The Consultant will revise the design and sheets in the same geographic area to account for the change in the approach to address on-site and off-site drainage. The Consultant will revise the corridor model between 103rd Avenue and the New River to address the developer driven changes and the drainage modifications. The Consultant will develop exhibits to support Design Team discussions with the Project Partners to select the drainage design to be incorporated into the construction documents. Project No.: TT0372 Contract No.: 2021-016 (Change Order 3) March 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BE90CAE Scope of Services \ Northern Parkway: 103rd Avenue to 89th Avenue MA RI COPA COUNTY TRANSPORTATION The Consultant will revise sheets to include developer driven improvements along Northern Avenue and along Ramp A in the southwest quadrant of the Loop 101 TI. These improvements impact the plan sheets, profile sheets, median staking sheets, and jointing detail sheets. The Consultant will revise the corridor model to incorporate the developer driven changes. The Consultant will include additional design sheets to detail ADA features within the TI area not previously included in the TT0372 contract. The Consultant will update and revise the MOT plans and specifications per Project Partner direction. The Consultant will develop quantities for the work listed in Section 1100.4 and provide unit pricing for items unique to these limits of work. The Prime will be responsible for incorporating these quantities and unit prices into the final Engineer's Estimate. Project No.: TT0372 Contract No.: 2021-016 (Change Order 3) March 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-1 56C9BEQOCAE Scope of Services l Northern Parkway: 103rd Avenue to 89th Avenue MARI COPA COUNTY TRANSPORTATION APPENDIX B&N - A DERIVATION OF COST Project No.: TT0372 Contract No.: 2021-016 (Change Order 3) March 2025 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Northern Parkway, 103rd Avenue to 89th Avenue Burgess & Niple, Inc. PROJECT NO. TT0372 Contract No. 2021-016 (Change Order 3) DERIVATION OF COST PROPOSAL SUMMARY (Figures Rounded To The Nearest $1) ESTIMATED DIRECT LABOR PERSON BILLING CLASSIFICATION HOURS RATE/HOUR TOTAL Sr. Project Manager 112 $ 79.38 $ 8,891 Sr. Engineer 280 $ 63.64 $ 17,819 Engineer 4 436 $ 53.63 $ 23,383 Engineer 3 388 $ 47.79 $ 18,543 GlS/Graphics 24 $ 40.88 $ 981 1,240 Hours Estimated Labor Cost $ 69,617 Overhead 188.21% $ 131,026 Subtotal $200,643 ESTIMATED OUTSIDE SERVICES AND CONSULTANTS Firm Cost All Traffic Data Services $ 5,000 $ - Total Estimated Outside Services $ 5,000 PROFIT (Direct Labor +Overhead) 10% $ 20,064 TOTAL ESTIMATED FEE $ 225,707 CONTRACT TIME Calendar Days 1888 oi L' \ aly 3/4/2025 Consultant Firm Signature Date 3/4/2025 Page 1 of 3 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BES0CAE Northern Parkway, 103rd Avenue to 89th Avenue PROJECT NO. TT0372 ESTIMATED STAFF HOURS - Final Design Burgess & Niple, Inc. Contract No. 2021-016 (Change Order 3) No | Hours! |r. Project} sr. GisiGraphi SI TASK Seale | Sits | sheet | Manager | Engineer | Engineer 4] Engineer 3] "™ - Total [Section 400 - Project Coordination ‘MCACC Coordination WA 2 6 0 28 92.0) ‘Drainage Coordination NA 4 4 40, 24 92.0 Tl Development Coordination WA 8 6 16. 40.0 Project Pariner MOT Coordination WA 12 2 az 36.0) [Section 800 - Technical Memoranda and Reports rH 44 ery 140 24 268.0] FTask 1100 - Plans, Specifications and Estimate Wost Terminus Extension WANA Ey 16 40 24 $8.0 IMCACC Driven Changes WA [NA 12 24 40 40 116.0) ‘Drainage Driven Changes WA_[_ NA 4 8 40 40 92.0) TI Development Driven Changes WA_|_WA 8 16 40 64.0 ‘Additonal ADA Detail Sheets WA_|_WA 8 40, 40 0 128.0 Project Pariner MOT Driven Updates WA [WA 8 24 16 48.0] Corridor Model Development. NA_|_NA 16 40 £0 40, 176.0) L 412 280 436 | 388 24 |f__ 1240.0] senees Paze2et3 Docusign Envelope ID: 1ECFE591-D458-4FA2-9748-156C9BE90CAE Northern Parkway, 103rd Avenue to 89th Avenue Burgess & Niple, Inc. PROJECT NO. TT0372 Contract No. 2021-016 (Change Order 3) ESTIMATE OF DIRECT EXPENSES a —————————————SE | _| ESTIMATED OUTSIDE SERVICES & CONSULTANTS All Traffic Data Services $ 5,000 $ = TOTAL ESTIMATED OUTSIDE SERVICES TOTAL ESTIMATED EXPENSES $ 5,000 3/4/2025 Page 3 of 3