Item Report

City of Tolleson — City Council (2025-05-27)

View PDF Meeting page

Extracted text (via pymupdf) 2158 characters
Item Number: I.2. 
 
 
CITY COUNCIL REPORT 
 
SUBJECT: 
Chasse Building Team Professional Services Agreement 
MEETING DATE: 
May 27, 2025 
 
TO: 
Mayor and Council 
FROM: 
Chris Hamilton, City Engineer 
REVIEWED: 
Reyes Medrano Jr., City Manager 
 
PURPOSE: 
The Development Services Department is seeking authorization for the City Manager to enter into and execute 
the Construction Manager at Risk (CM@R) Agreement between the City of Tolleson and Chasse Building Team, 
Inc., for Phase I and Phase II in the amount of $3,225,511 for pre-construction services and procurement of long 
lead items related to the Tolleson Aquatics Center project. 
 
BACKGROUND: 
On June 25, 2024, Council approved the first amendment with Adaptive Architects for the final design of the 
Tolleson Aquatics Center due to a site relocation.  A Request For Statement of Qualifications was advertised in 
March of 2023. 3 submittals were received, reviewed and scored by Staff.  After interviews, Chasse Building 
Team was selected as the candidate to move forward with as CM@R contractor.  
 
DISCUSSION: 
With the design nearing completion, the first phase of Contractor engagement includes review of design, 
specifications and construction costing to prepare the final guaranteed maximum price (GMP).  The Contractor 
would like to move forward with the procurement of long lead items that are on the critical path of construction. 
Upon completion of the design, a guaranteed maximum price for construction will be developed by the team 
and presented to Council for approval. 
 
BUDGET IMPACT: 
The City shall pay the Contractor an amount for the services at the rates set forth in the Fee Proposal. Funds for 
this agreement are available in the approved budget under the appropriate accounts designated for capital 
improvement projects through the Tolleson Aquatics Center line. Phase 1 is $160,000 and Phase 2 budget is 
$3,065,511. 
 
RECOMMENDATION: 
Staff recommends the City Council authorize the City Manager to enter into and execute the Construction 
Manager at Risk (CM@R) Agreement between the City of Tolleson and Chasse Building Team. 
 
ATTACHMENTS: 
None