Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
Organization
1
Mentions
1
Meetings
1
Jurisdictions
2023-11-20 – 2023-11-20
Activity range
All 1 Mentions
(1 meeting, 1 jurisdiction)
City of Scottsdale ·
Scottsdale City Council
· 2023-11-20
#1
Ashler Hills Park Construction Phase Contract – Approved on Consent. 2023-168-COS with Valley Rain Construction Corporation, in an amount not to exceed $8,753,376, to provide construction services for the Bond 2019 Project 55 – Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock). Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov Park Construction Phase Contract.
Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
Request
#2
WestWorld Master Plan Phase II Services Engineering Services Contract Amendment – Approved on Consent. amendment to the contract with Kimley-Horn and Associates, Inc., in the amount of $385,360, for WestWorld Master Plan Phase II Services. Location: 16601 N. Pima Road Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov
Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
Request
Activity by Jurisdiction
× clear filter
| Jurisdiction | Meetings | Items | Withdrawn |
|---|---|---|---|
| City of Scottsdale | 1 | 2 | — |
Meeting Timeline
Filtered by City of Scottsdale
Regular Meeting
Item 1
Ashler Hills Park Construction Phase Contract – Approved on Consent. 2023-168-COS with Valley Rain Construction Corporation, in an amount not to exceed $8,753,376, to provide construction services for the Bond 2019 Project 55 – Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock). Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov Park Construction Phase Contract.
(+1 more mention)
Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
All mentions in this meeting
#1
Ashler Hills Park Construction Phase Contract – Approved on Consent. 2023-168-COS with Valley Rain Construction Corporation, in an amount not to exceed $8,753,376, to provide construction services for the Bond 2019 Project 55 – Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock). Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov Park Construction Phase Contract.
Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
Request
#2
WestWorld Master Plan Phase II Services Engineering Services Contract Amendment – Approved on Consent. amendment to the contract with Kimley-Horn and Associates, Inc., in the amount of $385,360, for WestWorld Master Plan Phase II Services. Location: 16601 N. Pima Road Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, daworth@scottsdaleaz.gov
Adopt Resolution No. 12979 authorizing the following on-call electrical engineering
Request