Adopt Resolution No. 11797 authorizing Construction Bid Award No. 20PB029 with

Organization

1
Meetings
1
Jurisdictions
2020-05-19 – 2020-05-19
Activity range
Activity by Jurisdiction × clear filter
Jurisdiction Meetings Items Withdrawn
City of Scottsdale 1 1
Meeting Timeline Filtered by City of Scottsdale
Item 6 Osborn Road Parallel Sewer Main Project Construction Phase Services Contract – Approved on Consent. F Contracting, Inc., in the amount of $1,762,913.83, to provide construction phase services for the Osborn Road Parallel Sewer Main – Bishop Lane to Miller Road project. Staff Contact(s): Dan Worth, Public Works Director, 480-312-5555, dworth@scottsdaleaz.gov
Adopt Resolution No. 11797 authorizing Construction Bid Award No. 20PB029 with