C-number: C-64-23-304-X-00
Revision: 00
Vote — approved
Ayes: Thomas Galvin, Kate Brophy McGee, Mark Stewart, Debbie Lesko, Steve Gallardo
Item Text
61. AMENDMENT TO BID AND AWARD FOR ROADWAY CONSTRUCTION ON OLIVE AVENUE Amend Bid Solicitation approved on May 24, 2023 (C-64-23-304-X-00). Which approved the solicitation of bids for the Maricopa County Department of Transportation’s Transportation System Management project. Per the original Board approval to construct: “Award the contract to the lowest responsive responsible bidder, provided that the lowest responsive responsible bidder does not exceed the Engineer’s estimate by more than ten percent”. The Performance Measure of Delivering the Fiscal Year TIP Budget has changed to Fiscal Year 2026, 2027 TIP Budget. The Funding expenditure impact by FY’s has changed to FY2026: $6,788,000 and FY2027: $17,846,000. The Engineer’s estimate has increased by $3,630,000 which is more than ten percent of the previous Engineer’s estimate. Supervisory District No. 4 (C-64-23-304-X-01)