← Back

C-number: C-73-24-073-X

C-number: C-73-24-073-X-00
Item: #57
Revision: 00
Vote — approved
Jack Sellers yes
Thomas Galvin yes
Bill Gates yes
Clint Hickman yes
Steve Gallardo yes
Ayes: Jack Sellers, Thomas Galvin, Bill Gates, Clint Hickman, Steve Gallardo
Item Text
57. 240056-CMR, MARICOPA COUNTY ELECTIONS FACILITY (PHASE 1 CONTRACT) Approve and award a Construction Manager at Risk (CMR) Phase 1 Pre-Construction contract between Maricopa County and Core Construction at a not to exceed amount of $1,324,514.00 for pre-construction services of the new Elections Facility for Maricopa County, tentative address: 801 W. Jefferson St., Phoenix, Arizona 85003 with a term of 663 calendar days from issuance of the Notice to Proceed. (C-73-24-073-X-00)
Attachments (1)

C-number: C-73-24-073-X-01
Item: #51
Revision: 01
Vote — approved
Thomas Galvin yes
Kate Brophy McGee yes
Mark Stewart yes
Debbie Lesko yes
Steve Gallardo yes
Ayes: Thomas Galvin, Kate Brophy McGee, Mark Stewart, Debbie Lesko, Steve Gallardo
Item Text
51. 240056-CMR, MARICOPA COUNTY ELECTIONS FACILITY (PHASE 2 / GMP1 CONTRACT) Approve and award a Construction Manager at Risk (CMR) Phase 2 Construction Services contract, GMP #1 (Guaranteed Maximum Price), between Maricopa County and Core Construction in the amount of $18,251,519.00 for site utilities, excavation of the entire site - approximately one city block, and shoring services of the excavated areas for the new four-story Elections Facility, located at 801 Jefferson St., Phoenix, AZ 85007. The GMP will also include costs associated with standard contractor General Conditions, which include among other items, fencing, overhead items, trailers, site security, etc. This project is located in Supervisor District 5. The new facility is designed to consist of four stories including a basement totaling approximately 260,000 square feet. Final construction contracts (GMP #2 and GMP #3) are expected to include foundations, structure, and early procurement items and the remaining site and building construction work. The two additional GMP’s will be brought to the Board of Supervisors under future agenda items. Using multiple GMPs’ will accelerate the construction process. (C-73-24-073-X-01)

C-number: C-73-24-073-X-02
Item: #76
Revision: 02
Vote — approved
Thomas Galvin yes
Kate Brophy McGee yes
Mark Stewart yes
Debbie Lesko yes
Steve Gallardo yes
Ayes: Thomas Galvin, Kate Brophy McGee, Mark Stewart, Debbie Lesko, Steve Gallardo
Item Text
76. 240056-CMR, MARICOPA COUNTY ELECTIONS FACILITY PHASE 2 GMP#2 Approve and award a Construction Manager at Risk (CMR) Phase 2 Construction Services contract, GMP#2 (Guaranteed Maximum Price), between Maricopa County and Core Construction in the amount of $157,033,185.00 for the construction services of the new Downtown Elections Facility, located at 801 Jefferson St., Phoenix, AZ 85007. The new facility is designed to consist of four stories totaling approximately 260,000 square feet and will include a basement level with three levels above grade. The Phase1 contract was previously approved by the Board of Supervisors for $1,324,514.00 for pre-construction services to include constructability reviews, cost estimating, and value engineering. The Phase 2 contract, GMP#1 was previously approved by the Board of Supervisors for $18,251,519.00 for on and offsite utility improvements, site excavation, and shoring (approximately one city block). Approval of GMP#2 will enable the balance of the construction of the facility that was not included in the previously approved GMP#1. This project is located in Supervisor District 5. (C-73-24-073-X-02)
Attachments (1)

3 item(s) sharing C-number base C-73-24-073-X