C-number: C-69-21-074-X
Vote — approved
| Bill Gates | yes |
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Steve Gallardo | yes |
105.CHANGE ORDER NO. 1 FOR GUADALUPE FRS INTERIM FIX FINAL DESIGN AND POST DESIGN (CI) Approve Change Order No. 1 in the amount of $400,000 and time extension to this Competition Impracticable (CI) contract that will allow the design consultant to prepare plans for a targeted demolition of the Guadalupe FRS Intake Structure which is failing and in need of immediate repair. Change order will also allow for the consultant to remain as the engineer of record during demolition and writing the comple
Item Text
105. CHANGE ORDER NO. 1 FOR GUADALUPE FRS INTERIM FIX FINAL DESIGN AND POST DESIGN (CI) Approve Change Order No. 1 in the amount of $400,000 and time extension to this Competition Impracticable (CI) contract that will allow the design consultant to prepare plans for a targeted demolition of the Guadalupe FRS Intake Structure which is failing and in need of immediate repair. Change order will also allow for the consultant to remain as the engineer of record during demolition and writing the completion report required by ADWR. The consultant will also assist the District with getting approval from ADWR and NRCS as to what the final permanent condition for the outlet structure can be. This Agenda Item impacts Supervisorial District 5. (C-69-21-074-X-01)
Attachments (1)
Vote — approved
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
60. CHANGE ORDER NO. 2 FOR GUADALUPE FRS INTERIM FIX FINAL DESIGN AND POST DESIGN Approve Change Order No. 2 in the amount of $350,000 to the contract that will allow the designer to remain as the engineer of record during the demolition and to write the completion report required by ADWR. The consultant will also assist the District with getting approval from ADWR and NRCS on the final permanent condition for the outlet. Black and Veatch Inc. has prepared plans at the 100% level for the complete demolition of the existing intake structure and its replacement with a gated inlet located on the dam embankment. Those plans have not been approved by either ADWR or NRCS. The gated inlet construction cost is estimated to be over $500,000 for what was to be the interim condition. The District wants to avoid expending those funds without knowing what the approved final long-term solution can be. History has shown that it could take considerable time to get approval from NRCS and a waiver on the outlet pipe size from ADWR. This Agenda Item impacts Supervisorial District 5. (C-69-21-074-X-02)
Attachments (1)
Vote — approved
| Thomas Galvin | yes |
| Kate Brophy McGee | yes |
| Mark Stewart | yes |
| Debbie Lesko | yes |
| Steve Gallardo | yes |
Ayes: Thomas Galvin, Kate Brophy McGee, Mark Stewart, Debbie Lesko, Steve Gallardo
Item Text
74. CHANGE ORDER NO. 4 FOR GUADALUPE FRS INTERIM FIX FINAL DESIGN AND POST-DESIGN Approve Change Order No. 4 for Guadalupe FRS Interim Fix Final Design and Post-Design in the amount of $90,000 to the contract that will allow the Engineer of Record to accomplish as-builts and a construction completion report from the demolition of the intake structure. This Agenda Item impacts Supervisorial District 5. (C-69-21-074-X-03)
Attachments (1)
3 item(s) sharing C-number base C-69-21-074-X